Schepis, N. & Ors v. Elders IXL Ltd [1986] FCA 634
Federal Court of Australia
Full text
Select any passage to save a personal note with optional tags.
"Ul nuthet Reda ; . Ko, ' ;
CATCHWORDS
TRADE PRACTICES - reliance on respondent's expertise - reasonable
time only allowed.
FEDERAL COURT - interest - applying State law - Western Australia -
statute applicable to courts generally - whether jurisdiction to
award.
Trade Practices Act 1974, ss.52, 71(2)
Supreme Court Act (W.A.) 1935-1979 ss.32, 34
Ned Schepis & Ors.
v. Elders IXL Limited
WA G68 of 1986
PINCUS J.
BRISBANE
24 DECEMBER 1986
\ FEDETAL +
G AUSTRA:
Pay 3
Aur 1
a
.
IN THE FEDERAL COURT OF AUSTRALIA )
WESTERN AUSTRALIA DISTRICT REGISTRY ) W.A. GOB of 1986
GENERAL DIVISTON )
BETWEEN: NED SCHEPIS, CARMELO SCHEPIS, VENY SCHEPIS
and JOHN SCHEPIS
Applicants
AND: ELDERS IXL LIMITED
Respondent
MINUTES OF ORDER
JUDGE MAKING ORDER: PINCUS J.
DATE OF ORDER: 24 DECEMBER 1986
WHERE MADE: BRISBANE
THE COURT ORDERS THAT:
i. The respondent pay the applicants the sum of
$51,000.
2. Costs be reserved.
3. The time for the filing of a notice of appeal he
extended until 28 January 1987.
NOTE: Settlement and entry of orders is dealt with in
Order 36 of the Federal Court Rules.
(s
IN THE FEDERAL COURT OF AUSTRALIA )
WESTERN AUSTRALIA DISTRICT REGISTRY ) W.A. G68 of 1986
GENERAL DIVISION )
BETWEEN: NED SCHEPIS, CARMELO SCHEPIS, VENY SCHEPIS
and JOHN SCHEPIS
Applicants
AND: ELDERS IXL LIMITED
Respondent
PINCUS J. 24 DECEMBER 1986
REASONS FOR JUDGMENT
This 18 a case about the cause of the relative failures
of two crops of tomatoes grown by the applicants on their property
near Perth in the 1984/85 and 1985/86 seasons. The applicants'
case 1s that the principal cause of the relative failures was that
they relied on an irrigation system supplied by the respondent for
watering and fertilisation of the tomatoes, but that system worked
very poorly. I call the failures "relative" because, although
tomatoes were produced 1n each season, they were not as_ good,
large or numerous as they should have been.
There is credible expert evidence that the system was
deficient as alleged, and nothing to contradict it. No witness
has been called by the respondent as to the efficacy of the system
it supplied. For the reasons explained below, it seems clear that
the respondent must be held liable under s.52 of the Trade
2.
?
Practices Act and under the general law, but the extent to which
it 1s liable is a complicated question depending on the analysis
of a mass of evidence. It is common ground that the two tomato
crops were not very successful, and that causes having nothing to
do with the respondent made at least some contribution to their
unsuccess. It is not possible by any mathematical process to
apportion the effects of the various causes, and I have, in the
end, adopted a broad estimate. In arriving at it I have had to
reach conclusions on a number of contested factual questions
mentioned below. Of these, the one which is most important is
whether the respondent should be held liable for the results of
the deficiencies in the irrigation system throughout the whole of
the two seasons, or whether the loss should be "cut off" at an
earlier date; on that point, as will appear, my conclusion is in
favour of the respondent, principaily because I think the
applicants should have obtained advice other than that of the
respondent at a tame earlier than they did.
Pleadings
The statement of claim inthe form in which 1t came
before me alleged that the applicant Ned Schepis approached the
respondent to design and supply an automatic irrigation and
fertiliser system, and that the applicants made known that they
required "automatic and variable irrigation and fertilisation of
individual bays of tomato plants at varying rates of watering and
application of fertiliser specified by the applicants". There was
also to be a self-cleaning filtration system operating
automatically. The defence, to put it simply, denied that the
3.
respondent undertook to design anything, but as will appear, that
issue was not seriously contested.
The statement of claim also alleges that the respondent,
by Trevor Guest, represented to the applicant Ned Schepis, ain
substance, that the respondent could design and supply an
efficient system which would meet the applicants' requirements.
