Select any passage to save a personal note with optional tags.
JUDGMENT No. 22! C/..2G 0
LIMITED DISTRIBUTION
NOT FOR PUBLICATION
CATCHWORODS
CONTRACT —- formation - intention to enter legally binding
relations ~- construction project ~ application of standard form
construction management contract unresolved - no concluded
agreement.
Trade Practices Act 1974 s.52
Stack v Coast Securities (No.9) Pty Ltd (1983) 154 CLR 261
ROKEBY CONSTRUCTIONS PTY LTD v UNIVERSAL WALDECK LIMITED and
MOTIVE GROUP LIMITED
WAG 161 of 1987
FRENCH J.
PERTH
14 JULY 1988
IN THE FEDERAL COURT
OF AUSTRALIA
WESTERN AUSTRALIA
DISTRICT REGISTRY
GENERAL DIVISION
ee ee ee ee ee
NO. WAG 161 of 1987
BETWEEN: ROKEBY CONSTRUCTIONS PTY LTD
Applicant
and
UNIVERSAL WALDECK LIMITED
First Respondent
and
MOTIVE GROUP LIMITED
Second Respondent
MINUTE OF ORDER
JUDGE MAKING ORDEER: FRENCH J.
DATE OF ORDER: 14 JULY 1988
WHERE MADE: PERTH
THE COURT ORDERS THAT:
i. The application is dismissed.
2. The applicant is to pay the respondents' costs of the
application.
Note: Settlement and entry of orders is dealt with in
Order 36 of the Federal Court Rules.
IN THE FEDERAL COURT
OF AUSTRALIA
WESTERN AUSTRALIA
DISTRICT REGISTRY
GENERAL DIVISION
ee eee
NO. WAG 161 of 1987
BETWEEN: ROKEBY CONSTRUCTIONS PTY LTD
Applicant
and
UNIVERSAL WALDECK LIMITED
First Respondent
and
MOTIVE GROUP LIMITED
Second Respondent
CORAM: FRENCH J.
14 JULY 1988
REASONS FOR JUDGMENT
Introduction
This case concerns the allegedly wrongful termination of
a contract under which the respondents are said to have engaged
the applicant to oversee substantial works connected with the
construction of a caravan park and tourist resort at Broome.
Although a claim under s.52 of the Trade Practices Act
was also pleaded, it does not appear that it ever had much
substance. That 18 not to say that it was pleaded merely to
attract the jurisdiction of the Court. No attack was made on the
plea or choice of forum prior to or at trial and, accepting, as I
do, that the contract claim falls within the court's accrued
jurisdiction, that jurisdiction 1s not lost by reason of the
2.
failure of the primary federal cause of action. The jurisdiction
is, of course, discretionary - Stack v Coast Securities (No. 9)
Pty Ltd (1983) 154 CLR 261 - but in the circumstances that the
parties were before the court ready to proceed to trial, I have no
doubt that a proper exercise of that discretion requires that I
hear and determine the application.
Factual Background
Kenneth John Turner is the managing director of Rokeby
Constructions Pty Ltd which carries on business as a builder. His
wife is the only other director. The company, which was
incorporated in 1978, has been concerned largely with industrial
and commercial bu.rldings. Mc Turner has had substantial
experience in the industry. For 8 years before setting up Rokeby
Constructions he was the senior quantity surveyor and commercial
manager for Watts Construction.
In the early 1980's he became interested in Broome and
its possibilities for development and associated building work.
In June 1983 the Department of Lands and Surveys invited
applications for the purchase of Broome Lot 1783 on the basis that
the purchaser would erect a "caravan park and tourist
accommodation" of not less than 100 bays thereon within a 2 year
period. Turner organised a syndicate with a view to making a
submission for such a development but the syndicate was unable to
settle upon a suitable scheme and that exercise did not proceed.
It appears that no acceptable application was received
by the Department at that time.
