NOVELTY FAIR THEATRES PROPRIETARY LIMITED V. RALPH SYMONDS LIMITED
High Court of Australia
Full text
Select any passage to save a personal note with optional tags.
10 22 if
/ Git
oak '
IN THE HIGH COURT OF AUS RALIA
NOVELTY FAIR THEATRES PTY. LTD.
if
Judgment delivered alSydnay
on. Wednesdays 6th April 196
WM, Houston, Gort. Print, Melb,
NOVELTY FAIR THEATRES PROPRIETARY LIMITED
Ve
RALPH SYMONDS LIMITED
ORDER
Appeal dismissed with costs.
Ov. ATR THEAT. ROP! 'ARYL:
Ve
(ONDS LIMITED
Zuenenr
AYLOR J
NOVELTY FAIR THEAT! PROPRIETARY LIMITED
Ve
RALPH SYMONDS LIMITED
This appeal is concerned with the rights of
the parties under a contract whereby the appellant agreed to
purchase from the respondent a quantity of "Alumply" for use
as a component in the erection, in a suburb of Melbourne,
of an open-air moving picture screen. The name "Alumply"
denotes a product manufactured by the respondent and it
consists of sheets of specially brushed aluminium which are
affixed to a backing consisting of plywood. Its reflective
capacity is said to be high and after discussions between the
parties the appellant and its advisers decided that alumply
should be purchased and used as a facing for the screen in
question. As erected the screen was unsatisfactory. So much
is common ground. The principal defect and the only one
with which we need concern ourselves was that from the moment
of its erection the screen exhibited, in use, a number of dark
lines. These were said to be about two inches wide and they
extended vertically from the top to the bottom of the screen.
In these circumstances the appellant brought an action against
the respondent in the Supreme Court of Victoria in which it
claimed damages for breach of contract. The claim was
resisted by the respondent who also counterclaimed for the
unpaid balance of the price. In substance, the appellant's
claim was based upon the alleged breach of conditions,
expressed and implied, relating to the suitability of the
alumply for the purpose for which it had been purchased. The
action was heard without a jury and, in the result, judgment
was entered for the respondent both on the claim and counterclaim
This appeal is now brought in an attempt to have that judgment
set aside and to have judgment entered for the appellant.
In order to appreciate the submissions made
by the appellant on the appeal it is necessary that we should
make more particular reference to the terms of the contract
which it alleged was made and also to the precise character
of the goods to which it was said to relate, First of all
it should be said that it was the appellant's intention to
erect a screen 44! high and 106' wide. But the respondent
did mot undertake to provide a sheet of alumply of these
dimemsions. What it undertook to provide were strips, or
panels, of alumply forty-four feet long by thirty-four and
seven-sixteenths inches wide and three-eighths of an inch
thick, These were to be delivered from Sydney to the
appellant's site in Melbourne where it proposed
to attach the panels vertically to an existing framework.
We mention these matters because by its statement of claim the
appellant alleged that the respondent had "agreed to sell and
deliver to the plaintiff at Tooronga in the State of Victoria
a cinema screen facing measuring 106' x 44! of a material
known as 'Alumply' for the sum of £2,664. 16. 0", Thereupon,
it was alleged that it was a term and condition of the contract
that "the said 'Alumply' would be so treated by the defendant
that it would when used as a cinema screen facing have a high
degree of reflectivity and further that (a) such reflectivity
would be uniform throughout the full length and breadth of
the said screen facing; (b) the said screen facing would be
free from shadows or distortions and (c) the screen facing
would be in every way satisfactory". The respondent by its
statement of defence denied any such contract and went on to
allege that the only relevant contract between the plaintiff
and the defendant was a contract by the terms of which the
defendant undertook to supply sheets of alumply sufficient to
make a cinema screen facing 106' x 44' and to prefabricate,
drill, pack.and deliver the same. Needless to say, there
was mo such contract as was alleged by the appellant but
3.
the trial proceeded on the basis that the subject matter of
the transaction was as alleged by the respondent and it was
on this view that his Honour proceeded to consider what
conditions or warranties the contract contained. In the
events which have happened we feel bound to approach the
questions raised on the appeal in the same way. This
approach, however, involves a difficulty which is not mrely
formal for one of the appellant's submissions was that proof
that the screen was found to be defective immediately upon
its erection was sufficient to establish a breach of the
express: . warranty which it asserted. But the express
warranty alleged by the statement of claim was said to be
annexed to a contract for the sale of a cinema screen facing
measuring 106' x 44" and there was no such contract. Nor,
in the circumstances of the case, is it possible to treat
the warranty alleged in para. (4) of the statement of claim,
which, in terms, related to a screen facing of the specified
dimensions, as applicable to a large number of panels to be
used as components in the manufacture of a screen facing.
