Gartenmann Ceiling Systems Australia Pty Ltd & Anor v Pollution Control Engineering Pty Ltd & Ors [1987] FCA 744
Federal Court of Australia
Full text
Select any passage to save a personal note with optional tags.
*
FOR LIMITED DISTRIBUTION
SUDOMENT No. TAS Sin
IN THE FEDERAL COURT OF AUSTRALIA)
)
NEW SOUTH WALES DISTRICT REGISTRY)
)
GENERAL DIVISION ) No. G180 of 1985
BETWEEN: GARTENMANN CEILING SYSTEMS
AUSTRALIA PTY. LIMITED
First Applicant
DRAUGHT INDUSTRIES PTY. LIMITED
Second Applicant
AND: POLLUTION CONTROL ENGINEERING
PTY. LIMITED
First Respondent
PETER KINGSLEY BONSER
Second Respondent
GRAEME JOHN NEALE
Third Respondent
POLLUTION CONTROL ENGINEERING
PTY. LIMITED
Cross-Claimant
GARTENMANN CEILING SYSTEMS
AUSTRALIA PTY. LIMITED
Cross—-Respondent
CORAM: GUMMOW J. - \A
DATE: 23 DECEMBER 1987 so ON
PLACE: SYDNEY oo coe E
1! ~. on ~
REASONS FOR JUDGMENT Tm a ~
o\ Fedhis . COURT OR * "t
~ A, TAWA a
INTRODUCTION LPP ee
IT von
The dispute between the parties concerns the efficacy
of a conveyorised powder coating plant for metal ceiling tiles,
used primarily in office and like premises. The plant was
manufactured, designed and supplied by the first respondent
("Pollution Control") for use upon the premises of the first
applicant (""Gartenmann") at Tomago, Newcastle. The plant
became "operational" in the last week of August 1983. The
applicants seek damages. They base their claims in contract
(including collateral contract), tort (negligence, "negligent
misrepresentation", and deceit) and also claim for
contraventions of ss.52 and 53 (c) of the Trade Practices Act
1974 ("the TP Act"). Despite the array of causes of action,
the parties were, in the end, not seriously at issue as to
matters of law. However, they were at serious issue upon a
number of issues of fact. Once those issues are resolved, the
questions of legal liability will fairly readily be answered.
The principal heads of complaint concern alleged
deficiencies or short-comings in production rate, production
cost (though these are inter-related) and in quality of the
paint-finish and gloss level of the tiles produced from the
plant. In May 1984, two additional powder guns were added to
the automatic powder booth and in May 1985, new reciprocators
were installed in the same booth. The meaning of these terms
will shortly appear. What is of immediate significance is the
applicants' view, expressed in oral evidence, that, following
these changes, the plant began to produce a finished product
which has been, generally speaking, of acceptable quality,
although complaint still is made of production rate and cost.
The applicants assert that in respect of the
complaints made by them, the respondents are liable first by
reason of misstatements allegedy made as to the quality and
characteristics of the plant to be supplied by Pollution
Control. These misstatements are said to give rise to claims
for contravention of the TP Act, collateral contract, contract,
negligent misrepresentation and deceit. Further, it is alleged
that the respondents are liable because there was failure to
exercise in a number of respects reasonable care and skill in
the design of the plant, in breach of contract and of a duty of
care in tort.
I deal first with the alleged misstatements and the
evidence relating thereto. In the Statement of Claim, they
are expressed variously, to reflect the differing legal bases
on which they are put. However, they reflect the same factual
disputes and may be summarized as being complaints that,
contrary to what was represented or contracted for, the powder
coating plant:
(a) was not capable of regularly pre-treating and
powder-coating more than 800-900 metal ceiling
tiles of the type used by Gartenmann in its
business during the course of any normal
eight-hour shift operated by the said business,
and, in particular, was not capable of pre-
treating and powder-coating 3,000 such tiles per
eight-hour shift;
(b) could not pre-treat and powder-coat each such
metal ceiling tile at a cost which, when added to
the cost of manufacturing the uncoated tile, was
equal to or less than the cost of manufacturing a
metal ceiling tile from "Colorbond"" steel;
(c) could not pre-treat and powder-coat each such
metal ceiling tile, at a cost which was any less
than approximately $1.10 per tile, and, in
particular, could not do so at a cost of
approximately $0.26 per tile;
(d) could not produce a metal ceiling tile which was
even in colour and degree of gloss and
suitable for use in the construction of ceilings;
(e) was not capable of pre-treating and
powder-coating the metal extrusions used in the
suspension of metal ceiling tiles;
(£) did not comply in all respects with all relevant
health and safety legislation and regulations and
industrial standards. .
No case in respect of ground (f) was made at the
hearing. In respect of ground (b), Mr. Bonser (the second
respondent) did not know of the cost of manufacturing from
Colorbond at any material time and there is no other evidence
that the cost was made known to the respondents. Ground (b)
thus was not substantiated. For ground (a), the applicants
rely upon oral statements and upon the terms of the written
addenda to what I later describe as "the proposal". For the
$0.26 cost in ground (c}), reliance is placed on the addenda.
Colour variation and gloss (ground (d)) is addressed
specifically in the oral evidence. The final complaint, ground
(e), is directed to the longest aluminum extrusion used in the
framework that supports ceiling tiles when in place. Reliance
here is placed upon the proposal when read in surrounding
circumstances.
THE BUSINESS OF GARTENMANN
Gartenmann has carried on, since about 1973, the
business of the manufacture and distribution of painted metal
ceiling tiles. The company is managed by Mr. Paul Crockett and is
one of a group of three family companies operated by the Crockett
family. Another of them, J.A. Crockett Pty. Ltd., is managed by
Mr. Phillip A. Crockett (Mr. Paul Crockett's brother) and carries
on the business of installing ceilings on contract. Draught
Industries Pty. Ltd. ("Draught"), the second applicant, is a
wholly owned subsidiary of Gartenmann and is the present operator
of the powder coating plant in contention in these proceedings.
This followed a transfer from Gartenmann with effect from
September 1983. The shareholding in the companies is divided
equally between Mr. Paul Crockett, Mr. Phillip Crockett and
their mother, Mrs. Lorna Crockett. Mrs. Crockett inherited her
shares following the death of her husband, Mr. Arthur Crockett,
in 1982. Mrs. Crockett plays no active part in any of the
businesses. Mr. Paul and Mr. Phillip Crockett have been the only
directors of the family companies since the death of Mr. Arthur
Crockett. The major role in the events with which this case is
concerned was played by Mr. Paul Crockett and I shall refer to
him simply as Mr. Crockett.
In order to comprehend the nature of the complaints made
by the applicants, it is necessary briefly to describe the
operation of the powder coating plant.
The unpainted ceiling tiles are manufactured in a
separate operation. They are then brought across to the powder
coating section of the factory. There is a range of ceiling tile
sizes, but the most frequently used is the perforated 1200mm x
300mm tile ("the standard tile"). The unpainted tiles are
loaded onto a conveyor and are suspended by "jigs". Jigs are
metal hooks which attach the product to the conveyor; they also
serve the important purpose of earthing the product and for this
purpose must be kept sufficiently clean at the point of contact
with the tile.
After loading onto the conveyor, the metal tiles are
"pre-treated". In this case, two possible methods of
pre-treatment are involved. The proposal put to Gartenmann by
Pollution Control posed as alternatives trichlorethylene and
phosphate pre-treatment. Gartenmann chose the recommended (and
more expensive) phosphate method. Pre-treatment involves first
the spraying of the tile with heated chemicals and then the
passage of the tile through a heated fresh water rinse cycle
within the pre-treatment plant. Heat is provided by means of two
gas burners. The pre-treatment process cleans the tile and
readies it for powder-coating. It is vital to the powder coating
process that the metal be clean and, in particular, free from oil
or grease which may have been applied to the metal to inhibit
rust.
The wet, pre-treated tile then passes through a dry-off
oven; powder cannot be applied to a wet product. Further, the
tiles have turned up edges and water tends to accumulate in the
corners of these edges after the tile has been rinsed in the
pre-treatment plant. Hence, the particular importance of the
dry-off oven.
After the dry-off stage, the tile is ready for the
application of powder. Powders are of two kinds, polyester and
epoxy. Epoxy powder is required for a low gloss finish, as was
needed for the ceiling tiles produced by Gartenmann. The powders
are supplied in white and various colours. The plant as
designed has two powder booths on line, one in which powder is
applied by automatic use of "powder guns", the other in which an
Operator applies the powder by manual use of the powder guns.
In the automatic booth, the powder is applied by means of a
"reciprocator" which moves the powder guns vertically over a
measured distance and at an adjustable rate. Powder can also be
applied by a human spraying the tiles as they pass by on the
conveyor. Powder which has not adhered to the tiles is filtered
from the air and retained for re-use, mixed with "virgin" powder.
The powder is positively charged as it is emitted from the nozzle
of the gun. In this way, the powder is electrostatically
attracted to the metal tile earthed via the jig and conveyor.
The tile next passes through the infra-red cure oven.
The cure oven consists of reflective panels and infra-red lamps.
The heat is radiated in this way, reflected rather than conveyed
by the more conventional convection method used in gas and oil
fired ovens. These rely upon the ascension of heated air. The
cure time and temperature are quite critical; this is especially
so with the epoxy powders used by Gartenmann. Cure time is
controlled by the speed of the conveyor, and the application of
heat. This is adjustable by varying the amount of current
passing through the lamps.
The oven is divided into three zones further to
facilitate heat adjustment. Accordingly, it should be possible
to achieve an acceptable cure by either or both altering the
conveyor speed and the current passing through the lamps. There
are limits to the amount of heat that can be applied to the
powder without scorching it or "over-baking" it. Therefore,
there is a point at which it becomes impossible to increase the
heat output of the oven and the line speed and still achieve a
satisfactory cure. From a production point of view, it is
obvious that a faster conveyor speed means increased production
and reduced running costs.
After emerging from the cure-oven, the coated tile is
manually removed from the jig at the point of loading. It may
then be distributed without any further processing.
THE FACTS
Before August 1983, Gartenmann ceiling tiles had been
manufactured by use of Lysaght's "Colorbond", a pre-painted sheet
metal from which the ceiling tiles were worked into the desired
shape by Gartenmann. As the Colorbond sheet metal had to be cut,
it suffered corrosion problems. Mr. Crockett was also
dissatisfied with the consistency of the paint finish applied to
Colorbond and its continuity of supply. Colour variation is
particularly critical as it may be barely perceptible until the
ceiling tiles are installed. It 18 at that time that colour
variation becomes particularly noticeable.
It was in this state of dissatisfaction with existing
procedures and materials that Mr. Crockett looked for something
better.
In September or October 1982 Mr. Crockett read some
brochures issued by Wagner Spraytech Australia Pty. Ltd.
("Wagner") concerning the ""powder-coating"" process. Mr.