On 27 June 1986 the Department of Lands and Surveys
again invited applications under s.45A of the Land Act 1933 for
the purchase of Broome Lots 1783 and 2065 "for the purpose of
"caravan park" and "holiday and tourist accommodation"" on
specified terms and conditions. There was evidently considerable
interest in the proposed release and Turner realised that a
substantial submission would be required from the _ successful
applicant. He discussed the matter with Mr Wally Edwards, then
managing director of Universal Electronics Limited, now known as
Universal Waldeck Limited. Edwards was interested in expanding
his company's activities into construction work and agreed to a
submission going in on the basis that Universal would be _ the
developer, Rokeby Constructions would be the builder and Nr
Jeffrey Freeman, an architect known to Turner, the project
architect. The project was to be financed by Universal. Freeman
and Turner were to prepare the submission. They went ahead and
produced a document entitled "Proposed Tourist Village & Caravan
Park, Broome for Universal Electronics Limited". In the course of
its preparation Turner went to Broome at his own expense,
consulted with relevant authorities and took photographs of the
site. The submission and accompanying drawings were lodged on 12
August 1986. The drawings were prepared by Freeman, with the
assistance of Bonser Bradshaw, Consulting Engineers, who provided
a computerized drafting facility. Turner, however, was not
satisfied with the submission as filed and thought that it needed
more input. He knew a Mr Paul Cook, one of the principals of the
Motive Group Limited, a tour operator with an involvement in
4.
tourism in the Broome area. He approached Cook with a view to
involving his company in the development. He subsequently told
Edwards that the Motive Group was interested and Edwards said that
he would have discussions with the principals of that company.
Turner and Freeman were later invited to a meeting held at' the
Motive Group offices on 16 September 1986. Edwards was present,
representing Universal, along with Clive Nelthorpe and Paul Cook,
representing Motive Group. It was agreed to withdraw the proposal
submitted by Turner on 12 August and to lodge a more elaborate and
comprehensive submission. If it were accepted, then Universal and
Motive Group would participate in the development as joint
venturers, Rokeby Construction would be the builder and Turner the
project manager. The second more elaborate and polished
submission was commenced and submitted within 10 days of the
meeting. It was entitled "Tourist Resort Village and Caravan
Park Broome A joint proposal by Universal Electronics Limited
and Motive Group Limited".
The introduction to the submission explained that 1t was
proposed to develop the "Holiday and Tourist Accommodation" site
in the style of a fully inclusive resort village based on the
"Club Mediterranee" concept. The caravan park was to be planned
as "an all en-suite first class development". The Project Team
was set out in the submission as including Mr Turner as' Project
Manager, Mc Freeman as Architect, and Rokeby Construction Pty Ltd
as Builder.
Submissions were considered by a body described as a
Land Board which heard applications from prospective purchasers of
the land including the respondents on 26 September. Turner
attended along with Edwards, Cook, Freeman and a _ landscaping
consultant. The Board took evidence on oath, principally from
Cook but also from Turner and Edwards. Subsequently Edwards was
advised that the Universal/Motive Group application was successful
and he so informed Turner. They arranged to meet to discuss
getting the project under way. According to Turner they met on 6
October. Edwards had no recollection of the date but thought it
was the 20th as his records showed an appointment with Turner on
that day. In the end not a great deal turns on the difference.
It 1s clear that the joint venturers had a meeting on 10
October at which Edwards and Mr R. Lewis were present representing
Universal, and Messrs. Nelthorpe and Cook on behalf of Motive
Group. A note of that meeting records that:~-
"It was agreed to proceed with the project in two parts.
firstly the Carapark, and then the resort. Each to be
held by separate Pty Ltd companies." (sic)
The note goes on to record that Universal and Motive
Group were to have equal interests in the companies to be formed
for the two stages of the development. However, item 5 of the
note recorded:-
""Carapark to be 50/50 costs shared from day one, and
50/50 participation in the venture. Resorts to be 50/50
during the reasessment period, with final decisions as
to equity to be taken later." (sic)
Item 8.0 provided that Universal was to "handle
6.
construction" and Motive Group to "handle operation and
Promotion". Under the heading "MATTERS FOR FURTHER CONSIDERATION"
reference was made to revaluing the assets associated with the
caravan park and expanding the company "to provide sufficient
tangibility (sic) to be subject of a soundly based float". Item
11.2 noted that the tourist development, together with development
at Araluen, Port Kennedy and Margaret River, "could be considered
for inclusion in the proposed float". According to Edwards, it
was decided at this time that the joint venturers would commit
themselves to the development of the caravan park but that there
would be no commitment made to the resort. This is at odds with
the terms of the submission to the Land Board on the strength of
which the land was released. Nor is it supported by the minutes
of the meeting of 10 October. While it is clear from that minute
that the caravan park was to be constructed first, the uncertainty
regarding the tourist resort seems to have related to the precise
mode, timing and corporate vehicle for its construction.
