Select any passage to save a personal note with optional tags.
CATCHWORDS
TRADE PRACTICES - Contract for the erection of a dwelling
house - Alleged representation by builder that it was feasible
to erect a house of a particular design upon the land -
Quantification of damages.
CONTRACT LAW - Contract to erect house in accordance with a
particular design - Quantification of damages for breach.
SECRET COMMISSION - Commission received by agent of applicant
from first respondent - Recoverability.
Trade Practices Act 1974 s6.52, 82.
NSW G.217 of 1987
JILL CHRISTINE TURNER v HUDU PTY LIMITED trading as HENDRIKS &
&
Wilcox J
Sydney
8 July 19868
IN THE FEDERAL COURT OF AUSTRALIA
NEW SOUTH WALES DISTRICT REGISTRY
GENERAL DIVISION
CORAM
PLACE:
DATE:
No. NSW G.217 of 1987
BETWEEN: JILL CHRISTINE TURNER
Applicant
AND: HUDU PTY LIMITED trading as
HENDRIKS & ROBERTS
First Respondent
HOME BUILDERS CORPORATION
OF NSW PTY LIMITED
Second Respondent
AND BETWEEN: HUDU PTY LIMITED trading as
H KS & ROBER
WILCOX J
SYDNEY
8 JULY 1988
Cross-Claimant
AND: JILL CHRISTINE TURNER
Cross-Respondent
MINUTES OF ORDER
THE COURT ORDERS THAT:
2.
Judgment be entered in favour of Jill Christine
Turner against Hudu Pty Limited in the principal
proceeding in the sum of twenty-eight thousand nine
hundred and twenty-two dollars and seventy-seven
cents ($28,922.77).
Judgment be entered in favour of Hudu Pty Limited
against Jill Christine Turner in the cross-claim in
the sum of twenty-one thousand one hundred and
twenty-three dollars and three cents ($21,123.03).
The amount of the judgment entered under order 2 be
set off against the amount of the judgment entered
under order 1, leaving a net balance of seven
thousand seven hundred and ninety-nine dollars and
seventy-four cents ($7,799.74) payable to Jill
Christine Turner by Hudu Pty Limited.
Judgment be entered in favour of Jill Christine
Turner against Home Builders Corporation Pty Limited
in the sum of one thousand seven hundred and
ninety-six dollars and forty cents ($1,796.40).
The respondents, Hudu Pty Limited and Home Builders
Corporation Limited, pay to Jill Christine Turner her
costs of these proceedings provided that, as between
themselves, the said respondents shall bear the
Note:
burden of the costs so ordered to be paid in the
proportions Hudu Pty Limited 90% and Home Builders
Corporation Limited 10% and each of the said
respondents shall indemnify the other in relation to
costs paid to Jill Christine Turner in accordance
with those proportions.
Settlement and entry of orders is dealt with in Order
36 of the Federal Court Rules.
IN THE FEDERAL COURT OF AUSTRALIA
NEW SOUTH WALES DISTRICT REGISTRY No. NSW G.217 of 1987
GENERAL DIVISION
BETWEEN: JILL CHRISTINE TURNER
Applicant
AND: HUDU PTY LIMITED trading as
HENDRIKS & ROBERT.
First Respondent
HOME BUILDERS CORPORATION
OF _NSW PTY LIMITED
Second Respondent
AND BETWEEN: HUDU PTY LIMITED trading as
H R & ROBERT
Cross—-Claimant
AND: JILL CHRISTINE TURNER
Cross-—Respondent
CORAM: WILCOX J
PLACE: SYDNEY
DATE: 8 JULY 1988
REASONS FOR JUDGMENT
There is before the Court a single principal
proceeding in which separate claims are made against each of
two respondents: Hudu Pty Limited, a builder carrying on
business in the Gosford district under the title Hendriks «&
Roberts, and Home Builders Corporation of NSW Pty Limited, a
company which, in 1985, carried on business as an agent for
builders. The two claims are linked in that they both arise
out of a decision by the applicant, Jill Christine Turner, to
have a dwelling house erected upon a vacant allotment owned by
her at Terrigal, on the New South Wales Central Coast. The
evidence in each matter overlaps, to some extent, and each
claim is founded -- at least in part -- on s.52 of the Trade
Practices Act 1974. But each has to be considered separately.
