Comco Constructions Pty Ltd v Leisure Holdings Australia Pty Ltd [1986] FCA 209
Federal Court of Australia
Full text
Select any passage to save a personal note with optional tags.
Trade Practices - Building contract - formation of contract -
course of dealing - appointment of builder - final price not
established - contract concluded - part performance - appointment
of another builder - breach of contract - assessment of damages -
loss of potential profit.
Trade Practices Act 1974 8.52
Cases:
G. Scammell _ and Nephew Ltd. v. QOuston (1941) A.C. 251
William Lacey (Housiow) Ltd. v. Davis (1957) 1 WLR 932
Sabemo Pty. Ltd. v. North Sydney Municipal Council (1977) 2 NSW
L.R. 880
Jones & Lyttie Ltd. v. Mackie (1918) 2 W.W.R. 82 (Can.)
COMCO CONSTRUCTIONS PTY. LTD. v. LEISURE HOLDINGS AUSTRALIA PTY.
LTD.
No. WA G24 of 1986
MUIRHEAD J.
PERTH '
30 MAY 1986
aro,
eer
Wits ts ee,
ne
cereee wes
ee re
S s
were wey pee,
IN THE FEDERAL COURT
OF AUSTRALIA
WESTERN AUSTRALIA
DISTRICT REGISTRY
GENERAL DIVISION
No. WA G24 of 1986
eed
BETWEEN:
COMCO CONSTRUCTIONS PTY. LTD.
Applicant
and
LEISURE HOLDINGS AUSTRALIA PTY. LTD.
Respondent
MINUTE OF ORDER
JUDGE MAKING ORDER: MUIRHEAD J.
DATE OF ORDER: 30 May 1986
WHERE MADE: PERTH
THE COURT ORDERS THAT:
Judgment for the applicant in the sum of $54,675.07 plus
costs to be taxed.
Note: Settlement and entry of orders is dealt
with in Order 36 of the Federal Court Rules
OT nr oO
en ners
ee re een eee
ae . ey Oa
Awe
woe oe
IN THE FEDERAL COURT
OF AUSTRALIA
WESTERN AUSTRALIA
DISTRICT REGISTRY
GENERAL DIVISION
No. WA G24 of 1986
BETWEEN:
COMCO CONSTRUCTIONS Pry LTD
Applicant
and
LEISURE HOLDINGS AUSTRALIA PTY LTD
Respondent
CORAM: MUIRHEAD J.
30 May 1986
REASONS FOR JUDGMENT
The applicant (Comco) seeks damages from the respondent
(Leisure) arising out of breach of contract allegedly entered into
between the parties in August 1984. In the alternative Comco
claims that certain representations of Leisure constituted false
and misleading conduct in breach of s.52 of the Trade Practices
Act 1974 whereby it suffered loss and damage.
Comco, a building company commenced to carry on business
in Western Australia in 1983. The events giving rise to the
action occurred relatively early in its business life at a time
when it was important that work be secured and successfully
performed. Its managing director Mr. Ken Doubikin has long
experience in the building industry, having started off his life
Ww
in that field as an apprentice carpenter. Mr. C. McLaughlin, a
civil engineer was employed by Comco as project manager of the
works in issue.
At material times Leisure carried on business as a
developer in Western Australia. Mr. Jon Warren is its managing
director and Mr. Dean Scook, also a director, played the principal
role in the negotiations and events leading up to the alleged
contract. BFC Finance Ltd. (BFC), a Sydney based company, was
Leisure's financier for the project in question. Mr. Ken Bohatko
was its principal real estate administrator. The persons
mentioned above and others gave evidence. As to the history of
the matter there is not great dispute save on one or two critical
matters. Thus the credibility of the witnesses on disputed
factual matters is of importance. Be that as it may the history
of the matter is of some importance as it serves to explain what
at first glance was an unusual course of dealing between the
parties.
In 1983 Leisure was engaged upon a major home unit
development comprising 40 units at Highgate known as the
Peppertree project (Peppertree). BFC was the financier of that
project and building difficulties were encountered. BFC appointed
Comco to audit and act in the capacity of a watchdog. Because of
a past bankruptcy a builder, Mr. Lister, engaged on Peppertree
which as I have said was a substantial project, was not acceptable
to the financier. After negotiation and discussion it was agreed
in effect that Comco would take over as builder on Peppertree.