Crockett contacted Wagner on about 9 November 1982 and was
referred, by Mr. Geoff. Cuthbert, to Mr. Peter Clink, the New
South Wales agent for Pollution Control.
The two principals of Pollution Control were Mr. Bonser
(the second respondent) and Mr. Neale (the third respondent).
Mr. Bonser had considerable experience in "infra-red technology"
and by 1983 had been involved in the design and installation
of about one hundred ovens. He had worked for Fostoria-Fannon
(Aust.) Pty. Ltd. for about ten years up to 1979, and in that
time had been concerned with the installation and commissioning
of the first "hot melt" conveyorised powder coating system in
Australia. Mr. Neale's expertise was directed more to powder
spraying and dust and fume control equipment. In 1971, he had
taken part in the design and supply of the first successful
installation in victoria of a powder recovery system. He and Mr.
Bonser regarded their skills as complementary.
A meeting was arranged between Mr. Crockett and Mr.
Peter Clink at the offices of J.A. Crockett Pty. Ltd. in
Newcastle. Mr. Crockett remembers nothing of this meeting though
he does not dispute that it occurred. Mr. Crockett's brother,
Mr. Phillip Crockett, recalls the meeting taking place. Mr.
Clink also recalls the meeting. At this meeting, information was
collated by Mr. Clink concerning Mr. Crockett's envisaged
production requirements and the dimensions of the Gartenmann
product. Mr. Clink used a standard form of Pollution Control
entitled "Request for Proposal-Data Sheet". At that meeting,
arrangements were made for a demonstration for Mr. Crockett at
the premises of Robert Mandl Pty. Ltd., ("Mandi"), at Matraville,
a Sydney suburb. A powder coating plant designed by Pollution
Control was in operation there. The purpose of this meeting was
also to introduce Mr. Crockett to Mr Bonser, to discuss the
powder coating process and to decide if he wished to continue
further with his enquiries.
The meeting at the Mandl plant took place on 11 November
10.
1982. In attendance were Mr. Crockett, Mr. Peter Bonser, Mr.
Peter Clink, Mr. Dermot Hatfield (a representative from Robert
Bryce & Co. Ltd., a powder supplier) and Mr. Tom Boal of Wagner.
Mr. Crockett had with him samples of his standard sized ceiling
tiles and Mr. Bonser was given by Mr. Clink the "Request for
Proposal-Data Sheet" setting out the information gleaned by Mr.
Clink from the meeting with Mr. Crockett. Mr. Neale was not
present on this occasion.
At the Mandl plant, Mr. Crockett's sample tiles were
suspended from a conveyor and were coated with powder which was
applied by a person spraying the tiles in a manner intended to
simulate the operation of an automatic spray gun. This was done
several times and after each application of powder the tile was
"blown off" and the powder re-applied until the parties were
satisfied that powder had been uniformly applied to the tiles.
The tiles were suspended back to back on the conveyor; an
important objective of the tests was to establish the feasibility
of coating the tiles in this manner. It was envisaged that the
tiles would pass by two guns, each mounted on a reciprocator on
either side of the conveyor. The concern was whether this
configuration would allow sufficient powder to "wrap around" the
tiles and "dust coat" the rear of the ceiling tile sufficient to
inhibit corrosion, the face side of the tile being the critical
area of finish. The conveyor speed at the tests was 1.5 metres
per minute.
The coated tiles were passed through the cure oven and
the results were then examined. There is no evidence of
complaint or concern as to evenness of colour. However, there is
some considerable conflict in the evidence as to Mr. Crockett's
li.
reaction to the gloss level of the finished product. Mr.
Crockett recalls asking Mr. Bonser whether a lower gloss level
could be achieved as Gartenmann ceiling tiles had to be in a low
gloss finish. Mr. Crockett recollects Mr. Bonser telling him
that "this would not be a problem". On the other hand, Mr.
Bonser recollects Mr. Crockett's reaction as being one of general
satisfaction with the finished product. He does not
specifically recall Mr. Crockett's alleged concern with respect
to gloss. However, Mr. Clink does recall Mr. Crockett
mentioning gloss levels. I accept that this matter was raised
with Mr. Bonser and that Mr. Crockett stressed, and Mr. Bonser
accepted, the importance to him of a low gloss finish. The level
of gloss is dependent upon the particular powder used and Mr.
Bonser was aware that a low gloss finish was required.
Mr. Crockett indicated that he was "interested" in the
plant. After the tests were completed, Mr. Bonser, Mr.
Crockett, Mr. Clink and Mr. Boal of Wagner went to lunch for
further discussions.
It is at this lunch on 11 November 1982 that Mr.
Crockett alleges various matters were discussed concerning the
performance of the proposed plant. In particular, Mr. Crockett
gave evidence that on this occasion he told Mr. Bonser that he
required a minimum production capacity of 2,000 tiles per eight
hour shift, on the basis that Gartenmann currently manufactured
about 1,000 tiles per eight hour shift. However, as I have
indicated, what the applicants pleaded was an oral representation
as to 3,000 tiles (Amended Statement of Claim, paras. 11 (a) (and
particulars (i) (A)), and paras. 18, 25, 29, 38 (and particulars
(iii)). Mr. Crockett also gave evidence that he said to Mr.
12.
Bonser that the cost of painting each tile must be near the cost
of using Colorbond. However, as I have earlier stated, Mr.
Bonser was not told the actual cost of Colorbond. Importantly,
Mr. Crockett says he told Mr. Bonser that he had a project budget
of $125,000 and Mr. Bonser replied that "we should be able to do
it for that". Mr. Crockett also recalls Mr. Bonser saying that
"you will be pleased with the finish".
Mr. Bonser recalls discussion concerning the
pre-treatment of extrusions, aspects of infra-red heating, a
project budget of $100,000, and problems with Colorbond with
respect to supply and colour variations. I have already found
that at the Mandl plant, Mr. Crockett had stressed and Mr. Bonser
had accepted the importance to Mr. Crockett of a low gloss
finish. However, Mr. Bonser emphatically denies any mention of
projected output, stating that at such an early stage it would
have been impossible for him to give such a forecast; in any
event, Mr. Bonser states that he is very careful not to discuss
projected output in preliminary discussions of this type.
In assessing the various versions of what was said at
this lunch, on 11 November 1982, it must be recalled that Mr.
Crockett had no independent recollection of a meeting with Mr.
Clink two days earlier at the premises of J.A. Crockett Pty.
Ltd.; this circumstance tends against acceptance that he had
the strong recollection for which he contended of particular
matters discussed at this lunch. Mr. Clink, in his evidence,
denied any mention of 2,000 tiles per shift; he did recall the
figure of 158 units per hour being raised (i.e. 1264 units per 8
hour shift) and a projected figure of 830,000 units per annum,
These matters had been recorded by him on the Request for
13.
Proposal-Data Sheet at the Newcastle meeting, two days earlier.
Most of the matters that Mr. Bonser recalls as being discussed
at the lunch were matters of peculiar interest to him, such as
infra-red ovens, and are matters that he believes he would
probably have discussed in those circumstances.
Both Mr. Crockett and Mr. Bonser recall Mr. Crockett
asking for firm figures in the form of a quotation. A detailed
quotation was provided to Mr. Crockett and it is the only
contemporary record that purports to embody matters agreed upon
at this meeting. There is no mention in the body of the proposal
of the figure 2,000 tiles per shift, although in the addenda
there is a reference to 3,000 tiles. However, the significance
of that figure of 3,000 tiles was a matter of much debate at the
trial.
In the circumstances I have described, I conclude that
that figure of 2,000 tiles per shift was not put to Mr. Bonser on
11 November. I find that Mr. Bonser did not represent that the
plant was to be capable of pre-treating and powder coating 3,000
ceiling tiles in a normal eight hour shift, as pleaded by the
applicants.
It will be recalled that Mr. Tom Boal of Wagner (the
powder application equipment suppliers) was present on 11
November at the Mandl plant tests. On 22 November 1982, Mr.
Boal sent to Mr. Bonser a quotation for the supply of three
powder guns and two reciprocators. As I have indicated, the
reciprocators are devices that move the spray guns in a vertical
pattern in the automatic booth of the plant. Mr. Boal had
assessed the needs of the plant on the basis of the Mandl test
and in his letter to Mr. Bonser he recommended as follows:
14.
"We are pleased to confirm herewith our recommendation
for the application equipment to powder coat perforated
ceiling tiles for Gartenmann Ceiling Systems Australia
Pty. Ltd. at the conveyor speed used in the trials at
the Robert Mandl plant on 11 November 1982.
We consider that two automatic guns on reciprocators
would be required with a single manual gun for touch up
purposes..."
This is an important matter, as the applicants allege
this configuration proved to be inadequate. The guns and
reciprocators are referred to in the proposal as being "prime
cost" items. Mr. Crockett understood a "prime cost" item to be
(and his understanding is not disputed) a separate item that is
"bought outside" as a necessary extra, the price of which, though
quoted, is subject to variation. Mr. Boal's recommendations
were made on the basis of the Mandl plant line speed which was
1.5 metres per minute. Pollution Control was to receive from
Wagner an unequivocal performance guarantee covering the powder
application equipment which became prime cost items in the
Gartenmann plant.
On 22 November 1982, Mr. Bonser telephoned Mr. Crockett
and advised him that the written submission was almost ready. On
26 November, Mr. Bonser telephoned Mr. Crockett and informed him
that the "final figures" for the plant were $89,825 for a
trichlorethylene pre-treatment plant or, alternatively, a
phosphate pre-treatment system could be provided. In that event
the cost of the plant would be $126,191. Mr. Crockett agrees
that in these telephone calls, no mention was made of quality of
the finished product, nor the quantity to be produced.
Following these discussions, a few days later Mr.
Crockett received in the mail a document entitled "Gartenmann
Ceiling System Australia Pty. Ltd. Proposal for the Design,
15.
Manufacture and Commissioning of Powder Coating Plant... ."
("the proposal"). The proposal is dated 29 November 1982. With
specification and addenda, it is a document of some twenty five
pages. It specifies that mechanical and electrical installation
is work not included.
Mr. Crockett relies upon various matters set out in the
proposal as being instances of misleading or deceptive conduct
and alternatively as warranties, concerning the performance of
the plant with respect to production output and price, on a per
tile basis of applying the coating. In particular, Mr Crockett
points to the figures of 3,000 tiles per shift and 26 cents per
tile referred to in the addenda to the proposal. Gartenmann also
alleges that the document warrants that long extrusions could be
pre-treated and processed through the plant, whereas the cheaper
option of the trichlorethylene plant did not have this
capability. I will return further to consider the text of the
proposal.
Following the receipt by Mr. Crockett of the proposal,
telephone conversations took place between Mr. Crockett and Mr.