Ms Turner's land is known as lot 43, Duncan Street,
Terrigal. The allotment has a westerly aspect. In its natural
condition, the land sloped, at a relatively steep but even
grade, from Duncan Street to the rear boundary. No doubt
because of the slope of the land, Ms Turner had always had in
mind that, when she constructed a house upon the allotment,
she would wish to have a split level building.
In about May 1985, Ms Turner contacted Mr Paul
Wilson, a principal of a building company known as TRK
Constructions Pty Limited. She gave to Mr Wilson a sketch
which she had prepared showing a floor plan for a
three-bedroom split level home. Mr Wilson forwarded to Ms
Turner a letter dated 25 May 1985 quoting the sum of $42,652
as a price for the erection of a house in accordance with the
sketch plan. The quotation was to include all drafting,
engineering, council and survey fees.
Miss Turner did not act on this quotation
immediately. Early in October 1985, apparently at the
suggestion of an officer of her building society, she
contacted a Mr Paul Kelly, an employee of Home Builders
Corporation. During the course of her initial telephone
conversation, she sought information as to the nature of his
organization. According to the evidence of Ms Turner, Mr
Kelly informed her "that the Corporation acted on behalf of
the consumer, looking out for their interests really in the
building game, protecting them really from the pitfalls that
can be associated with the industry and they can really act as
a mediator between that person and the builder and against any
unfair advantage on the builder's behalf and just generally
oversee negotiations and just make sure everything was above
board and fair and honest". Mr Kelly told Ms Turner that she
would not have to pay any money, that the corporation offered
a free service to the public. Apparently Ms Turner told Mr
Kelly that she already had a quotation and Mr Kelly told her
that he would "ask around their builders for a comparable
figure on the selected plan" in order to protect her
interests. Following this conversation Ms Turner sent to Mr
Kelly a copy of the quotation prepared by Mr Wilson and the
sketch plan upon which it was based.
On 12 October 1985 Ms Turner visited Mr Kelly at the
offices of Home Builders Corporation. She was accompanied by
her sister, Anne Gorvin, and a friend, Kurt Seeback. Mr Kelly
informed Ms Turner that he had investigated Mr Wilson and had
found that he was unreliable and not trustworthy, that his
last project was incomplete due to a lack of funds and that he
was in dispute with a client. Mr Kelly expressed the opinion
that Mr Wilson was "a bad risk and unreliable" and suggested
to Ms Turner that she would be better off with one of the
builders on their list rather than taking an unnecessary bad
risk.
According to the evidence given before me by Mr
Wilson, none of this was true. Despite Mr Kelly's denial, I
accept the evidence of Ms Turner, which is corroborated by Ms
Gorvin and Mr Seeback, that he did speak disparagingly of Mr
Wilson. It is difficult to escape the conclusion that he did
so for the purpose of steering Ms Turner in the direction of
one of his client builders and thereby enabling his company to
earn a commission.
During the course of this discussion, the party was
joined by Mr Mark Hicks, Managing Director of Hudu. Mr Hicks
had already been furnished with a copy of the plan prepared by
Ms Turner and there was then a general discussion regarding
the floor plan layout and also the lighting of the building.
During the course of the discussion a reference was made by Ms
Turner to the proposed siting of the house. She informed Mr
Hicks that the land was a sloping site and that she had always
wanted to have a split level home. According to Ms Turner,
she went on to say that she wanted the house "to sit on top of
the land". Ms Turner says that Mr Hicks responded to this by
saying "that will be right, yes, fine" and waved his hand. So
far as Ms Turner is aware, Mr Hicks had not then seen the
land.
The meeting ended upon the basis that Mr Hicks would
prepare a quotation. On 16 October 1985, Hudu submitted to Ms
Turner a quetation in the sum of $41,950. The quotation
included a reference to certain additional options.
Apparently Ms Turner discussed these options with Mr Kelly.
Some of the options were adopted and a revised tender in the
sum of $44,970 was submitted by Hudu on 25 October. This
tender included a provision that the plan and specification
would be prepared by Hudu "based upon sketch submitted". As
requested, Ms Turner paid a deposit of $1,000 on 29 October.
On the same day, Hudu signed a letter addressed to Home
Builders Corporation promising to pay that company a
commission of $1,796.40 as commission on the agreement between
Hudu and Ms Turner. $500 was paid forthwith, the balance
later. At no stage was Ms Turner informed that Home Builders
Corporation would seek, or that it was paid, any commission
from Hudu. Her belief was that Home Builders Corporation
provided a free service at government expense.
