Select any passage to save a personal note with optional tags.
JUDGMENT No, om. S8.0.9 2%.
CATCHWORDS
TRADE PRACTICES - finance for unit development and subdivision - misleading or
deceptive conduct - whether representations by financier of intentions to advance
moneys and pay outstanding trade creditors - whether appointment of receiver valid -
whether trespass.
'Irade Practices Act 1974 s 52
HOLLISTER DEVELOPMENTS PTY LIMITED (RECEIVER AND MANAGER
APPOINTED) v. CUSTOM CREDIT CORPORATION LIMITED
No. WAG 36 of 1992
FRENCH J.
PERTH
16 November 1994
RECEIVED
17 NOV 1994
FEDERAL COURT OF
AUSTRALIA
PRINCIPAL
REGISTRY
IN THE FEDERAL COURT )
OF AUSIRALIA )
WESTERN AUSTRALIA )
DISTRICT REGISTRY )
)
GENERAL DIVISION No. WG 36 of 1992
BETWEEN: HOLLISTER DEVELOPMENTS
PTY LIMITED (PECEIVER AND
MANAGER APPOINTED)
Applicant
and
CUSTOM CREDIT
CORPORATION LIMITED
Respondent
MINUTE OF ORDER
JUDGE MAKING ORDER. FRENCH J.
DATE OF ORDER: 16 NOVEMBER 1994
WHERE MADE: PERTH
THE COURT ORDERS THAT:
1. The apphcation is dismissed.
2. The applicant 1s to pay the respondent the sum of $3,573,395.
3. The applicant 1s to pay the respondent's costs of the application and of
the cross claim to be taxed.
NOTE: Settlement and entry of Orders 1s dealt with in Order 36 of the
Federal Court Rules.
IN THE FEDERAL COURT
OF AUSTRALIA
WESTERN AUSTRALIA
DISTRICT REGISTRY
GENERAL DIVISION
No. 36 of 1992
BETWEEN: HOLLISTER DEVELOPMENTS PTY LIMITED
(RECEIVER AND MANAGER APPOINTED)
Applicant
and
CUSTOM CREDIT CORPORATION
Respondent
CORAM: FRENCH J.
16 NOVEMBER 1994
REASONS FOR JUDGMENT
Introduction
Hollister Developments Pty Limuted (Hollister Developments) 1s a land
developer and builder which undertook a project involving the construction of home
units and the subdivision of land at Kenwick Although imtually financed by Citibank
Savings Limited, the developer sought refinancing from Custom Credit Corporation
Limited (Custom Credit). Custom Credit advanced Hollister Developments the sum
of $1.35 millon. Subsequently, Hollister Developments encountered cashflow
problems and had further discussions with Custom Credit about additional finance. It
maintains that Custom Credit made certain representations in the course of those
discussions and subsequent correspondence, they being representations about its
intentions to advance moneys to Hollister Developments and to pay outstanding trade
creditors so that the project could proceed. Hollister Developments asserts that
Custom Credit has not honoured its commitments, has engaged in misleading or
deceptive conduct and has wrongly appomted receivers over the property the subyect
of the development project. It claims damages under various heads and other rehef.
Custom Credit cross claims for moneys which it has advanced to Hollister
2.
Developments and moneys due under a mortgage in favour of Citibank which was
subsequently assigned to Custom Credit
The Pleaded Case
Hollister Developments 1s a land developer and builder On 28
November 1988 it became the registered proprictor of Lot 5 Stafford Road, Kenwick
(the home unit land) It says that, at all material times, it was undertaking the
construction of 64 home units and four commercial units on that land A mortgage in
favour of Citibank Savings Linuted was registered against the land on 21 March 1989
securing an advance of $2,500,000 by that company. he mortgage lability was
guaranteed by Samuel Papotto, a director of Hollister Developments, under a deed
dated 17 March 1989 Arrangements with Citibank were said to permit partial
discharges on the sale of any completed home units. Holhster Developments also
became the registered proprietor of Lots 2 and 33 Stafford Road (the development
land) on 15 November 1989. The company was at all times developing that land for
subdivision into 40 building lots.
On 15 November 1989 and 30 November 1989 respectively, a first
mortgage was registered on the development land and a second mortgage on the
home unit land to secure an advance of $1.35 million from Custom Credit. The terms
of the mortgage included an entitlement to $20,000 in favour of Custom Credit as a
Project Risk Fee to be made available to Custom Credit at settlement. This was
debited to its account with Custom Credit on 27 November 1989. Custom Credit says
that the $20,000 was included in the sum advanced and represented a risk fee. These
matters were not seriously im issue.
Hollister Developments says that the construction of the units on the
home unit land was planned and implemented in stages. Twenty five units were to be
completed by November 1989, ten in February 1990, ten in May 1990, ten in August
1990, nine in December 1990 and the four commercial units in February 1991.
Periodic sales were planned to generate cashflow for Hollister Developments to
finance ongoing construction Following registration of the moitgages, construction of
the home units commenced as did development of the development land, These
Matters aie not contested but are not adnutted by Custom Credit
Before December 1989, vatious of the home units constructed by
Hollister Developments were sold on the condition that settlement would occur before
the end of 1989. The sales lapsed because the lots in Stage 1 were not available for
dealings by that time. This meant that Hollister Developments could not make
projected repayments to Citibank and incurred additional interest charges. Cashflow
difficulues arose and the company accumulated outstanding debts to traders and
contractors. Creditors pressing for payment totalled $270,673.84. These matters are
not admitted by Custom Credit.
Hollister Developments says that in May 1990, Papotto was approached
by Stephen Lewis, a senor executive of Custom Credit, who told him that Custom
Credit's Australian Manager, James Bonwick, was in Western Australia and wished to
discuss existing and future business relationships with Hollister Developments. A
4.
meeting was held between Papotto, Lewis and Bonwick in May 1990. The holding of
the meeting 1s common ground but Custom Credit says its stated purpose was to
discuss Hollister Developments' facility. At that time Custom Credit says it had
informed Hollister Developments that the facility interest capitalisation level of
$95,000 would be fully drawn by May 1990 and that Hollister Developments should
make arrangements to meet further payments. During the meeting with Lewis and
Bonwick, Papotto allegedly told them that Hollister Developments was in the process
of buildin, on the home unit Jand and subdividing the development land, that it
planned to build the units in stages, that 25 units were alieady approved for dealing,
and that Lots 1, 6, 10 and 19 had been sold It ts also said that Lewis and Bonwick
were told of the delays that Hollister Developments had experienced and the
consequent cashflow and creditor problems. They were told the 25 units completed
could be sold for $1.8 milion quickly or $2 milion on an orderly marketing basis, that
Hollister Developments had heard from intending buyers in respect of the
development land but needed to provide its creditors with assurance as to the
availability of future funding for which there was a need in order to complete the
balance of the units and the development land.
It is alleged by Hollister Developments and denied by Custom Credit,
that at that meeting Custom Credit represented to Hollister Developments that:
"18 At such mecting the Respondent indicated and
represented to the Applicant
(a) that the Respondent was
willing to and able to and
would discharge or purchase
the Citibank mortgage by mid
(b)
(c)
(d)
(ce)
(f)
(8)
(h)
June 1990
that the Respondent was in a
position to assume the role of
sole lender over the home
unit land and development
land for the purpose of
providing funds to finalise
both projects
that any proposed funding
would provide for and permit
partial discharges and
consequent repayment of part
of the sums advanced or to be
advanced
that the Respondent was in a
position in offer to the
Applicant in respect to future
arrangements Joml vepture
profit sharing ariangemic nts as
distinct. from the Applicant
borrowing and paying interest
that the Respondent was in a
position to pay out the said
pressing trade creditors
particularised in the First
Schedule hereto by mid June
that the Respondent was
agreeable to making available
to the Applicant further funds
to enable the Applicant to
market a house and land
package on the development
land as distinct from vacant
blocks alone
that the Respondent was in a
position to provide weekly
payments to contractors and
Suppliers to allow the rapid
finalising of the home units
and the development land
subdivision
that the Respondent was
agreeable to informing
contractors and others trading
with the Applicant as to the
availabilty of funds with a
view to comforung such
6.
contractors and others and
inducing them to proceed with
providing goods and services
for the purpose of finalising
the works above refcrred to
QQ) that the Respondent was able
and willing to provide a letier
of approval for the purpose of
the Applicant, demonstrating
to creditors and contractors
and others that the Applicant
had the financial abihty to
complete the works above
pleaded"
Custom Credit did not suggest. it 18 said, that there was any requirement
express or implied, that upon funds being advanced by Hollister Developments they
would be repayable other than by virtue of the sales program of the home units, the
commercial units and the development land. Hollister Developments alleges that at
Custom Credit's suggestion and representation, it made application to Custom Credit
to refinance the home unit land and the development land for a loan in the amount
of $5,394,541. Subsequently, according to Hollister Developments, Lewis and
Bonwick verbally indicated to Papotto and Westlake that a loan of $5,396,000 had
been approved. The alleged representations, and the alleged verbal approval are all
denied by Custom Credit.