Other representations were also alleged, but it is not necessary
to deal with them. The defence denies that any such
representations were made. Then the pleadings show, in substance,
an agreement that there was a contract to buy an irrigation system
for $13,270.25, and that the contract was carried out. The
statement of claim also alleges that the representations were
false in that, inter alia, the system failed to meet the
applicants' requirements.
Counsel for the respondent took the point that s.52 of
the Trade Practices Act cannot create liability for mere broken
promises; however, for reasons which will appear, it ais not
necessary to determine how that principle applies to the present
case. The defence also pleads that the system supplied was. one
specified by the applicants; that allegation was not' seriously
pressed, although there was some evidence that Ned Schepis
participated in the selection of some equipment.
The statement of claim goes on to say, in effect, that
the representations were false in that the respondent did not have
the capacity to design and supply such a system as was required.
The applicants' pleading further says that each representation was
a term of the contract, and alternatively that it was an implied
term of the contract, that the system would be reasonably fit for
the purpose for which it was supplied. Lastly, the applicants
plead a case in negligence.
As the hearing progressed, it became clear that one of
the applicants' complaints, not covered by the pleading, was that
the equipment had been supplied too late in the first season -
1.e. in the 1984/85 season, and that the delay had caused a loss.
Counsel for the applicants sought to amend, but counsel for the
respondent informed me, and I accepted, that the respondent would
not be able to meet that case without further investigation which
would necessitate an adjournment. In the special circumstances,
1t seemed to me unfair to force the respondent to litigate the
issue of delay, without an adjournment properly to prepare its
case on that rather complicated question. Since the applicant did
not wish the amendment to be granted on terms as to an
adjournment, I refused the application for amendment. That had
consequences adverse to the applicants, for they attributed part
of their loss - rightly as 1t seemed to me - to the fact that the
system was not installed until rather late in the 1984/85 tomato
season.
Ned Schepis and Trevor Guest
Under this heading I deal with the evidence of the
applicant Ned Schepis and that of Trevor Guest, they being the two
principal witnesses as to the dealings between the parties. Both
5.
of them appeared to me fairly honest witnesses, although Guest
was, early in his evidence, somewhat unco-operative.
Schepis is an automotive mechanic by trade, but he and
his family have for some years had experience in market gardening.
In 1982, he received a letter from the respondent regarding
Guest's availability as an "irrigation specialist" and received a
business card, which was tendered, to the same effect. He met
Guest and discussed irrigation problems with him. Guest explained
that his own experience in arrigation was principally in
"overhead" systems, meaning thereby systems in which water 15
sprayed into the air, rather than being run or trickled onto the
soul. That known limitation on Guest''s experience 15 of
importance and bears upon the reasonableness of the applicants'
continuing to rely upon the respondent after difficulties arose
with the system supplied by the respondent, a subject further
discussed helow.
Schepis says that in the 1982/83 season he had an
arrigation system which he installed after consulting Guest and
others, one of the latter being described as the "local irrigation
adviser". In that season, the applicants put in 5-6,000 tomato
plants and in the 1983/84 season intended to increase their
planting to about 12,000. That proposal was discussed with Guest
who took measurements, heights and levels and roughly designed an
irrigation system, apparently for no fee. That system worked
fairly well. It incorporated means of fertilising the plant but
not "automatic" means.
Coles Stores bought tomatoes from the applicants in the
1983/84 season and asked, during or at the end of that season, if
the applicants could increase their production. Schepis formed
the view that he could not do so without automating his irrigation
and fertilising system, and spoke to Guest in April 1984 on the
subject. Guest told Schepis that an automatic system could he
provided and that he had experience with automatic reticulation of
water. However, Schepis knew that Guest was not really
experienced in the specific sort of system the applicants desired.
About the middle of 1984, Guest again took steps to design a
system to suit the applicants' requirements and, for some months,
had numerous conversations with Schepis about the matter.
Guest's evidence was that about this time he sent a
representative from "Hardies" to Schepis. Although Schepis did
not admit that, I find it to have occurred, and find, more
generally, that at all material times Schepis was aware that Guest
relied, at least to some extent, upon Hardies with respect to
technical matters. The respondent acted as agent for distribution
of Hardies' irrigation products.