During November 1985, a plan and specification was
prepared for submission to the local council, Gosford City
Council. The plan was prepared by a draftswoman, employed by
Hudu, upon the instructions of Mr Hicks. According to Mr
Hicks, he inspected the site before the plan was prepared but,
to his knowledge, the draftswoman did not do so. He says that
he specifically instructed the draftswoman not to show any
excavation in this plan. The plan shows a layout
substantially similar to that on the sketch plan prepared by
Ms Turner. As envisaged by her, the building has two
different levels. The front level consists of an entry porch,
adjoining the carport at the left hand side of the building, a
lounge room and the main bedroom. The only entry to the front
of the house is from the carport. The floor plan shows a
single step from the carport into the entry porch, although
the site elevation indicates three steps in this position.
The floor level of the remainder of the house, as
depicted in the plan, is half a metre higher than that of the
lower level. Access to this higher level is gained by four
steps from the lounge to the dining room and also by two steps
from a small corridor outside the main bedroom to a corridor
leading past the bathroom towards the two rear bedrooms.
The plan contains two side elevations and a
cross-section showing the split. In each of those drawings
there is a bold line which, it is agreed, represents the
ground level. Furthermore, it is agreed that the form of the
line is that habitually used to indicate natural ground level,
as distinct from excavated ground level. Except in the
position of the carport, the line slopes across the site ina
manner consistent with its being intended to indicate a
natural fall. The drawings, particularly the cross-section,
clearly indicate that the building is intended to stand free
of the ground, except in the carport area.
There is no reference on the plan to any excavation
of the site, except for a notation on the site plan: "cut and
fill to carport area only". The area, the subject of this
notation, is cross-hatched and it corresponds with the area of
the carport as shown on the floor plan.
Two notes inscribed on the plan ought to be
mentioned. In the information column on the right hand side
of the plan there is a note: "Ground levels are approximate
only". Amongst the notes immediately adjoining the floor plan
is a note: "The 'split' in this residence may differ to that
shown. Builder will determine 'split' on site according to
falls in land".
The council approved the plan and specification,
apparently in either late November or December. On 20
December 1985, Hudu wrote to Ms Turner enclosing a copy of the
proposed contract and the council's stamped plans and
specification. The letter suggested that Ms Turner consult
her solicitor or the building society and that, when the
documents were approved, she make an arrangement for an
appointment at which the contract could be signed. It is not
clear whether Ms Turner obtained any advice regarding the
contract documents. However, she did in fact attend a meeting
at the office of Hudu on 1 February 1986, when the contract
was signed.
On 26 February 1986, Hudu wrote to Ms Turner a letter
which contained a report made by Slater, Jessop & Armstrong
Pty Limited, consulting engineers. The report referred to an
inspection which had taken place on 12 February and the
results obtained from a test bore sunk on the property. The
engineers expressed the view "that the strata found 500mm
below surface is suitable to carry the proposed loading". The
report went on to specify the footings and piers which would
be required on the site. Reference was made to the necessity
to make special provision for the foundations in the vicinity
of the building upon the adjoining allotment to the north, lot
42. That building had been constructed in an excavation made
to the allotment. The covering letter from Hudu informed Ms
Turner that there would be an additional cost of $478 for the
footings and piers and that she had the option of determining
the contract if she was unwilling or unable to meet this
additional cost. Ms Turner accepted the extra expense.
Some time in late February or early March, the site
was substantially excavated. The excavation involved the
whole of the land upon which the dwelling was intended to be
constructed and it had the effect of flattening out the site
so that it then conformed, broadly at least, with the shape of
the land as shown on the approved plan. A further effect of
the excavation was to lower the level of the rear wall of the
building, as compared with its position if it had been erected
upon the natural ground level, by 1.3 to 1.5 metres; the
difference being explained by a slight cross-fall. [In the way
in which the excavation was finished, there was left a steep
batter at the rear of the house. The top of the batter
extends above the top of the windows in the back wall of the
house, as it is now constructed.
Following the excavation, the construction of the
building proceeded rapidly. There was contact between Ms
Turner and Hudu during the course of construction. A number
of letters were exchanged regarding minor building details
and, according to Ms Turner, she spoke to Mr Hicks upon a
couple of occasions. However, although Ms Turner inspected
the site from time to time, she did not make any comment or
complaint regarding the excavation.