Hollister Developments says that Custom Credit partially implemented
its verbal approval by informing some trade creditors of the availability of finance,
disbursing funds and informing Citibank that Custom Credit intended to purchase or
payout the Citibank mortgage.
7.
Hollister Developments alleges that in rehance upon Custom Credit's
conduct and representations it abandoned the staged approach to the construction of
the home units, incurred obligations to contractors, refrained from obtaining
alternative finance, told Citibank that Custom Credit would pay 1t out in mid-June
1990 and told trade creditors that they also would be paid out by that time. Hollister
Developments complains that Custom Credit did not pay out Citibank or pressing
trade creditors.
Various requests were allegedly made by Hollister Developments to
Custom Credit for a written Ictter of approval of the advance Hollister
Developments says it was told the approval was delayed because of internal
administrative problems being experienced by Custom Credit Custom Credit did not
indicate that the loan would not be fully proceeded with nor that it would be
repayable other than from the proceeds of sale of units and building lots. The loan
was approved on 18 July 1990.
Subsequently, Hollister Developments took up with Custom Credit on a
number of occasions the matter of paying out Citibank and pressing creditors.
Custom Credit allegedly said such payments could not be made until security had
been finalised. Hollister Developments says it made various approaches to Custom
Credit to have the secunty documents approved. Such documentation was never
made available to it. Nevertheless, Custom Credit continued to make more advances.
Hollister Developments received further demands from its trade creditors and in the
period leading up to August 1990 was in financial difficulty. A meeting was held
8.
between Papotto, Brash and others representing Custom Credit on 4 September 1990.
Hollister Developments says Papotto was told that the loan was proceeding but that
security documentation was held up because of Custom Credit's internal
arrangements. It was agreed that the balance of funding to finance the home unit and
development lands was $145,000 for the homes and $44,000 for the subdivision. A
revised sales program was agreed. The revised agreement was contained 1n a letter
dated 4 September 1990. The terms of the letter were partly implemented by Custom
Credit making available various payments to Hollister Developments from 7
September 1990 to 5 December 1990.
An offer to purchase the 25 home units was said to have been made on
7 September 1990 by one Steve Skelin for $2 million. Citibank would not become
involved but directed Hollister Developments to take the matter up with Custom
Credit. Citibank declined to negotiate as it was awaiting payment by Custom Credit
of its mortgage. For this reason the proposed sale did not proceed.
By a notice dated 28 September 1990, Citibank demanded repayment of
its advance by reason of alleged default on the part of Hollister Developments.
Hollister Developments took the matter up with Custom Credit which refused to
make payment to Citibank of the amount owmg. On 12 October 1990, Custom Credit
demanded repayment from Hollister Developments of sums advanced by it. At the
time, according to Hollister Developments, 1t was not in default under its loan
arrangements with Custom Credit. The notice was said to be defective.
9.
A further written offer was made by Skelin on 16 October 1990 to
purchase 55 units the subject of the home unit development for a price of $3,505,000.
The offer was referred to Custom Credit which directed Hollister Developments to
take the matter up with Citibank. Citibank refused to become involved on the basis
that it was awaiting payment out of the Citibank mortgage. For that reason the
proposed sale did not proceed.
By a deed dated 31 October 1990, the guarantee and indemnity
executed by Papotto on 17 March 1989 was assigned by Citibank to Custom Credit.
The Citibank mortgage was transferred to Custom Credit on 12 November 1990 and
paid out on that day save for the sum of $20,000 or thereabouts still due to or
claimed owing by Citibank.
Custom Credit at no time has paid out pressing trade creditors. On 28
November 1990, it appomted receivers and managers pursuant to the Citibank
mortgage which had been assigned to it and pursuant to 1ts own mortgages. Hollister
Developments says that the purported appointment was and 1s invalid as there was no
default entithng or enabling such appointment. Alternatively, it contends that the
demand for payment made on 12 October 1990 was premature as on a proper
construction of the agreement of 4 September 1990 no demand could lawfully have
been made before 27 October 1990 nor before the date of appointment of the
receivers. Hollister Developments says that by reason of the appointment it has
suffered damages.
10.
By notice dated 21 January 1991, Custom Credit demanded payment
from Papotto of moneys claimed by it in respect of the Citibank mortgage and in
respect of sums advanced by Custom Credit to Hollister Developments. Hollister
Developments says that Custom Credit at all times knew it intended to rely upon the
representations and undertakings made and given by Custom Credit. Those
representations are said to have been false in various respects which are
particularised. In so far as they were representations as to future matters they were
made without reasonable grounds and reliance 1s placed on 351A of the Trade
Practices Act 1974. Hollister Developments says that the representations and conduct
of Custom Credit constituted misleading or deceptive conduct in contravention of s.52
of the Trade Practices Act 1974 as a result of which Hollister Developments suffered
loss and damage.
Hollister Developments goes on to plead that Bonwick, on behalf of
Custom Credit, told Papotto and Westlake that 1t required all umits on the home unit
land to be completed concurrently and not in stages. Previously, during May 1990,
Custom Credit had decided on a policy of lending further moneys in Western
Australia only if contractually obliged to do so, or if necessary to complete projects.
Neither Bonwick nor any other representative of Custom Credit informed any
representative of Hollister Developments of the existence of that policy. The fatlure
of Custom Credit to warn Hollister Developments of the existence of the policy or to
qualify its statement of willingness to consider advancing further funds by revealing
that any lending would be limited by the policy constituted misleading or deceptive
conduct. Alternatively, it 1s said that Hollister Developments had a reasonable
ll.
expectation that 1t would be informed of any material restrictions on the althty of
Custom Credit's staff to make further advances of the kind desned by it and the
failure to reveal the policy was therefore nusleading or deceptive Again, Hollister
Developments says it has suffered loss or damage by reason of that conduct. A plea
of estoppel is also raised based upon the alleged assumption of Hollister
Developments that loan contracts had been made and that Custom Credit would not
call up its loans or any of the moneys to which it was entitled other than pursuant to
the terms of the loan contracts and that the funds hable to be repaid to it would be
aid out of the sales of the property the subject of the mortgages
Pp Properly j BAL
A claini m trespass 1s raised based on the entry onto the home unit land
and development land by Custom Credit and aggravated and exemplary damages are
claimed. Relief is sought by way of a declaration that the appointment of the receiver
was unlawful, damages for breach of contract, damages under s.82 of the Trade
Practices Act 1974, damages for trespass, exemplary and/or aggravated damages and
relief under s.87 of the Act.
Custom Credit contends that the basis upon which further funds were
advanced to Hollister Developments was different. It contends that all that it
represented to Hollister Developments was that it was prepared to consider making
payments to selected trade creditors to enable the project to continue. Such further
advances were to be at the absolute discretion of Custom Credit. Payments were
made to Hollister Developments, from time to time, on this basis. There was no
obligation to pay all of the trade creditors.
12.
Custom Credit admits receiving a request for a "bridging loan" consisting
of $5,394,541 from Hollister Developments in July 1990 After some consideration, a
loan of $5,396,000 was approved and Hollister Developments was informed, 1n writing,
of the approval. Hlowever, that approval, 1t is said, did not constitute an offer to loan
as it was subject to certain terms and conditions. Acceptance of the written approval
resulted, at best, in an agreement to enter into a loan agreement upon the fulfilment
of those conditions Those conditions included one which requued adequate security
to be provided Hollister Developments did not fullil this condition As a resull,
there wis no buding pronnse to advance the $5,396,000 appro d.
In addition, Custom Credit cross clams on the original loan agreement
and mortgages with Hollister Developments and upon the Citibank mortgages which
had been assigned to it on 31 October 1990. It also cross claims for the addittonal
sums which it subsequently lent to Hollister Developments to enable the payment of
some of the trade creditors.
Hollister Developments, it 1s said, had defaulted and breached various
conditions in the loan agreements and the mortgages, thus justifying the written
demands by Custom Credit and the appointment of receivers and managers. In total,
Custom Credit claims $3,573,395.10 from Hollister Developments, being the sum still
owing as at 30 June 1993.
13.
Flollister Developments' Kenwick Pro,ect
- Early History November 1988-November 1989
John Samuel Papotto described himself in evidence as a business
advisor. He began engaging in property development in a small way in 1982 In 1986
his involvement became more serious and in Jate 1987 he took over a $2 company
called Rawang Nominees Pty Ltd. That company later became [Flollister
Developments Pty Ltd. Hollister Developments carried out two subdivisions of land
at Maida Vale It was involved with a unit development at Fast Perth, project house
construction at Woodvale and Murdoch, and other comnn wial developments
In 1988 there had been a significant increase in market values for unit
development. On 28 November 1988, Hollister Developments purchased land at Lot
5 Stafford Road, Kenwick for the purpose of carrying out a 64 home unit
development. Planning approval had already been obtained. The purchase price was
$440,000. Initial finance for the construction was provided by Reliance Finance in the
amount of $1.5 million. Hollister Developments started to try to sell units off the
plan from the time the land was purchased. It began marketing them in a small way
in August 1988 and subsequently commenced what Papotto described as a vigorous
advertising campaign. In about January 1989, a man called Karl Victor was employed
by Hollister Developments as Proyect Manager for the proposed development at
Stafford Road. He became a director of the company. Some works had already
begun on the home unit land before he joined the land. These included earthworks
and drainage. Victor prepared cost estimates for the types of unit to be constructed
on the home unit land. This did not include allowances for the earthworks and
14.
drainage already constructed. The costs were limited to the costs of construction
According to Victor, the average cost per square metre of the units was $270. He
claimed to have made this estimate in 1989 It was clear, however, that the estimate
did not include any component for preliminary works comprising earthworks and
drainage. Nor did it cover landscaping costs, sewerage connection, fencing, carpets,
window treatments or rectification of defects.