Hardies submitted a design of an automatic system, but
Schepis rejected it as too dear, According to Schepis, Guest said
that he would produce a cheaper design. Guest was inclined to say
that he took no responsibility for design, but merely transmitted
to the applicants Hardies' ideas about design. In
cross-examination, however, he substantially abandoned that
position, and I am satisfied that he assumed responsibility, in
large part, for supplying a design, relying upon such information
7.
"supplied by Hardies as he thought fit. It would seem to have
been, in a commercial sense, rather reckless for the respondent,
through Guest, to have done this. It had no true expertise
available in the area. Of course, no design fee was paid. It
must have been clear to Guest that if the system failed the
applicants might sustain considerable losses. However, I do not
think Guest is the sort of Man who gives thought to
self-protection above all else; he was genuinely anxious to help
the applicants, no doubt partly in order to make a sale, but also
because he 1s temperamentally so inclined. He worked on the
applicants' irrigation system in his own time, as well as in that
of his employer.
I find that Guest told the applicants about the middle
of 1984 that he would submit a design with a cost estimate. No
design was ever produced, but Guest, working on the basis of
Hardies' design, supplied a quotation Listing equipment which he
thought was necessary to achieve the applicants' purposes. The
design was implicit in the selection of the equipment. Guest gave
evidence that he knew nothing about automatic fertilisation and
Schepis gave no evidence that Guest ever claimed expertise in that
area. JI think Schepis was determined to have the system designed
for no charge, if he could, and to some extent exploited Guest's
over-enthusiasnm.
Schepis intended to use the quotation from the
respondent to "shop around", no doubt endeavouring to get the same
equipment cheaper elsewhere, having the advantage of the
respondent's design work. In the event, however, the quotation
8.
.
'arrived too late to enable him todo that. Schepis had no
understanding of the extent to which expertise is in truth
necessary in the selection and layout of irrigation equipment of
such a sophisticated kind as he desired. He seems to have been
willing to accept the risk that such a modestly experienced person
as Guest might prove incapable of supplying the requisite
technical knowledge.
Equipment supplied by the respondent arrived and was
installed, in important respects, under the supervision of Guest.
The only person with any real claim to relevant technical
experience who took part in the installation was an electrician
engaged by the applicants, one Gary Pruden. However, as Pruden
made clear i1nhis evidence, he also had to rely upon Guest's
supposed knowledge, having no experience of the kind which was
relevant to the specific task in hand.
The applicants intended to plant seedlings from about
the beginning of October 1984. They intended to have the system
operating before planting, but 1t arrived too late, for reasons
which do not require examination. Towards the end of October, the
system was put into operation, but the pipe joins started to part
under the water pressure. Remedial steps were taken on Guest's
advice, including the fitting of a "non-return valve", use of 45
degree joins instead of 90 degree joins, and bolting of the
unions.
At the end of November 1984, a critical part of the
system arrived, namely a pump having the function of injecting
9.
.
fertiliser into the systen. That was selected by Guest, but
erroneously so. Since it was clear to Guest that it could not be
installed on the discharge side of the main pump, he put it on the
suction side with results mentioned below; for present purposes,
1t is enough to note that the pump did not work properly. Even
before that, the plants were suffering from lack of water and
fertiliser.
The intention from the outset was, as I have mentioned,
that the system would be automatic. It was intended to supply
irrigation and fertilisation to different parts of the applicants'
cultivation by electrical controls, without the necessity of human
intervention. None of the persons who were engaged in the task of
establishing the system, however, had sufficient relevant
experience. As time went on, and the deficiencies of the system
continued, one would have expected Schepis to lose confidence in
Guest; for example, Schepis says in his evidence that the pipe at
the pump end of the system blew out several times during the
season, despite the fact that the unions had been bolted. The
evidence continued:
"Mr. Guest a inspected the system on a number of
occasions but could not explain why these blow-outs
were occurring."
Schepis' evidence was that at the end of 1984 he told
Guest that the system was constantly blocking and that the means
of clearing the filters (by reverse flush) did not appear to he
working. Schepis said, and I accept, that when the system was
examined on that occasion breakages and missing parts were
10.
discovered. Guest advised Schepis to put in a non-return valve,
and he took that and other measures.
Schepis also said, and I find, that the controller did
not automatically cause each section of the cultivation to he
fertilised at its appropriate rate, as was intended. Guest
suggested that time delay clocks be installed. That was done, but
they did not cure the problem.