When Edwards and Turner met in October no one else was
present. They discussed a number of topics including the
appointment of consultants and Rokeby's role in the project.
According to Turner, it was agreed that the caravan park was to be
constructed immediately, to be opened for the start of the tourist
season in May-June 1987. The object was to generate cash flow as
the construction of the tourist resort would be the more expensive
exercisé. It was agreed that Freeman, the architect, and Bonser
Bradshaw, the engineers, should be appointed on account of the
work they had already done. Edwards nominated plumbers and
electrical consultants he wanted. He asked Turner what he
expected out of the project. Turner said he wanted a
"construction management agreement with a 6.5 per cent fee", The
"construction management agreement" was explained by Turner in
evidence as a reference to the standard form of construction
management contract published by the Master Builders' Association.
That form of contract sets out terms and conditions of the
appointment of a construction manager to provide management
services and to exercise the functions there set out. Clause 6
provides that the construction Manager is to "organise
commencement of the Works, and in consultation with the Principal,
co-ordinate construction of the Works by the Trade Contractors so
as to achieve Final Completion in accordance with the terms of the
Contract". The contract contemplates that the principal shall pay
trade contractors direct upon the recommendation of the
construction manager (cl.9(a)). The construction manager is to be
paid fees for pre-construction management services and management
services during the construction stage (cls.13 and 14(a)). For
management services during the construction stage the fee can be
calculated as "a percentage of the Cost of the Works as set out in
Schedule 5" (cl.14(b)). The "Cost of the Works" means costs and
expenses incurred by the construction manager and by the principal
in the construction stage of the works, whether paid for or not
{cl.1). By cl.17, termination of the agreement could be effected
by either side upon 10 days' written notice to the other. Clause
17 provided:-
"Either party shall have the right and power to determine
this Contract at any time by giving to the other party
ten (10) days notice in writing of his intention to so
determine. The notice of determination shall be sent by
certified mail."
According to Turner's evidence-in-chief, Edwards
accepted the proposal and agreed that claims would be submitted on
a monthly basis. The claims were to include invoices rendered by
contractors which had been paid for by Rokeby and were to be
reimbursed, invoices made out to the joint venturers direct by
trade contractors and a claim for the manager's fee. Turner did
not intend to raise any charge for pre-construction management
services although it does not appear from the evidence that he
said so to Edwards.
It was Edwards' evidence that he had never previously
heard of the construction management contract and that he
responded to Turner's proposal by saying "well you know, I do not
know that contract, please get it ready for me and get it to me".
This was put to Turner in cross-examination, but he said he did
not recall such a reaction. He agreed that it was probably true
to say that there was no discussion of what was comprised in the
6.5% fee. In re-examination however the following exchange took
place (Tr.137-138):-
MR DAVIS — It was put to you by my learned friend that
Mr Edwards said to you that he had no experience of the
construction management contract; do you recall him
saying that?
MR TURNER - he might have said it. I do not recall, no.
MR DAVIS - Okay. Do you recall him asking you any
questions about the construction management form of
project management?
MR TURNER — Not at that meeting, no.
MR DAVIS - Right. Do you recall whether Mr Edwards was
aware that the MBA contract was a_= standard form
contract?
MR TURNER - I am not aware that he did not know it, no.
MR DAVIS - No, but was he — did you put it to him at
that meeting that the terms you expected were according
to a standard form?
MR TURNER - Yes, standard MBA.
MR DAVIS -— Did Mr Edwards say anything to indicate
whether he accepted or rejected your terms?
MR TURNER - At that meeting?
MR DAVIS ~ Yes?
MR TURNER —- No.