Papotto believed that Rehance Tinance would advance funds to a total
value of $2 milhon to support the project. Jn the event the additional funds were not
torthcoming from that source and the project had to be refimanced through Citibank
Savings Corporation Ltd. On 23 February 1989, Citibank wrote to Hollister
Developments indicating that 1ts application for finance had been approved in the
amount of $2,500,000 with a maturity date of 12 months from the date of settlement.
The loan was an interest only loan with principal due at maturity or on the sale of
individual units.
On 15 March 1989, Hillier Parker carried out a valuation of the
proposed development on the home unit land for Citibank. The valuation was based
upon market investigations in Kenwick and surrounding suburbs and referred to
recently recorded unit sales in new developments with 12 or more individual units
The average price for the proposed three bedroom units was projected at $80,000 and
for the two bedroom units, $72,000. The gross on-completion value was assessed at
$4,944,000.
15.
Citibank took a first mortgage, F053088, over Lot 5 to secure the
advance. The mortgage was dated 17 March 1989 On the same day, Papotto
executed a Deed of Guarantee and Indemnity in favour of Citibank guaranteeing
Hollister Developments' obligations under the mortgage. Construction of the units
commenced in May or June 1989.
Karl Victor wrote to the City of Gosnells on 27 July 1989 setting out a
works schedule which, he said, was based upon currently available trades having
regard to the downturn in the industiy. Assuming a comir neement dute of 7 August
1989, he proposed to have six pads completed at the end of week 1 and fittings, frxing,
painting and downpipes completed at the end of weeks 7 and 8. There would be six
new starts each week to complete 64 houses by the end of December 1989
According to the statement of claim, the building of the 64 home units
on Lot 5 was planned and being implemented im stages comprising the completion of
25 units in or about November 1989 as a first stage, followed by three stages involving
the completion of ten units each in February, May and August 1990, A fourth stage
in which nine units would be completed by December 1990 and a final stage in which
four commercial units would be constructed in February 1991. This, it was said, was
"deliberately planned to enable periodic sales of home units to provide the applicant
with a cash flow" (para.7 statement of claim). On the face of it, however, the letter
was not consistent with the kind of staged development propounded in the statement
of claim.
16.
It was Papotto's evidence that units comprising Stage 1 of the project
had been sold in 1988 on the basis that settlement would occur when the Strata Plan
for the units had been approved for dealings The latest date fo scttlement on that
basis was evidently December 1989. A number of sales did not go ahead because the
strata plan was not approved for dealing until April 1990. The Gosnells Shire had
evidently declined to issue the necessary clearances because of a deficiency in fence
lines Some contracts which had been entered into were renegotiated, other
prospective purchasers decided they would wait until the project was completed
Marketing of the units began in a small way im August 1989 and an advertising
campaign was commenced around December 1989. J.J. Ilookeis, Thornlie Branch,
carried out the marketing
By November 1989, much of the money borrowed from Citibank had
been used on the project. Papotto repeated in his evidence the pleaded allegation
that Lot 5 was always designed to be built in stages and that when Hollister
Developments borrowed from Citibank it was always acknowledged that there would
be additional funds to complete. By November 1989, according to Papotto, Stage 1
comprising 15 units had been completed. Stages 2, 3 and 4 each comprising 10 units,
were 40% to 70% completed. Stage 5, comprising 9 units, was 80% complete. In
cross-examination, he said "staged development" meant "various units in certain
stages" (227). Asked to identify any document which suggested that a five stage
development was being pursued in August 1989 he referred to strata plans being "in
place" and the issue of building licences in stages. Cross-examined about Victor's
letter of 27 July 1989 to the City of Gosnells he said that the letter did not reflect the
17.
way he wanted Victor to go. He also said however that the letter had nothing to do
with staged development. When Victor was cross-examined, he said Papotto had told
him when he joined the company that he had to complete the development as fast as
he could. He believed he could proceed in that way. He agreed that at first Papotto
had told him to start work on all the units and endeavour to complete all of them at
the same time. That was Victor's original plan. However, about one third of the way
through the project he became aware of money problems which set back the
construction. There was a change of tack to try to complete 10 units so some could
be sold to finance ongomg construction. It was appaient fiom the evidence that the
so called staged development was in truth a response to financial exigenues in an
attempt to complete a certain number of units to finance ongoing construction of the
balance. It was not planned and implemented as asserted in the pleading or im
Papotto's evidence. Further support for this view came from a valuation prepared by
Hilher Parker for Citibank in March 1989. No reference was made to a staged
development in that report which, if a staged development had been planned, would
be expected to have contained some reference to it.
In November 1989, Papotto decided that Hollister Developments should
exercise the options it had to purchase land adjacent to Lot 5 Stafford Road, being
Lots 2 and 33 Stafford Road. He approached Custom Credit for finance for the
acquisition and subdivision of the development land and for what he said was Stage 2
of the development on the home unit land. On 8 November 1989, Custom Credit
approved an advance of $790,000. At about this time, however, there were further
discussions between Papotto and Mr Rob See, an officer of Custom Credit, in which
18.
Papotto said that he was expecting clearances to enable strata title approval of Stage
1 of the home unit land but that there was going to be a cashflow problem In the
event, on 10 November 1989, Custom Credit approved an advance of $1,350,000 in
lieu of the previously approved advance of $790,000.
The terms of the second approval were set out im a letter to Hollister
Developments dated 10 November 1989. $400,000 was to be advanced at settlement,
$335,000 to be progressively advanced against builders' claims for the development
land, $500,000 to be advanced progressively against builders' claims for the home unit
land, $95,0U0 to represent an interest caprtalisation facility and $20,000 to be a profit
share at settlement payable to Custom Credit. The security for the loan was a
registered first mortgage over the development land, a registered second mortgage
over a house owned by Hollister Developments at 30 Moss Street, Huntingdale and a
registered second mortgage over the home unit land. A security deposit of $100,000
was to be lodged with Custom Credit. The loan was subject to various conditions
including four arms-length pre-sales of single residential lots bemg achieved prior to
development funding. The $100,000 security deposit was to be lodged with Custom
Credit prior to funds bemg advanced on Stage 2 of the home unit land.
In a form of application prepared internally by a Custom Credit officer,
Mr P.F. Lewis, the purpose of the advance was described as follows:
"To fund Stage IE of a 62 strata tutled residential unit development at
Lot 5 Stafford Road, Kenwick and the acquisition and subdivision of
Lot 2 and Part Lot 33 Stafford Road, Kenwick into 24 residential
lots * (Exhibit 1 Vol 3-37)
19.
And under the heading "PREAMBLE" appearing in the same document the following
was stated:
"Mr Papotio has approached the corporation to fund Stage II of a 62
Strata utled residential unit development on the properly adjoining
the subdivision Stage I has been completely presold and will scttle in
January/February 1990 completely eliminating Citibanks [sic] 1st
Mortgage Stage Ji will incorporate 10 units leaving the Corporation
with a debt of $500,000 over 10 units (approximate value $800,000)
This development will also aid in reducing the subdivisions [sic] costs
as sewerage lines and cquipment arc close at hand"
Notwithstanding what appeared in the application, Papotto dened in
cross-examination that he had approached Custom Credit on the basis that he was
seeking funding for a second stage of the development incorporating ten units. He
said the funding he was sceking was "to assist the development" and that no specific
stage was mentioned at all. Asked to explain how the reference to funding of Stage 2
had appeared in the application, Papotto said that he could possibly have told Custom
Credit that 1t would be repaid out of Stage 2 of the development. The fact was, as
Papotto conceded, that construction had commenced on all proposed units on the
home unit land by August 1989. It was put to him that by November 1989, Hollister
Developments had commenced work on each of the 62 units that it intended to
construct. Initially he dened that, saying that some of them only had slabs laid.
However, subsequently he agreed that the laying of the slab constituted the
commencement of construction. It was consistent with Victor's evidence and
supportive of the conclusion that I have already expressed that the so called staged
development was, in truth, a response to financial exigencies.
20.
The letter of approval from Custom Credit included a requirement for a
security deposit of $100,000 to be lodged with Custom Credit prior to funds beimg
advanced on the home unit land. On the internal application form, the amount of
"applicant's funds" was shown as $110,000 and then later as $100,000 When Papotto
was referred to this in cross-examination he said that he had no idea of how the sum
of $110,000 came to be in the application form and that it was the first time that he
had heard he was to put in either $100,000 or $110,000. He accepted that there was
a condition in the letter of approval that he should lodge $100,000 with Custom Credit
but contended that an officer of the company, Mr Jim Richardson, waived the
condition.
