Bond Corporation Pty Ltd v Thiess Contractors Pty Ltd & Ors Thiess Contractors Pty Ltd v. Bond Corporation Pty Ltd [1988] FCA 1
Federal Court of Australia
Full text
Select any passage to save a personal note with optional tags.
PRACTICE AND PROCEDURE - construction contract - powers of
arbitrator - power to modify contractual rights - inability of
court to do so =- injunction restraining respondent from proceeding
with arbitration varied.
Northern Regional Health Authority v Derek Crouch Construction Co.
Ltd [1984] 1 OB 644
Neale v Richardson [1983] 1 All ER 753
Robins v Goddard [1905] 1 KB 294
BOND CORPORATION PTY LTD v THIESS CONTRACTORS PTY LTD and OVE ARUP
PTY LTD, ARUP PARTNERS PTY LTD, and OVE ARUP CONSULTANTS PTY LTD
THIESS CONTRACTORS PTY LTD v BOND CORPORATION PTY LTD
NO. WAG 114 of 1986
FRENCH J. bes
eal
4 TSANIYE
FEDERAL COURT
AUSTRALIA. CF
PRINCIPAL
REGISTRY
PERTH
20 January 1988
Meee inert See aD ore
;
ae
L
F
t
IN THE FEDERAL COURT
OF AUSTRALIA
WESTERN AUSTRALIA
DISTRICT REGISTRY
GENERAL DIVISION
NO. WAG 114 OF 1986
BETWEE N: BOND CORPORATION PTY LTD
Applicant
and
THIESS CONTRACTORS PTY LTD
First Respondent
and
OVE ARUP PTY LTD,
ARUP PARTNERS PTY LTD AND
OVE ARUP CONSULTANTS PTY LTD
Second Respondents
AND BETWEEN: THIESS CONTRACTORS PTY LTD
Cross-Claimant
and
BOND CORPORATION PTY LTD
Cross-Respondent
MINUTE OF ORDER
JUDGE MAKING ORDER: FRENCH J.
DATE OF ORDER: 20 January 1988
WHERE MADE: PERTH
THE COURT ORDERS THAT:-
1. The first respondent have leave to discontinue its
cross-claim.
2. The order made on 24 February 1987 be varied so that the
first respondent, its servants and agents be restrained
2.
until judgment be given in the applicant's action herein
or until earlier order from prosecuting beyond the
completion of all preliminary or interlocutory matters
an arbitration between the first respondent and the
applicant in accordance with the notice of reference to
arbitration served by the first respondent on 12
September 1986.
There will be liberty to any party to apply to further
vary or discharge this unjunction.
Costs.
Note: Settlement and entry of orders is dealt with in
Order 36 of the Federal Court Rules.
ae eee Ke ee ee
ta moe ree er -
poe ee weg ee
sr ecty sgicryctrere Sem
wo otmpen maar sae
pot me ee eee
IN THE FEDERAL COURT
OF AUSTRALIA
WESTERN AUSTRALIA
DISTRICT REGISTRY
eee
BETWEEN:
AND BETWEEN:
CORAM: FRENCH J.
20 January 1988
NO. WAG 114 OF 1986
BOND CORPORATION PTY LIMITED
Applicant
and
THIESS CONTRACTORS PTY LTD
First Respondent
and
OVE ARUP PTY LTD
ARUP PARTNERS PTY LTD and
OVE ARUP CONSULTANTS PTY LTD
Second Respondents
THIESS CONTRACTORS PTY LTD
Cross-Claimant
and
BOND CORPORATION PTY LTD
Cross-Respondent
REASONS FOR JUDGMENT
A question has arisen in this case as to the power of
the Court to fully resolve a dispute in which an engineer seeks to
invoke contractual machinery for the determination of variations
in sums otherwise payable to
construction contract.
it under a schedule of rates
2.
The proceedings were commenced on 24 November 1986.
They concern a dispute arising out of claims of time and cost
overruns and underpayments in connection with the provision of
road and associated earthworks for a redevelopment subdivision at
Millendon, near Perth. Cognate arbitration proceedings were
instituted by Thiess by Notice of Reference served on Bond on 12
September 1986. On 24 February 1987 Thiess was restrained by
order of this Court on the application of Bond, from further
prosecuting the arbitration. At that time no defences had been
filed.
On 17 March the Court ordered, on motion by Ove Arup,
that certain paragraphs of the statement of claim be struck out
and that Bond have leave to file an amended statement of claim by
30 March 1987. The matter proceeded on directions until 1 October
when, on a motion by Bond, orders were made to strike out a
portion of Thiess' de"ence and cross-claim and Ove Arup's defence.