About this time (December 1984), Guest left the
respondent's employ, having recommended to Schepis that he contact
Hardies Irrigation in Perth to seek a remedy for any problems he
encountered. In February 1985, during operation of the system,
part of it "blew to pieces" and Schepis complained to the
respondent, whose representative was then one Bachos. Having
consulted with Hardies and Bachos, by arrangement with the former
Schepis sent the injection pump, which was still not working
properly, to Hard1ies in Adelaide to be tested. He installed a new
pump in the meantime, which also did not work properly. There
were other difficulties, also, about that time, but in my opinion
1t must have become obvious before the end of the 1984/85 season,
that the system was seriously defective. If Schepis had ever had
the idea (as he apparently did) that Elders, through Guest or
otherwise, had been able to supply such a system as would fulfil
his requirements, he must have lost that illusion well before the
1985/86 season started. According to Schepis, the applicants
"could not afford outside consultants and had to rely on Elders
themselves for help".
ll.
He went on to say that between May and October 1985 he
contacted Bachos ona number of occasions to ask for help in
getting the system working. Bachos passed him on to a man called
Smith at Hardies who passed him on to a man called Chris. "Chris
was concerned but unfamiliar with the complexities of the system."
Thus, the respondent having made it clear enough that it could do
no more than pass the problem to its supplier Hardies, it was in
my view past time for the applicants to get expert assistance.
During the 1985/86 season, the system, at first, was
working as it had in the previous season - 1.e. very badly.
Ultimately Schepis contacted a person with the relevant expertise,
one Green, and the system was corrected and made to work properly.
However, that did not occur until January 1986, by which time much
damage had been done. During the 1985/86 season, prior to Green's
intervention, other ineffective remedial steps were tried, the
details of which it 1s unnecessary to recount. It should also be
mentioned that 1t 12S common ground that an insect, the "two
spotted-mite" attacked the crop in the 1985/86 season, However,
that 1s of no consequence because, in my opinion, the applicants
behaved unreasonably in failing to obtain advice from any
qualified person for such a long period of time, and Iam not
prepared to allow any losses in respect of the 1985/86 season. I
decline to do so, not on the basis of any general principle that
in such circumstances the time during which recovery is allowed
must be severely limited, but because of the particular
circumstances of this case. Of these, an important one is' that
Schepis was from the outset unwilling to pay for competent advice.
. 12.
Expert Evidence as to Defects of System
There was evidence from two people with sufficient
knowledge to analyse the deficiencies of the system. One was Mr,
J.D.S. Hill, an engineer, and the other an irrigation consultant,
Mr. P.E. Buck. The latter had no formal qualifications, but had
sufficient relevant experience to make his opinion of value.
Hill said that there were four things wrong with the
design: the metering pump was wrongly chosen, the filters were of
the wrong capacity, measures should have been taken to protect the
system against excessive pressure, and thicker pipes should have
been used in the higher pressure parts.
Of these deficiencies, 1n my view, the most serious was
the first. Hill explained that the suction effect of the main
pump (which, as I have explained, was mounted "downstream" from
the metering pump) was such that the metering pump had little
effect upon the course of events. The main pump had such strong
suction that it simply drew fertiliser straight through, whether
or not the metering pump was working. The result was that a basic
element of the system did not function. Instead of the flow of
fertiliser being elaborately controlled, the amount drawn into the
system depended upon random factors having nothing to do with the
crop's fertiliser requirements. As a result, sometimes too much
fertiliser was injected, and sometimes not enough. Only by chance
would the desired amount be introduced. I infer that Guest did
not have such understanding of the mechanism as to enable him to
make a proper choice of injector pump. The injector pump was in
' 13.
.
truth designed to be mounted on the other (positive pressure) side
of the main pump; Guest knew this.
As to the other three deficiencies, little need he
added. It should be pointed out, however, that the error made
with respect to filter selection appears to have been of an
elementary kind. The filters were designed to work with specified
minimum flow rates; the system produced a rate of flow well helow
them.