The Deed of Loan - 13 November 1989
On 13 November 1989, Hollister Developments entered into a Deed of
Loan with Custom Credit. Papotto, as guarantor, was also a party to the Deed.
Various provisions of the Deed are relevant to the question whether there was later a
default by Holhster Developments entitling Custom Credit to make demand and
appoint receivers. It 1s convenient to set out those provisions here.
The following definitions appear:
"2.13 "Collateral Security" means any and each other security or
covenant for the loan which is collateral to this Deed or to
which this Deed 1s collateral now or at any time 1n the past
or future held by the Lender including any Mortgage,
215 "First Advance" means the sum of ONE MILLION THREE HUNDRED
AND FIFTY THOUSAND DOLLARS (31,350,000 00) to be advanced by the
2.110
21.
Lender to the Borrower by progressive instalments in accordance with this
Deed,
"The date of first advance" means the 14th day of November 1989,
"Further Advance" means any sum which the Lender agrecs to advance to the
Borrower 1n accordance with this Deed,
"Interest Payment Days" means the 14th day of each month,
"Principal Sum" means -
21131 the whole of the balance
remaining unrcpaid (whether
due or not) from ume to ume
of the First Advance and cach
Further Advance (including all
moneys drawn, repaid and
redrawn), and
21132 all other advances of money
(by direct advances to the
Borrower, or by the Lender -
"Period of the Loan" means a period of onc (1) year
from the date of first advance,"
The following substantive provisions are also relevant:
"31
4.1
Subject to the comphance by the Borrower with the
terms covenants and conditions of this Deed to be
complied with by the Borrower prior to the making
of the First Advance, the Lender shall lend the
amount of the First Advance to the Borrower in the
manner provided for in this Deed
The Borrower shall repay the Pnncipal Sum or so
much thereof as shall for the time being be advanced
and remain unpaid to the Lender immediately upon
demand together with all interest due in accordance
with this Deed up to the date of payment.
5.2
22.
The Lender may not demand the repayment of the
Principal Sum prior to the expiry of the Period of the
Loan whilst the Borrower -
431 makes all payments of
Principal Sum and interest
provided for by this Deed, and
432 performs and observes all the
terms and conditions of this
Deed and ail Collateral
Security
The Bortower shall pay to the Lender interest
calvulated -
Sil from tune to ume on the
outstanding balame of the
Principal Sum,
$12 at the Standard Rate, and
$.13 from the date of first advance
of the loan,
on the Interest Payment Days in the manner
hereinafter set out and in each casc the payment of
interest shall be calculated up to and include the day
of payment and shall be computed with daily rests
PROVIDED THAT if and whenever a payment of
interest (clear of all deductions and taxes) on the
Principal Sum, or on so much thereof as for the time
being shall have been advanced and remain
outstanding, in respect to any period 1s made on its
due date or within eight (8) days at the Concessional
Rate of interest and provided no default exists in
respect of any previous payment of interest required
to be paid as aforesaid and provided further that all
and singular the covenants terms and conditions
herein and in any Collateral Security expressed or
implied up to the date of payment of such interest
have been duly and punctually performed and
observed THEN the Lender will accept interest
calculated at the Concessional Rate in lieu of the
Standard Rate
PROVIDED FURTHER and it 1s expressly agreed
that the Lender shall be at liberty at any trme and
from time to time by giving not less than one (1)
calendar month's written notice to the Borrower in
that regard either to increase or decrease the rate of
interest payable by the Borrower hereunder (both as
Xue Jo yunoo0e Jo yuswayNes Aue Jurpueisyimiou
shouoW pemns0g Joyo [je pue jsaz9quT
'ung yedroung oy1 jo wowed op soy Amdes
Sumuluos pue suruuns & powosp aq [Teys pooq sil Lu
spaptaoid ZZ osnepo-qng *Z asnejo ul poytoads sem yourkedas Jo apoul oul,
4. OSneya sTyy
UI OF poajar A[snotsaid ,siugWOAOIdUIT, Wd) 9Y) UT
Popnjour oq Os[P [JeYS & LZ] ASNeIO UT 0} polos; PUP]
ay uo ssuipjing JoyIo Aue pue sun yons Jo [Je JO
UONINISUOS YL fooioy € LT asnelO ul pouonUeWT
Ayzodoid ay uo situn Joy Ny NAsuOo 0} spusiUt I
yey) pue (asneyo sty) UT pauoluoUl oJOJoquiossy ,pUey
pres oY), Wo ay? UT popnyoUT aq osTe [yeys poaordut
se pur] Yory jo [[z) Joolay € ZT osne[D ul peuonuow
Ayodoid oy. uo syn Bunonnsuca Ajuasaid
st JOMOIIOg 9Y] yey) poole pue paspojmouwoe
JOYUNY st 3] ,syUowWeaoIduT, Wis) 2y} UT popnyoUl
9Q TIM OIA] WATRTSI UT SHON BUS pue Butd.UsUs
qEinionns [Te pue parnber se sooiases Joyo 10/pue
sed 'AWOMOo[a 'Fae 'aseIOMOS 'speOI UOTIEITUIT]
MoyUA Burpnpout osoyi seas [fe surpnpour
SO] YONs JO JUOUIGOJDAP SY SIO] POOTAIOS OWT puey]
ples ay) aptarp-qns 01 (,pue] pres ayy, Wo) oy) UT
papnpout Futag Joolay [ ZI asnejO Ul oO} perajal puey
aul JO Te) JoaaYy LLL asny[O url pouonuaw Ayodoid
ey. Jo Wwouryas ay) Joye 'spuaqur Jomom0g
ay? wy) prer8e pue pospyznouyre Aqary sty L9
SHONVACY JAISSHUOOUd JO MIANVAL Ou
SUMOTOJ SIP sew pracy OY) JapUN syuvMarv SJaaol0g sy Suoury
- LVHL SAVMTV GHdIAOUd
JooIny LIL asneya pue ¢¢ asneyg Jopun arqesed
{snormatd ysozoiwut Jo syuauyesur ay) jo nay ul
Japunany arqe (ed sjuourpeysut oy) auooag Udy) [TeYs
SWUOUIPISUL PrA Yons Jo JUNOWe suzy A[uIpsOvR
Jopunryoy «apquded jsagaqui JO siuoWyeysuT oy)
ut uoneues fue Jo nou wd DOU yons (ue <q Lew
pur (RY [CUOIsMUOD ay PUR WEY PAPPUPIS ay) 02
"€%
24.
other matter or thing whatsoever and this Deed and
any Collateral Security shall remain in full force and
effect unul @ formal discharge thereof shall be
granted and executed by the Lender"
Clause 11, relating to collateral securities, provided:
"111 The Borrower shall duly and punctually observe and
perform all of the covenants and conditions
contained in any Collateral Security to be performed
on the part of the person giving such Collateral
Security
112 = Ifa Mortgagor or Grantor defaults at any time in the
obsivene oor pe:formane of any covenant
agresinenat Of condiuon on the pet of dit
Moityagor or Grantor in any Collateral Secuiity then
that default shall be deew.d to be difalt by the
Botrower under thus Deed '
The general default clause was cl.12 which provided in the relevant parts:
"121 If the Borrower-
1211 defaults in the payment of any
part of the Principal Sum or
of interest or any other
moneys secured by this Deed
or any part thereof
respectively on the day or time
or in the manner hereinbefore
appointed for payment thereof
respectively and that default
continues for eight (8) days,
1213 defaults in the performance or
observance of any Collateral
Security,
12.1.4 the Borrower does any act,
deed, matter or thing or
knowingly or willingly permits
or suffers any act, decd,
matter or thing to be done by
or through its means or
instrumentality whereby or by
25.
reason Or means whereof the
secunty Or position of the
Lender under this Deed shall
be in the opinion of the
Lender become deteriorated
or lessened in value,
THEN and in any of those cases the remaining
provisions of this clause shall become operative
122 The Principal Sum (or so much as shall be then
owing) together with all interest accrucd and all
other of the Secured Moneys Gf any) shall become
immediately duc and payahle and be paid by the
Borrower to the Lender, or the Lender may exercise
any and cach power confured or implied by this
Deed or by Lavy *
Clause 17 sets out the securities for the loan
A mortgage, E234393, dated 13 November 1989 was executed by
Hollister Developments in favour of Custom Credit as a first mortgage over the
development land and as a second mortgage over the land at 30 Moss Street,
Huntingdale. A mortgage, E245889, dated 13 November 1989, was also registered as
a second mortgage over the home unit land. The first mortgage over the home unit
land was E053088 dated 17 March 1989 in favour of Citibank. The mortgagor 1s
shown as Rawang Nominees Pty Ltd which was the previous name of Hollister
Developments.
