EARTHWORKS PTY. LIMITED V. THE GLADSTONE HARBOUR BOARD 6/1953
High Court of Australia
Full text
Select any passage to save a personal note with optional tags.
EARTHWORKS PTY. LIMITED
THE GLADSTONE HARBOUR BOARD
WELLLAMS de
611953
Jate delvered 21 JuLy 1993
JUDGMENT (ORAL)
EARTHWORKS PTY. LIMITED
ve
THE GLADSTONE HARBOUR BOARD
JUDGMENT (ORAL) WILLIAMS J.
This is an appeal from an order of the
Full Supreme Court of Queensland dismissing an appeal by the
plaintiff company in a suit in which it was non-suited by the
learned trial judge. The plaintiff which was incorporated
on 2nd April, 1951, sued for the balance of noneye/aue "rom
the defendant to the plaintiff for work and labour done and
materials supplied by the plaintiff to the defendant at its
request. The amount claimed in the statement of claim was
£8,656.13. 9, but I understand that the plaintiff now claims
a sum of approximately £10,000. The way in which this claim
arose is, shortly stated, as follows. The defendant Board
advertised for tenders for the excavating, carting and placing
in position to height specified, of some 150,000 cubic yards or
more of filling material in order to reclaim approximately six
acres of foreshore at Auckland Point, Gladstone. Mr. Re Wiles
put in.a tender to do this work for 5/4d. per cubic yard solid
measurement at the quarry site. The tender which he signed
was stated to be for and on behalf of a company to be formed.
He received a letter in reply from the Secretary of the Board
on the 31st October, 1950, referring to this reclamation job,
as it was called, which said:
"As your tender, 5/4d. per cubic yard (solid) was the
lowest received for the above job, the following
recommendation has been submitted to the Under Secretary
to The Treasury in connection with same:-
'That, providing Mr. Wiles of Wiles Welding Works,
861 Ann Street, Brisbane, can satisfy the Treasury
as to the bona fides of the Company proposed to
be formed, and of its ability to carry out the work
tendered tor, authority to be given for the acceptance
of his tender.'"
I emphasize the words "for the acceptance of his tender".
A further letter followed from the Secretary of the Board on
the 27th November, 1950, which said:
"I am directed to advise that your tender, five shillings
and fourpence (5/4d.) per cubic yard, solid measurement
at the quarry site, for the excavating, carting and
placing in position to height specified, some 150,000
cubic yards or more of filling material in order to
reclaim approximately six (6) acres of foreshore at
Auckland Point, Gladstone, has been accepted by the
Board.
Time for completion thirty (30) weeks from commencement".
It is perfectly clear from Kelni Baxter,
L.Re 2 CoP. 174, and all the subsequent cases, many of which
were recently reviewed by this Court in Vickery ve Woods, 85
CLR. 336, that it is quite impossible for anyone to make a
contract as agent for a company which has not yet been
incorporated, so that, although Wiles purported to tender for
and on behalf of a company to be formed, the contract was in
law a contract between Wiles and the Board which was personally
binding on Wiles. It was a contract on the part of Wiles to
perform the specified work on behalf of the Board, the payment
to him for the work to be done to be 5/#d. per cubic yard.
The work was actually commenced in January 1951 and carried on
in the name of two companies which it was proposed to form at
the time, but which were never incorporated, and it had
progressed to a considerable extent and payments had been made
prior to the incorporation of the plaintiff company. The Board
was informed that this company had been incorporated on the
2nd April, 1951, by a letter of the 3rd April, 1951, from the
solicitors for the plaintiff, or for Mr. Wiles,whichever they
were,to the Board, stating that they enclosed copy of
certificate of incorporation and had to advise that the first
directors were Leslie George Morwood and Wiles. The letter
stated that the change in name arose through the Companies!
Office having already received an application for registration
in the name previously selected. The letter also stated that
the contract would be completed and all matters done in the
name of the above company. No reply was received from the
Board to this letter.