I gained the impression from Hill's evidence that no
extensive theoretical training is necessary to enable one properly
to design an irrigation system. In his opinion people who market
irrigation equipment generally have enough knowledge to calculate
pressures and flow-rates. That supports the applicants' case,
because it makes it seem reasonable for the applicants, in the
first instance, to have assumed that Guest might have, or at least
have ready access to, such information as was needed to permit a
proper selection of equipment. It does not follow, however, that
the applicants were entitled, when they knew that serious mistakes
in equipment selection must have been made, simply to bill their
losses to the respondent. Particularly is that so when the
respondent''s amateur design work had been free and the applicants
were aware that proper qualified advice was available. I do not
accept that the applicants were, at relevant times, unable to
expend the relatively modest sums necessary to engage people to
inform them what was wrong with the system. Schepis expended
monies in taking certain relatively ineffectual remedial steps, on
the advice of Hardies and in consultation with Pruden.
14.
Buck gave evidence that he has been a private irrigation
consultant for some years, and that his firm charged "some $400
odd per day inclusive". The most obvious deficiency, in his
opinion, was the insecure pipework. He agreed that the filters
were wrongly selected. In his view, apart from the correction of
the fertilising metering system (which had already occurred at the
date of his inspection), other upgrading steps were necessary to
achieve satisfactory operation and reliable performance. He
estimated their cost to be $6,000.
It should be added that Mr. Green, who was responsible
for correcting the fertiliser metering system, was not called, but
his report of 13 February 1986 was tendered. According to
Schepis, some months elapsed between his first request for Green's
help and Mr. Green's supplying 1t. I infer that Schepis did not
press him to come as a matter of urgency.
Conclusions as to Liability
To some extent, the deficiencies in the system were such
as cannot be attributed to any fault on the part of the
respondent. That particularly applies to electrical work done by
Mr. Pruden, who made no secret of his lack of understanding of the
operation of the components with which he had to deal. That,
however, is a matter to be taken into account in assessing the
damages. It is my opinion that the respondent is liable to the
applicants in respect of each of the three causes of action
pleaded - i.e. under s.52 of the Trade Practices Act, for breach
of contract and for negligence.
liable:
(i)
(ii)
(i121)
15.
To be more specific, I hold that the respondent is
Under s.52 of the Trade Practices Act, in that it
represented that it had the expertise and capacity to
design and supply an efficient system, but did not have
either, and in that it represented that the system
(consisting 1n the selected components) it supplied was
such as would meet the applicants' requirements, whereas it
was not of that description.
In contract, by virtue of the term implied under s.71(2) of
the Trade Practices Act in that the system was not
reasonably fit for the purpose (made known by the
applicants to the respondent) for which 1t was supplied.
In negligence, in that, having assumed a relevant duty of
care, it negligently failed properly to design the relevant
system.
I did not understand counsel for the respondent, in the
end, to submit that there was no liability; he confined himself to
a submission that there was no liability under the Trade Practices
Act, but made no such submission with respect to the allegation of
negligence.
It was contended on behalf of the applicants that in the
particular circumstances of the case, it did not matter whether
16.
damages were assessed in tort or in contract. Prima facie, in
suits brought under s.52 of the Trade Practices Act, the former
method is appropriate: Gates v. City Mutual Life Assurance
Society Ltd. 63 A.L.R. 600 at p.609. That involves an assessment
on the basis of a comparison between the applicant's financial
position had he never entered into the transaction, and his
position in fact. Here, it appears that I should start from the
assumption that if the applicants had not obtained the equipment
selected by the respondent, they would have obtained
properly-selected equipment which would have worked, and
fertilised the plants with reasonable efficiency. In contract, in
situations of this sort, the applicants are entitled to be put in
that position which they would have occupied had the breach never
occurred: Gates' case at p.607. It therefore appears to be
correct, aS was submitted, that the measure of damages, in the
particular circumstances of this case, 1s the same in tort as in
contract.
Quantum
It is necessary to introduce this subject by referring
further to expert evidence. A number of persons claiming relevant
biological knowledge were called, principally Messrs. Parnell,
Gratte and Hawson. There was also Mr. Burt from the Department of
Agriculture. His evidence concerned a theory advanced by the
respondent about a substance called Alar, which turned out not to
require examination.
17.
Mr. Parnell is a botanist, but has not a great deal of
experience relevant to tomato-growing on a commercial scale. I
derived assistance from his evidence, however, in the general
support he gave to the account given by Schepis of his
difficulties with the irrigation system. Gratte and Hawson are
both government advisers of considerable experience, particularly
with reference to vegetable-growing. Gratte saw the property only
in 1986, and for the reasons explained above, I am not prepared to
allow any damages in respect of that period. However, I have
taken Gratte's evidence into account as throwing light upon the
standard of management of the property; Gratte's opinion was' that
Schepis was a grower of only average ability. Hawson's evidence
suggested that the area in which the applicants' farm is located
1s not quite as surtable for tomato growing as land further north.