Bonser on 14 and 15 December 1982. Arrangements were made for
Mr. Crockett, his brother Mr. Phillip Crockett and Mr. Warren
Bale, the proposed plant supervisor, to visit the offices of the
respondents in Bayswater, Melbourne and to inspect other
Pollution Control designed plants in operation at the factories
of other clients. The meeting tock place on 17 December. Mr.
Bonser met the parties at the airport and they then went to the
Pollution Control office in Bayswater. A meeting took place
between those parties and Mr. Neale, the third Respondent. On
Mr. Crockett's evidence, nothing of significance was discussed.
16.
Mr. Bonser then took Mr. Crockett, Mr. Phillip Crockett and Mr.
Bale on an inspection of three other powder coating plants in
operation at the plants of other clients of Pollution Control.
Following this inspection, the parties met up again with Mr.
Neale at a "hotel-restaurant" in the Bayswater area and had
lunch.
Both Mr. Phillip Crockett and Mr. Paul Crockett in their
evidence state that over this lunch statements were made
concerning the quality of the finish to be provided and the
projected output of the plant. With respect to the quality of
the finish, both Mr. Paul and Mr. Phillip Crockett recall
statements being made to them concerning the ability of the plant
to provide an even colour and gloss coating to the tiles. Mr.
Paul Crockett recollects Mr. Bonser saying that Pollution Control
were the leaders in infra-red technology in Australia and
Gartenmann were not going to have any complaints about colour or
gloss. Mr. Phillip Crockett recollects Mr. Bonser using words
in an immaterially different form. Both the Crocketts recollect
some annoyance on Mr. Bonser's part at this matter being raised.
Mr. Bonser denies having spoken in this way, although he
recollects that the problem of colour variation was discussed.
Mr. Neale does not recall any discussion of colour variation and
gloss problems. Mr. Bale did not give evidence. I accept that
words to the effect stated above were used by Mr. Bonser.
With respect to the capacity of the plant to coat tiles,
Mr. Paul Crockett recollects referring to the proposal and saying
to Messrs Bonser and Neale words to the effect:
"Wwe asked for 2,000 tiles per shift and you are giving
us 3,000."
Mr. Neale is alleged by Mr. Paul Crockett to have replied to the
17.
effect:
"When it came to working out the speeds and doing the
calculations it came to 3,000 tiles per shift."
Mr. Paul Crockett recollects nothing further of significance
being discussed over lunch.
Mr. Phillip Crockett's recollection of the alleged
discussion concerning production rate is to be contrasted with
his brother's recollection. Mr. Phillip Crockett recollects Mr
Bonser (not Mr. Neale) proffering the figure of 3,000 tiles per
shift, with Mr. Neale cautioning Mr. Bonser not to be "too quick
in coming forward with those kinds of figures".
Mr Bonser in his evidence does not recollect any
discussions concerning the' production rates or the estimate of
3,000 units per shift referred to in the addenda to the proposal.
Mr. Neale denies that there was any mention of production rates
during the lunch. He strongly denies that any minimum
requirement of 2,000 tiles per shift was ever mentioned to him.
In these circumstances, I find that there was no
statement made (to the effect of that pleaded by the applicants)
as to production at the rate of 3,000 tiles per shift. I also am
not satisfied that a figure of 2,000 minimum production was
propounded by either Mr. Bonser or Mr. Neale. There may have
been some mention by one or both of the Crocketts of production
rate in a general sense, but I am not satisfied that any such
discussion had the specificity asserted by the Crocketts for
their case on ground (a), as I earlier have described it. of
course, the Crocketts differed in their recollection of events
and, given the lapse of time and the social nature of the
occasion in question, this is not surprising.
18.
As I have said, I find that in conversation over lunch
on 17 December 1982, the importance of evenness of colour was
stressed to and accepted by Mr. Bonser. I have also found that
on this occasion the importance of a low gloss was again stressed
to and accepted by Mr. Bonser (as it had been on 11 November, was
shortly to be stressed again by Mr. Rees and was further to be
stressed by Mr. Crockett on 9 February 1983). The legal
significance of what was said on these occasions, is, of course,
another matter, bearing particularly in mind that the
representation pleaded was that the plant would give each tile a
finish which was even in colour and degree of gloss. I find that
no representation in the terms pleaded was made. I deal further
with this topic under the heading "Gloss and Colour".
In reaching these conclusions, I have been assisted by
the demeanour of the witnesses and the manner in which they
recalled events. If on one issue one witness 1s preferred to
another, and conversely on other issues, this is not the result
of an adverse finding on credit. The point is that in all the
circumstances, I prefer the strength of the recollection of
different witnesses on different questions.
I return to the narrative of events. Following the
lunch on 17 December 1982, the parties returned to the Bayswater
offices and were met there by Mr. Howard Rees and Mr. Ian Rose;
both men were employees of Robert Bryce & Co., powder suppliers.
Mr. Rees gave evidence at the hearing, which I accept. Mr. Rees
had had a clear recollection and impressed me. He had dealt with
Mr. Bonser since 1970 and the two men were well known to each
other. Mr. Crockett also had had telephone conversations with
Mr. Rees prior to meeting him in Melbourne.
19,
Mr. Rees warned the Crocketts that powder coating
ceiling tiles was a very difficult operation as the requirement
of uniformity in colour was critical. Mr. Rees then told the
Crocketts about a customer who powder coated ceiling tiles and
had "a hell of a lot of trouble". Mr. Rees told the Crocketts
that because they sought a low gloss finish, they must use epoxy
powder which has a comparatively narrow "thermal latitude".
This is the degree of temperature variation within which a
satisfactory cure could be achieved. Mr. Rees recalls Mr. Paul
Crockett mentioning that "one of the most important features of
his plant was going to be colour consistency and gloss". Mr.
Rees warned Mr. Crockett that epoxy powder was prone to overbake
if the infra-red cure oven was not correctly monitored. Mr.
Rees gave evidence that at this point Mr. Bonser became excited
and told Rees to "mind his own business and that the design and
performance of the oven was a matter of his own expertise". Mr.
Rees indicated a preference for convection ovens in conjunction
with epoxy powders though he did say in cross-examination that
infra-red ovens were best suited to flat "two dimensional"
products and that at the relevant time the majority of plants
utilized infra-red ovens. Mr. Rees summed up the dilemma of oven
choice as follows:
"There is nothing perfect in these industrial systems.
If you choose an epoxy powder and you choose it by
reason of a requirement of low gloss, then the one thing
that must be examined is the overbake resistance of the
coating. This is the resistance of the coating to
withstand changes in oven conditions and epoxy powders
have a poor history of resistance to overbake
conditions. They will change colour, particularly if we
are talking of pastel colours. Now, polyesters are more
overbake resistant but, of course, they cannot be
produced with a consistently reproduceable low gloss.
The chemical resistance of both coatings is about the
same. The application conditions probably favour
polyester."
20.
Mr. Bonser, Mr. Neale and Mr. Clink visited Newcastle on
9 February 1983 to obtain from Mr. Crockett the written purchase
order for the plant and a deposit. The purchase order
identified the proposal but went on to specify three further
design requirements. On that occasion, Mr. Crockett gave a
practical demonstration of the problem of colour variation in
ceiling tiles by placing two tiles in a ceiling and pointing out
colour variations that only then, with installation, became
apparent to the eye. I find that again on this occasion, Mr.
Crockett stressed the importance of consistency of colour and low
gloss. The price was $129,973 and a "deposit" of $20,584 was
paid with the order.
On 22 February 1983, Mr. Bonser wrote to Mr. Crockett
enclosing an energy schedule for the powder coating plant and
informing him that an "Order Confirmation" with revised
specifications and all drawings including the final plant layout
would be forwarded shortly.
On or about 2 March 1983, after the proposal had been
accepted by Mr. Crockett and a deposit paid, Mr. Crockett had a
telephone conversation with Mr. Rees. Mr. Rees again expressed
his concern at the use of infra-red heat in conjunction with
epoxy powder. Mr. Crockett telephoned Mr. Bonser e1rther that day
or the next day, expressed his concern at Mr. Rees' reservations
and asked if a convection oven could be installed in place of the
infra-red oven. Mr. Bonser reassured Mr. Crockett that this
problem would not occur with the Pollution Control oven design.
Mr. Crockett accepted this advice and decided to stay with the
infra-red oven. There is, in my opinion, no case that this
advice was given without reasonable care by Mr. Bonser. In any
21.
event, if Mr. Crockett had opted for a gas fired oven, it would
have meant a substantial increase in cost and a requirement of
extra floor space. I have referred to the evidence as to
Gartenmann's budget limits for the project.
It was the practice of Pollution Control to issue "Order
Confirmations" which incorporated any departures from the
quotation in respect of which the order was placed.
The "Order Confirmation" is dated 7 March 1983. There
is a covering letter which refers to alterations to the conveyor
"to further improve the handling and tracking of long products"
and states that engineering, purchasing and manufacture is now
well advanced. The covering letter conveys a request that, if in
agreement, Gartenmann sign both copies of the order confirmation
and send one copy back to Pollution Control. This was not done.
Nevertheless, my conclusion is that the order confirmation was
tacitly accepted and that the writings that constitute the
contract between Pollution Control and Gartenmann comprise the
proposal (with addenda), the purchase order and the order
confirmation. There was an issue, with which I deal later, as to
whether the contract was also partly oral.
The order confirmation sets out the price of the
component parts. This list is divided between components
designed, manufactured, supplied, delivered and commissioned by
Pollution Control and components which were listed as "P.C.
items". Both the proposal and the order confirmation listed
"product hanging racks" as "Specific Items for Client's Supply".
The order confirmation repeats the system design speed of 1.37
metres per minute.
On 6 April 1983, Mr. Bonser wrote to Mr. Crockett
22.
giving a progress report and advising that training had been
organised for Mr. Bale. On 10 May 1983, Mr. Bonser wrote a
letter to Mr. Crockett enclosing a revised layout drawing
providing for a repositioned conveyor drive. In this letter,
Mr. Bonser expressed concern at the use by Gartenmann of
"uncoated steel sheet", "in lieu of the zinc seal as originally
envisaged". Mr. Bonser foreshadowed that "1t may not be
feasible to process the tiles in the 'back to. back'
configuration" and that the tiles be "off-set" to minimise or
eliminate the problem. Pre-treatment of this sheet metal, also
known as CRCQ, is critical as it is coated with oil to inhibit
corrosion.
Between 27 June and 1 July 1983, Mr. Neale attended at
Newcastle to supervise the commencement of the installation of
the plant. Mr. Bonser visited the Gartenmann premises on 28
August, 7 September, 3 October and 24 October 1983. On the
last occasion, he was accompanied by Mr. Bradford, a powder
coating consultant engaged by Gartenmann at Mr. Bonser's
suggestion. Mc. Bonser's visits were to assist in the
commissioning of the plant.