Cashflow Difficulties - December 1989 to May 1990
Construction of the units proceeded although not without difficulty. On
30 November, the building inspector for the Town of Gosnelis carried out a site
mspection of the home unit land with Victor. A number of problems were identified
26.
with respect to roof framing of the units. By a letter dated 1 December 1989, the
Town Clerk required seven items of rectification work to be carried out to make the
frames structurally adequate before approvals necessary for the issue of strata titles
would be gianted by the Council. Papotto had no recollection of the 1tems hsted in
the letter. The correspondence was directed to Victor. Another letter from the Town
of Gosnells on 27 December 1989 drew attention to the need to rectify fencing which
had been erected in non-compliance with fencing by-laws. This requirement and the
direction to remove some sandfill were to be camplied with before strata titles could
issue,
Papotto had orginally contemplated securing the requisite approvals
from the local authority to enable him to obtain issue of the strata titles by the end of
December 1989. The approvals were not forthcoming because of the construction
problems identified i the correspondence from the Town of Gosnells. As a result,
projected sales were unable to proceed and Hollister Developments began to
experience cashflow difficulties. It was unable to meet its commitments to creditors.
According to Papotto, however, creditors knew that the development was a big one
and were prepared to wait to some extent.
On 31 January 1990, Citibank agreed to readvance $300,000 to Hollister
Developments from the proceeds of capital reductions upon settlement of the first ten
units. The funds were to be made available on a draw down basis at the discretion of
Citibank. In February 1990, Papotto arranged additional overdraft finance to the
extent of $300,000 secured by a charge over his home in favour of the Commonwealth
27.
Bank. Hollister Developments was still having trouble meeting with the requirements
of the City of Gosnells. On 26 February 1990 the City of Gosnells wrote advising of
various matters to be resolved prior to the issue of strata titles. These related to
fencing, cracking in the units, provision of acceptable fire hydrants and a fire main
and the location of tall growing trees.
In the same month, Stephen Lewis was appointed as Business
Development Manager with Custom Credit and given responsibility for the Hollister
Developments' account Fle met Papotto on site on 2 March 1990) Papotto told hira
that television marketing of the units was commencing and that ten units hud already
been sold. He also told Lewis that he had standby funding available from the
Commonwealth Bank. Papotto told Lewis that the expected cost of completion of the
subdivision at this stage was $177,000. At the time there was only $110,000 available
from Custom Credit under the terms of its advance. Lewis raised the possibility of
resort to the standby finance available from the Commonwealth Bank. Papotto
became very agitated, threatening legal action and said that he would stop work on
the subdivision. He also indicated that he might take his business elsewhere. Lewis
told him that it was necessary to establish where they were with both developments
and to work together to resolve problems.
On 14 March, Lewis wrote to Papotto confirming that following the final
progress payment of $60,000 there were sufficient funds available at the then current
interest rate to cover March and April interest requirements. The letter concluded:
28.
"A capital injection, altcrnative cashflow or take out finance 18 to be in
place to facilitate payment of the monthly mterest from May 1990
onwards "
Custom Credit wrote to Citibank on 30 March confirming that it agreed that Citibank
should allow Hollister Developments to redraw $300,000 following initial settlements
of a similar amount. Citibank's priority thereafter was to be reduced at any
subsequent settlement by full proceeds, including deposits held pnor to settlement
Citibank was asked to confirm the arrangement.
In the first three months of 1990, only two offers to purchase units were
made and accepted. There were four in April and three in May. It was put to
Papotto that sales were hard to come by through the first half of 1990. He said that
was not really the case and then said that the company was not "pushing them that
hard either"
On 18 April 1990, Custom Credit wrote to Papotto pointing out that the
monthly interest on the $1.35 million advanced had been capitalised for the last time
and that interest due on 15 May would have to be paid. On 23 April, Custom Credit
wrote to Citibank advising that the offer ta agree to the readvance of $300,000 to
Hollister Developments had lapsed, Cittbank not having responded to 1t On 8 May
1990, Papotto wrote to the Commonwealth Bank advising that at that time LJ.
Hooker in Thorntie were selling two to three units per week and that Hollister
Developments estimated that within 26 weeks it should be able to clear all
commitments to the various financial institutions. His statement that two to three
units per week were being sold was false. He tried to defend his statement in cross-
29.
examimation by suggesting that he was referring to the number of offers per weck
coming in In this and other respects, Papatto represented as an unrehable, evasive
and argumentative witness.
On 10 May, Craig Dawson, a lending officer of Custom Credit, wrote to
Brian Wales & Associates requesting them to prepare an assessment of the costs to
complete the reinstated subdivision. On 17 May. Mr Brash the Operations Manager
for Custom Credit, advised that interest for the month of May was $24 222 88 of
which anly $9,76058 could be capitalised. A resultant hability of $14.462 30 was
pointed out and payment requested On 21 May 1990, Brian Wales & Associates
advised Custom Credit that the development land subdivision would cost $220,965 to
complete.
About the middle of May 1990, Papotto approached Desmond Westlake
to act as a finance broker to raise funds for Hollister Developments to complete the
project. Westlake is an accountant, property developer and licensed real estate
agent. He was also a bankrupt at the material time. He made an application for
further finance with Citibank and spoke to three or four other financiers orally to
gauge their attitude to the development. In the event, he was engaged by Hollister
Developments effectively to manage the completion of the project on the home unit
land. Although it was his recollection that he commenced that retainer on 6 June
1990, it appears he actually started on 29 May 1990 as 1s recorded in a note in his
diary.
30.
By the end of May, Papotto was experiencing a "hard time" with trade
creditors. A few had stopped work because they had not been paid. In the meantime,
Custom Credit appointed James Bonwick to take an overseeing or supervisory role in
relation to existing advances which had been made In May 1990, the then State
Manager of Custom Credit was dismissed and Bonwick appounted to act in his place
until a permanent appointment could be made. He reviewed Hollister Developments'
account in late May 1990 and decided to meet with Papotto Stephen Lewis arranged
the mi cting for 30 May
Papotto Mects Bonwick and Lewis 30 May 1990
At the meeting, Bonwick introduced himself and told Papotto of the
background to his visit to Perth. He told him that there had been significant changes
in the Perth office and that several of the company's officers had been dismissed. He
told Papotto he had been appointed as State Manager to assuime control of the office
and review accounts where it was perceived that there were problems. Hollister
Developments' account was one in respect of which Custom Credit perceived there
was a problem. Bonwick said he was happy to discuss the position and asked Papotto
to bring him up to date about the progress of the development and to provide a
report about its future.
Bonwick said in evidence that Papotto spent 15 or 20 minutes
endeavouring to explain the status of the project, the problems he had had with
obtaining titles to Stage 1 units, clearance on the land subdivision and with cashflow.
He told Bonwick he did not have sufficient funds to complete the balance of the units
31.
in Stages 2, 3, 4 and 5. Bonwick told Papotto that he wanted a submission about the
status of the project in seven days setting out his requirements for continuing support
from Custom Credit. He made it clear that support would be discretionary depending
upon whether Custom Credit "deemed it appropnate" to provide it Papotto
suggested that the best thing to do would be to complete the development in one
stage rather than continue to stage it. Bonwick said he did not think that was an
appropriate 1dea_ Papotto told him there was a significant number of trade creditors
pressing Hollister Developments for payment and that unless some of them were
paid, the job would probably cluse down. Bonwick suggested that Papotto mcorporate
the position of the outstanding trade creditors into the submission to Custom Credit.
Bonwick said he was prepared to consider the provision of carry on finance while the
question of an increase in the facility to Hollister Developments was considered. He
asked Papotto whether he had the capacity to pay interest because the facility
previously extended was fully drawn in regard to its interest component. There was
also discussion about the Citibank facility. The possibility that Custom Credit might
pay out Citibank was considered. The future of the development land was also
canvassed. Papotto suggested that it would be appropriate to continue development
of the land subdivision and build houses on it. Bonwick did not agree. He suggested,
however, that Papotto could include in his submission some reference to the cost of
completing the land subdivision without the necessity to build houses. In relation to
the home unit land, Bonwick was most concerned to ensure that sales of units already
negotiated and any future sales take place as quickly as possible in order to reduce
Hollister Developments' debt to Custom Credit. The meeting ended with Bonwick
thanking Papotto for his tme and asking him to get back to Custom Credit within the
32.
following seven days. He had made no decision at that meeting on Custom Credit's
attitude to Hollister Developments' account
On Papotto's version of the conversation, Bonwick asked him how
Hollister Developments was going to meet future interest payments on the advance
that was now nearly fully drawn. He told Bonwick that Hollister Developments had
other assets that it could sell to service the loans. According to Papotto, Bonwick was
quite happy with that advice. Papotto also said he explained to Bonwick the
arrangements with Citibank and that he had had a cashflow problem because of the
delay in obtaining strata titles. He said he told Bonwick that ditficultics had arisen
with trade creditors which would be overcome in due course There was some
discussion about the possibility of release of government funds to subsidise first home
buyers late in that year. According to Papotto, Bonwick asked how Custom Credit
could become more involved and help Hollister Developments. Papotto said he had
responded that the only thing they needed was money to which Bonwick replied:
"Oh, well, we'd look at becoming a sole lender for you, paying out
Citibank, and what else do you need?"