By letter dated 3 April 1986, Hudu wrote to Ms Turner
informing her that the council required her to retain the side
of the excavated area and that the council would not pass the
premises for habitation unless this work was done. Hudu
quoted a cost of $1,500 for a retaining wall. This wall was
to be erected upon the common boundary of lot 43 and lot 44.
Lot 44 adjoined to the south and contained a house erected
upon the unexcavated allotment. The letter went on: "Due to
the extra costs that would be caused to you by stopping the
works and awaiting your reply and the extra costs that would
be caused by not doing the footing at this stage we are
continuing and pouring the footing". Ms Turner was asked to
respond accepting one of two alternatives: to have Hudu carry
out the footing for the retaining work only, at a cost of
$700, or to carry out both the footing and the retaining wall
10.
itself, at a cost of $1,500. On 13 May 1986 Ms Turner wrote
to Hudu about a number of matters. In this letter she stated:
"I also advise that I formally accept the cost of $1,500 for
the retaining wall to be constructed along the side of the
house". Thereafter Hudu constructed the retaining wall.
The house reached the stage of substantial completion
at the beginning of August 1986. On 7 August Hudu wrote to Ms
Turner enclosing an account for extras amounting to $7,851.24.
The letter requested payment of this amount together with the
supply of a letter of satisfaction to enable Hudu to receive
from the building society the balance of the original contract
sum. Although this sum was not specified in the letter, it is
agreed between the parties that the balance then owing on the
original contract sum was $8,555. This amount is still
outstanding.
Ms Turner did not accede to the requests contained in
the letter of 7 August. She had, in the meantime, taken steps
to investigate the position regarding excavation. She
retained a surveyor, J R Mortensen Pty Limited. On 11 July
1986 that company furnished a report to Ms Turner of a survey
made by Mr Mortensen of the land. The report contained the
comment that the natural fall of the land is much steeper than
was indicated on the building plan. Mr Mortensen attached to
the report a photocopy of the two side elevations shown on the
building plan on which he marked in red the natural fall of
the land prior to excavation. As already mentioned, this
shows that, at the rear, the building was 1.3 to 1.5 metres
11.
lower than it would have been if erected on the natural ground
level. The report also contained some photographs upon which
the natural ground level was marked in red.
At about this time Ms Turner also consulted Mr Norton
G King, a building consultant. Mr King inspected the plan and
specification and the building and he advised that the
building had not been erected in accordance with the plans, as
a result of which extra expenses had been, and would be,
incurred. Thereafter Ms Turner declined to make any further
payments to Hudu. There was correspondence between the
parties, and their solicitors, regarding access to the
building for inspection purposes -- Hudu taking the position
that payment was required before possession would be given to
Ms Turner -- regarding certain incomplete and defective items
and in relation to the possible resolution of the dispute. On
19 January 1987 the solicitors for Ms Turner suggested a
meeting to see whether a settlement could be reached but
Hudu's solicitors responded by demanding payment of the full
amount of the claim beforehand. On 20 February the
applicant's solicitors forwarded a copy of Mr King's report,
with other documents, and again suggested a conference to
explore settlement. There was no positive response and, on 25
March 1987, the solicitors again wrote. This letter contained
the following paragraph:
"We confirm earlier correspondence to you that
our client is paying rent in the vicinity of
$120.00 per week whilst the property remains
incomplete and we also confirm the actions of
your client some time ago in changing the
locks on the property to ensure that it
retained control of the site. The rent being
paid for alternative accommodation by our
12.
client forms part of her claim as she is also
having to pay her mortgage payments to the
building society in respect of her loan on the
property and obviously the longer it takes for
the suggested conference to be held the more
difficult it will become to reach a settlement
in view of our client's claim increasing at
the rate of approximately $120.00 per week."
The response to this approach was a letter of 23 April 1987 in
which the solicitors for Hudu, on behalf of their client,
threatened to commence proceedings for the amount claimed to
be owing. But, before they did so and on 20 May 1987, the
present proceeding was commenced.