Bond was ordered to provide certain particulars and a motion by
Thiess for a separate trial on the issue of quantum was dismissed.
Thiess, by motion filed on 28 October 1987, moved for
leave to discontinue its cross-claim and to lift the restraint
with respect to the prosecution of its arbitration with Bond.
Alternatively, it seeks a modification of the restraint to enable
it to complete all interlocutory matters in the arbitration.
hore
e
le
r
'
3.
In support of its motion Thiess contends that uts
dispute with Bond involves issues which can only be resolved by
the exercise of contractual powers conferred upon the engineer,
Ove Arup, or in lieu thereof, by an arbitrator appointed under the
terms of the contract. Its dispute cannot fully be resolved in
this Court, for the Court, it is said, lacks the "power" conferred
upon the arbitrator by the terms of the contract.
By the cross-claim Thiess pleaded a Schedule of Rates
Contract whereby it agreed with Bond to undertake and carry out
earthworks, roadworks and stormwater drainage works to create
approximately 170 divisional lots at Brigadoon Stage 1, Millendon
(para.5). The contract comprised a number of documents uncluding
a formal instrument of agreement and General Conditions of
Contract, AS2124/1981.
The cross-claim was explored in some detail in my
reasons for decision on the strike out motion, which were
published on 1 October 1987. It is sufficient for present
purposes to summarise its content by reference to the contentions
in 1t that Bond was liable to Thiess as follows:-
1. Pursuant to clause 40 of the General Conditions -
payment for variations to the works which were of
such number, nature and consequences that the
Schedule of Rates became inapplicable to them.
(paras. 11-19)
2. Pursuant to clause 23 - on the basis that the
variations were directions within the meaning of
clause 23 of the General Conditions - for loss and
expense beyond that provided for elsewhere in the
contract (paras. 20-22).
4.
3. Pursuant to clause 23 = by reason of delays on the
part of Ove Arup in providing notice of variations
- for loss and expense not provided for elsewhere
un the contract (paras. 23-26).
4. Pursuant to clause 23 - by reason of directed
deviations from the works programme ~- for loss and
expense not provided for elsewhere in the contract.
This basis for liability is pleaded in the
alternative to a plea basing liability on clause
34.3, which clause survived the strike out motion
(paras. 35-42).
5. Pursuant to clause 23 - by reason of delay on the
part of Ove Arup in granting a suspension of the
works under clause 35.2 of the contract - for loss
and expense not provided for elsewhere in the
contract (paras. 43-47).
6. Pursuant to clause 35.4 and alternatively clause 23
- the suspension being due to Ove Arup's action -
extra costs incurred as a result of the suspension
(paras. 48~51).
7. Pursuant to clause 23 and alternatively clause 36.4
and alternatively at common law —- by reason of
delays in Thiess' completion of the works and its
entitlement to a 33 week extension ~- loss and
expense (paras. 52-55).
As appears from the preceding, the cross-claim asserted
liabilities in large part relying upon clause 23 of the General
Conditions of Contract. But no entitlement to payment arises
under that clause until the Superintendent, Ove Arup, has
determined the amount of loss and expense and given notice in
writing thereof to Bond and Thiess. No such determination was
pleaded.
Clause 49 of the General Conditions provides for the
resolution of disputes or differences arising out of the contract
by a two tier decision-making process, first involving a
Stated
wens wns
meet rote.
5.
determination by the Superintendent and in the event
dissatisfaction with his determination, a reference
arbitration. The text of the clause is as follows:-
49.1 Procedure for Settlement of Disputes.
Notwithstanding the succeeding provisions of this
clause, the Contractor shall, 1£ the work under the
Contract has not been completed, and subject as
otherwise provided for in the Contract continue without
delay to perform and execute such work and in so doing
shall comply with all directions given by the
Superintendent pursuant to the Contract.
All disputes or differences arising out of the
Contract or concerning the performance or the
non-performance by either party of his obligations under
the Contract, whether before or after the completion of
the Works, shall be determined as follows:
(a) One or both of the parties shall notify the
Superintendent in writing that a dispute under
this clause has arisen and shall within
fourteen days of such notification submit the
matter at issue in writing with detailed
particulars to the Superintendent for
determination and the Superintendent shall,
within fourteen days after receipt thereof,
give his determination to both parties to the
Contract.