Clearly Mr. Doubikin was regarded with confidence by Mr. Bohatko
wna
ve otlaw
Tt eee
a eee
uUce. in
wid ipdeta ocumtil lates itayves, by tye davactors of Ler
uy
the meantime Leisure had another development in the pipeline. the
Peach Tree project. (Peachtree) BFC was the proposed financier.
There is no need to deal in detail with the contractual
arrangements concerning Feppertree but Comco aqreed to take it
over on a very small margin. I accept Mr. Doubikin's evidence
expressed in the following terms:
"I agreed to that unrealistically low margin on the
first contract in good faith. Leisure Holdings
indicated to me that providing things went well between
us, we could look forward to subsequent major
contracts, and it was indicated that Mr Lister would
probably still serve their purpose on minor contracts."
It was, I find, most important for Leisure's operations
that it should have a reliable builder available, acceptable to
its financier, a builder with the capacity to get on with and
finish comparatively large projects. Leisure was selling units
before construction off plan and significant difficulties or
delays served not only to increase its interest liabilities but
were likely to cause embarrassment with pre-construction
purchasers. Work on Peppertree commenced early in 1984.
Mr. McLaughlin was project manager and the project in its early
stages was ahead of schedule. Towards its termination date Comco
expertenced difficulties, which on the limited evidence available
fo me, I find was probably due, not to its default but to
inefficient supervision by Leisure's architect. Be that as it
may, discussions took place early in 1984 concerning Peachtree. I
find a mutual understanding emerged between Leisure, Comco and BFC
that Comco would be builder on that project if broad agreement as
to terms could be reached. Leisure's architect prepared a broad
TY ee
tres
fey re oe tee
Fie
Tere ery
roe eee = ere
moar sy etee
An 8.
eee ee we
design of this new project which involved the construction of
approximately 50 units. Later a pictorial facsimile was prepared
(Exhibit A.5). On 30 April Mr. McLaughiin and Mr. Dean Scook
discussed this project, and by memorandum dated that day the
former reported to Mr. Doubikin in the following terms:
"Dean also said that Ralph & Beattie will prepare to
Csicl Bill of Quantities for Peach Tree, which should
ensure that documentation will be completed before we
commence construction. Leisure Holdings also intend to
submit our name as Builders in June to the Council and
avoid a repetition of demolition rat baiting hold ups
and delays in the issue of a Building License."
Mr. Doubikin expressed his understanding of the position
At that time as follows:
"My understanding of the matter was that we were going
to proceed down a path of doing exactly what we had
done with Peppertree; pricing the job, calling
subcontract quotations and hopefully reaching a price
which was viable for the project."
In May 1984 some union interest in the Peppertree
project was evident and it was determined at a meeting arranged by
Mr. Doubikin in May 1984 that a site allowance would apply not
only to Peppertree but also to Peachtree from its anticipated
commencement until termination (Exhibit 32). I mention this as it
is consistent with the general intention of the parties that Comco
would continue as builders. This general intention is further
evidenced in Exhibit R.27, being Leisure's application for finance
to BFC "to finance the purchase of land and construct 50 pre-sold
gtrata titled units on Peachtree Lane". The application nominated
"Comco Constructions Pty Ltd" as the 'builder'. This application
woe eter
ee meeps -
y en i ae re . ns
reat
a yo wat
> won
bears date 11 May 1984 and LL contains the information that at
that date "23 of the 50 units are sold off plan".
Subsequent events which I merely precis satisfy me that
from this stage onwards it was mutually contemplated that Comco
would be likely to build Peachtree. With the consent of Leisure,
Comco advertised in "The West Australian" of 16 June inviting
subcontractors to register interest in the proposed development.
Comco drafted the advertisement stating "We have been appointed
builders and project managers" for the development (Exhibit A.2).
This was done to minimise initial delays on the assumption that
Comco would be the builder. Mr. McLaughlin prepared a form of
notice to subcontract tenderers and Mr. Scook suppiied him with a
coloured isometric photo of the project. A meeting was held
early in July at which Mr. Bohatko was present when both
Peppertree and Peachtree were discussed. At that meeting Mr.