MR DAVIS ~ He did not say anything. Did he indicate
when he would tell you?
MR TURNER -— No, there was no conversation on that, no.
MR DAVIS ~ Did he indicate that you should commence work
on the project?
MR TURNER - Yes.
MR DAVIS -— When?
MR TURNER - Immediately.
FRENCH J. ~ Well, did he ever say to you whether he
accepted or rejected those terms in so many words?
MR TURNER - No.
MR DAVIS - Did Mr Edwards at any time during that
conversation suggest any particular terms of your
engagement himself?
MR TURNER - No.
MR DAVIS - So when you suggested the MBA standard form
construction management contract, you are saying he did
not suggest any deviation from that at all?
MR TURNER ~- No, that is correct.
FRENCH J. ~ Sorry; he never suggested any deviation from
that?
MR TURNER - No.
FRENCH J. — Did he indicate whether he accepted that as
a basis for your agreement?
MR TURNER - Yes, I just - he said what do you want and I
10.
said that is what I was after.
FRENCH J. - Did he ask - I thought you said earlier in
cross-examination that he asked you for a copy of that,
to have a look at it or something; is that right or have
I got that wrong?
MR TURNER ~ I do not believe so at that meeting."
And further at p.138:-
"MR DAVIS - Did he make any comment at all?
MR TURNER —- On the contract?
MR DAVIS — On the proposition that you put to him?
MR TURNER -— No."
Edwards on his own evidence told the Court that he
accepted that Turner would be involved in the construction but did
not come to any concluded view about the precise nature and terms
of his involvement.
It was common ground that Turner was to get the project
under way immediately and he proceeded to do so by appointing a
firm of surveyors to do physical feature surveys. He also
appointed consultants and had Freeman prepare conceptual drawings
with detailed plans being prepared by Bonser Bradshaw using their
computer facility. Final documentation however, was not completed
until 13 March 1987. In the meantime, a foreman, one Roland
Parthezius, was appointed on site on 1 December by Rokeby and work
commenced on that date. About 3 weeks prior to that time, on 6
November, Turner visited the site with Edwards and Waldeck, who
was also a director of Universal.
11.
A construction schedule was prepared. It is common
ground that Rokeby worked on the site although the pleaded detail
of the work done was not admitted. However, it is apparent that
the company was engaged in the construction of the caravan park
from 1 December 1986 until 16 March 1987. The significance of the
latter date will appear below.
The company through which the joint venturers were to
carry out the project was incorporated on 14 November 1986 as Eden
Caravan Park Pty Ltd, although, according to Turner, he did not
become aware of 1ts existence until early February 1987. In _ the
event, work proceeded in connection with the project through
December to March. Planning approval was obtained and site
clearing carried out by the Broome Shire by mid-December. Design
plans for various aspects of the work were commenced, an
"environment study" was prepared and an electrical sub-station
built. By the end of January tenders had been called for
earthworks, siteworks, plumbing and electrical works. These
comprised the major elements of the construction of the caravan
park. A tender was let for the provision of pre-fabricated
buildings, being chalets and ablution block units associated with
each caravan bay.
On 2 February 1987 Universal appointed an in-house
building expert or project manager to its staff. H1S name was
Peter Cue and it was his function to oversee new developments and
maintain existing ones for the Universal Group. He effectively
became Universal's project manager in relation to the caravan park
12.
development. Indeed, it was he who processed the first claim for
payment by Rokeby. This claim was not made in written form until
13 February 1987 when Turner sent to Eden Caravan Park Pty Ltd, in
answer to a written request from Mr Cue, a copy of outstanding
invoices for payment on the project. Turner had previously
requested payment of the invoices as he was being pressed by
contractors. However, there had been some difficulties as between
Universal and Motive, the latter having experienced financial
difficulties following its involvement in activites associated
with the America's Cup race.