(b) If either party 1s dissatisfied with the
determination given by the Superintendent, or
1f he fails to give his determination,
pursuant to (a) of this clause, the
dissatisfied party may not later than
twenty-eight days after the Superintendent is
required to give his determination give notice
in writing to the other party requiring that
the matter at 1ssue be referred to arbitration
and specifying with detailed particulars the
matter at issue and thereupon the matter at
issue shall be determined by arbitration. If,
however, e1ther party does not within the said
period of twenty-eight days give such a notice
to the other party requiring that the matter
at issue be referred to arbitration the
determination given by the Superintendent
pursuant to (a) in this clause shall not be
subject to arbitration.
of
to
6.
(c) Arbitration shall be effected -
(1) by a single arbitrator mutually agreed
upon in writing between the Principal and
the Contractor;
or failing such agreement upon such an
arbitrator within one month after the notice
in writing aforesaid 1s received by one party
from the other party,
(11) by a single arbitrator nominated in
writing by the President of the
professional body nominated in the
Annexure and if no such annexure entry is
made by the National President of the
Institute of Arbitrators Australia, such
nominee not being an employee of the
Principal or of the Contractor or having
had any association with the Works;
or if the President fails or refuses so to
nominate such a person within one month after
having been requested by either party to make
such a nomination,
(iii)by an arbitrator appointed in accordance
with the provisions of the laws relating
to arbitration in force in the State or
Territory named in the Annexure hereto.
(d) A reference to arbitration under this Clause
49 shall be deemed to be a reference to
arbitration within the meaning of the laws
relating to arbitration in force in the State
or Territory named in the Annexure hereto and
the arbitration proceedings shall be conducted
in that State or Territory. The arbitrator
shall have all the powers conferred by those
laws and it shall be competent for him to
enter upon the reference without any further
or more Formal submission than is contained in
this clause. The arbitrator shall also have
the power to award interest.
49.2 Payments During Arbitration. Any payment due or
payable by the Principal shall not be withheld on
account of the arbitration proceedings unless' so
authorized by the Contractor or required by the
arbitrator."
owner es
SUES OTT eee
STINE SET rar erie ye
Sree
dee werner ag nee
7.
Thiess argues that an arbitrator would be empowered to
make determinations of a kind, which it says the Superintendent
ought to have made under cl.23. It further contends that these
are not determinations of a kind that the Court can make. [In
effect, cl.23 is said to provide a machinery for completing the
definition of the contractual relationship by reference to the
decision of a third party in circumstances where such definition
1s required.
The Notice of Reference to Arbitration dated 12
September 1986 invoked cl.49.1(b) of the General Conditions and
identified the matters at issue as being:-
",..in respect of the Contractor's claims for -
(a) payment of a reasonable sum or upon a quantum
meruit for work (including variations) carried out
by the Contractor; and/or
(b) payment pursuant to the Contract for work
(including variations) carried out by the
Contractor; and/or
(c) payment of other monies pursuant to the Contract;
and/or
(d) damages; and
(e) payment of interest
and the Superintendent's rejection thereof. Detailed
particulars are contained in the five (5) volumes
enclosed with this notice."
The order made in these proceedings on 24 February 1987
affecting the proposed arbitration was in the following terms:-
'
i}
i
"TL,
upon certain factors set out in the Reasons for
follows:-
(2)
(3)
(4)
(5)
8.
The First Respondent its servants or agents be
restrained until further order from prosecuting an
arbitration between the First Respondent and the
Applicant in accordance with the Notice = of
Reference to Arbitration served by the First
Respondent on 12 September 1986.
The First Respondent have liberty to apply to vary
or set aside this order on 48 hours' written
notice."
The restraint order was made in reliance, unter
The arbitration proceedings have not gone beyond
the point of the initial notice and appointment of
arbitrator.
There is no real prejudice demonstrated by the
first respondent were it to prosecute its claim as
a cross-claim in this court.
All disputes between all parties can be resolved in
these proceedings.
There are overlapping issues as between' the
proceedings in this court and the dispute referred
to arbitration which would lead to inconsistent
findings of fact and law as between the two
tribunals.
This is not a case in which the resolution of the
arbitration proceedings would lead to a resolution
of issues in this litigation."
alia,
Decision as
When the motion for the injunction was argued before me
on 15 and 16 January 1987, Thiess did not then make any point that
any aspect of the dispute referred to arbitration would not be
cognisable in this court. That point, as counsel for Bond has
said, is first taken on this motion, some 8 months after the
9.
restraint was imposed. It is a point which could have been taken
prior to the filing of the cross-claim and the extensive debate
that ensued on the strike out motion.