On 16 August 1983, Mr. Crockett wrote to Mr. Bonser
referring to a telephone conversation of 13 August 1983,
regarding an outstanding progress payment for the powder
coating line. It is in this letter that Mr. Crockett first
records written dissatisfaction with the line. At the time of
the letter, the line was partly installed and thus not yet in
operation. Mr. Crockett there states that "it appears" that
the phosphate plant as supplied cannot process CRCQ in "back to
back" configuration which he says automatically reduces
23.
production by 50%. (As mentioned above, Mr. Bonser had
already cautioned Mr. Crockett on this topic in his letter of
10 May 1983.) In the letter of 16 August, Mr. Crockett then
refers to the addenda to the proposal. Mr. Crockett states
that the use of CRCQ was discussed with Mr. Bonser and a
representative of Robert Bryce (the powder supplier) in the
December meeting in Melbourne. Mr. Crockett also states in the
letter that there was never any mention of a 50% reduction in
output using CRCQ.
The next correspondence in evidence is a letter of 15
February 1984 from Mr. Crockett to Mr. Bonser. This refers to
a conversation of 10 February 1984 and states that "we would
again bring to your attention the problem we have had and are
still occurring with the plant as designed and manufactured by
your company".
Three complaints are made therein, the first
concerning production. "Poor performance" is said apparently
to be brought about by "two major design faults". Mr.
Crockett alleges that despite the indicated figure of 3,000
tiles per shift in the proposal (which he said was relied
upon), only 30% of that figure has been attained despite
employment of a specialist, Mr. Bradford. In fact, at Mr.
Bonser's suggestion, Mr. Bradford had spent some time at the
plant in October 1983 towards the end of the commissioning
period of the plant, and Mr. Bradford had achieved satisfactory
production at a line speed of between 1.2 and 1.3 metres per
minute with a tile sized 1800mm x 300mm, and using a redesigned
jig. This tile was not the standard tile size (1200mm x 300mm)
and was painted in "Inca Gold" colour. Mr. Crockett did not
24.
ask Mr. Bradford to redesign the jig in use for standard tiles.
The order confirmation had made it clear that jig design
("product hanging racks") was a matter for Gartenmann. The
complaint as to production also concerns powder application.
The second complaint made is with respect to the
pre-treatment plant. There are three items within this
complaint; the first concerns corrosion within the plant, the
second is that the burners have not been installed properly,
and the third is that no drain tanks have been supplied.
Finally, Gartenmann complains "as yet no access ladder has been
supplied".
It is noteworthy that Mr. Crockett makes no complaint
in this letter (as is made in these proceedings) concerning the
incapacity of the pre-treatment machine to process long
extrusions (ground (e)). It is not disputed that the
pre-treatment machine cannot perform this work. The dispute is
as to whether Pollution Control had represented or contracted
that it would do so.
Mr. Bonser wrote to Mr. Crockett a letter dated 17
February 1984, at a time when he had not yet received Mr.
Crockett's letter of 15 February 1984. In that letter, Mr.
Bonser deals proleptically with various of the matters raised
by Mr. Crockett. The material parts of Mr. Bonser's letter are
as follows:
Pursuant to our discussions and inspection of the
above plant we wish to advise of our concern on
matters pertaining to plant operation and maintenance.
We note that:
Fibreglass products are still being processed within
the precincts of the powder plant despite our repeated
advice that this will inevitably result in product
contamination and equipment deterioration.
25.
Seepage into the spray pretreatment plant pits is
continuing and appears to be increasing. We are
concerned that unless urgent steps are taken to
rectify this problem that apart from a general
deterioration of the equipment a serious failure of
the sophisticated electronic control systems of the
gas burners must be anticipated.
The silhouette panels of the phosphate plant have been
modified thus destroying the protective powder
coating. To prevent rapid rusting of these panels
they should be thoroughly cleaned, each prime
undercoated and treated with a rust resisting enamel.
Insufficient attention is being given to general
Factory cleanliness and specifically to jig
maintenance.
It is quite disappointing to be advised at this late
stage that you are experiencing operational
adifficulties with the plant and the adoption of what
seems to us a completely negative attitude to
resolving these matters to everyone's satisfaction.
The main points of contention are as follows:
Uniformity of automatic powder application.
We have an unequivocal performance guarantee from the
Wagner Company covering their equipment for the
Gartenmann application.
It was our understanding that the production results
achieved during my last visit were acceptable and as
we have received no advice to the contrary plus being
under considerable pressure to finalize our account we
have made our final payment to Wagner for your
equipment. We are now in an invidious position of
negotiating with a supplier on a _ commercially
completed contract.
However Wagner assure us of their fullest cooperation
and advise that they are providing temporary equipment
for your evaluation of "two-gun" operation, plus some
modified deflectors to improve dispersion .
Water Dry-off
It was made perfectly clear in all our discussions and
in our written submissions of the problems to be
anticipated in economically drying products subsequent
to cleaning especially pockets of water and we recall
your acknowledgement of this fact. The operational
methods [rack design, compressed air jets, air knives,
product modification, surfactants etc.] to eliminate
or mitigate the problem were all suggested to you by
our company. The optimum method(s) is best determined
by operational experience with the complete range of
products to be processed.
26.
Gas Burners
We agree there has been an inordinate delay in
resolving this matter. Our subcontractor has been
absent for an extended period. We now have his
recommendation and we will shortly forward the
necessary components to effect a rigid mounting for
both burners.
Pressure Gauge
The pressure gauge on the rinse tank was reported to
yourselves as being faulty. It is currently under
warranty and if returned will be replaced free of
charge.
Production Rate
The data set out in the addendums [sic] 1 and 2 of our
preliminary submission dated 29 November 1983 were
specifically stated as being estimates only and cannot
in any way be construed as a guarantee of performance.
To the best of our knowledge no reputable manufacturer
would contemplate providing such a guarantee because
of all the known variables plus lack of direct control
of actual coating plant operations. Our experience is
that normally systems exceed the nominal design rate
and this has been the case in all plants [Geelong
Windows, Villante Industries, Organic Coatings,
Clifton Mackie, etc.] installed and commissioned since
the conclusion of your project.
The two factors in particular are making a major
contribution to limiting plant productivity:
1. The compromise use of flight bars to allow long
length extrusions to be processed rather than
high density loading of the ceiling tiles
directly to the conveyor chain provided as
originally envisaged.
2. The extremely poor thermal latitude of the low
gloss powders you are required to process. This
is a direct result of the "flattening" agent
introduced into the formulation. We believe even
a slight reduction in gloss level criteria would
be beneficial.
Finally, we wish to re-assure you of our continuing
interest and cooperation as we believe it is to our
mutual interests to resolve your immediate problems,
and it is pleasing to hear, that you are having
considerable success in penetrating the Newcastle and
Sydney markets.
Your attention is invited to our letter dated 4th
January 1984. The amount outstanding should be
amended to read $6,121.00. If we have not received
payment of this amount by Friday, 2nd March 1984, we
will immediately institute proceedings under Section
364 of the N.S.W. Companies Code.
27.
In response to Mr. Crockett's letter of 15 February
1984, Mr. Bonser wrote a letter dated 24 February 1984. Init
he referred to his letter of 17 February 1984, the contents of
which I have just set out. Mr. Bonser stated that the jig
design was a major determining factor in successful operation
of the plant and was an "ongoing process". Mr. Bonser noted
that it was "common practice" for companies lacking the
necessary experience to appoint a specialist to assist in the
day to day operation of the plant, especially in the early
stages of operation. Mr. Bonser concluded with a demand for
payment within seven days.
The letter of 17 February 1984 was replied to on 7
March 1984. Mr. Crockett expressed "extreme concern" regarding
what he said was "the poor performance of the plant in coating
panels". Mr. Crockett states that this had been a point of
contention and that "at no time have we indicated to the
contrary". However, in cross-examination, Mr. Crockett
accepted that Mr. Bradford had achieved satisfactory results at
a satisfactory line speed in October 1983.
Mr. Crockett also refers in his letter to recent
discussions with Wagner to the effect that the original
specification was for two spray guns per side. This is
contrary to Mr. Boal's letter of 22 November which I have
earlier set out. Mr. Crockett also alleges in his letter that
the dry-off oven was inadequate when tiles were in a "back to
back" configuration.
Significantly, there is no reference to the alleged
oral representations made to Mr. Crockett and Mr. Phillip
Crockett in December 1982. Reliance is placed by Mr. Crockett
28.
in his letter only on the addenda to the proposal.
Gartenmann filed a Statement of Claim against
Pollution Control in the District Court on 6 April 1984.
These proceedings were discontinued after the commencement of
the proceedings in this Court. However, in the District Court
the claim was that in breach of contractual condition and
warranty, the product cost per tile was 39 cents rather than 26
cents. In evidence in this Court, Mr. Crockett claimed as at
1983 a production cost of $1.10 per tile. Further, the other
issues in the District Court proceedings were limited to rate
of production; it was alleged that the defendant fraudulently
misrepresented a production rate of 3,000 tiles per day, whilst
the plant was not capable of "properly coating even 1,000 tiles
per day". This was also alleged to be a breach of contract.
Otherwise, there was no allegation as to quality of product,
or, in particular, as to deficiencies in gloss and evenness of
colour.
THE PROPOSAL AND THE ADDENDA
Mr. Crockett points to the proposal as containing
representations concerning the performance of the plant which
he relied upon to his detriment. The first representation that
is alleged to appear is that the more expensive pre-treatment
alternative, the phosphate plant, (that purchased by Garten-
mann) would pre-treat five metre lengths of aluminium
extrusions (i.e. ground (e) of the complaints earlier
described). The evidence discloses that the pre-treatment
machine is incapable of pre-treating these long extrusions and
that arrangements have been made to pretreat them "off-line".
29.
This slows production and is more labour intensive. The matter
in dispute between the parties is whether Mr. Bonser and Mr.
Neale or either of them represented orally or in writing in the
proposal that the phosphate pre-treatment machine would process
these extrusions "on-line". There is no dispute that such
extrusions could be passed through the system on the conveyor;
the debate is as to whether "pre-treatment" was to be "on-line"
or "off-line".
Mr. Bonser and Mr. Neale are adamant that the plant
was designed to pre-treat ceiling tiles, not long extrusions.
Mr. Paul Crockett is equally adamant that he required these
long extrusions to be pre-treated on-line.
The only immediate evidence on this point 1s what is
set out in the proposal. There is no allegation of any direct
oral representations. However, at the meeting with Mr. Clink
on 9 November 1982, Mr. Crockett had stated that five metre
aluminum extrusions would be processed one day a month, and
this information was passed on to Mr. Bonser by Mr. Clink at
the Mandl plant meeting two days later. Further, Mr. Bonser
explained to Mr. Crockett at the meeting at the Mandl plant
that the normal method of pre-treating long aluminium
extrusions was in a batch type "chromate conversion" plant.
Neither plant offered in the proposal was of this type.
Indeed, Mr. Crockett was constructing the necessary tanks to
enable pre-treatment of such long extrusions during the
commissioning of the plant.