The claim made by Ms Turner against Hudu is put in a
number of ways. As I have said, reliance is placed upon s.52
of the Trade Practices Act, the argument being that Mr Hicks'
response to Ms Turner's intimation that she wanted the house
"to sit on top of the land" constituted a representation as to
the feasibility of the plan she had proposed for the site. I
have difficulty in seeing that there was such a representation
but I do not think that it is necessary to reach a concluded
opinion upon that matter because I am of the opinion that Ms
Turner is entitled to succeed upon at least one of her
alternative claims: breach of contract. There is no
jurisdictional problem about the matter being disposed of on
this basis. Hudu expressly concedes that the 8.52 claim was
made bona fide and I am of the view that this concession is
properly made. The damages available to Ms Turner upon her
contract claim are not less generous than those which would be
recoverable under 8.82 of the Trade Practices Act for a breach
of 8.52.
13.
The contract claim made by Ms Turner is pleaded in a
number of ways but it includes the simple claim that Hudu
failed to execute the works properly, that is in accordance
with the agreed plans and specifications. I think that this
case is made out.
There is no doubt that the building, as erected,
departs from the agreed plan. The plan shows no site
excavation, other than to the carport area, whereas it is a
feature of the building as erected that substantial excavation
has taken place. But Hudu says that the discrepancy between
the agreed plan and the building as erected does not
constitute a breach of contract because there was a prior
understanding between Ms Turner and Mr Hicks that the site
would be excavated to the extent necessary to accommodate the
plan. Ms Turner denies that any such agreement was made.
I have no hesitation in accepting Ms Turner's
evidence upon this question. According to Mr Hicks, he had
several meetings with Ms Turner before the contract was
signed. On each of these occasions, he says, at least one
person other than Ms Turner was present: either Mr Kelly, Ms
Gorvin or Mr Seeback. According to him, on at least one
occasion there was considerable discussion about the
suitability of the site during which he "told her quite
plainly the plan did not suit the block. Ms Turner was quite
adamant that was the plan she wanted. I was quite sure,
adamant, that it did not suit". On that occasion, he said,
there was much talk regarding steps, etc. None of this was
14.
put to any of the three people who, according to Mr Hicks,
might have been present. The alleged conversation related to
a matter at the heart of this case; it is inconceivable that,
armed with instructions upon the matter, counsel for Hudu
would have failed to put questions to these witnesses about
the conversation. It is true that Mr Kelly was an
unsatisfactory witness, who claimed not to recall many
important matters, but this was a conversation of some moment.
It is also true that Mr Kelly claimed himself to have warned
Ms Turner about the unsuitability of the plan -- a claim which
was also not put to Ms Gorvin or Mr Seeback and which I do not
believe -- but that is a different subject matter from the
alleged conversation between Mr Hicks and Ms Turner.
However, there is an even better reason than the
conduct of this case for rejecting Mr Hicks' evidence
regarding an agreement for excavation: the form of the plans
themselves. These plans were drawn under the direct
supervision of Mr Hicks, at a time later than the alleged
conversation with Ms Turner when it was agreed that the whole
of the building site would have to be excavated. Yet there is
no hint of bulk excavation upon the plan. The plan clearly
suggests that the building will be erected upon the existing
slope, save for some cut and fill in the carport. To erect
the home in an excavation, to a different fall, would be to
depart from the plans in a significant manner; as is
indicated by the perceived need to construct retaining walls
to hold firm the excavation. Acceptance of Mr Hicks' evidence
would involve the attribution to him of an intention to
15.
mislead the local council upon a material question and to
commit an offence by erecting the building in a manner
inconsistent with the plan: see Local Government Act (NSW)
1919 8.306. What motive would there be for such behaviour,
agreement having already been reached with Ms Turner upon the
need for excavation? Why not show the excavation upon the
plan?
The point goes further than the mere absence from the
plan of any reference to excavation. The plan clearly
suggests that the house is to be fitted to the natural fall of
the land, not that the land is to be moulded to the
constraints of the house plan. I have already quoted the plan
note regarding adjustment of the "split" shown on the plan.
No adjustment would be necessary if the site was to be shaped
before building commenced. The site could be levelled to the
exigencies of the plan. Furthermore, the adjustment was to be
made "on site according to falls in land". Mr Hicks expressly
agreed in his evidence that the words "falls in land" were a
reference to the natural fall of the land. But what would be
the relevance of that fall upon an excavated site?