In spite of all that, there is no consideration of
prejudice to Bond or Ove Arup which would justify a refusal to
entertain and deal with Thiess' motion on its merits. The
critical 1ssue raised by the motion 1s whether or not the Court is
in a position to resolve all matters in dispute between the
parties. If 1t us, then nothing has changed since the restraint
was imposed. If it is not, then it would be unfair to deny Thiess
access to the only dispute resolution facility which can make the
determinations 1t seeks.
It 1s submitted that the arbitrator 1s authorised by
cl1.49.1(b) to determine "the matter at issue". In this case, the
matter at issue includes the alleged failure on the part of Ove
Arup to make appropriate determinations under cl.23. The
arbitrator, 1t 1s said, has a power to substitute his view for
that of the Superintendent under the contract and to make
appropriate determinations or decisions. Bond argues that the
question reduces to one of whether Ove Arup has acted in
accordance with the strictures of cl.23.1 which provides:-
"The Superintendent shall exercise in a reasonable and
equitable manner the powers conferred on him by the
Contract."
pan wae:
10.
This is, 1t is said, a duty cognisable by a court of
law. Though it imposes no contractual obligation on Ove Arup, its
breach 1s a breach by Bond. There is little reported case law on
the question of the extent of the respective powers of court and
arbitrator in a case such as the present. The only English
authority directly on point 1s the decision of the Court of Appeal
in Northern Regional Health Authority v Derek Crouch Construction
Co. Ltd [1984] 1 QB 644. There the relevant contract empowered
the arbitrator to "open up, review and revise any certificate,
opinion, decision, requirement or notice" given by the building
owner's architect. Appealing against the refusal by an official
referee to grant injunctions restraining arbitration the building
owner contended that it was an implied term of the building
contract that if the parties should litigate rather than
arbitrate, the court would have the same powers as the arbitrator.
The Court of Appeal rejected this argument. Dunn Ld at 664 said:-
"In my judgment it is not necessary to imply the term
suggested in clause 35. The contract gives the
architect wide discretionary powers as to the
supervision, evaluation and progress of the works. The
parties have agreed that disputes as to anything left to
the discretion of the architect should be referred to
arbitration, and clause 35 gives wide powers to the
arbitrator to review the exercise of the architect's
discretion and to substitute his own views for those of
the architect. Where parties have agreed on machinery
of that kind for the resolution of disputes, it is not
for the court to intervene and replace its own process
for the contractual machinery agreed by the parties."
Brown-Wilkinson LJ observed that in an action based on
contract the court can only enforce the agreement and has no power
to modify 1t in any way:-
r
f
'
'
a
t
'
i
'L
ll.
"Therefore, if the parties have agreed on a specified
machinery for establishing their obligations, the court
cannot substitute a different machinery. So, in this
contract the parties have agreed that certain rights and
obligations are to be determined by the certificate or
Opinion of the architect. In an action questioning the
validity of an architect's certificates or opinion given
or expressed under clauses 22 or 23 of the main
contract, in my judgment the court's jurisdiction would
be limited to deciding whether or not the certiricate or
opinion was legally invalid because given, for example,
in bad faith or in excess of his powers. In no
circumstances would the court have power to revise such
certificate or opinion solely on the ground that the
court would have reached a different conclusion since so
to do would be to interfere with the agreement of the
parties." (667)
His Honour identified two functions of the arbitrator,
the first to determine disputes on legal rights, the other to
modify contractual rights by substituting his own discretion for
that of the architect:-
"Therefore as a matter of principle I reach' the
conclusion that if this matter were to be litigated in
the High Court (whether before the official referee or a
judge) the court would not have power to open up, review
and revise certificates or opinions as it thought fit
since so to do would be to modify the contractual
obligations of the parties. The limit of the court's
jurisdiction would be to declare inoperative any
certificate or opinion given by the architect if the
architect had no power to give such certificate or
opinion or had otherwise erred in law in giving 1t. The
court could not (as an arbitrator could) substitute its
discretion for that of the architect." (667)
The Master of the Rolls, Sir John Donaldson, at 671,
said that the function of the court 1s to determine facts and to
enforce the contractual rights of the parties. The arbitrator
under the contract in question however, had a double function:-
ee Oe ee eg oe
- 12.