Pollution Control submits that the opening paragraph
of the proposal, properly construed, represents that, although
the phosphate plant could not pre-treat long extrusions, its
30.
design was such that after pre-treatment off-line, they could
be passed through the system on the conveyor, thereby allowing
for the loading and unloading of the line from the same point.
If the trichlorethylene plant was chosen, not even this would
be possible. This is because the pre-treatment method for
that system involves the immersion of the product in tubs
whereas in the phosphate system the conveyor operates on a
single plane which is suitable for the uninterrupted passage of
long objects. I accept this construction of the opening
paragraph.
The opening paragraph of the covering letter to the
proposal provides as follows:
"We are pleased to forward our firm
Quotations, Specifications and General
Apptoach Drawings covering the design,
manufacture, supply, delivery and
commissioning of a 'Turn Key' Plant for the
above project. As requested, we have
submitted alternative proposals covering
either phosphate pretreatment and cleaning
or an ''in-line' trichlorethylene degreasing
plant. The phosphate plant would be
suitable for both cleaning and conditioning
of a wide range of metal substrates,
zincseal, mildsteel, aluminium, etc.
However the alternative plant would clean
only and would not process long extrusions
although plant layout would permit powder
coating and curing. Subject to application,
it would be necessary to pretreat the
extrusions off-line which normally consists
of de-smut, rinse, etch, rinse and chromate
conversion. This latter process may require
a relatively expensive effluent treatment
system, the actual requirements being
subject to local statutory authorities.
At page 3 the following appears as the penultimate
paragraph of the covering letter and qualifies the above
introduction:
"Pinally, to assist with plant selection, we
have included as addendums [sic] our
31.
estimates of the anticipated operating costs
for both plants. The estimates in both
cases are based on the Automatic Plant and
assume a single shift only. If the cost of
additional ''off-line' pretreatment and some
Timitation of system capability for contract
coating are given due consideration, the
phosphate proposal would be the more
attractive option." [italics supplied]
Significantly, reference there is made to "additional
off-line pretreatment". This indicates that at least a
portion of pre-treatment was anticipated as being done
off-line. This is another consideration supporting the
interpretation I have preferred.
The paragraphs set out above are important in another
respect. The first recites Mr. Crockett's request that
alternative proposals be forwarded setting out the relative
costs of the trichlorethylene and phosphate pre-treatment
plants. The second refers to "addendums [sic]" being "our
estimates of the anticipated operating costs for both plants".
The applicants submit that these estimates were relied upon as
forecasts as to the production capacities of the plant and the
actual cost of coating the tiles in the alternative plants
(i.e. grounds (a) and (c) as previously described). The
respondents submit that the addenda were included in the
proposal only to highlight and contrast the differing running
costs of each pre-treatment system "to assist with plant
selection"; they were not forecasts of the capabilities of the
phosphate plant and have no such operation, whether as
representations or contractual terms.
I accept the submissions of the respondents on this
issue. The language I have referred to largely speaks for
itself. In addition, I should refer to the index. The
32.
second page of the proposal is an index. This lists as the
last entry "Addendums [sic] Estimation of Operating Costs".
Otherwise, the addenda are not referred to in the proposal save
for the final paragraph in the covering letter, which I have
set out. If the addenda contained estimates of the operating
costs of the plant and its capacity to produce ceiling tiles
per normal eight hour shift, one would expect reference to be
made to them in the body of the proposal. However, each
aspect of the plant is discussed separately, in the proposal,
and its design parameters are listed without mention of the
addenda.
The addenda were prepared on the evident assumption
that production was of standard tiles. However, Mr. Crockett
intended to powder coat not only his entire range of ceiling
tiles, being of seven sizes, but also to undertake contract
work (if available) and to powder coat various extrusions
associated with the Gartenmann ceiling system, including
"inserts" and "top hats". In these circumstances, it would be
an unwarranted assumption to treat any production estimate
(even if the addenda could properly be so read) as valid for
Mr. Crockett's purposes as described above. This, in my view,
provides a setting for a true application of the doctrine of
"unwarranted assumption" as explained in Lego Australia Pty.
Ltd. v Paul's (Merchants) Pty. Ltd. (1982) 60 FLR 465 at 474.
Nevertheless, as the applicants rely upon matter in
the addenda as forecasts of the plant's capabilities and do so
as the cornerstone of their case on grounds (a) and (c), I will
proceed to deal with their submissions on the _ footing
favourable to them as to the representational or contractual
33.
Mature of the addenda. However, even on this footing, I find
that the applicants do not succeed, both because they have not
properly construed the addenda and because they have not shown
the plant, properly maintained and operated, to have the
shortcomings complained of by then.
The addenda comprise two pages and are reproduced as
Schedules 1 and 2 to these reasons.
Addendum 1 deals with the trichlorethylene system
plant. Addendum 2 deals with the phosphate system plant. As I
have said, Gartenmann purchased the phosphate system plant.
Some items in Addendum 1 (e.g. "powder") are incorporated by
reference into Addendum 2.
The matter that must be decided is whether the addenda
provided Mr. Crockett with a detailed estimate of production
quantity and cost per tile (24.6 cents in Addendum 1, and 26
cents in Addendum 2) or, as the respondents assert, whether the
addenda represented an attempt on their part to provide a
comparison between two alternative pre-treatment plants, those
calculations being sufficiently detailed to be useful but
proceeding from assumed figures, the assumptions being common
to each equation.
I turn now further to consider the terms of the
addenda.
It is to be noted that the figure of 3,000 tiles per
day, which is the figure that Mr. Crockett relies upon as being
the critical production estimate, is found in the section of
the calculation in Addendum 1 dealing with "powder
consumption". It is not set out beside a heading of its own
nor is it the result of any visible calculation. It appears as
34,
"Production Rate 3,000/day" and is repeated lower down as
"3,000 x 5 x 46 weeks = 690,000 panels". The figure of 690,000
appears also in Addendum 2 in the calculation of cost per tile
of 26 cents. Also under the "powder" heading in Addendum 1 are
the words "Assume 50 micron thickness and 1.2 S.G." The 50
micron thickness refers to the depth of the powder coating on
the tile and S.G. refers to specific gravity which is the
relative weight of the powder; the lighter the specific
gravity the further the powder will cover per kilogram. The
evidence disclosed that the figure of 1.2 for the specific
gravity of white powder was erroneous, the specific gravity in
fact being approximately 1.66. However, the same figure
appears in each addendum and the respondents' submission is
therefore valid for the purposes of the exercise, for which
they contend, a comparison between the two systems using
constant hypotheticals.
Mr. Crockett in his evidence agreed that some of the
figures in the addenda were hypothetical. However, he did not
agree that the figure of 3,000 tiles per shift or the "bottom
line figure" of 26 cents in Addendum 2 were hypothetical
figures.
Mr. Crockett did shift his ground. In cross-
examination, he conceded that many of the figures in the
addenda could be described as "hypothetical estimates". In
re-examination, Mr. Crockett said that his understanding of the
words hypothetical estimates meant "estimates that are not
based on fact". Mr. Crockett then denied that he regarded the
figures present in the addenda as being hypothetical. But, in
the end, his view as to the bottom line figure of 26 cents per
35.
tile is expressed by his answer to the following question:
Did you regard the ultimate quantification
of the powder cost in both of those addenda
as a hypothetical estimate in terms of your
understanding?
No, I deemed those to be actual costs.
[italics supplied]
In respect of production estimates, (ground (a)), the
"Request for a Proposal-Data Sheet" completed by Mr. Clink
after the initial meeting with Mr. Crockett on or about 9
November 1982, set out "158 units /HR" as being the "usage per
day" set out to calculate powder consumption. This figure
could only have come from Mr. Crockett. As I have said, Mr.
Crockett does not recollect that meeting. In his evidence of
conversations shortly after this first meeting (which I have
already dealt with), Mr. Crockett alleges that he required at
least 2,000 tiles to be processed per shift, but I have made
adverse findings on this issue. Indeed, this figure does not
appear in the proposal itself and no contemporaneous complaint
was made of its absence.
Finally, with respect to the alleged firm production
quantities and costs, it is to be noted that with each
component specification in the proposal, a "design parameter"
was set out which is typically in the range of .5 to 1.5 metres
per minute conveyor speed depending upon the product being
processed. Although a "system design speed" is given, i.e.
line speed, of 1.37 metres per minute, such a wide operational
parameter exists and makes the conclusion that any "bottom line
figure" was provided, as alleged, in the addenda all the more
unwarranted.
Although Mr. Neale and Mr. Bonser were, by the
36.
December meeting in 1982, in a position to make a calculated
Prophecy as to production, they did not do so by means of the
addenda. This is apparent from the very wide production
parameters set out in each individual specification provided in
respect of each major piece of machinery forming part of the
plant. No reference is made in these specifications to the
addenda. Gartenmann were responsible for the operation and
maintenance of the plant. Line speed depended upon the nature
of the product to be processed. Mr. Bradford, who gave
valuable evidence with respect to production techniques, stated
that he made an average of 30-40 adjustments to the cure oven
each day to adjust the curing process on the one product. In
all the circumstances, it would be all the more improbable that
a firm production estimate would be provided.
In support of ground (a) (the allegation that in
breach of the representation as to production of 3,000 tiles
per eight hour shift, the plant was capable of powder coating
only 800-900 tiles per eight hour shift), Mr. Crockett tendered
two production record books and he distilled from these a
document entitled "Summary of the Applicant's Production
Output". This Summary purports to cover the period from
December 1984 to December 1986. It is divided into two
sections, being "750 or less" and "750 or more". The Summary
only records production of ceiling tiles and was tendered on
that basis.
The production record books record not only production
of ceiling tiles, but also of the various extrusions which form
part of the Gartenmann ceiling suspension system and which have
been passed through the plant. The recording of the processing
37.
of the extrusions was phased out and no record at all was kept
of the processing of contract work.
The summary sets out the number of ceiling tiles
processed on given dates. It was conceded by Mr. Crockett in
cross-examination both that there was production on dates not
set out in the Summary and that on some of the dates that were
mentioned in the Summary products other than ceiling tiles were
being processed. An example pointed to by counsel for the
respondents is production on 8 January 1985. No mention is
made of this date in the Summary, as no ceiling tiles were
processed. However, the production book recites that 387
sprinkler inserts and 1,004 top hats were processed. Both
items were part of the Gartenmann product range. On 9 January
1985, the Summary indicates that only 318 ceiling tiles were
coated but the production records reveal that on that day 360
"top hats" were processed along with 381 inserts. The result
is that on that day, 1,059 units were processed. The following
day, 10 January 1985, the Summary discloses that 851 tiles were
processed. No mention is made of the 611 inserts processed,
nor the 360 censors. Total production for that day was 1,822
units. The evidence also reveals that it was commonplace for
the powder coating plant to remain idle awaiting a sufficient
amount of product to be brought across from the manufacturing
portion of the Gartenmann operation to give a reasonable
production run for the powder coating plant.