Doubikin was informed by Mr. Bohatko that the finance agreement
was about to be executed and he sought a letter from Comco
confirming its participation as builder. This letter was
despatched on 10 duly (Exhibit A.33). Mr. Doubikin stated that at
that meeting it was "reaffirmed that Comco Constructions were to
be the builders of Peachtree". Mr. Bohatko's recollection was
that there was no confirmation to that extent but he said "No I
have no recollection of that. I do know and can add that we were
all talking in terms positively, as I said, of the project
proceeding but no official confirmation of that nature". The
evidence tends to support Mr. Doubikin's recollection, which is
disputed by Warren and Scook. It is not of primary importance as
it is not claimed an agreement had been reached at this stage, but
fre pert pe epee eee ee
. worse 4. He ay
ek ee
wWhiteyer the tituation., I fisd thavs war seneral expectation that
Somes would secform the pburidec's cole. Thereafter BFC provided
Tomco with a cory of its offer to provide finance to Leisure.
Finance apparently being in hand Leisure instructed its
Quantity Surveyors to prepare a bili of quantities. Mr.
McLaughlin was invited. prior to its preparation, to discuss the
bill of quantities and shortly after he received the first plans
he had seen. On 25 July the bill of quantities was supplied to
Comco (Exhibit A.7) and Mr. McLaughlin set about pricing the bill.
He contacted subcontractors concerning prices and with the help of
a planning consultant prepared a preliminary construction
programme. Mr. McLaughlin's understanding at that time was
expressed by him as follows:
"We were the only people pricing the actual works and we
were to obtain the most competitive submission. We
would then put on our agreed mark-up at the end and
submit them to the client for approval. It was to be
an open situation and I was quite happy to show them
all the aspects of our price, virtually on a page by
page basis if need be."
This open approach to the project was maintained by
Comco throughout. Leisure played its cards closer to the chest.
It was then hoped that the building works were to
commence on 1 September 1984 for completion at the end of July the
following year.
Early in August 1984 Mr. Scook instructed Comco to
proceed with demolition, rat baiting and investigation of water
table levels, preliminary steps designed to shorten time. These
steps were duly performed, invoiced and paid for in due course.
On 14 August Comco's tender had been prepared and a meeting was
arranged to discuss it. It was above Leisure's budgeted figure
and a general discussion took place to find ways and means of
scaling it down. Leisure's architect, Mr. Harler was present and
not only price pruning but design changes to effect economies
were, I find, discussed.
I heard much evidence about Leisure's 'budget' figure
for building costs and subsequent variations of price. I
observe that however Leisure may have regarded its budget figure
it was initially based on -estimates not supported by detailed
Plans and specifications. It is clear to me that the system
adopted posed real difficulties. The budget was reached - at an
early stage, a stage not far divorced from sales 'off plan' and a
Stage when a market building price had not been obtained. But
having sold units 'off plan' Leisure's scope for design changes
was somewhat limited. I find with confidence that "it was in' the
contemplation of the parties that ways and means of reducing price
could be found, by substitution of materials and by simplification
of some aspects.
Mr, Doubikin's evidence as to the meeting on 14 August
was as follows:
"Was there any response from Leisure Holdings people?
~--Yes. Mr Warren confirmed our understanding that the
figure was in excess of what they were hoping to
achieve. He indicated that it was fair. We made the
concession in respect of our preliminary allowances
which resulted in us pulling our general labour
ay wore er eee se
~ tas fer "ye
a a't
an
wr he.
8.
allowance from three men down to two. We told him that
any savings which resulted from subcontracts, cheaper
subcontracts, would be afforded to his benefit, and Mr
Harler was fairly convinced that he could effect
considerable savings by a few design changes that he
had in mind.
Was there any mention of a figure expected to be
reduced as a result of those design changes?---We felt
that $200,000 was quite on the cards."
On 16 August Mr. McLaughlin says he was advised by Mr.