Papotto said that he raised the question of creditors and that Bonwick responded:
"Well, we'll get rid of your creditors for you; we'll give you enough
money to pay out your creditors; we'll consolidate both loans"
The upshot, according to Papotto, was that Bonwick opened the door for Hollister
Developments to go away and think about his proposition and come back with a
33.
proposal. Papotto's estimate of the cost to completion was about $400,000 for the
entire project. No reference was made to Custom Credit's lending policy m Western
Australia. A long term plan was discussed which involved completing the unit
development, getting the subdivision finished and doing other projects. On
completion of the two projects Custom Credit would involve itself in jot ventures
with Hollister Developments at a later stage
Cross-examined about his account of the conversation, Papotto said that
Bonwick invited him to consolidate his loans by paying out existing creditors including
Citibank. He offered Hollister Developments the opportunity "to put a proposal
together on those grounds". Asked if there was a commitment by Bonwick to provide
the money, Papotto said:
"I believe that was the basis of it, yes".
He asserted in his evidence that he left the meeting with no doubt that he had a firm
assurance from Bonwick that Custom Credit would advance to Hollister
Developments enough to pay out Cittbank and complete both developments. It was,
he said, a matter for him to choose whether or not to take up the offer. Despite the
fact that on his account he had an offer of financial salvation from Bonwick, Papotto
claimed in evidence that he said he would consider the position.
Papotto's evidence on the conversation and, in particular, his suggestion
that Bonwick made a firm commitment was inherently improbable. It was plain that
34.
the development was in a precarious state. Hollister Developments had effectively
fully drawn its advance from Custom Credit, there were pressing creditors of the
order of $270,000 and Bonwick had come in to tighten, not to loosen, the criteria for
advances and their supervision. In my opinion, the account given by Bonwick is by far
the more probable account of the meeting. I do not accept Papotto's version.
Stephen Lewis was also present at the meeting of 30 May and gave
evidence consistent with that of Bonwick. He said the meeting concluded on the basis
that Papotto would prepare a submission to Custom Credit and in the meantime, at
its discretion, Custom Credit would "diip feed" the project It follows that T do not
accept that the representations allegedly made by Custom Credit at the meeting were
made. No promises or firm commitments were proffered beyond a statement of
readiness to consider a submission for finance. Nothing said in the course of the
meeting, m my opinion, constituted or was capable of constituting musleading or
deceptive conduct on the part of Custom Credit as alleged in the statement of claim.
Westlake Meets Bonwick and Lewis - 6 June_1990
A meeting took place between Westlake representing Hollister
Developments, and Bonwick and Lewis, representing Custom Credit, on 6 June 1990.
The meeting took place about Spm that day. Westlake introduced himself as having
been appointed Project Manager by Hollister Developments. Bonwick was surprised
as he had believed that he would be seeing Papotto. Westlake, he said, went to some
lengths to convince him of his credentials. There was discussion about Hollister
Developments' trade creditors. Westlake told Bonwick that there were substantial
35.
numbers of unpaid trade creditors in respect of earlier parts of the development and
pressing creditors on the existing development. He was endeavouring to reconstruct
who those trade creditors were. Bonwick said, as he had on 30 May, that Custom
Credit would consider paying "the existing trade creditors". By that term he meant
"people that were on the site then and there".
Bonwick said he told Westlake what he had told Papotto about the
problem in the Custom Credit office. He told Westlake that he had come to Western
Australian to review facilities where it was beheved that these were problems and that
Hollister Developments' account was one of them He repeated to Westlake that he
had previously asked Papotto for details of the project as it stood at the present time,
costs to complete the project, a sales program, updated feasibility of the project and
details of the financial position of Hollister Developments and Papotto. Westlake told
Bonwick he would go away and try to collect the information Bonwick did not meet
Westlake again except on one occasion when he bumped into him mm the lift foyer at
Custom Credit on the following week.
Westlake's account of the meeting was that 1t took about three hours
and that Bonwick said it would be better for Custom Credit to take over all
responsibilities for funding Hollister Developments. There was, he said, a general
agreement that it would be in the best interests of Custom Credit that they have all
the homes finished at quickly as possible. He was cross-exammed at some length
about the conversation with Bonwick and Lewis. Without rehearsing the detail of that
cross-examination, I am satisfied that the account given by Bonwick was the more
36.
probably accurate account and that again he made no commitment on behalf of
Custom Credit to provide any finance. There was nothing in Custom Credit's conduct
on this occasion that could be characterised as representational m any relevant sense
or misleading or deceptive. Counsel for Hollister Developments agreed in final
address that Hollister Developments did not claim that it was misled at that date into
believing that it would get the full facility. On the other hand, it seems to have been
contended that Custom Credit would pay outstanding creditors to the extent of
$267,000. I am satisfied that no such commitment was made In the event Custom
Credit paid creditors of Hollister Developments on a selective or "drip feed" basis.
The Application for Bridging Finance
Shortly after the meeting of 6 June, Westlake prepared a letter from
Hollister Developments to Custom Credit which sought bridging finance. The letter
was undated and was signed by Papotto. It was accompanied by a number of sheets
of financial information in relation to the project prepared in large part by Westlake
and based, at least in part, upon information supplied to him by Papotto and Victor.
Westlake accepted in cross-examination that his role at Hollister Developments at this
stage was to marshal the information for submission to Custom Credit. The covering
letter specified loan requirements of $5,394,541 calculated as follows:
1. Existing Loan Custom Credit $1,490,000
2 Trade Creditors $3 267,000
3 Cost to complete land
subdivision S 131,000
4 Cost to complete Stafford
Village § 486,000
37.
5 Cost to complete Super Deli
and House $ 150,000
6 Payout Citibank loan $2,541,017
7 Payout contract of sale
subdivision land S$ 79,500
8 Interest on loan capitalised
(approx) $250,000
$5,394 541
The loan was to be repaid from the sale of.
1 Stafford Park Units $1,657,030
2 Land $1,139,000
3 Super Deh and House $ 381.000
$6,176,050
The first two sheets accompanying the Ietter showed projected income
and expenditure for the home unit land and the development land respectively.
Income from the sale of the units was shown as $4,657,050 less expenses of
$3,765,000, yielding a net profit of $892,050 The sale of the subdivided land was
estimated to generate income of $1,519,000 against expenses of $1,026,200, yielding a
profit of $492,800. These figures, of course, presented the overall project, including
both the home unit and development lands, as viable in the event that the bridging
finance sought were able to be obtained.
The Viability of the Project
It is appropriate at this stage to consider, in the light of the figures used
38.
in the letter, the viability of the project ou the assumpuion that the finance requested
had been advanced In so doing it should be noted that the figure of $1,519,000
shown as the sales figure im tespect of the development land, was broken up into
components of $380,000 for the Super Deh and Hlouse on the development Jand and
$1,139,000 for the balance.
It may be observed at the outset that the letter shawed grovs sales
figures for the home unttys and th developmen! land which did not take infty account
g I
comnusson espens s that apposed an the accom. watt nents A commission
figure of $124,000 was showa oo the tt enichars os the com russian corr ited tus
the sale of the home units A fizure of $15.000 was suown as comimission in relation
to the sale of the development land 'That latter figure, however, appeais to have
been calculated on the assumption that a sum of $380,000 would be obtained from
the sale of the Super Deh and House As the necessary approvals were not
forthcoming for their proposed construction, a pro rata estimate of a reduced
commission payable in respect of the sale of the development land was proposed by
senior counsel for Custom Credit at $38,000 which I accept as appropriate. On that
basis, commission expenses of $124,000 and $38,000 would need to be taken into
account in calculating the profitability of the project as a whole as at June 1990.
The letter from Hollister Developments to Custom Credit showed an
amount of $2,541,017 to pay out the Citibank loan. However, as can be calculated
from a facsimile letter dated 12 June 1990 from Citibank to Papotto, the overall
liability at that time, after adding back additional advances, was $2,915,922. The
39.
Citibank facsimile showed a total amount due of $2,628,093, comprising the orginal
advance of $2,500,000, arrears of $92,569, interest of $35,124 and estimated Fmancial
Institution Duttes of $400. The facsimile disclosed further construction draws of
$287,829 which, when added to the amount of $2,628,093, gave a total amount due to
Citibank (before credits for proceeds of umit sales) of $2,915,922. This exceeds the
figure shown in the Hollister Developments' Iette: by $374,905
The Holster Developments Jeter also estimated raterest co ty as
$280 000) But the co etoaed Co tors Cred ated Cruibank debts exer eded $4 ou dhon,
o1UNg Miest nn oxces. Of ZU, por annum Tact ors subse s aa of cour.) for
Custom Credit that on the reasonable assumption (in the light of subscquent market
conditions) that the units and blocks would tthe 12 months to complete and sell from
June 1990, the minimum interest would exceed $500,000. Westlake agreed in cross-
examination that the figure of $250,000 for interest which was shown tn the letter was
"a very conservative estimate". It was based upon an assumption that the sales would
all be achieved by January 1991 in accordance with a projected cashflow statement
attached to the letter. That cashflow projection was given to Westlake by Papotto.