A further pointer to the truth, in my opinion, is
provided by the engineer's report regarding footings and
piers. It will be recalled that this report referred to a
strata 500mm below surface which was suitable to carry the
proposed building. The engineer's report proceeded upon the
basis that this strata would be used, and Hudu made its demand
for extra money for the footings and piers upon this basis.
16.
Yet excavation in the manner said to have been agreed would,
at least, have substantially interfered with this strata. The
engineers would have had to re-assess the position. I think
that the report makes clear that they did not envisage
excavation; yet an experienced builder would realise the
necessity of disclosing to the engineers the intention to
excavate in asking them to advise upon the necessary footings
and piers.
I think that the truth is that insufficient attention
was given by Hudu to the problems of this site. I do not
accept that Mr Hicks inspected the site before the plan was
drawn. Had he done so he would have been alerted to the fact
that the floor plan proposed by Ms Turner was not, without
adjustment, suitable for the site. He would have proposed
some amendments. Had Ms Turner proved unreasonable he would
have had the option of declining the job. But I think that
Hudu committed itself to the contract without realising that
there was a problem and, when Mr Hicks and/or Mr Hendriks
found that there was a problem, it was decided to resolve the
problem by excavating the site. Excavation was, of course,
one possible solution. But it was the prerogative of Ms
Turner, not of Budu, to decide how to resolve the matter. The
company was not justified in unilaterally departing from its
contractual obligation and in delivering to her at the end of
the project a building which, because of its position, is
materially different from that required by the plan.
17.
In reaching the above conclusions I do not overlook
the submission made by counsel for Hudu that Ms Turner's
failure to complain to the company of the making of the
excavation until August, when the final payment was due,
indicates that she had earlier agreed to the excavation.
Under some circumstances a failure to complain affords
powerful evidence that a particular event is in accordance
with the prior consent of the person who might otherwise be
expected to complain. But in this case there is no middle
ground. It is not as if Hudu's case was that there was an
oral variation of the agreement after the plan was drawn. Mr
Hicks' evidence is that all this was agreed before the plan
was drawn; and, for the reasons indicated, that evidence is
simply not credible.
Moreover, in assessing Ms Turner's silence to Hudu,
it is relevant to note that, in early July, she had arranged
an inspection and survey by Mr Mortensen. She was clearly
dissatisfied before August. Although I find it a little
surprising that she said nothing to Mr Hicks immediately upon
discovering the excavation, it is understandable that she
would wish to have the situation expertly assessed before
taking it up with Hudu. It is not as if an earlier comment
could save the situation. From her point of view the damage
was done when she first discovered the excavation.
18.
I am satisfied, from the evidence of Mr King, that a
direct consequence of the incorrect siting of the building
will be the necessity to perform the following additional
work:
Work already carried out by Hudu
$ $
Retaining wall 1500.00
Remove excavated
material 429.00
Rock excavation 270.50
Extra access cost 349.00
2548.50
plus 20% margin 509.70 3058.20
Work yet to be performed
Extension of southern
retaining wall 1280.00
Removal of excavated
material at front 630.00
Reinstatement of ground 3780.00 5690.00
8748.20
I do not allow the sum of $478.00 claimed for footings and
piers. As I have indicated, I am of the opinion that the
engineers' view was that this cost would be incurred if the
house was built upon the unexcavated site.
To this sum must be added any diminution in value
occasioned by the fact that, even after those works are
carried out, the building will be sited lower than envisaged
by the plans. Notwithstanding the evidence of Mr A T Starkey,
a qualified valuer called on behalf of Hudu, I am satisfied
19.
that there will be a loss of value. With every respect to Mr
Starkey, I think that he has neither fully appreciated the
effect of the change nor adequately investigated local market
conditions. I prefer the evidence of Mrs G A Everson, an
experienced valuer who has investigated sales in the immediate
area. Mrs Everson expressed the view that the house, as
constructed in the excavation, would be worth about $9,000
less than if it had been erected at the correct level. I
appreciate that it would not have been possible to build upon
the unexcavated site a home which exactly followed the agreed
plan. Some modification, even if only to increase the number
of internal stairs, would certainly have been required.
Whether such a modification would have increased or decreased
the cost of the building was not explored at the trial and I
do not think that I should make any assumption about that
matter, one way of the other. I therefore accept the figure
of $9,000 loss of value without making any adjustment for any
saving achieved or extra expense incurred, as a result of any
necessary design modifications.