On 24 February, Turner and Cue met and went through a
handwritten list of invoices to 31 January 1987 prepared by
Turner. These totalled $66,221.41, of which Rokeby had paid
$13,872.69 itself. In addition, Turner included a claim for
Rokeby's fee, being $4,364.71, representing 6.5% of total
invoices, less consultant's fees. He went through the list with
Cue and pointed out the fee component. Cue paid all invoices on
that day. in particular he reimbursed Rokeby for the invoices it
had met and paid the 6.5% fee claimed. These last two figures
totalled $18,223.45. The cheque for that amount given to Turner
was drawn on the account of Eden Caravan Park Pty Ltd and the R. &
I. Bank at Perth and was made out to Rokeby Constructions Pty Ltd.
From mid-February, according to Edwards, the developers
were expressing doubts about the progress of the project.
Contractual arrangements with Rokeby had not been concluded and
there was concern about the accuracy of the initial estimates for
the cost of the work. Edwards asked Cue to push Turner and
13.
Freeman to get the detailed documentation finished and cost
estimates prepared. On 23 February, Turner completed the MBA
standard form of construction management contract, as a contract
between Eden Caravan Park Pty Ltd and Rokeby Construction Pty Ltd.
It was delivered to Edwards who referred it to Cue along with
various trade contracts. Cue came back to Edwards and asked
whether he realised what form the contract took. Edwards read it
briefly and said he would have to talk to Turner about it.
By 2 March the final documentation was nearly
complete and Turner proposed detailed estimates with help from
Parthezius in Broome. There were set out in an 18 page
handwritten document and came to a total cost of $3,765,265,
which, with Rokeby's fee of 6.5%, amounted to $4,010,000. This
contrasted with the estimated cost of $2.36 million set out in the
original submission to the Land Board. Turner explained that' the
difference reflected increases in site coverage leading to a 145
bay plan whereas the original submission envisaged only 100 bays.
About this time Universal had engaged a valuer from L.J.
Hooker to assess the value of the project for the purpose of
raising loan finance. The valuer's figure was only $3.2 million,
substantially less than the projected costs. On becoming aware of
this discrepancy, Edwards rang Turner and asked him to come round
to his house to talk about the estimates and areas in which costs
might be reduced. They had a long discussion about the project.
Edwards said that he was not confident that some of the
sub-estimates making up the total estimated cost of the work could
be maintained. Turner told him that they had a very good quality
14.
park. The real problem he said was not with the cost estimate but
rather the valuation and that they needed to get the valuation up.
Edwards did not accept this. The meeting concluded on the basis
that both Turner and Edwards should do what they could to bring
the costs down. Edwards expected Turner to propose changes' to
designs and materials which might have that effect. Edwards
directed Cue to arrange with Turner to get their consultants
together to work on the problem generally. On 9 March a meeting
of consultants was held at which Edwards was briefly present to
state the cost cutting objective. Cue presided and Turner was
also present. Possible areas of cost savings totalling $557,000
were identified and the minutes of the meeting concluded with the
note:-—
"Meeting finished at 1.00 with all parties now waiting
for the Executive Director to decide on the cuts
required."
It would appear that the reference to the Executive Director was a
reference to Edwards.
In the meantime, according to Edwards, the directors of
Eden Caravan Park Pty Ltd, of which he was one, concluded that
they could not accept the proposed construction management
contract with Rokeby. At about that time Edwards had made some
handwritten notes of his own setting out various options to
achieve cost reduction. There were three principal headings
"valuation", "Costs" and "Options to Delete". Under the heading
"Costs" the following appeared:-
15.
"Current 3,765,000
Plus
Rokeby 244,725 (+ on site 50,000)
Consultants (6 1/2) 2% 130,000
Auster 244,725
$4,387, 450
Say $4.4 million (Stage 1)"
The reference to "Auster" appears to have been a
reference to Auster Plumbing and Construction, a business carried
on by Universal as one of its divisional activities. When asked
in cross-examination why he had noted the same figure against
Auster as that against Rokeby, Edwards said he had no idea.
Under the heading "Options to delete" the following
appeared:-
. Earthworks/Siteworks $ 70,000
- cut thickness
~ organise BC and kerbs ourselves
- width outside kerb.