He emphasised the importance of climatic conditions in successful
tomato growing.
There was other evidence called, from Mr. H.G. Leitch
and Mr. L.J. Dickson, dealing with the "early blight" problem in
the 1986 year. It seems to me unnecessary to say anything on that
topic.
There was a considerable volume of evidence directed to
the question whether, and if so to what extent, the applicants'
losses might be attributed to causes other than the breaches on
behalf of the respondent. It is necessary to mention some of the
more important of them.
. 18.
Schepis admitted that his spraying of his plants to
discourage diseases would have been more effective if he had had
what are called "droppers" fitted to his spray boom. However, in
my opinion, that deficiency is not shown to have had any
significant effect upon his output in the 1984/85 season. A more
important additional cause of the applicants' difficulties,
admitted to by Schepis, was the delay in supply of the irrigation
system, referred to above. It is my view that part of the
applicants' loss is attributable to that cause. Mr. Ainslie, for
the respondent, argued that as to the delay and in other respects,
the applicants' case was left too vague to enable a_ sufficiently
accurate assessment of damages to be made. I do not agree; there
1s no possibility of apportioning the loss among the various
causes in an arithmetical way: cf. the remarks of Gibbs J., as
his Honour then was, in Ted Brown Quarries Pty. Ltd. v. General
Quarries (Gilston) Pty. Ltd. (1977) 16 A.L.R. 23 at p.37.
Next, in my view, Schepis failed to take Guest's advice
that the main pipe should be buried. That contributed to some of
the failures which occurred. The expert evidence shows that the
whole system is insecure. Mr. Ainslie argued that the principal
problem could have been overcome 1f Schepis had taken Guest's
advice to fit a non-return valve, a solution which was ultimately
adopted.
I am satisfied that there was some fault on the part of
Schepis which contributed to parting of joins and bursting of
components. However, it seems to me clear that the principal
fault was in design, or to be more specific, in specification of
' 19.
items of equipment and that may properly be laid at the door of
the respondent. Although parting of joins and other hreakages
caused interruptions in watering and fertilisation, in my opinion
the main problem was that the fertilisation system installed
simply did not work, for the reasons mentioned above.
Next, Schepis admits that there were blockages in the
system fairly early, and in my opinion (although the evidence is
not all one way on this point) 1t is likely that they were largely
due to accumulation of iron oxide in the area of the fine outlets.
Guest, rightly, suggested that a water sample be taken. The
problem was correctable and ultimately corrected; no fault is
attributable to the respondent in respect of these blockages.
Schepis admits, in effect, that he was at fault in
failing to supply a 200 litre tank from which the fertiliser was
to be pumped. However, there is not reason to think that that
fa1rlure caused any significant loss.
Next, there is evidence that suggests that a problem
contributing to the losses was that Schepis overtaxed the water
supply. It is my view that he did not do so, and I accept that
there was plenty of water.
I now turn to the details of the damages claimed. The
principal item is the loss in respect of the 1985/86 season which
I have totally excluded. In respect of the 1984/85 season, the
applicants claim a loss of $59,737.52.
20.
The calculation 1S criticised on a number of grounds.
It is said that there were probably some cash sales of tomatoes
which were unrecorded. I am satisfied that that is so, but think
them likely to have been small in amount.
More importantly, Mr. Ainslie argues that a considerable
reduction must be made to allow for causes in respect of which the
respondent has no legal responsibility, and in particular, the
delay in supply of the system. It appears to me that those causes
can only be taken into account in a broad way. I am quite
satisfied that the principal cause of the loss was the most
obvious one, namely that the fertiliser supply system did not
work.
The next level of dispute about the claim for loss 1s
that according to the respondent's case the "gross anticipated
income" claimed 1s much too high. That submission relied largely
upon the evidence of Mr. F.R. Schoonens, an agronomist employed by
the respondent. In my opinion, although there 1s nothing wrong
with Mr. Schoonens' arithmetic, there 1s no justification in the
evidence for the assumptions on which the calculations are based.