Mrs Everson also expressed the view that the house
now bore a "stigma", resulting from its lengthy period of
non-occupation, which might excite purchaser resistance. She
thought that an additional $1,000 should be allowed to
compensate for the stigma. However, this argument assumes
that the relevant date, for consideration of any loss of value
consequential upon the breach of contract, is mid-1988. I do
not think that this is correct. The relevant date is that
20.
upon which the house might have been sold by Ms Turner, had
she wished to extricate herself from her predicament by sale.
For reasons which I will indicate, I put this time at 31 July
1987. I am not satisfied that the delay till that day was
such as to attract any financially significant stigma.
In addition to the above, Ms Turner makes two claims:
for the cost of completing and rectifying various items and
for rent. She also claims interest upon any balance payable
to her. As to the first item, I am relieved from attempting
to quantify the cost of attending to the list of minor items
identified by Mr King by the fact that the parties have
sensibly reached an agreement, reduced to a written
undertaking given to the Court, as to what will be done.
Should there be any breach of that undertaking, Ms Turner will
have an appropriate remedy. I can deal with damages upon the
basis that this work will be done without cost to Ms Turner.
It is only fair to Hudu to say that it seems that Hudu was
always willing to attend to any legitimate complaints about
these matters and that it would probably have done so long
ago, but for the larger dispute between the parties.
The claim for rent is founded upon the circumstance
that Hudu has declined to give possession of the house to Ms
Turner until it received the moneys claimed by it from her.
The company argues that it is entitled to take this attitude
by virtue of cl.27(g) of the contract between the parties.
That sub-clause reads:
21.
"(g) Upon payment by the Owner of all monies
due to the Builder, the Builder shall at
the request of the Owner make available
the keys to the Works and upon acceptance
thereof the Owner shall be deemed to have
entered into actual possession thereof
and to have acknowledged that the works
have been completed in accordance with
this Agreement whereupon the Builder
shall be relieved and discharged from all
responsibility hereunder save for any
liability under the Defects Liability
Period. Upon acceptance of the keys as
aforesaid the Works shall in all respects
be at the sole risk of the Owner."
It is clear that the amount claimed by Hudu for the
balance of purchase price and for extras, being the sum of
$16,406.24, is due to the company; subject to any offset
against moneys payable by Hudu to Ms Turner. If, upon
balance, Ms Turner owes money to Hudu, Hudu is justified in
the stand which it took regarding the delivery of possession.
If, upon the other hand, no money is owing to Hudu, Hudu is
not justified in keeping Ms Turner out of possession of the
premises. In this eventuality, part of the damage suffered by
her is the burden of rent payments during such period as was
reasonably required to allow her to resolve the matter and to
obtain possession.
I have assessed the total loss sustained by Ms
Turner, being for extra costs of $8,748.20 and for loss of
value of $9,000.00, at $17,748.20. In an account made up in
August 1986 there should have been deducted the amount due to
Hudu, $16,406.24, leaving a balance of $1,341.96 due to Ms
Turner. It follows that cl.27(g) did not operate to entitle
Hudu to deny possession to Ms Turner and that a rental
22.
allowance ought to be made. But I do not think that it would
be fair to allow rent up to the present time. By August 1986,
when notice of practical completion was given, Ms Turner was
aware of the fact and extent of the excavation. She already
had obtained advice from Mr Mortensen. She received Mr King's
advice in early September. Although I appreciate and applaud
her desire to settle the dispute by negotiations, far too much
time was allowed to pass before the proceeding was commenced
in this Court. And the matter was not thereafter prosecuted
with notable expedition. I think that it is reasonable to say
that, with the benefit of a "flying start" in August 1986 and
treating the matter with the urgency it deserved, the
applicant and her advisers ought to have been able to secure
resolution of the matter -- if necessary by judgment in this
Court -- by the end of July 19867. Rent to that day, and that
day only, should be allowed.
The rent paid by Ms Turner was $70 per week for the
period 9 August 1986 to 28 November 1986, a period of 16
weeks. This figure amounts to $1,120.00. During the period
of 35 weeks from 28 November 1986 to 31 July 1987 she paid
rent of $120 per week -- a total of $4,200. The total rent
allowed should therefore be $5,320.