. Tiling to Ensuites only 24,000
Remove Chalet C, 51,000
Remove covered rec area 8,000
Remove sites 1-10 (camping) 90,000
. Reduce concrete strength 6,000
- delete more en-suites (20) $190,000
$439,000
convert Rokeby to a consultant $150,000
$589,000
The figure of $150,000 appears to refer to the saving
16.
that could be achieved by the proposed conversion. Edwards'
evidence suggests that that was the fee he contemplated should be
paid to Rokeby. I am inclined to think however, that the fee he
was contemplating to Rokeby was in the order of $95,000. Nothing
much turns on the discrepancy which may result from the fact that
counsel for Rokeby put it to him in cross-examination that he was
contemplating a $150,000 fee for the company.
On or about 18 March Edwards telephoned Turner at home
and told him that the developers could not accept the proposed
contract with a 6.5% fee. They had, he said, to take cost cutting
measures and while they wanted him to remain involved in the
project, it could not be on the basis of a construction management
contract. He suggested a consulting arrangement. He acknowledged
to Turner that he had put a lot of work into the project and said
that the developers wanted to see him with a fair return out of
it. Turner expressed his disappointment and said he would think
about it. Turner's recollection of the conversation is recorded
in a note which he made on the night of the conversation and later
transcribed on to a separate piece of paper that was admitted as
Exhibit 25. That record read as follows:-
"Ww. Edwards 8.15 pm Wed 19 March '87
Advised KJT cannot afford to pay his project manager's
fees - was alright when contract was small as original
submission
Advised they will be building it anyhow & I would only
be duplicating them & they have to make a profit
Could retain me as a consultant to help them on this &
other projects.
Pay for work done to date. Pay for introducing the
project to them etc.
17.
Thanks for everything ~- think about it and let them
know."
The substance of the conversation so recorded was not disputed by
the respondents. Though it is evident that Edwards and Turner
recall different elements of it, their recollections do not
conflict in any material way.
Edwards rang Turner again the following Monday, 23 March
and they arranged to meet on Thursday, 26 March at 9 a.m. At that
meeting Edwards retraced in conversation the ground covered in the
telephone discussion of 18 March and suggested that a consultancy
with a fee at 1 1/2 to 2% would provide a satisfactory return for
Turner's effort. He also said the company had other projects and
that there was good ongoing business to be had.
Turner replied that he was unhappy and that if that was
the way Edwards thought, then he could "stick it".
They had no further contact in relation to the Broome
project although curiously Turner did continue to do. other
unrelated work for Edwards.
The Pleadings
_ The statement of claim alleges uncontroversial
background facts in paras. 1 to 7 and at para.8 contends that
prior to the second submission to the Land Board, Rokeby,
Universal and Motive had agreed that if the submission were
18.
accepted Motive would participate in the development as joint
developer with Universal, Rokeby would participate in it as
builder and Turner would participate in it as project manager.
This much is admitted by the respondents. More importantly
however, and central to Rokeby's case, is the assertion in para.10
that following the acceptance of the proposal by the Land Board,
it was agreed between Turner for Rokeby and Edwards for the
developers that:~
(a) Rokeby would participate in the development as
construction manager.
(b) Rokeby would be paid a fee for its services as
construction manager equivalent to 6.5% of the total
project costs.
(c) Rokeby would submit monthly invoices of expenditure
incurred for and on behalf of the developers as progress
claims, such invoices to include the agreed 6.5 per cent
fee for Rokeby.
Paragraph 11 of the statement of claim pleads that as at
October 1986 by reason of these matters a "contract arose between
the developers on the one part and Rokeby on the other for the
construction management of the caravan park and tourist resort
village project by Rokeby". It is then said that Rokeby, in
rel1rance upon the agreement, was fully engaged as_ construction
Manager _for the first stage of the project namely, the
construction of the caravan park (para.12). Submission and
payment of the first progress claim is pleaded (paras. 13 and 14)
and it is contended that by reason of the submission of the second
19.
proposal, the work done by Rokeby in reliance upon the agreement
pleaded, the submission of its progress claim and the payment of
its progress claim "the developers are estopped and should not now
be heard to deny the existence of the contract pleaded in
paragraph 11 herein" (para.15). Paragraph 17 alleges with
reference to the telephone conversation of 18 March 1987 that:-
"On or about 19 March, 1987 Edwards orally advised Turner
that the developers could not afford to pay Rokeby's
construction management fee and terminated the
engagement of Rokeby as Construction Manager for the
project."