By way of aside, it can be noted that the assumed sales program in that cashflow
projection was reflected in a capital reduction program imposed as one of the
conditions of the approval of additional finance by Custom Credit in a letter dated 18
July 1990, which will be referred to later in these reasons In any event, Westlake
agreed that if sales were to drag on for sw months beyond the six months assumed in
the cashflow, then an interest allowance of at least anather $250,000 would be
needed.
40.
On the income side of the equation, it cin be assumed in favour of
Hollister Developments that the figure of $1,139,000 for sule of the development Jand
represented a reasonable assessment of its hkely yeld The Super Deh land actually
realised $48,000. The value of the home units 1s shown in the letter at $4,657,050
But a licensed valuer, Clanan Marr, called by Hollister Devclopments, had valued the
units on 4 October 1990 at an average of $76,000 for a three bedroom unit and
$66,000 for two bedrooms Marr had signed the valuation piepared by Hilher Parker
m Mach 1989 of $80,000 for three bedrogin ties and $77 000 for two b doer units,
ging a tatel valu: ot S4.949,00) Siyuats had beets edoat 2? dane (doe pross
prices of N132,950 dhere wer OC) uns da total, se Sf rem aaad to be sald at the
time of the valuation Forty four were thiee bedroom uatts, tun were two bedroow
units. The value of the remaining units was therefore $4,004,000 The value of all 60
including proceeds of those sold by 12 June, would be $4,440,950. On this basis the
viability of the proposal could be assessed in terms of projected expenditure and
income as follows:
Expenditure
Costs estimated by Hollister
Developments 1n letter to
Custom Credit $5,394,541
Citibank - further advances 3 374,905
Commission on unit sales $ 124,000
Commission on land sales $ 38,000
Additional interest § 250,000
Deduct Super Dell and House
costs {S$ 150,000)
Total Expenditure $6,031,446
41.
Income
Subdivision sales $1,139,000
Deli land value S$ 48,000
60 home units $4,440,950
Total Income $5,627,950
The above calulatiod stows a propected di ficimey Of £03, 196 It can
be cecepted tit there hacen portifier tes who it ths process OF a sessimm a ety
Nevertheless, tue fipuics do, at least im by opinion, prevent the conclusion bring
reached that, on the balance of probabilith , the project was capuble of yielding a
profit having regard to current market conditions
Mr Marr was referred to another valuation prepared by K J. Collins for
Citibank on 12 October, in which he valued the units at $67,000 to $71,000 for those
with three bedrooms and $59,000 to $62,000 for those with two bedrooms. Marr
accepted, upon being pressed in cross-examination, that Collins' opinion was within
the bounds of a reasonable valuer's opinion That, of course, would indicate a more
parlous outlook than on the assumed unit values derived from Marr's own assessment.
The general conclusion that the project was not viable is supported by comments
made i a valuation report prepared by Christie Whyte Moore which was in evidence.
There it was said that valuation calculations set out in the report indicated that the
home unit development should not have proceeded beyond the conception stage given
the associated uncertainties, msk and poor return Calculations in that report in
42.
relation to the home unit development indicated, as at May 1990, a proyecicd Joss of
$27,851.
Overall, I am satisfied on the balance of probabilities that the project
was not capable of yielding a profit within the 12 months or so from May 1990 even
on the assumption that the money sought from Custom Credit were advanced
Progiess Poy ments Afier 6 June Mecting
On 8 June 1990, Papotto wrote to Custom Credit se lene a dacn
advame of $50,000 to pay costs of development Or the same dey he a a'2 a request
for a drawdown of $50,000 agamst "the agreed loan" to Hollister: Developments 'This
was to meet administration and supervision wages and particular trade creditors. On
8 June 1990, a sum of $50,000 was made available to Hollister Developments by
Custom Credit. Further carry on payments were made by Custom Credit on 15 June
totalling $48,600. On the same day, Custom Credit wrote to Hollister Developments
pointing out that the existing account was in arrears to the extent of $14,462.30 due
on 14 May 1990 and $25,303.10 due on 14 June 1990. A cheque for the total arrears
was requested by 25 June 1990. Also on 15 June, Custom Credit sent a cheque for
$1,723 direct to Phillips Fox, a creditor of Hollister Developments and $48,600 was
remitted to Hollister Developments. A further cheque comprising $30,000 was
forwarded to meet ongoing commitments on 27 June. On 28 June 1990 a further
amount of $64,770.01 was paid, being $16,768.90 less than the amount claimed of
$81,538.91. Other payments of $80,305 38, $31,308.54, $68,800 and $58,131.86 were
made in July. Custom Credit continued thereafter to make payments on a selective
43.
basis to specific creditors This was sometimes referred to m evidence as a "drip
feed".
The Letter of Approval - 18 July 1990
On 18 July 1990, Lewis signed a submission and recommendation in
favour of an advance of $5,396,000 to Hollister Developments. It was noted in the
submission that
"TR. apphcant his a cheqaer Pobetor fo ob vatby sy erditics a
pres estips Ve ate prosets the Sapper aeqgu Soo) ftule
cay quapletion Of AC propech ys Chavet Coutts, tay Loss
On the same day Custom Credit sent to Hollister Developments a letter
stating that it had approved in principle an advance subject to certain conditions The
amount of the loan was $5,396,000 for a maximum term of 12 months. Payments of
the principal were to be made by way of reductions from sales through August,
September, October and November of 1990. The remaining balance was to be paid
within the term of the loan. Security requirements included mortgages over Hollister
Developments' and Papotto's properties and a guarantee by Papotto. Conditions of
the approval included the following:
"Valuations by pancl valuer on the Moss Strect and Hollister Way
properties along with written confirmation from prior mortgagecs
establishing equity of $30,000 and $80,000 respectively "
Papotto said in evidence that on receipt of the letter he rang Lewis and complained
that conditions setting out a timetable for the sale of the units and the use of the
44,
equity in the two residences as additional security had never been discussed
According to Papotto, Lewis said, "Sign the letter and Ill get the conditions waived
but you'll need to sign it or we're not going to give you any more moncy". On that
basis, according to Papotto, he signed the letter and sent it back. Lewis' only
evidence-in-chief on the point was of a conversation with Papotto after the valuations
had come in in which he said that the offer had fallen away because they were
msufficient. In cross-examination he was asked whether Papotto had complatned to
him about the Jetter contammg matters which had not been cre ussed This he
emphatically demed, as he abo domed the s.egestion that he had told Papoito to sign
or he would not get tho money there is nothing im Vestlake s evtdeme to suggest
that he was told of any proposed waiver of conditions contained in the letter He was
asked im cross-examination about discussions he had had with Lewis between 18 July
and 29 August when he left the employment of Hollister Developments. He made no
reference to any mention of a waiver of valuation or other conditions in those
subsequent conversations. I am not satisfied on Papotto's evidence that Lewis said
what was attributed to him. Even in its own terms the language of Lewis' promise
'Tll get the conditions waived" suggests he would have had to refer to higher authority
in any event. The promise itself so expressed could not be taken as a waiver.
Upon receipt of the letter, Westlake said he rang all creditors
immediately and told them the loan from Custom Credit had been approved.
Following the letter Westlake said that he had a number of discussions with Lewis
asking whether documentation for the loan would be finished. According to
Westlake, he was told the documentation was being prepared.
45.
On 24 July 1990, Lewis recensed a valuation of Papotto's house at
$123,000 The house property at Hollister Way was valued at $290,000 The
valuations were less than those required to meet the conditions of the letter of
approval of 18 July. When told of this result by Lewis, Papotto lost his temper and
banged the telephone down. Lewis told both Papotto and Westlake that the offer had
fallen away with the failure to meet the valuation conditions. At the end of July and
early August 1990, Lewis ceased to have responsibility for the Hollister Developments'
loan and passed it over to another oliver, Paul rash who was then employed as
Senin Property Linance Manager with Custom Credit) Brash met with Papotte on 21
August 1990 ar Custom Cis Cs ottts Brash mtroduced ho wself to Papotto aad sud
that he had called the mecting because he was now taking over control of the account
and wanted to discuss with him various aspects of it. The discussion covered sales
programs of the units, costs and associated matters Brash told Papotto that Custom
Credit was concerned, that there was a need to have sales of the umits and the land to
reduce Hollister Developments' debt. He put to Papotto that Hollister Developments
should try to adopt a sales program to ensure that the debt reduction could be made.
Papotto was almost non-committal in response, but accepted that there was a need to
get sales of the units and was confident that he could achieve that Papotto asked
whether or not mortgage documents were being prepared in accordance with the
letter of 18 July 1990. Brash told him they were not. Brash said the reason that
security documentation was not bemg prepared was that the valuations had indicated
that Papotto's equity in the properties had not reached the appropnate level. Papotto
became quite angry at that time and criticised the valuer and the valuation.
46.