Scook that "Comco were to be the builders of the Peachtree Lane
project. He stated he was told "that we were to use our every
endeavour to try and reduce the price wherever possible by getting
reduced prices and coming up with practical design alternatives to
reduce the price and try and bring it close to their budget
figure". He also told me that Mr. Scook was flying to Sydney that
evening to confer with BFC and he was asked to prepare a 'cash
flow' on the project so that the financial commitment could be
more clearly defined. Mr McLaughlin hastily prepared the cash
flow (Exhibit A.10) and delivered it to Mr. Scook. In the
meantime he had conveyed the news of Comco's appointment as
builder to Mr. Doubikin who told me that he immediately telephoned
Mr. Scook. He stated:
"---T told him that I was pleased that the agreement had
finally been reached that Peachtree was to be built by
Comco Constructions and that we would be doing
everything in our power to make sure that it got moving
as quickly as possible and contribute any energies at
all that were required of us in the meantime.
Do you recall Mr Scook's reaction?---Mr Scook was very
pleased also that it was a fait accompli, and in fact
it was at that time that he told me incidentally that
we had beaten Mr Lister by $20,000."
one Fy Sea
9.
Unknown to Comco, Leisure had obtained prices from Mr.
Lister, the original builder engaged on Peppertree.
I pause at this stage to observe that Mr.Scook denied
the meeting with Mr. McLaughlin on 16 August and he denied the
telephone call with Mr. Doubikin the same day. This was a
critical day in the long series of events, as it represents the
day when Comco claims it established an agreement for the building
of Peachtree and it is appropriate for me to make my findings on
credibility. I found Mr. McLaughlin and Mr. Doubikin to be most
impressive witnesses. Mr. McLaughlin is no longer employed by
Comco, he now works for another firm. I am satisfied that he was
not partisan; he did not hesitate to make concessions in
cross-examination when the facts or truth so required. Mr.
Doubikin I assess as being an entirely trustworthy and careful
witness. He is a clear minded individual and I am confident that
he would not lie to suit his own interests. The demeanour of Mr.
Scook and Mr. Warren was generally good; they are both intelligent
men. But they did not exhibit the same frankness, or the capacity
to answer questions simply and to the point. Where the evidence
of Mr. Scook or Mr. Warren conflicts with that of Mr. Doubikin or
Mr. McLaughlin I accept the latters' testimony in preference. I
find that on 16 August 1984 Mr. McLaughlin was advised that Comco
was to be the builder and I find that the subsequent telephone
conversation between Mr. Scook and Mr. Doubikin took place in
terms of the latter's testimony.
stew
ies tie
~aee
awe ee cae eo
we 7 A
wes tnt
wees
ae
_
10.
Subsequent events were, in my view, consistent only with
that agreement having been reached. Regular discussions took
place between Mr. Scook and Mr. McLaughiin not only as to the
Peppertree and Peachtree projects but also to a further proposed
development on nearby land called the Jasmin project (see Exhibit
A.11l). On 23 August Comco having obtained rat baiting and
demolition licences directed demolition of premises for the sum of
$6700 (Exhibit A.12). Late in August Mr. McLaughlin went on leave
and in his absence Mr. Doubikin worked on the cost figures
reducing the price to 91,963,000 (in round figures) still above
the 'budget' of $1,834,000 but substantially lower than the first
price of $2,127,000. It was always in the contemplation of the
parties that when the lowest achievable figure had been reached
they would enter into a formal building contract, referred to in
the evidence as "Edition 5B" as required ultimately by the
financier. The parties were working mutually to that end.
Early in September 1984 whilst the parties awaited the
necessary building licence Comco took some further positive steps
such as ordering tiles for the project. I find that Mr. Scook
requested the builder "to firm up their pricing and to try and get
fixed prices wherever possible to make sure that with a slightly
delayed start it would not mean an escalation in pricing". Comco
took such steps (see Exhibits A.18, A.19, A.20 and A.21).
Up to this stage the relationships between the parties
was good. I am satisfied that Comco's work on Peppertree, which
had been ahead of schedule, had been to Leisure's benefit and it
TI,
Se
red
wea F
a
woarws ge
ll.
augured well for the future. The evidence of Mr. Bohatko shows
clearly that he also had confidence in Comco and in view of the
fact that Peachtree was to be almost totally financed this was an
'
important factor.