Both parties claim pre-judgment interest on the
moneys due to them. Each is entitled to such interest, but
the effect of the set-off is that interest will only be
actually paid upon the net balance. In calculating interest I
adopt the rate of 15% per annum, being a reasonable reflection
23.
of the cost of money during this period. However, interest on
the rent should be allowed only from the end of the rent
period, 31 July 1987.
In the result, there will be judgment for Ms Turner
against Hudu in the principal proceeding in the sum of
$28922.77, made up as follows:
$
Extra costs incurred 8748.20
Loss of value 9000.00
Loss of rent 5320.00
Interest at 15% pa on $17,748.20
from 7 August 1986 to date 5102.60
Interest at 15% pa on $5320.00
from 31 July 1987 to date 751.97
28922.77
There will be a judgment in the cross-claim in favour of Hudu
in the sum of $21,123.03, calculated as follows:
$
Amount due on cross-claia 16406.24
Interest on that sum at 15% pa
from 7 August 1986 to date 4716.79
21123.03
The net amount payable to the applicant is the sum of
$28,922.77 less $21,123.03, that is $7,799.74.
I turn now to the second claim of the applicant,
against Home Builders Corporation. This claim is brought only
under 8.52 of the Trade Practices Act, the alleged
misrepresentation being that Home Builders Corporation
provided independent advice to consumers in the building
24.
industry, that is potential building owners. It is clear that
it did not do so. On the contrary the company was in the
business of soliciting business on behalf of builders. The
conduct of the company towards Ms Turner was deceptive and it
amounted to a clear breach of s.52.
The only real question about the claim against Home
Builders Corporation is whether Ms Turner suffered any loss as
a result of that company's conduct. Home Builders Corporation
did not appear at the trial, and I have therefore not had the
benefit of any submissions on its behalf. However, having
regard to certain evidence given by Mr Hicks, I think that the
proper finding is that the effect of the payment of the
commission was to increase the price charged by Hudu to Ms
Turner. Mr Hicks said that Hudu paid a commission calculated
at 4% of the contract price and that this cost represented
part of the company's overhead expenses. He agreed that, in
arriving at its tender price, Hudu calculated its direct costs
and added a margin and that the margin incorporates "all
overheads". It follows, as one would expect, that this
particular outgoing found its way, at least indirectly, into
the price charged by Hudu to Ms Turner. Mr Hicks said that
Hudu paid a commission calculated at 4% of the contract price
and that this cost represented part of the company's overhead
expenses. He agreed that, in arriving at its tender price,
Hudu calculated its direct costs and added a margin and that
the margin incorporates "all overheads". It follows, as one
would expect, that this particular outgoing found its way, at
least indirectly, into the price charged by Hudu to Ms Turner.
25.
In that way she was occasioned loss by reason of the
misrepresentation. She would not have been in the position of
indirectly paying commission had she been told the true
position. The reason is that, according to evidence given by
her which I accept, she would not have knowingly become
involved in any transaction where a commission was being paid.
In my view the amount of the payment is recoverable by her.
There is, of course, a general principle that a
principal is entitled to recover from an agent the value of
any secret commission, or other benefit, obtained by the agent
in derogation of the agent's duty to the principal. The claim
was not pleaded in this way but, had it been, Ms Turner would
have been able to rely upon that principle. The result would
have been the same.
There should be judgment in favour of the applicant
against Home Building Corporation in the sum of $1,776.40, the
amount of the commission payment.
As between the applicant and the two respondents,
costs should follow the event; that is, Ms Turner should be
entitled to recover her costs against either respondent. But,
as between the two respondents, there should be an
apportionment, made on a time basis. The claim against Hudu
occupied the overwhelming majority of the hearing time so
that, as between the two respondents, Hudu should bear 90% of
the applicant's costs.
26.
I certify the twenty-five (25)
preceding pages to be a true copy of
the Reasons for Judgment of
his Honour Justice Wilcox.
Associate t ponte ote:
Date: 8 July "1988
Counsel for the Applicant
and Cross-Respondent:
Solicitors for the Applicant
and Cross—-Respondent
Counsel for the Pirst Respondent
and Cross-Claimant:
Solicitors for the First Respondent
and Cross-Claimant:
No appearance by the Second Respondent
Date(s) of hearing:
Mr I D Falukner with
Miss J C Gibson
Glasson, Gemmell «
McGill
Mr N F Francey
McCarthy Writer & Ryan
14, 15, 16 and 17 June