When the matter came before the Full Supreme
Court the learned Chief Justice delivered a judgment with which
the other two members of the Court agreed. The material
passage in the judgment of the Chief Justice reads as follows:
"Either there was a contract between the Gladstone Harbour
Board and Wiles for work which was performed by the
Plaintiff after its incorporation as the agent of Wiles,
or there was a novation of the contract between the
Gladstone Harbour Board and Wiles whereby after the
incorporation of the plaintiff in April 1951, by the
consent of Wiles, the defendant and the plaintiff a new
contract was substituted for the original contract and the
rights and liabilities of the several parties were
determined by Wiles's being discharged from the obligations
of his contract and the plaintiff's being substituted for
him as a contracting party with the defendant. Whichever
is the correct construction of the effect of the dealings
between the parties, the plaintiff's claim in this action
must fail."
I agree substantially with this passage,
although it is not necessary, to my mind, to tie oneself to
the fact that such part of the work as the plaintiff company
performed after its incorporation was performed by the plaintiff
as the agent of Wiles. The purpose of this appeal is to seek
anew trial, so that we start with the premises that the
learned trial judge was wrong in non=suiting the plaintiff
and the Full Court was also wrong in upholding him if there
was any evidence on which the jury could reasonably find an
obligation in favour of the plaintiff imposed on the Board by
implied contract or rule of law to the effect stated in the
plaintiff's claim. As I understand Mr. Hart's argument he
says there was evidence on which the jury could reasonably find
that it was never intended that Wiles should perform the work
for which he had tendered but that it was to be performed by the
company which he intended to form and by that company only on
behalf of the Board and that everyone concerned believed that
after the company had been incorporated there was a contract
-& -
to do the work between the plaintiff and the defendant, whereas
in law there was no such contract. Accordingly the legal position
was that the company had done the work on behalf of the defendant
and the defendant had accepted it. Applying the principles which
are discussed in Craven-Ellis v. Canons, Limited, 1936, 2 K.B. 403,
in Johnsons Tyne Foundry Proprietary Limited v. Maffra Corvoration,
77 ColeRe Ste and in other cases he sought to bring the
plaintiff's case within the proposition that an implication arises
by contract or rule of law to the effect that in such
circumstances a person on whose behalf work is done is bound
to pay a reasonable amount to the person who does the work from
which he has benefited and can be sued on the common money counts
for a quantum meruit. He then sought to show from the evidence
that the 5/4d. per cubic yard was not a reasonable amount to pay
for the work and that in addition to the payment of 5/4d. a cubic
yard which the Board has already paid or is willing to pay, the
plaintiff should recover £10,000 or thereabouts as additional
remuneration for the work which it did in the reclamation.
To my mind no inference was reasonably open
to the jury on the facts on which such a claim could be based.
at? two inferences were reasonably open to the jury. Those were
the inferences to which the learned Chief Justice of the
Supreme Court referred. There does not appear to me to
be any evidence that the original contract entered into between
Wiles and the Board was ever novated, thet is to say any evidence
that, with Wiles's consent, there was substituted for that
contract a contract between the plaintiff company and Wiles.
The only reasonable inference open to the jury on the evidence
seems to me really to be that there was one contract and one
contract only from the beginning to the end, that is to say
the contract between Wiles and the Board, and it is immaterial
whether the work done by the plaintiff pursuant to that contract
was done by it as the agent of Wiles or as an independent
contractor. So far as the Board was concerned it was
immaterial what relationship existed between the plaintiff and
Wiles. Wiles was the person who had contracted to do the work
and he was the only person who could claim payment from the
Board. If contrary to my opinion any other inference is
reasonably open on the facts, it could only be the inference that
there had been a novation of that contract so that from a certain
date, presumably the 2nd April, 1951, the plaintiff company was
substituted for Wiles as the principal to whom the Board looked
for the future performance of the work and the person who could
claim payment from the Board for the work which was done. after
that date. But the contract would, of course, be novated in
its entirety and the only payment which the plaintiff could
claim under the novation would be the payment provided for in
Wiles's tender, that is the payment for the work at 5/id. per
cubic yarde
For these reasons I am of opinion that the
appeal must be dismissed with costs.
WEBB J. : I agree,
KITTO J. : I agree.
TAYLOR Je : I also agrees
Appeal dismissed with costs.
Related laws
No related documents linked yet.
You've got 21 of 22 free Acts left this visit. Sign up anytime for Facts, Related, and study briefs too.