On 23 August 1990, Westlake left his employnient with Elollister
Developments Fhs departure followed a disagreement about payment of his fees
with Papotto. During the months of May, June, July, August and September, interest
was accruing due to Citibank in respect of its advance. It was put to Papotto that
Hollister Developments had failed to make payments of interest due to Citibank in
those months He denied that fact. However, it 1s plain that interest was due to
Citrtbank during those months and that it was not paid
On 3 Scptembe the new State Manaer of Custoin Cred Gordon
Asmus, together with Paul Brash, met Pepotio Bre introduced Asmus to Papotio
and said that the purpose of the meeting was to discuss the progress of the project at
Kenwick. Brash put various items of information to Papotto about the amount of
debt owing under the Citibank mortgage, the amount owing to Custom Credit and
other financial information He asked Papotto if the information he was putting to
him was correct. He reiterated that Custom Credit was most concerned that sales be
achieved in both the unit development and the land subdivision in order to reduce the
debt. He told Papotto that if the sales were not achieved, the Corporation would sell
the property under its mortgage powers Papotto presented a list of creditors at the
meeting and asked whether or not they could be paid. Asmus said that the Custom
Credit was not prepared to pay them and that they should be the responsibility of
Hollister Developments.
47.
The J -ctter of 4 Septernber 1699
Brash wrote a follow up letter of 4 Septeinber 1990 mm which he noted
that the cost to complete the unit development was then $145,222.08 and the cost to
complete the subdivision on the development land was $44,000, representing Water
Authority charges. There were then outstanding creditors on both projects and claims
totalling some $328,000 of which Hollister Developments expected to pay $267,000.
The letter went on to say that it was agreed that a sales timetable, which was set out,
must be aclucved in ord: + to avind Custom Credit setline as mortgagee In th. event
that there were less thea three unconditi ab sates of dots aim the subdivisten by 21
September 1990, a sales proge tin would be set by Custom Cirdit. An' uipated
costings for the development wele set out Hollister Developments was requested to
countersign the letter and return it to Custom Credit which it did In my opinion, it
was with a view to protecting its own position as mortgagee that Custom Credit was
endeavouring to settle a program for the sale of the units so that the overall debt
position of Hollister Developments could be reduced. Custom Credit was also
continuing to make progress payments on a "drip feed" basis to keep the project going
so that some units could be completed for sale.
I do not regard the letter of 4 September as embodying any waiver or
variation of Custom Credit's right as against Hollister Developments, nor as
embodying any variation of existing contractual arrangements. It did little more than
set out a plan for managing the ongoing progress of the project and for the orderly
sale of the units.
48.
The Custom Credit Policy
In the statement of claim it 19 said that during May 1990 Custom Credit
had decided on a policy of lending further money 1n Western Austraha only if
contractually obliged to do so or if it were necessary to complete projects. The
complaint 1s made by Hollister Developments that neither Bonwick nor any other
representative of Custom Credit imformed any representative of Hollister
Developments of the existence of the policy. The policy as detailed im answer to
interrogatories, was expressed thus
"[astrucuons wer. even to oh ois of das unit of the respondent in
Western Austriba known gs} operty Lintnuidl Services to implement
@ pulicy that loans were only tu be made if the respondent
(1) was already legally commutied to advancing mon.cs
{i1) deemed it necessary to advance monies to complete
projects "
I accept that a general policy in these terms existed at the relevant time. However,
counsel for Hollister Developments had difficulty in hus closing address in explaining
just how any conduct of Custom Credit was rendered misleading or deceptive by
virtue of the existence of the policy. It was suggested that Papotto would not have
borrowed further funds from Custom Credit if he had known about the policy. But
there 1s nothing to suggest, and counsel was unable to point to anything to suggest,
that Custom Credit would have acted any differently in the absence of the policy. In
my opinion, the failure to disclose the policy did not falsify anything that Custom
Credit said or represented by its conduct, nor did it cause Hollister Developments to
act in any way differently from the way it would have acted if it had known of the
49.
existence of the policy.
The Case in Misleading or Deceptive Conduct
The general thrust of Hollister Developments' case in misleading or
deceptive conduct was expressed by counsel in his closing address thus:
it is the applicant's case that up tll May 1990 1 was proceeding with
the devclopment of lot 5 im stages, that wt was defkcted from that
course by the mspondent's invitation to it to apply fur a new facility,
aed by ty mu).auhog or decepive conduct relating to the propos.d
new facihty That is to say, the apply eat would not ha apphad for
the new fecshity but for the musteading or @.veptive Conduct"
As 1s apparent from the reasons already given, I am satisfied that there 1s nothmg m
the conduct of Custom Credit which should be characterised as misleading or
deceptive as alleged. In particular, I am not satisfied that 1t made any unconditional
commitment to advance $5.396 million. The conditions expressed in the letter of 18
July 1994 were not met. I do not accept Papotto's evidence that those conditions
were waived by Lewis. On the contrary, the position 1s as Lewis put it to Papotto that
the offer had lapsed. The general position of Custom Credit was consistent with that
of a financier endeavouring to protect its position and existing security without
exposing itself unnecessarily to additional risk.
The Appointment of the Receivers
On 28 September 1990, Citibank sent Hollister Developments a notice
of default for non-payment of money due under the terms of its mortgage, E053088.
On 12 October, Custom Credit sent a notice of demand for payment of all money
50.
owing to it under the mortgages E234393 and E245889 dated 13 November 1989. On
16 October 1990, a solicitor for Hollister Developments wrote to Custom Credit
objecting that the demand was defective because it did not state the amount of money
required to be repaid or give a ground or reason upon which the repayment was
required. It was also said to be in breach of an agreement with Hollister
Developments evidenced by the letter of 18 July. The solicitors for Custom Credit
rephed, asserting that the notice was valid They referred to Eollister Developments
default of mterest due to Custom Credit On 31 October 1990, Citibank assigned 1s
interest in its morigage 053068 to Custom Credit Notice of the assignment was du'y
given to F 'liister Developments The principal sun owing upder the mortgage was
$2,748,200.77 as at 30 October 1990. On 28 November 1990, Custom Credit
appointed jot and several receivers and managers of the properties under its
mortgage E234393 and the assigned mortgage E053088.
Under the Deed of Loan dated 13 November 1989, Hollister
Developments was obliged by cl.11.1 to observe and perform all the covenants
contained 1n any collateral security, which term was defined in cl.2.1.3 to include "any
and each other security or covenant for the loan which is collateral to this Deed...
including any Mortgage". By cl.11.2 a default under a collateral security is a default
under the Deed. By cl.12.1.3, a default in observance of a collateral security renders
the principal sum and interest under the Deed immediately due and payable. By cl.17
of the Deed, provision 1s made for execution of the mortgages. The powers
exercisable under the mortgages are, it was submitted, powers "conferred or implied
by this Deed" under cl.12.2. I accept that the requirement to execute the mortgage
51.
confers upon the mortgagee and therefore the Jender under the Deed the power to
appoint receivers and that this can rightly be identified as a power conferred by the
Deed albeit it is expressly provided for in the mortgage document.
The question anses then whether there has been a default which would
properly ground the exercise of that power. In my opinion there was such a default at
least in the failure to make the interest payments required by cl.5.1 of the Deed. The
power conferred by the Deed 1s not conditioned by spe: tfication of the breach in any
notice of demand or default The defiults were continuing, albeit not acted upon for
a considerable time. Thcy were not waived Custom Credit's forbearance in this
respect does not prevent it from exercising the powers that it did. No question of
trespass on the part of the receivers arises.
The Cross Claim
As Hollister Developments has failed to make out any case against
Custom Credit, the only matter that remains 1s the question of Custom Credit's cross
claim against it for moneys owing on the Deed of Loan, the Citibank mortgages and
the further advances which were made to enable the payment of some of the trade
creditors during the construction period The amount of the claim 1s able to be
calculated from the report prepared by Jeffery Herbert on Hollister Developments'
claim for damages. The amount owing to Custom Credit 1s calculated from Annexure
8 to the Report and 1s the sum of the credit amount of $1,350,000 at the beginning of
the Annexure, representing the initial loan and $2,223,395.10 which represents the
sum of additional payments thereafter including liability under the Citibank mortgage.
52.
That represents a total of $3,573,395 10. Judgment on that cross claim 1s likely to be
of academic interest only as it appears that Hollister Developments will not be in a
position to meet any part of 1t. No claim for statutory interest 1, made There will
therefore be judgment on the cross claim in the amount of $3,573,395.
I certify that this and the preceding
fifty one (51) pages are a true copy of
the Reasons for Judgment of his Honour Justice French
Associate: Abia
Date) /b/n/44
Counsel for the Applicant: Mr R.B. Pringle QC and Mr B. Duckham
Solicitors for the Applicant: B.W. Duckham & Co.
Counsel for the Respondent: Mr C.L. Zelestis QC and Ms A. Liscia
Solicitors for the Respondent: Mallesons Stephen Jaques
Dates of Hearing: 22-26, 29, 30 November 1993
Date of Judgment: 16 November 1994