It is admitted that immediately after that date Rokeby ceased
work, left the project site and handed over all drawings and
documents relating to the project to the developers.
Rokeby says that the purported termination was a
repudiation of the contract that it had with the developers, was a
breach of that contract and that by that breach it has suffered
loss and damage (paras. 19 and 21). Its claim for damages is
calculated as a loss of profit by taking 6.5% of the final project
cost for the caravan park, said to be $4,507,423, and 6.5% of the
estimated project cost for the tourist resort village, said to be
$6.5055 million. On this basis the total fee entitlement is
$686,557.49. Credit is given for fees paid of $4,364.71 and
expenses saved, leaving total net profits foregone of $565,797.79.
In an amended joint defence filed on behalf of both
respondents at the commencement of the trial, the developers
deny any agreement as to the fee to be paid, saying that Turner
20.
and Edwards, while agreeing a percentage fee, did not agree what
project costs were to be the basis of its calculation. In the
alternative they say that if there were an enforceable agreement
between the parties it was a condition that the parties would
execute a standard form MBA construction management contract and
it was a term of that contract that either party might determine
it at any time whereupon the principal would pay to the
construction manager the balance of his fee based on the cost of
the work executed to the date of termination.
They admit that the applicant performed certain work in
respect of the project but deny it was performed pursuant to any
contract. In the event that there was a binding agreement 1t 15
further pleaded in the defence that such agreement provided that
the developers were to incorporate a company for the caravan park
and the tourist resort village stages of the development
respectively and that it was the company so incorporated that was
to engage Rokeby in each case. While denying that Edwards
terminated Rokeby's employment as construction manager, the
developers contend that, if he did so, he was entitled to do so
pursuant to the terms of the agreement by reason of the provisions
of cl.17 of the standard form contract.
In its reply Rokeby says that, if 1t were to be engaged
by Eden Caravan Park Pty Ltd and a company called Broome Resorts
Pty Ltd, that was a term of its agreement with the developers and
that the failure of those companies to so engage it was a_ breach
by the developers of the agreement. Further, Rokeby denies' that
either party might determine the agreement at any time under the
21.
MBA construction management contract and says the termination
power in cl.17 thereof can only be invoked by either party for
good and sufficient reason and not unreasonably or vexatiously.
Further, it is pleaded that neither of the developers at any time
acted or purported to act pursuant to cl.17.
Formation of the Agreement
It is critical to Rokeby's case that it establish the
formation of a legally enforceable agreement under which it was
engaged by the respondent as a construction manager for the
development on a fee calculated at 6.5% of total project costs.
Rokeby's case was conducted on the basis that the agreement was
concluded in the course of fTurner's meeting with Edwards in
October 1986. What was said on that occasion no doubt had to be
understood in the light of the history of the development and
earlier understandings of what Rokeby's role would be. It is in
this context important to note that the respondents admit that it
was previously agreed that if the proposal to the Land Board were
accepted, Rokeby would participate in the development as a builder
and Turner as project manager. But that agreement, absent further
terms, was at best an agreement in principle, not intended to have
legal force and effect. Nor, so far as 1t goes, does it reflect
the terms of the agreement relied upon by Rokeby. Under the
latter as pleaded, Rokeby was not to act as builder but to provide
the services of a construction manager. As such it was to act as
agent for the developers or their chosen corporate vehicle. It
would not have involved Rokeby in engaging sub-contractors on its
own account.
22.
Some of the evidence given by Edwards tended to suggest
that as at 18 March he was of the view that there was a concluded
arrangement of some kind. He referred in his handwritten list of
"Options to delete", to converting Rokeby to a consultant, the
implication being open that there was some previously understood
arrangement between them. On 18 March, in speaking to Turner of
the developers' inability to afford project manager's fees,
Edwards said, according to Turner's note, that it was "alright
when contract was small as original submission" (sic). Again,
this might be taken as a reference to some pre~existing
arrangement which could not be continued. And the offer on that
occasion to provide consultancy work on other Universal projects
might also be seen as reflecting a consciousness of some
pre-existing commitment being withdrawn. In the end, however, in
my opinion, these matters are inconclusive. So, too, is Cue's
payment of the 6.5% fee claimed by Rokeby on 24 February. Cue was
not anvolved and indeed, appears not even to have been employed by
Universal in October when the pleaded agreement was said to have
been concluded.