But as the weeks went by difficulties were encountered
by Comco at Peppertree due principally, I find, to the
inadequacies of supervision by Leisure's architect. The situation
was described by Doubikin in the following terms:
"What was the situation on the Peppertree project at
that time, Mr Doubikin?---The job was causing us
considerable concern. We just simply could not
progress the job due to problems associated with the
architect's inactivity or inability or - - -
What - on certifying progress payments?---On every
issue, We were not being paid moneys; we were not
having our variations dealt with; we were not receiving
instructions; we had trowels just standing around ~
trowel hands just standing around with trowels
dripping, waiting to find out at what point they should
stop and the job at that stage was in a terrible mess,
It was an unfortunate set of circumstances because we
had actually achieved a very good progress on the job.
We were six, seven, eight weeks ahead of schedule at
one stage and at that point in time we were getting
back to where we had almost lost all that credit. We
were getting nowhere with - it was an unusual contract;
the client was actually the person who was handling
instructions tous andwe seemed to have difficulty
obtaining the architectural assistance that we
definitely required. In fact, that was virtually the
start, I guess, of an arbitration that subsequently
took place with respect to Peppertree.
So as a result of these difficulties you were
experiencing on the Peppertree site - you mentioned the
architect - what was the state of your relationship
with Mr Warren and Mr Scook of Leisure Holdings at that
point?---I would describe it as a state of balance. We
were either going to be supported in our opinion as to
how things were or we were going to be sunk as a result
of their accepting Mr Harler's advice as to why things
were as they were. I would say that at that stage our
relationship was still intact, although under
suspicion."
were ee
12.
I am satisfied that in the face of Comco's requests for
variations on the Peppertree project Leisure's attitude to Comco
underwent change. To this stage the parties had worked in
apparent co-operation to prune the projected cost of Peachtree to
a figure closer to Leisure's budget figure, a sum in itself fixed
at a stage when it could be no more than a pretty rough estimate.
It is probable that Leisure determined, despite its August
agreement, to find other ways and means, including if necessary
another builder to proceed with Peachtree. Without consulting
Comco, Leisure determined on anew approach and put together a
package which involved proposed developments at Bunbury and the
Jasmin and Poplar Court projects in addition to Peachtree. They
called for tenders on a "design and construct" basis from other
builders. This came to the knowledge of Comco which by this time
regarded itself as the Peachtree builder, which was actively
pursuing preliminary matters and which had designated a project
number in its accounting procedures to Peachtree. On 16 October
Mr. McLaughlin wrote to Leisure requesting a meeting. He stated
inter alia "We are extremely concerned at your non-approval of the
recent variations submitted on the Peppertree Grove Units and the
possible loss of the Peachtree Lane project" (Exhibit A.22).
Two days later Mr Doubikin wrote to Mr Warren by letter
which I regard as unequivocal and which quite plainly indicated
that the Peachtree project had been awarded to Comco and that
company would not accept departure from the basic agreement
(Exhibit A.34). The meeting took place on 22 October and the
minutes taken by Mr. McLaughlin and Mr. Warren's comments thereon
ror om:
13.
are in evidence (Exhibits A.23 and A.24). Comco was given to
understand that the tenders were designed to ascertain competitive
prices, the package had been designed to explore the possibility
of overall savings on the four projects and that Comco was to he
the 'preferred choice' for future projects. On this basis, and
without I find departing from its stance on Peachtree, Comco
submitted a tender on the package. There is no necessity to deal
with subsequent events. By letter dated 8 November (Exhibit A.36)
Mr. Doubikin was informed that in respect of the package, which
included Peachtree, '"Jobec, builders have been appointed
Prospective Builders".
Leisure's conduct in this matter is difficult to
understand, save on the basis that for reasons which I find were
associated with Peppertree it had determined that it would not
adhere to the bargain struck with Comco. During the hearing
Leisure's witnesses, Mr. Warren and Mr. Scook adhered to the view
that as no price had been finally agreed, and no written contract
prepared, no contractual relationship had been established. And
yet it engaged another builder to do the job on a basis that had,
it seems to me, even less certainty as to price.