I am satisfied that the mode of calculation presented on behalf of
the applicants in exhibit 6 1s basically correct, subject to one
qualification, namely that 1t is necessary to take into account
additional packaging and labour costs, for the reasons set out in
the report of Horwath and Horwath dated 17 October 1986. The sum
in question in respect of the 1984/85 season is $3,631.28 and the
necessity for that adjustment is conceded by the applicants.
21.
In my view, a reasonable estimate of the quantum of the
applicants' losses as a result of the breaches on the part of the
respondent which I have found in respect of the 1984/85 season is
$40,000. To that must be added the costs of repairs and
modification which do not appear to be challenged, namely $2,589.
There was discussion at the hearing as to the impact of
taxation upon these losses. It was conceded that as to lost
income no adjustment should be made on account of taxation.
Counsel for the respondent contended, however, that some
adjustment is necessary in respect of the tax advantage (by way of
allowable deductions) accruing on account of expenditure on
repairs and modifications. In the circumstances of this case, it
seems to me that no such adjustment should be made.
Interest
That leaves for consideration aclairm for interest.
Although the amount involved in the interest claim is not very
large, the legal point 1s one of some difficulty. The primary
foundation on which the claim was put was s.32 of the Western
Australian Supreme Court Act 1935-1979, which need not be set out
in full; it is so framed as to permit an award of interest up to
judgment in actions of this sort brought in the Western Australian
Supreme Court. The section, however, applies to "the Court" which
is defined as meaning the Supreme Court of Western Australia, s0
that prima facie the section is not available in these
proceedings.
22.
Under s.32(3) of the same Act, the right to recover
interest applies to proceedings in a Local Court except where the
sum for which judgment is given does not exceed $750. Under s.34
of the same Act:
"The several rules of law enacted and declared by
this Act, shall be in force and take effect 1n all
courts whatsoever in Western Australia so far as
the matters to which such rules were laid shall be
respectively cognisable by such courts."
It therefore appears that (subject to a limitation where
there are proceedings in the Local Court and the judgment does not
exceed $750) the power to award such interest as I have mentioned
is a general one applying to Western Australian courts.
It appears to me that in the end the problem 1s the same
as that dealt with in Neilsen v. Hempston Holdings Pty. Ltd. 65
A.L.R. 302 at pp.311, 312. I there discussed a similar Queensland
provision applicable to Courts generally in Queensland. Counsel
referred me to the reasons of the Full Court in Centrepoint
Freeholds Ptv. Ltd. v. T.N. Lucas Pty. Ltd. (1985) 60 A.L.R. 187
at p.198-9 suggesting that the question depends on whether the
State statute uses expressions wide enough to apply to the Federal
Court. Although I accept the authority of the Centrepoint
Freeholds case as to its result, I do not, with respect, agree
that the question depends on whether the State statute giving
power to award interest uses language wide enough to apply to this
Court. When such statutes speak of "all courts" they mean all
State courts. In State Bank of New South Wales v. Commonwealth
Savings Bank of Australia (1986) 67 A.L.R. 123, a similar problem
* 23.
was approached on the basis that the question is whether the State
law is one "relating to procedure" within the meaning of s.79 of
the Judiciary Act.
I adhere generally to the view I expressed in Neilsen v.
Hempston Holdings Pty. Ltd. (above) at pp.311 and 312:
"State statutes picked up by s.79, especially those
relating to 'procedure, evidence and the competency
of witnesses', must be so drawn as to apply to
State courts only and when s.79 makes such statutes
binding on 'all courts exercising Federal
jurisdiction in that State ...' it must mean to
make them binding as if they referred to the latter
category of courts."
The minor reservation I have is that the expression
"must be so drawn" overstates the matter; typically such State
statutes will be so drawn as to apply expressly to State courts
only, but some such statutes do not mention courts at all. But
even where they do not, they set out to regulate procedure in
State courts only. It 1s s.79 of the Judiciary Act which makes
them applicable here, and where the State law (whether procedural
or otherwise) applies to State courts generally, s.79 appears to
require that it be treated as binding in proceedings in this
Court.
I am, therefore, of the view that interest 1s allowable
and will allow an additional sum of $8,400 (being at the rate of
12%) under this heading.
There will be judgment for the applicants, rounded off
° 24.
to $51,000. Costs will be reserved for further consideration.
{ certify that this and the 23 preceding
pages are a true cory of tho reasons for
judgment herein of His Honour
Mr, Justice Pincus pest Lygone
Associate
Dated 24 cece. ben 1986