The issue is, in my opinion, determined by fTurner's
evidence in re-examination, which makes 1t clear that while it was
agreed that he and his company would have a significant
involvement in the supervision of the contract, the terms of that
involvement were not then decided. Turner proposed to Edwards
that he be paid a 6.5% fee under the terms of the standard
construction management contract. His evidence in re-examination
and that of Edwards supports the inference that Edwards did not
23.
accept the proposal at that time. I also accept Edwards'
evidence that he wanted to see the proposed standard form contract
before agreeing it. Edwards' indication to Turner that he should
begin work immediately does not, 1n my opinion, constitute an
acceptance of his proposal in the circumstances of this case. In
some circumstances such a directive might amount to acceptance,
but given Edwards' stated ignorance of the terms of the' standard
form and his desire to see it, no acceptance could be implied from
his conduct. On this basis I conclude that as at October 1986 no
legally enforceable agreement as pleaded was arrived at in
relation to Rokeby's role in the project.
Estoppel
Rokeby relies in the alternative upon the proposition,
pleaded in para.15 of the statement of claim, that, by reason of
the matters set out in paras.8, 12, 13 and 14, the developers are
estopped and should not now be heard to deny the existence of the
contract alleged in para.11. As pleaded, it was sought to base a
cause of action on the alleged estoppel. The elements of the
estoppel relied upon were as follows:-
1. The commissioning and submission to the Land Board of
the second proposal which showed Rokeby as builder and
Turner as project manager (para.8).
2.° That Rokeby in reliance upon the agreement pleaded in
para.il was fully engaged as construction manager for
the first stage of the project, namely, construction of
the caravan park, and did various things pursuant to
24.
that engagement (para.12).
3. That Rokeby submitted and received payment for its first
progress claim which included a claim for its fee of
6.5% of the costs.
The plea cannot succeed. To the extent that it relies upon the
alleged formation of the agreement of October 1986, it cannot
stand unless that agreement was formed and I have already found
adversely to Rokeby in that respect. Otherwise no relevant
representation or promise is identified to support the estoppel.
The statement in the submission to the Land Board that Rokeby
would be builder and Turner the project manager is not in accord
with the contract that Rokeby now seeks to set up and under which
it claims to have been appointed not as builder but as
construction manager.
In the event, the reality is that Rokeby proceeded to
carry out work without the benefit of a concluded agreement or
clear promise as to the terms of its remuneration. It was paida
fee and, no doubt, would have been entitled on some basis to a
reasonable remuneration for such of the work as it did with the
acquiescence of the respondents. In my opinion, however, no case
for either representational or promissory estoppel is made out.
CONCLUSION
No case having been put for contravention of s.52 and
there being no evidence on the face of it to support such a case,
the applicant's claim must fail for want of a concluded agreement
25.
as alleged.
There were other issues addressed during the trial
relating to the proper parties to the alleged agreement, whether
the applicant should have sued specifically in its capacity as
trustee, whether there was a right to terminate under the
agreement, if agreement there was, and what effect the termination
clause in the standard form of contract would have on the recovery
of damages. There was the question whether what Edwards said in
the telephone conversation on 18 March would have amounted to a
termination of the alleged agreement, if agreement there had been.
There was also the question of damages. None of these matters
need be addressed for it seems to me that the application fails at
the threshold. The application will be dismissed.
26.
I certify that the preceding
twenty five (25) pages are a
true copy of the Reasons for
Judgment of his Honour
Justice French.
Associate: DeleroMr Seika
Date: [4 Tug (4s&
Counsel for the Applicant: Mr R. Davis
Solicitors for the Applicant: Messrs. Keall Brinsden
Counsel for the Respondent: Mr P. Kyle
Solicitors for the Respondent: Messrs. Dwyer & Thomas
Dates of Hearing: 4, 5, 6 and 7 July 1988
Date of Judgment: 14 July 1988