As I commented earlier, Leisure's approach to the
building development was unusual. It was not the situation of
preparation of detailed plans and specifications followed by the
calling of open tenders. It seems to me that having reached a
pretty arbitrary budget figure and having sold 'off plan' weil
before building started Leisure was determined to use every
endeavour to prune building costs. Having sold units, the savings
i.
pan
ae
teoege
wre wr
cms
. ao.9
Be
Ste rn gs ote ere ge
eae mapa
14,
to be effected by design alterations were thus limited, and it is
probable that Comco''s firm approach to variations on Peppertree
led Leisure to engage another builder which it was hoped would be
more amenable to its dictates.
In reaching my findings I have kept well in mind the
prior history of the matter and the relationship between the
parties.
I find that in the course of the negotiations Comco
operated in a completely open manner with Leisure being prepared
to reveal and discuss every aspect of its costing and the basis of
its tendering. This was consistent with the relationship,
encouraged by the financier, wherein the parties regarded.
themselves as a team. The establishment of a firm client builder
relationship had obvious advantages to Leisure as a developer,
just as it had clear advantages to Comco which thereby had an
assured future source of work. These were the considerations which
weighed with the parties during the negotiating stage and it
explains why, as I find, the final agreement that confirmed
previous expectations Comco would be builder was reached' in an
informal manner. I also stress that at the time when Leisure
abrogated the agreement the question of cost reduction was being
actively pursued by Comco and I can only assume, (as he did not
give evidence) by Leisure's architect. The gap between the
'budget figure' and the final contract price was narrowing and at
the time the contract was taken from it, Comco was energetically
taking steps which can only be rationalised on the basis of its
understanding that it was builder for the project.
My eee
wt wey + an
pee pee oer ee
"Fs : .
iw
in
The steps taken by Comco arter 16 Aucdust were not steps
av
taken in the course of tender. Nor do I find there was a separate
agreement to the effect that Comco would carry out steps on behalf
of Leisure on the basis that if Leisure did not appoint it as
builder a financial adjustment would be effected. The submission
in September 1984 of Comco's invoice for demolition works and site
clearance. which included the builder''s margin (Ex. A.16), is
consistent only with the relationship of client and apointed
builder. (See also Exhibits A.19, A.20 and A.21.)
It is not a function of the court to interpret documents
and dealings between parties as leading to a finding of consensus
ad idem, when there was obviously no consensus. Lord Maugham
expressed the situation in commercial contracts simply in
G. Scammell and Nephew Ltd. v. Ouston (1941) A.C. 251 at 255:
"In order to constitute a valid contract the parties —
must so express themselves that their meaning. can be
determined with a reasonable degree of certainty. It
is plain that unless this can be done it would be
impossible to hold that the contracting parties had the
same intention; in other words the consensus ad idem
would be a matter of mere conjecture. This general |
rule, however, applies somewhat differently in.
different cases. In commercial documents connected
with dealings in a trade with which the parties are
perfectly familiar the court is very willing, if
satisfied that the parties thought that they made a
binding contract, to imply terms and in particular
terms as to the method of carrying out the contract
which it would be impossible to supply in other kinds
of contract: see Hillas & Co. v. Arcos, Id. 147 L. T.
503, 511, 512, 514.
My Lords, it is beyond dispute that if an alleged
contract is partly oral and partly in writing it is
necessary to take the whole of the negotiations into
consideration for the purpose of seeing whether the
parties are truly agreed on all material points, for if
wpe me
wT
raremar oor
haat
ve
oh
ne ee nee oe
a: San Sw 4 se
T
Panama)
Tye ye,
a
16.
they are not there Js no nindaing contract. Nor is it
right to construe a letter or other document forming a
part of the negotiations in such a case without regard
to the oral statements which also form a part of them."