In fairness to Mr. Crockett, the Summary was tendered
on the basis that it referred only to ceiling tiles. However,
I was not assisted in assessing the true production capacity of
the plant by evidence of this type. The applicants' evidence
38.
as to production capacity is on the whole unsatisfactory. I
cannot be satisfied that on any given day the plant was
processing ceiling tiles exclusively.
I find that the addenda do not substantiate the
applicants' case on grounds (a) and (c).
CONCLUSIONS AS TO GROUNDS (a), (b), (c), (e), (f£)
In my view, the applicants have failed to make out
their case on ground (a) that the plant was incapable of
producing more than 800-900 tiles per eight hour shift. Indeed,
as it happened, it was not shown whether the plant, with
careful attention to jigging, properly maintained and monitored
by skilled operators, lacked the capacity over an eight hour
shift to powder coat 3,000 standard tiles. I have already
dealt with grounds (b), (e) and (f). For the reasons given in
dealing with the proposal and the addenda, I reject ground (c).
That leaves ground (d) i.e. gloss and colour.
GLOSS AND COLOUR
The applicants claim is that the respondents
represented that they were able to design, manufacture, supply,
instal and commission a powder coating plant which would give
each tile treated in the plant a finish which was even in
colour and degree of gloss, and suitable for use in the
construction of ceilings. This representation is alleged in
the Statement of Claim to have been made orally (a) on 11
November 1982, not at the Mandl plant, but over lunch in the
restaurant, in Sydney, by Mr. Bonser to Mr. Crockett; (b) at
the restaurant on 17 December 1982 at Bayswater, Victoria, by
39.
Mr. Bonser and Mr. Neale to both the Messrs. Crockett; and (c)
on 9 February 1983 at Newcastle by Mr. Bonser and Mr. Neale to
Mr. Crockett. The representation is also alleged to have been
made in writing in the proposal documents, but plainly that was
not s0.
I have stated my findings of fact as to what was said
on these three days. I have found that on four occasions (on
11 November 1982, twice on 17 December 1982 and on 9 February
1983) which do not correspond precisely with the occasions
particularised, the importance of a low gloss was stressed to
and accepted by Mr. Bonser. I have also found that on 17
December, Mr. Bonser responded to Mr. Crockett with words to
the effect that he was not going to have complaints about
colour or gloss. All of this falls short of the terms of the
representation pleaded. It is important to appreciate that the
meetings in question, as to one of them, proceeded, and as to
the others, followed upon provision of the proposal. This, as
I have said, was a most detailed document. It was followed in
March 1983 by the written confirmation. The parties were
businessmen. At the meetings a range of topics was discussed.
Two of the meetings were in a social setting, over lunch.
The findings of fact fall short of holding that any
unequivocal statement was made, in form or substance, by Mr.
Bonser or Mr. Neale to Mr. Paul Crockett or Mr. Phillip
Crockett that Pollution Control would provide a plant that
would give to each tile treated in the plant a finish which was
even in colour and degree of gloss and suitable for use in the
construction of ceilings. Certainly, as I have held, the
importance attached by Gartenmann to gloss and evenness of
40.
colour was made clear to and accepted by Mr. Bonser. But it is
a further step (and one the evidence does not warrant) to find
that an assurance as to the gloss and evenness of finish of
each tile was given to the Messrs. Crockett. Whether each
tile had these qualities would depend not only upon the design
of the plant, but upon a number of variables, including
operation and maintenance of the plant, matters which were
beyond the control or responsibility of Pollution Control and
were accepted as the province of Gartenmann.
Further, even if the case be approached on the footing
that Gartenmann relied on statements to the limited effect I
have found, that would not mean there flowed the legal
consequences Gartenmann alleges. I deal with the various bases
on which it puts its case. As to deceit, there was no case
made out that what was said was knowingly false and uttered
with reckless disregard for or indifference to the truth. As to
collateral contract (and this is also true of the allegation of
a contract partly written and partly oral), in my view the
statements were not promissory in form within the meaning of
the principles expounded in J.J. Savage & Sons Pty. Ltd. v
Blakney (1970) 119 CLR 435 at 442; Ross v Allis-Chalmers
Australia Pty. Ltd. (1980) 55 ALJR 8 at 10, 11; Hospital
Products Ltd. v United States Surgical Corporation (1984) 156
CLR 41 at 61; Gates v City Mutual Life Assurance Society Ltd.
(1986) 160 CLR 1 at 5, 10-11. As to negligent mis-represent-
ation:
(i) I assume, without deciding, that provided the
conditions for the existence of a special
relationship exist, in Australia a duty to take
41.
care may arise between A and B in relation to
statements made in negotiations preceding entry
into a contract between A and B; in my view,
contrary to the submissions of the applicants,
the application in this country of the reasoning
in Esso Petroleum Co. Ltd. v Mardon Ltd. [1976]
QB 801, was not decided in State of South
Australia v Johnson (1982) 42 ALR 161; rather,
it was assumed because not disputed.
(ii) I assume also that the respondents owed to
Gartenmann a duty to exercise reasonable care,
skill and diligence in making the statements
that I have found were made: Greig and Davis,
"The Law of Contract", pp. 848-849.
(iii) However, in my view, there was no breach of any
such duty and there was no lack of reasonable
care on the part of the respondents; installat-
ion, operation and maintenance were, as I have
said, matters for Gartenmann and in his cross-
examination Mr. Crockett indicated he understood
them as such; nor does the history of the
operation of the plant (with particular
reference to gloss and evenness of colour) bear
out a case for negligence made against the
respondents. I deal elsewhere in this judgment
with the facts which lead to these conclusions.
Finally, I turn to Part Vv of the TP Act. The
applicants relied on ss. 52 and 53 (c). The second applicant
was not a party to the contract. The TP Act, if applicable,
42.
would operate to outflank any barrier that the doctrine of
privity might place in the path of recovery of damages by the
second respondent for breach of contract. However, I have
concluded that there was, by virtue of the conduct in which I
have found the respondents to have engaged, no contravention of
s. 52 or s. 53 (c). I have already referred to the setting in
which the conduct occurred. I bear in mind what was said by
Gibbs CJ in Parkdale Custom Built Furniture Pty Ltd. v Puxu Pty
Ltd. (1982) 149 CLR 191 at 199:
The conduct of a defendant must be viewed as
a whole. It would be wrong to select some
words or act, which, alone, would be likely
to mislead if those words or acts, when
viewed in their context, were not capable of
misleading. 'It is obvious that where the
conduct complained of consists of words it
would not be right to select some words only
and to ignore others which provided the
context which gave meaning to the particular
words. The same is true of acts.
In particular, as the decision of Fisher J 1n Pappas v
Soulac Pty. Ltd (1983) 50 ALR 231 shows, where statements are
made either before or in the course of negotiations for a
significant transaction for sale and purchase of property,
those statements are to be assessed not in isolation but in
the overall context of the negotiations.
Mr. Bonser and Mr. Neale did not represent that the
plant would produce tiles each of which was even in colour and
degree of gloss. If the applicants had sought such a high
degree of assurance, then the Messrs. Crockett may well, as
businessmen, have sought to include such a written provision in
the contract. It would then have been for Pollution Control to
accept, modify or reject that provision. The statements that
were made were made in a setting in which Pollution Control
43.
appreciated the limits of Gartenmann's budget and_ the
responsibilities of Gartenmann as to installation, operation
and maintenance. Against that background, Pollution Control
understood and accepted what Gartenmann wished to achieve as to
colour and gloss of tiles by purchase of the plant from
Pollution Control and proper installation, maintenance and
operation of that plant.
Further, and as an independent reason for decision,
the representation contended for by the applicants (and this is
true not only of the present ground, ground (d), but also
grounds (a), (b), (c) and (e)), was not as to an existing or
past fact. Rather, it was a forecast or prediction as to the
future, and the applicants could only have succeeded by showing
on the part of the respondents' knowledge of falsity or
reckless indifference: Bill Acceptance Corp. Ltd. v G.W.A.
Ltd. (1983) 50 ALR 242, Johnson v Eastern Micro Electronics
Pty. Ltd (1986) 70 ALR 339, R.G. Steedman v Golden Fleece
Petroleum Ltd. [1986] ATPR 40-660. Nothing in the present case
indicates any statements were made by Mr. Neale or Mr. Bonser
with knowledge of falsity or reckless indifference within the
meaning of these authorities.
I should add that the conduct complained of took place
before the insertion of s. 51A in the TP Act, by the Trade
Practices Revision Act 1986. I do not suggest that the
application of s. 51A would have produced a result favourable
to the applicants.
Even if the statements I have found did amount to
representations or promises susceptible of legal consequences
if performance were deficient, I would still not hold the
44,
respondents liable for breach. The evidence of what happened
in the course of production does not show breach as claimed by
the applicants.
The applicants led evidence only of four jobs on which
some tiles produced at the plant allegedly were of
unsatisfactory quality. The first complaint made concerns some
990 ceiling tiles supplied by Gartenmann to Adco Constructions
Pty. Ltd. for installation in the Murwillumbah Branch of the
Commonwealth Bank. These tiles were the first batch of tiles
ever distributed and it is clear that the commissioning process
of the plant then was incomplete. Mr. Crockett claims that
the tiles were affected by colour variation and insufficient
coating. The tiles were manufactured in October 1983, prior
to Mr. Bradford's engagement. Mr. Crockett gave evidence that
"the colour variations complained of were very noticeable. . "
Mr. Crockett replaced 990 tiles and claims damages of
$17,703.40 which includes a component for freight and Mr.
Crockett's inspection at the site.
In respect of this complaint, it is clear that the
plant had not yet properly been set up at the time of
manufacture of these tiles. Changes had been made to various
parts of the plant and it was premature for Gartenmann to send
out a quantity of tiles not carefully checked at the factory.
Mr. Bradford, during the evidence as to his visit to
the plant in October 1983, said the following:
"what did you notice about the general
organisation of the men working on the line?
They did appear to be working in a
disorganized fashion.
Could you elaborate what you mean by that
please?
45.
I believe the gentlemen were new to the
facet of powder coating and were therefore
not being able to understand actually what
the process they had to carry out
particularly in the area of the operator,
who was actually looking after the spray
guns, the oven temperature, had not had any
experience in this type of system before and
he was certainly working in a_ total
disorganised fashion not knowing really what
to do next.
What was his responsibility that you
observed?
I believe he was responsible for the whole
operation of the plant..."
Mr. Bradford also expressed the view that the line was
understaffed. Mr. Crockett in his evidence said that to him
the experience of operators was irrelevant. However, in his
cross—examination, he accepted that plant maintenance, quality
control and skilled operation were vital to production of a
merchantable product.
The operator referred to by Mr. Bradford was Mr. Bale.