"He has first the right and the duty to review the
architect's decisions (in which I include certificates,
opinions, requirements and notices) and, 1f appropriate,
substitute his own. Second, he has to declare the
rights of the parties on the basis of the situation
produced by his own revising activity. The Latter is
truly an arbitrator's Function. The former 1s not."
In my opinion, the power given to the arbitrator in
cl.49.1{(b) to determine the "matter at issue" 1s wide enough to
encompass substitution of his own determination for any disputed
determination of the Superintendent. To that extent the powers he
zs given import the two functions identified by Donaldson MR in
the Crouch case.
The decision in Neale v Richardson [1938] 1 All ER 753
was cited but is, I think, distinguishable from the present case
on the same basis that Sir John Donaldson MR distinguished it in
Crouch. In Neale v Richardson the issue of a final certificate
was a condition precedent to payment and the architect refused to
issue it. The court held that as the architect declined to act
and no arbitrator was appointed, it was able to determine the
rights of the parties without regard to the absence of the
certificate. As the Master of the Rolls said in Crouch at 671:-
"This seems to me to be very different from deciding
that the court can substitute itself for the architect
or exercise the powers of an arbitrator under a clause
such as the J.C.T. clause. The court in Neale v
Richardson [1938] 1 All ER 753 was merely performing its
normal function, uninhibited by the absence of the
certificate."
iz
f
Tyre cae cee oe
wot
13.
Robins v Goddard [1905] 1 KB 294, was a case in which a
contractor sued a building owner to recover sums due on
certificates by the architect. The defendant said by way of
defence and counterclaim that the work and materials supplied were
defective and unsuitable. At trial the certificates were held to
be conclusive, but on appeal it was held that the arbitration
clause destroyed the finality of the certificates and that
consequently the Gefendant was entitled to set up the defence and
counterclaim for the action. At 303 Stirling LJ said:-
"The arbitrator 1s to have power (with certain
exceptions not including the certificates in question)
to open up, review, and revise, among other things, any
certificate, and to treat the matter before him as if no
certificate had been' given. These certificates,
therefore, were not intended to be absolutely binding
and conclusive. No doubt on an application made at the
proper time the dispute might have been referred to
arbitration; but it has not been referred. and the
Matter remained open for decision under the ordinary
jurisdiction of the Courts, and the defendant was
entitled to his ordinary legal remedies and to have his
case heard."
To say that, is not to say that the court could exercise
the arbitrator's substituted decision-making functions.
It might well be possible for Thiess to raise a
cross-claim based upon a failure by Ove Arup, attributable to
Bond, to exercise "in a reasonable and equitable manner" the
powers conferred on 1t by the contract. That course however, may
not offer the same direct substitutive remedial power as is
available to the arbitrator. I say "may not" because it is
'
br
'
'>
'
'
'
few ep eve e
14,
conceivable that the court might be able by some appropriate
exercise of its remedial powers or of a combination thereof, to
rrive at a similar result. It remains to be demonstrated that
the court could do so. In the circumstances and given the
significance of cl. 23 determinations to Thiess' cross-claim I
think the best course for the present is to allow it to proceed at
least through all interlocutory stages necessary to prepare for
the hearing of the arbitration. The matters at issue as disclosed
in the Notice of Reference are wide in their terms and as Framed
they are capable of encompassing issues able to be resolved by the
court. No doubt in the course of the interlocutory proceedings in
the arbitration, the issues will be better defined than they are
at present.
The parties may come back to the court in that regard if
it is thought that some confinement of the matters to be raised
before the arbitrator is appropriate to avoid unnecessary overlap
between the arbitral and the judicial proceedings.
I propose therefore to order that Thiess have leave to
discontinue its cross-claim and to vary the injunction in order
that it may proceed through the necessary interlocutory stages in
connection with the arbitration.
co oncte
wwe ane
15.
I certify that the preceding
fourteen (14) pages are a true copy
ef the Reasons for Judgment of His
Honour Justice French.
Associate: Moveols Wee
pate: LO Gun) \A8
Counsel for the Applicant and Cross-Respondent: Mr P. Tottle
Solicitors for the Applicant and Cross-Respondent: Robinson Cox
Counsel for the First Respondent and Cross-Claimant: Mr P.
Clifford
Solicitors for the First Respondent and Cross-Claimant: Freehill
Hollingdale & Page
Counsel for the Second Respondents: Mr L. James
Solicitors for the Second Respondents: Kott Gunning
Date of Hearing: 28 October 1987
Date of Judgment: 20 January 1988