(See generally Halsbury's Laws of England (4th Edition)
Vol.9)
I am not dealing here solely with a claim for
reimbursement of expenditure made in contemplation of contract,
for example toa quasi contractual arrangement which has at its
source the principles relating to quantum meruit. (See William
Lacey (Hounslow) Ltd. v. Davis (1957) 1 WLR 932; Sabemo Pty. Ltd.
v. North Sydney Municipal Council (1977) 2 NSW L.R. 880.) In the
latter case Sheppard J. carried out a careful examination of the
authorities relevant to the development of a party's right to
remuneration or compensation for work done arising quasi ex
contractu, not by reason of a concluded contract. (See
particularly at 900-901.) Those were cases where by unilateral
decision the proposed work was not proceeded with. Here the work
did proceed, another builder being appointed, not only after Comco
had been appointed but after it had taken steps in the performance
of the agreement and the building works. As I commented at the
outset the negotiations and the agreement itself were unusual in
form, but the oral agreement cannot be analysed, isolated as it"
were, from what had gone before. The fact that the respondent
breached the agreement, part performed by the applicant before the
agreement was incorporated in the written form contemplated by all
concerned does not deprive the applicant of its right to damages.
This is not a case where the project was abandoned, in which case
the measure of damages to the applicant may well have been limited
to the work done prior to breach. The work, already in my view
Soyo
1 toe 4
1?.
part performed by the applicant, proceeded and at a time when the
applicant was ready willing and able to continue to finality as in
my view was mutually contemplated. As I have mentioned Leisure's
change of heart was in my view probably associated with Comco's
insistence that it should be paid its entitlement upon Peppertree
- an issue which was determined eventually by arbitration.
I find that on16 August 1984 Comco was appointed
builder of Peachtree, that with the approval of Leisure it took
positive steps as builder to ensure the project could start
without delay and without escalation of costs. A final agreement
as to price had not been reached but there was agreement in
principle that the price would be defined in the Edition 5B
agreement after not only Comco but Leisure and its architect had
further explored costs savings and design changes.
I find the contract pleaded in paragraph 20 of the
Statement of Claim and the matters pleaded in paras 23 and 24 of
the Statement of Claim are established. The contract and its
breach are proved. Comco is entitled to damages consequent upon
such breach, which include reimbursement of expenses incurred as
contract works or in anticipation of and to the benefit of such
works.
In assessing damages I take into account the evidence of
the witness Greaves which I accept.
I allow the following:
vee
4,
- ayes
ae?
mayen
2 Se ite
18.
Newspaper advertisomoent $ 99.60
John Roth and Associates 5 248.00
- Construction Programme
Applicant's costs associated with $ 370.00
construction programme
Second Foreman at Peppertree to $ 5,000.00
ensure continuity - allowed at
Water table excavation and
investigation
Executive Plant Hire $ 108.00
Comco $ 73.00
Demolition expenses $ 3,996.25
Work and design changes - Comco $ 1,450.00
Workers Compensation -
interest allowance not allowed
Retention - bricklaying team $ 1,433.22
Rat baiting $ 200.00
Site amenities $ 704.00
$13,682.07
Less progress payments recovered $_9,007.00
$ 4,675.07 .
In addition the applicant claims $76,200 by way of loss
of profits.
The evidence before me shows and it was common ground-
Comco was prepared to accept 5% of the appropriate figure for
calculating the builder's margin (Exhibit R.25). The evidence of
Mr. Ralph the quantity surveyor is that normally neither a
builder's margin nor an allowance for project administration is
included in a bill of quantities - a builder will generally make
allowance for his profit margin and overhead expenses in
submitting his costs to the individual bill items. But it was his
NT eet ere me re
2 omy i a
19,
firm, on instruction from Leisure, which prepared the bill of
quantities where individual provision was made for both project
administration and the builder's margin. Mr. Doubikin has
assessed loss of profit by accepting the project cost figure at
$1.8 million, 5% of which is $90,000. From this he has deducted
his company's allowance for project administration and the
evidence of Mr. Ralph supports the approach that such
administration should be incorporated in the margin, not
chargeable as a separate item on the job. In the bill the
applicant allowed $13,800 for project administration. This
allowance may well have been reduced in due course but the
procedure gives the respondent a maximum allowance. Thus Mr.
Doubikin arrived at his claim for loss of profit at approximately
$76,200.00.