Mr. Bonser had arranged training for him prior to the
commissioning of the plant. It will be recalled that it was
shortly before this that the tiles for the Murwillumbah project
were manufactured. There have been a total of four operators
of the plant since its commissioning in 1983.
The second project where tiles were rejected was at a
building in Loftus Street, Sydney. The tiles were installed in
February through to March, 1984. Here, 2,500 tiles were
replaced. A complaint was made to Mr. Crockett. Mr. Crockett
inspected the tiles in situ and observed that "the coating on
the ceiling tiles was noticeably uneven and a large number of
them were affected by a 'W' pattern". The evidence disclosed
that the 'W' pattern on the tiles was caused by a failure on
46.
the part of the powder application equipment adequately to coat
the tiles as they passed by it suspended from the conveyor.
Accordingly, it was indicative of the powder coating equipment
not being able to keep pace with the line speed adopted by Mr.
Crockett. During this period Mr. Crockett had increased the
line speed from 1.2 (in October 1983) to 1.35 metres per minute
(in October 1984).
The solution to the problem was to purchase an extra
spray gun for each side of the conveyor thereby allowing the
product to be sufficiently coated at the conveyor speed adopted
by Mr. Crockett. Mr. Crockett was advised by Mr. Bradford in
October 1983 that he required two extra guns. This advice was
not acted upon until May 1984 (at a cost of $11,283) after the
tiles produced for the Loftus Street job had been found to be
defective.
Mr. Crockett answers this criticism on the basis
(which I find unacceptable) that owing to the failure of the
plant to produce tiles at 3,000 per shift, he was placed in
financial difficulty and could not afford the cost of the extra
guns. Mr. Crockett in his statement said that "I attributed
the ''W' pattern to the poor performance of the spray guns and
reciprocators". The reciprocators were not replaced until May
1985. Yet Mr. Plunkett (a consultant engaged by Gartenmann)
had advised in October 1984 that they be replaced. Mr.
Crockett did not send the reciprocators back to the
manufacturer for service.
However, Mr. Clink and Mr. Bonser had arranged for a
representative from Wagner to be present at the trials at the
Mandl plant in 1982 and that gentleman, Mr Boal, made a written
47.
recommendation to Mr. Bonser concerning the recommended number
of guns and reciprocators. In the quotation, Mr. Bonser
described the powder spraying equipment as a P.C. item. This
stands, as I have said, for "prime cost" and it serves to
identify parts of the plant that are not of the manufacture of
Pollution Control. If an error was made in the selection of
the powder coating equipment, it was an error made by Mr. Boal.
If there was an error, that error may have been induced by a
desire to keep the plant within budget.
The next difficulty complained of occurred in October
1984 in tiles supplied for installation in the Londonderry
T.A.F.E. Gartenmann complains that of the 3,600 tiles it
supplied, 200 had to be 'replaced because they were "badly
affected by colour and gloss variation". The final project
where complaint is made falls in the same period. It concerns
the Knox T.A.F.E. The order was received in December 1984.
Of the 10,000 tiles delivered to the building site 9,106 tiles
were repainted with satisfactory results and 900 tiles were
scrapped. Mr. Crockett frankly conceded that variations in
colour and gloss could be the result of an operator problem.
these are the only instances of allegedly defective
production over a period of some four years. The plant had
produced by June 1986 in the vicinity of 241,215 ceiling tiles.
The applicants have supplied 11,000 tiles produced by the plant
at a standard sufficient for installation in the new Parliament
House in Canberra. In his evidence, Mr. Crockett said no
special production techniques had had to be used with these
tiles.
In my view, the applicants have not established that
48,
any defects of colour or gloss in tiles produced by the plant
were the result of any failure to supply a plant capable of
producing ceiling tiles with a finish even in colour and degree
of gloss and suitable for use in construction of ceilings.
It follows that no breach of the kind complained of in
ground (d) has been established.
ALLEGED DESIGN DEFECTS
The applicants, in addition to the complaints already
dealt with in these reasons, as grounds (a), (b), (c), (dad), (e)
and (f), also put their case in negligence and contract on the
footing that (i) the respondents had a duty to exercise
reasonable skill, care and diligence in manufacturing,
supplying, installing and commissioning the plant, and that
they failed to discharge that duty, thereby giving rise to a
claim in tort for negligence, and (ii) that there was an
implied term in the contract that the plant be reasonably fit
for the particular purpose for which it was required, viz. for
use to powder coat metal ceiling tiles and extrusions. As to
the implied term, there was no ground, in my view, for implying
any terms as to metal extrusions insofar as pre-treatment
on-line. I refer to what I have already said on this part of
the case.
In support of both causes of action, the applicants
made complaints concerning line speed, the burners and the cure
oven.
They also pointed to other alleged deficiencies. To
an extent these overlapped with complaints as to line speed,
the burners and the cure oven. These other deficiencies were
49.
principally that (A) the cure oven was too short, (B) there was
poor powder flow in the powder booth, with uneven application
of powder to the tiles, (C) the reciprocators and powder guns
had failed to work effectively (although these were P.C. items
supplied by Wagner for whose design responsibility was not
taken by Pollution Control), (D) the filtering devices were
incapable of separating the powder from the atmosphere, causing
powder to escape the exhaust stacks and to find its way back
into the factory (although the proposal specifically had not
provided for supply of exhaust stacks), (E) the conveyor lacked
a take-up device, allegedly causing jerking when the conveyor
is started up and (F) the proposal had stipulated infra-red
heating rather than a convection oven (heated by gas), a matter
with which I have already dealt.
In dealing with alleged design faults, it is necessary
to refer to the expert evidence. However, in doing so, it
should be borne in mind that, while the plant was installed in
1983, the trial was in 1987, and that the experts had observed
the plant at different times over this period and not all had
seen it fully in operation in its original state.
EXPERT EVIDENCE
Expert evidence was called both by the applicants and
respondents. For the applicants, Mr. Clinton Ashton-Martin and
Mr. James Leonard Plunkett were called. Mr. Ashton-Martin has
extensive experience in industrial heating and since leaving
Wessburg & Martin Pty. Ltd. in 1977 has operated his own
consultancy business. Mr. Ashton-Martin has a Bachelor of
Engineering degree with Honours from Sydney University. Mr.
50.
Plunkett is a director of Fostoria-Fannon (Aust.) Pty. Ltd., to
which I have already referred when dealing with Mr. Bonser's
experience. That company has, since 1970, supplied various
components of powder coating equipment including reciprocators,
ovens and powder booths. Mr. Plunkett is a licensed
electrician (NSW) and a licensed "A" grade electrical mechanic.
He visited the plant in October 1984, February 1985, January
1986, and during the hearing in August 1987. Mr. Ashton-Martin
visited the plant in December 1984, January 1985, and in
February and August 1987.
Both gentlemen advocate alteration to the plant to
improve its performance. The recommendations made range from
very inexpensive, such as the fitting of vapour seals to the
pre-treatment machine, to very expensive such as replacing both
the dry-off and cure ovens with convection gas fired ovens.
Mr. Crockett purchased a gas fired oven in July 1986.
However, that oven, up to the time of the hearing in this
matter, had not been installed.
Mr. Ashton-Martin and Mr. Plunkett consider the plant
in its present condition incapable of producing tiles at 1.37
Metres per minute. However, as I have already stated, Mr.
Bradford had the line operating at between 1.2 and 1.3 metres
per minute in October 1983 and producing a product that was
acceptable to Mr. Crockett. Mr. Ashton-Martin agreed in
cross-examination that although he expressed the view that the
plant could not produce at 1.37 metres per minute, he did not
test the plant by operating it at this speed.
Neither Mr. Ashton-Martin nor Mr. Plunkett criticise
the powder coating plant on the basis that it was not fair
$1.
value for $100,000 or $125,000 which was the project budget.
This is a vital point, bearing in mind that the case concerns
the exercise of reasonable skill in relation to the designated
task. No doubt a better equipped plant could have been
supplied at a higher cost. Mr. Ashton~Martin gave evidence
that a convection oven would have involved a greater initial
expense. It is clear that a convection oven could not have
been installed within the budget and the floor space available
in 1983.
Dr. Jean Cross, a principal research scientist
employed by the C.S.I.R.0., was called by the respondents. Dr.
Cross has expertise in the area of deposition of electrostatic
powder coatings. Dr. Cross disclaims expertise in
pre-treatment plants, infra-red technology and chemical
composition of powder. Dr. Cross in her evidence stated that
theoretically one powder gun each side of the conveyor in the
automatic booth was sufficient. Dr. Cross expressed the view
that since the gun had been added to each side of the conveyor,
the booth was "rather small" for the purpose.
Dr. Cross observed the plant operating for the purpose
of a demonstration in March 1987. Dr. Cross noticed that the
powder flow from the guns was not uniform and powder flow had
ceased altogether from one gun until an operator made a manual
adjustment to it. A second gun was giving a low flow toward
the end of the demonstration in the production§ run.
Furthermore, the voltage on one of the guns had failed
completely. Dr. Cross noted that there was some indication
that "small fibres" had contaminated the powder. This may have
been the result of use of fiberglass near to the powder coating
52.
plant. As early as his letter of 17 February 1984 (which I
have set out earlier in these reasons) Mr. Bonser had warned
Mr. Crockett of the adverse consequences if fiberglass was not
removed from the immediate vicinity.
Dr. Cross agreed that in her view a decision had been
taken to favour in most cases lower cost components in the
line. She agreed that the improvements suggested by Mr.
Ashton-Martin and Mr. Plunkett would have been included in a
more expensive system. However, the lack of those improvements
were not, in Dr Cross's view, necessarily contributing to any
problems in coating uniformity. Dr. Cross stated that it was
her experience that the best finishes are obtained from plants
with the best maintenance and most dedicated operators, minor
differences in plant design being of lesser importance.
The respondents also called Mr. Miller. Mr. Miller
had expertise ranging from the design of powder coating plants
through to their installation. He inspected the plant on 4
March 1987. His first impression upon entering the plant was
that "a very poor level of housekeeping was evident". He also
observed that the tiles were jigged vertically, which did not
assist drainage of excess water remaining after pre-treatment.
He described the work hanging arrangements (i.e. the jigging)
as being very poor with little attention having been paid to
loading the conveyor in a manner to obtain maximum production
from the line.
Mr. Bradford, a very experienced plant manager, was
called and gave valuable evidence as to the state of the plant
in October 1983, and as to production techniques and
maintenance that should be undertaken. Mr. Bradford had acted
53.
as a consultant during the commissioning of the plant. As I
have said, he achieved satisfactory production at between 1.2
and 1.3 metres per minute with the 1,800 x 300 tile using a
redesigned jig. Mr. Bradford was not asked by Mr. Crockett to
devise an alternative jig for the standard tile. It had been
made clear to Mr. Crockett in the proposal and order
confirmation that jig design was a matter for Gartenmann.