The result is that we are left without any precise allegation
of the terms of the express warranty upon which the appellant
relies. However, the learned trial judge found that an
express warranty was given and since there is no appeal
against that finding we propose to deal with the appeal on the
basis that this was so and that its terms were correctly
stated by him.
His Honour found that the respondent's
representative, Symonds, told the appellant's architects
that the alumply which he could supply would, when used as
a@ screen facing, have a high degree of reflectivity and
provide a satisfactory screen. This assurance his Honour
treated as a promise by the respondent to supply materials
that would provide a reasonable satisfactory screen.
he
But such a promise, his Honour thought, added nothing to the
condition which otherwise. he would have thought proper to
imply pursuant to s. 19(a) of the Goods Act 1928. That,
in the absence of any express condition, such a condition
should be implied was, apparently, not in dispute for his
Honour said that counsel for the appellant "in his final
address conceded, rightly in my opinion, that it was an
implied condition of the contract that the alumply to be
delivered would be reasonably fit for the purpose for which
the plaintiff required the same". Nor was there any dispute
in the case that proof that the defects in the screen were
attributable to the unsuitability of the alumply panels as
a component would be sufficient to fix the respondent with
liability. To quote his Honour:-
"There can be no doubt that the presence of the lines
of the face of the screen is a serious defect and if the
plaintiff is right in its contention that this is due
to something-in the condition of the alumply sheets
present at the time of the delivery thereof, then the
sheets were not reasonably fit for the purpose for which
they were required, nor were they materials that would
provide the plaintiff with a reasonably satisfactory
sereen face. It would follow if these contentions
are made out that there has been a breach of the
conditions of the contract".
It should be stated at this stage that the black lines previously
mentioned occurred in the vicinity of the vertical edges of each
panel, and upon each panel they extended approximately one inch
from the edge. There was no suggestion that these lines
were in any way attributable to the fact that the screen facing
consisted of a number of panels placed side by side with the
result that a number of vertical joints was inevitable; the |
complaint was that by some cause or other the reflective
capacity of the strips adjacent to the longer edges of the panels
had been destroyed or substantially diminished. That this was
so is beyond doubt. But there was much speculation concerning
the question whether this was attributable to the condition
of the alumply as delivered or to its treatment thereafter
while in the appellant's hands and, as a consequence the cause
De
of this condition became a very material matter for inquiry
at the trial. The trial occupied a great many days and many
experts were called in an endeavour to throw some light on
the matter. A number of possible causes were suggested
but in the end his Honour found that the defects in the screen
were caused by corrosion. However, he went on to say that
he was unable to find in any of the possibilities suggested
by the parties any explanation that he was prepared to accept
as a cause of the corrosion and discoloration from which the
lines on the screen arose. He thought that it would be
highly speculative to attribute them to any of the
possibilities suggested by the plaintiff and added that if
he were compelled to choose between the various alternatives
placed before him, he would be disposed to think that the
defendant's suggestion that the edges of the sheets supplied
were damaged as a result of corrosion after they were
delivered was the most probable.
Upon the hearing before us the parties were
content to assume that the deficiencies in the screen were,
in fact, caused by corrosion though they were seriously in
dispute as to the originating cause of this condition. But
before dealing with the submissions which were respectively
made it is convenient to turn to the appellant's primary
submission which was that proof that the screen was defective
immediately after its erection was sufficient to establish
a breach of the express warranty which his Honour found had
been given.