Having found the respondent committed a fundamental
breach of the agreement there can be no doubt as to the
applicant's right to recover by way of damages the profit
reasonably anticipated and proved. The loss was of a type
reasonably in the contemplation of the parties and it was damage
arising in the ordinary course of things from the breach. See
Hadley v. Baxendale (1854) 9 Ex. 341; Victoria Laundry (Windsor)
Ltd. v. Newman Industries [19491 2 K.B. 528; Canada Foundry Co. v.
Edmonton Portland Cement Co. (1918) 3 W.W.R. 866 (P.C.): Hudson's
Building. and Engineering Contracts (10th Edn) 596.
I am satisfied as to the competence of the applicant to
carry out the work and I find that save for the breach it would
have done so. It was a job of the nature Comco sought. Mr.
Soygtee aye
— se er ae
he
20.
Doubikin was an experienced builder who knew the capacities and
limitations of his company which had of course recent experience
upon the Peppertree project. Exhibit A.40 sets out the contracts
secured by the applicant since the breach took place and Comco
appears to be pretty regularly engaged on a variety of building
projects, some modest, some substantial. I am satisfied that the
applicant had an efficient up to date administration and it would
be erroneous to find on the evidence that the loss of profit on
Peachtree was replaced by profit on another job which would not
otherwise have been secured. The evidence of the independent
witness Greaves was relevant on this aspect when he was dealing
with administration and fixed overheads:
"It is there as a set number of people who expand with
the volume of work that they have on. As far as I am
concerned, in particular, all my administration staff
or my tendering staff and my purchasing staff are a
fixed cost, so0 the more profit I maximise the more or
the less percentagewlse is that overall cost against ny
profits, bearing in mind as I said that this is going
on all the time, and I suppose in a sense it is like
putting fuel into a diesel bus. It is there all the
time. While it is traveling along, the more customers
or the more fares you get on to the bus, the cheaper
that fuel costs. It is a very similar situation as far
as building is concerned."
I accept Mr. Doubikin's evidence that had Peachtree gone
ahead with his company as builder he would still have "bid" for
the subsequent contracts he obtained. I also accept that whatever
the builder may determine as his margin, profit will vary
according to the fortunes of the particular project. The
applicant's counsel submits that in assessing entitlement to
damages for loss of profits - loss of the bargain - I should bear
in mind that the contingencies relating to profit on this type of
ran
oe eer =
es ke
en ee pete coe
yc
Ley oqeer
spre
wing Oe
iat An ban
—_— ar eee
' 21.
project may be favourable as well as adverse. But I must bear in
mind the nature of the project in question and the clients with
whom the applicant planned to be associated. I can feel no
confidence that had the agreement not been breached the road to
completion would have been altogether a smooth one. When the
parties were in negotiation there was optimism that Peachtree
would commence in August 1984 and would be finalised 10 months
later, i.e. about June 1985. Mr. Scook informed me that the job
has only just been completed. This is of no evidentiary value, as
a different builder was engaged and there may have been variations
of which I am not aware. But my assessment on the probabilities
is that Peachtree may have proved a difficult contract and in
assessing damages under this head I consider realism requires the
award of a sum substantially less than the amount claimed. Some
allowance must also be made for the time, labour and expense saved
by reason of the fact that the builder was by circumstance
relieved of his obligation to carry out the contract. (See Jones
& Lyttle Ltd. v. Mackie (1918) 2 W.W.R. 82 (Can.) (referred to in
Hudson at p.602)).
I award $50,000 damages for loss of profit, a total
award of $54,675.07. As I have found for the applicant in respect
of its cause of action based on breach of contract there is no
necessity to consider the claim as alternatively pleaded under the
ete eee
"F
ie see ioe
— ee
.
Kt
opty eres
enya p
ae 22.
Yrade Practices Act. Whilst the measure of damages under that act
may in some circumstances be assessed upon a different basis it
would in this case, if misleading conduct had been established,
make no difference to the outcome.
There will be judgment for the applicant in the sum of
$54,675.07 plus costs to be taxed.
I certify that this and the twenty-one
preceding pages are a true copy of the
Reasons for Judgment herein of his
Honour Mr Justice Muirhead.
Hsoecth |
Associate
Dated: 30 May 1986
ys
Sate aie
ra