Application by Epic Energy South Australia Pty Ltd [2003] ACompT 5 TRADE PRACTICES - access to pipelines - review of decision of Australian Competition and Consumer Commission to draft access arrangement - whether decision reasonable - calculation of optimised replacement cost - whether covered pipeline - Moomba to Adelaide Pipeline System - Gas Pipelines Access (South Australia) Act 1997 (SA) Gas Pipelines Access (South Australia) Act 1977 (SA) Application by Epic Energy South Australia Pty Ltd [2002] AcompT 4 followed Associate Provincial Picture Houses Ltd v Wednesdbury Corporation [1948] 1 KB 223 applied House v The King (1936) 55 CLR 499 applied Duke Eastern Gas Pipeline Pty Ltd [2001] ACompT 2 followed APPLICATION BY EPIC ENERGY SOUTH AUSTRALIA PTY LTD File No 6 of 2002
JUSTICE COOPER, PROFESSOR D K ROUND AND MISS M M STARRS BRISBANE (HEARD IN ADELAIDE) 10 DECEMBER 2003
IN THE AUSTRALIAN COMPETITION TRIBUNAL
Matter No 6 of 2002
RE: APPLICATION UNDER SECTION 38 AND/OR SECTION 39 OF THE GAS PIPELINES ACCESS (SOUTH AUSTRALIA) LAW FOR REVIEW OF THE DECISION BY THE AUSTRALIAN COMPETITION AND CONSUMER COMMISSION MADE ON 31 JULY 2002 TO DRAFT AND APPROVE AN ACCESS ARRANGEMENT FOR THE MOOMBA TO ADELAIDE PIPELINE SYSTEM UNDER SECTION 2.20(a) OF THE NATIONAL THIRD PARTY ACCESS CODE FOR NATURAL GAS PIPELINE SYSTEMS
BY: EPIC ENERGY SOUTH AUSTRALIA PTY LTD
TRIBUNAL: JUSTICE R E COOPER (DEPUTY PRESIDENT)
PROFESSOR D K ROUND
MISS M M STARRS
DATE: 10 DECEMBER 2003
WHERE MADE: BRISBANE (HEARD IN ADELAIDE)
THE TRIBUNAL ORDERS THAT: 1. The decision of the Australian Competition and Consumer Commission made on 31 July 2002 to approve an Access Arrangement pursuant to s 2.20(a) of the National Third Party Access Code for National Gas Pipeline Systems in respect of the Moomba to Adelaide Pipeline System ('the Decision') be varied. 2. The Decision be varied in the following manner: (a) An exchange rate adjusted cost of line pipe of $1 302.20 per tonne be used to calculate the Optimised Replacement Cost of the existing pipeline for the purpose of determining the initial Capital Base in valuing the Moomba to Adelaide Pipeline System ('MAPS') as a Covered Pipeline. (b) The expansion of capacity of the MAPS by 25 terajoules per day to satisfy the requirements of the operator of the Pelican Point Power Station be excluded from the System Primary Capacity ('the SPC') calculation and that the SPC of the MAPS for the purpose of the approved Access Arrangement be 323 terajoules per day. (c) All necessary and consequential amendments be made to give effect to such variations in terms of the amendments contained in 'Scenario 2' of the document 'Statement of Amendments Required to Access Arrangement'.
We try to embed the page this law was scraped from. If the site blocks framing, you still get the link and a local excerpt.
Last checked with source on —
Checking whether the official page can be embedded…
Plain-English simplify of this law: a short summary, key points, and both sides of the argument. Generated on first view via Replicate, then cached. Vote on what helps your study.
No study brief is cached for this law yet. Sign up to generate a plain-English brief.
Sign up to generate