This submission had two aspects. First of
all it was said that the express warranty relied upon was more
or less absolute in the sense that it involved the respondent
in liability if it could be shown that: the screen facing when
erected was defective. According to the 'argument advanced
it mattered nothing whether the screen was erected shortly
6.
after delivery of the panels, or whether, or not, there had
been an inordinate delay though it was conceded that if the
respondent could establish that the defects had arisen from
some neglect of the appellant after delivery the respondent
might escape liability. This contention, it will be seen,
treats the time of erection, and not the time of delivery as
the critical point for an examination of the suitability of
the panels. But it is sufficient to say that the warranty
as found by his Honour was directed to the suitability, and
in the circumstances of the case, to the condition of the
panels at the time of delivery and, that being so, this branch
of the contention cannot be sustained. The second aspect of
the contention is really concerned with the probative force
of the evidence that the screen was found to be defective
immediately after its erection. Proof of this fact, it is
said, established, at least prima facie, that the panels were
defective at the time of delivery and, thereupon, it was for
the respondent to displace the prima facie presumption. But
the onus of proof in a case of this character does not shift
during the courseof the trial. No doubt in many cases
evidence of a defect existing in goods at some stage after
delivery may sufficiently establish that the goods were
defective at the time of delivery. But the probative force
of such evidence must always be a matter of circumstance, and
degree and the question at the end of the trial must always be
whether, upon the evidence adduced, the plaintiff has
established the breach relied upon,
In the present case much more is known than
merely that the screen was defective when erected. On the
hypothesis acceptable to both parties the cause of its
defective conditon was corrosion and there was ample evidence
to show that the corrosion might well have been caused by the
manner in which the panels were treated by the respondent
after delivery had been made on the 6th September 1956.
7.
They had been packed in a special case or crate with narrow
packing strips separating the longer edges of each panel from
its neighbour. They had been transported from Sydney in
such a way as to ensure that from side to side the panels
stood vertically in the crate which contained them. The
appellant was specifically informed by the respondent that
the crate containing the panels would be lifted from the
transporting vehicle and placed upon the ground at the
appellant's site in the same upright position. But because
the respondent foresaw some difficulty in opening the crate
in this position it had the crate placed upon the ground in
such a way that each panel lay in a horizontal. plane. There,
with the exception of two panels which were removed for a day
or two, they were left for some five weeks subject, as his
Honour said: "to the effect of wind and rain save to the
extent that they were protected by the tarpaulins that were
supposed to be spread over them". And his Honour had no
confidence whatever that the tarpaulins were kept in position.
Indeed, it seems that at some stage after the two sheets
previously referred to had been removed the crate
deteriorated and broke and when the sheets were finally
removed for erection the site was described as being like a
quagmire as the result of the rain that had fallen. When
it is seen that there was abundant evidence, which is not
seriously in dispute, that if moisture penetrated between the
surfacesof the sheets at the edges of the packing strips
"there would be created an ideal setting for corrosion
by crevice action" it is obvious that proof that the screen
was defective when erected was quite inadequate to establish
that this resulted from defects existing in the panels at the
time of delivery.
The other contention advanced by the appellant
was that his Honour should have found affirmatively that the
corrosion complained of resulted from the application in the
respondent's works of a chemical, known as sodium
pentachlorphenate, to the edges, both side and end, of the
panels. This was applied primarily as a fungicide to the
edges of the plywood backing. But, it seems, its application
to aluminium, or to some forms of aluminium at least, will
induce corrosion and, according to the appellant, the
probable cause of the corrosion on the panels which the
respondent supplied was carelessness in the application of the
fungicide. _It is probable, it is said, that the operator
employed on this task applied it not only to the edges but
also to the face of each panel for a distance of one inch
or so from either side. This was, however, no more than
speculation, and there were good reasons why the learned
trial judge should not infer that it had occurred. In the
first place, there was, as we have already said, another
explanation of the corrosion that appealed more to him than
this speculative theory; in the second place, although the
evidence was. that the fungicide had been applied to the short
ends as well as the long sides of all the panels, there
was no sign of corrosion at the ends and there were two
panels (not those temporarily removed from the crate), the
sides of which were not affected at all, so that the theory
did not account for all the facts. In the result we can
see no reason why we should hold that his Honour should have
made an affirmative finding that this was the cause of the
defects of which the appellant complains.and, accordingly,
the appeal should be dismissed.
Related laws
No related documents linked yet.
You've got 21 of 22 free Acts left this visit. Sign up anytime for Facts, Related, and study briefs too.