Mr. Bradford gave evidence that, at the time he left
the Gartenmann plant, all aspects of the plant were working
well, the cure oven was giving uniform heat and the tiles were
evenly coated with powder. Mr. Bradford also stated that
maintenance of the cure oven is critical and that loss of
reflectivity within the cure oven caused by powder
contamination cannot be adequately compensated by increased
energy input into the oven as this results in uneven heat
distribution which in turn may cause colour and gloss
variation. This is also an important consideration in dealing
with the complaint as to line speed, to which I shortly will
come.
Mr. Bradford stated that the curing process is an
"extremely delicate process". Mr. Crockett was using epoxy
powders which were known by him to have a narrow thermal
latitude and were prone to overbake. Mr. Bradford devoted four
hours per week to maintaining oven reflectors in his plant.
The applicants put forward no satisfactory evidence of their
maintenance of the reflectors.
CONCLUSIONS AS TO ALLEGED DESIGN DEFECTS
As I have explained, the plant did produce a suitable
54.
product in large numbers over a long period. This tends to
suggest that any unsatisfactory product that was produced was
not the result of some design fault or defect which had a
universal effect. There was expert evidence to the effect that
the "housekeeping" of the applicants at and around the plant
was of low quality and that in particular insufficient
attention was given to maintenance of the cure oven.
Mr. Bradford and Mr. Miller gave expert evidence in
this area, Mr. Bradford gave evidence concerning his plant,
(which was comparable in this respect with that of Gartenmann)
that he would on average make between thirty and forty
adjustments per day to the cure oven alone, to compensate for
ambient temperature variations. Mr. Bradford was able to
process "off white" ceiling tiles at 1.65 metres per minute out
of his plant. This careful attention to detail was not
demonstrated by Mr. Crockett. Indeed, the opposite 1s the
case. The evidence is that the maintenance of records as to
plant settings is highly desirable if a product of consistent
quality is to be manufactured. Mr. Crockett kept no such
records.
Mr. Crockett alleges that the dry-off oven is not
performing satisfactorily and that he has been forced to employ
a person to blow off the excess water remaining on the tiles
after they emerge from the pre-treatment plant. This is done
by means of compressed air.
Since January 1985, the pre-treatment plant has been
operating without the burners that were installed. The
burners heat both the chemical spray section and the rinse
section in the pre-treatment plant. Since January 1985, the
55.
tiles have been processed in cold water rinse. Mr. Plunkett
had never seen both burners in operation. He advised Mr.
Crockett to have the burners repaired as the tiles could not be
dried properly if rinsed in cold water. Mr. Miller also
suggested that the cause of water adhesion to the tiles after
pre-treatment was the cold rinse of the product. Mr. Plunkett
also advised Mr. Crockett that the dry-off oven could he
improved for $1,500.
Mr. Neale gave evidence that the plant was designed on
the basis of a hot wash and rinse and this facilitated the
drying of the product in the dry-off oven. Mr. Bradford gave
evidence that when he visited the plant in October 1983, the
dry-off oven was working satisfactorily. Mr. Neale said that
the faults in the burners were caused by a lack of maintenance.
The burners were mounted beside the bottom of two tanks which
were themselves placed in concrete pits. Photographs were
tendered in evidence which depicted water seepage in the bottom
of the concrete pits adjacent to the burners. Rather than have
the burners repaired, as Mr. Plunkett recommended, and, if
necessary, the dry-off oven improved, Mr. Crockett has employed
a person to blow off the water with compressed air which, of
all of the options open to him, seems to be the least
satisfactory.
Mr. Crockett gave evidence that whilst a suitable
product was produced, this was only so if the line were
operated at a speed of 0.7 metres per minute, whereas the plant
was designed to run at a speed of 1.37 metres per minute, as is
indicated in the terms of the proposal. The slow speed, in Mr.
Crockett's view, led to greater cost of production, and this
56.
indicated a failure to meet the specification in the proposal.
However, when the plant was newly commissioned in October 1983,
Mr. Bradford had it operating at between 1.2 and 1.3 metres per
minute and producing tiles of a quality acceptable to Mr.
Crockett.
The applicants did not explain with any clarity why
the speed had since declined to 0.7 metres per minute. The
respondents invite me to infer, and I do infer, that the
reduction in speed is the result not of design defect, but of
general lack of maintenance and, in particular, a failure to
keep the cure oven in a state approximating to that when it was
commissioned. Once the reflectors in the cure oven are
contaminated with powder, longer exposure is needed to cure the
tiles and for that longer exposure slower passage through the
oven is required. There was a considerable body of evidence,
including photographs, of escaped powder throughout the plant
in general and near the automatic powder booth in particular.
This is adjacent to zone 1 of the cure oven. Mr. Bradford was
operating the three zones of the oven at 40% of their heat
capacity in 1983. In October 1984, Mr. Plunkett advised Mr.
Crockett that it was necessary to operate zone 1 of the oven at
100% of heat capacity. At that time, zones 2 and 3 were
operating at 25% of capacity. The sharp increase in power
input in zone 1 is consistent with powder contamination of the
reflectors in that zone.
A test was conducted by Mr. Plunkett to measure
temperature variation within the cure oven. Sensors were
placed in various positions on a 1,200mm x 350mm perforated
tile. The test was conducted in August 1987, after the trial
57.
had commenced. The reflectors had never been changed. They
had, however, been cleaned. The test disclosed a peak
temperature variation of 50°C. The maximum temperature
variation occurred between the middle of the tile and the
bottom of the tile, the bottom of the tile receiving the least
heat. The temperature at the top of the tile fell in
mid-range. This is consistent with the reflectors toward the
bottom of the oven being more heavily affected by powder
contamination thereby reducing their capacity to transfer heat.
On the day this test was conducted, Mr. Plunkett recommended
the reflectors be replaced.
Both Mr. Neale and Mr. Bonser are skilled and
experienced in the design and manufacture of powder coating
plants. I accept the thrust of their evidence that the plant
was of adequate design within the project budget and that it
requires service, maintenance and skilled operation to give
optimum performance. Mr. Crockett agreed in cross-examination,
that he had told Mr. Bonser he had a budget of somewhere
between $100,000 and $125,000 and that he was provided with a
plant to meet that budget. He agreed also that the plant was
not standard equipment but "one-off" and that it had variable
components such as line speed, oven temperatures and spray
pressure which were for the operator to control day to day.
Further, as Mr. Crockett also accepted, Gartenmann was
responsible for installation of the plant, and for its day to
day operation (including maintenance and quality control) and
if there were deficiencies in any of these matters, there would
be problems in production. I have indicated that there were
deficiencies in these matters.
58.
Despite the generality of the complaints by the
applicants in these proceedings, the only alterations made to
the plant by the applicants since it was commissioned have been
(a) alterations to a panel in the automatic powder
coating booth,
(b) the addition of "flight bars" to the conveyor,
(c) the purchase of two powder guns,
(d) the purchase of two new reciprocators.
As I have said, powder guns and reciprocators were
prime cost items, for the account of the applicants. The
number of guns to be used was a matter of trial and error after
the commissioning of the plant. The evidence does not show the
reciprocators were defective; they were replaced after some
nineteen months, with no complaint having been made to
Pollution Control or to Wagner. The alteration of the panel
was a minor matter of little cost. The flight bars were added
to the conveyor to facilitate the powder coating of the long
extrusions.
In my view, the applicants have not made out their
case on defective design.
CONCLUSION
By its Cross-Claim, Pollution Control claims from
Gartenmann the balance of the price for the plant, namely
$5,900. This occupied very little time at the hearing, there
being no dispute that if the Application failed, the
Cross-Claim succeeded.
In the result, the Application is dismissed with costs
(including any reserved costs) and Pollution Control has
59.
judgment in its favour on the Cross-Claim, with costs
(including any reserved costs). I will hear the parties as to
interest on the $5,900 recovered on the Cross-Claim;: see
Corporate Ventures Pty. Ltd. v Ian Turner & Partners Pty. Ltd.
(14 May 1987, unrep.).
60.
Schedule 1
ADDENDUM 1
TRICHLORETHYLENE SYSTEM
System Cost $89 ,000
Add Installation $11,000
TOTAL $100,000 Interest at 15% $15,000
Floor Space 2,400 sq.ft. at $4/sq.ft. $ 9,600
Trichlorethylene $1,000/month $ 1,200
Labor Two (2) operators at $20,000 p.a. $40 ,000
Power Cure Oven 80 kw
Trico 15 kw
Ancilliary 10 kw
105 kw at 8¢/kw hr x
1600 hrs p.a. $13,400
Powder Production Rate 3,000/day
Product dimensions:
1.2 x 0.3 = 0.36M? each
Say 0.46M2 each for
some covering of back
Assume 50 micron thickness and
1.2 S.G.
Coverage 17M2/kg
Allow 10% loss factor
coverage 15.3M2/kg
.. Powder Weight per panel =
0.45 x 1
15.3
= 0.29 kg
Annual Production:
= 3,000 x 5 x 46 weeks
= 690,000 panels
Powder usage = 690,000 x 0.29
= 20,000 kg p.a.
at $4/kg $80 ,000
TOTAL COST $170,000
Cost/product = 170,000 _
690,000 = 24.6¢ each
Ps 61.
@ as Schedule 2
ADDENDUM 2
PHOSPHATE SYSTEM
System $113,000
Add Installation $ 12,000
TOTAL $125,000
Interest at 15% $18,750
Floor Space 2,400 sq.ft. at $4/sq.ft. $ 9,600
Chemicals at $250/month $ 3,000
Labor Two (2) operators at $20,000 p.a. $40,000
Power Cure Oven 80 kw
Dry Off Oven 50 kw
Ancilliary _15 kw
145 kw at 8¢/kw hr x
1600 hrs p.a. $18,600
Gas 13 Therm @ 47¢ per therm
x 1,600 hrs $ 9,800
Powder $80 ,000
TOTAL COST $180 ,000
Cost/product = 180,000 -
690,000 = 26¢ each
® Note If TAK Chemical Solutions are utilised Gas cost would be
reduced by half i.e. to $4,900.00 p.a. due to lower
operating temperatures.
Counsel for the Applicants:
62.
Solicitors for the Applicants:
Counsel for the Respondents:
Solicitors for the Respondents:
Dates of hearing:
Date of Judgment:
I certify that this and
the preceding 61 pages are
a true copy of the Reasons
for Judgment of his Honour
Mr. Justice Gummow.
Associate Mash. pur
Dated: 23 December 1987
Mr. L.G. Foster
Messrs. Baker & McKenzie
Mr. G.H. Golvan
Messrs. Murray Stewart
& Fogarty
2, 5, 6, 9, 10, 11 and
12 March 1987
10, 11, 12, 13, 14, 17,
18, 19, 20 and 21
August 1987
1, 2, 3 and 4
September 1987.
23 December 1987