THE COMMONWEALTH OF AUSTRALIA V. A.E. GOODWIN LIMITED
High Court of Australia
Full text
Select any passage to save a personal note with optional tags.
IN THE HIGH COURT OF AUSTRALIA
LHS
Vv.
REASONS FOR JUDGMENT
ORIGINAL
Judgment delivered at:
'A. G. Brooks, Governoent Printer, Melbourne
0.7639/00
oe
THE COMMONWEALTH OF AUSTRALIA
Ve
A. E. GOODWIN LIMITED
ORDER
Judgment for the plaintiff for £26,726 11s. Od.
and costs.
THE COMMONWEALTH OF AUSTRALIA
Ve
A. E. GOODWIN LIMITED
JUDGMENT MENZIES J.
THE COMMONWEALTH OF AUSTRALIA
ve
A. E. GOODWIN LIMITED
When the trial of this action began, it appeared
that there were three issues: (1) whether there was a contract
between the parties for the manufacture by the defendant of
154 railway goods wagon bogies at the price of £698 each;
(2) whether the defendant had repudiated that contract; and
(3) if so, whether the Commonwealth's claim for £26,726 11s. Od.
damages was excessive. In the course of the trial, counsel for
the defendant, in the face of the strength of the plaintiff's
ease, abandoned the first and third matters, leaving for
decision the one question whether it had been shown that the
defendant had repudiated the contract.
Whether there was repudiation may be considered
(i) having regard to clause 23(1)(C) of the General Conditions
of Tender and Contract - a document forming part of the
contract ~ and (ii) independently of that provision.
It was argued for the defendant that no regard can
be had to clause 23(1)(C) because it constitutes an unlawful
attempt to oust the jurisdiction of the courts. That argument
I reject. My reason for doing so will become apparent from my
statement of my understanding of the effect of the provision
itself.
Not every breach of a contract amounts to the
repudiation of that contract. A breach, to be so regarded,
must be one going to the root of the contract. But the parties
to a contract may, if they wish, stipulate that a particular
breach should be regarded as amounting to the repudiation of the
whole contract. See the statement of law by Jordan C.J. in
amways Advertising Pty. Ltd. v. Luna Park (N.S.W.) Ltd,
2.
38 S.R. (N-S.W.) 632, at pp. O41 and 642. Such a purpose
clause 23(1)(C) was intended to serve and, as I read that
provision, it makes a failure to make progress with, or carry
out, a contract to the satisfaction of the Contract Board
constituted pursuant to the Supply and Development Act 1939-
1948 (hereinafter called "the Board"), inter alia, a breach
going to the root of the contract and amounting to its
repudiation unless the contractor shows cause, to the
satisfaction of the Board, why it should not have that effect.
So much of this provision as is relevant here is obviously not
concerned 'in any way with ousting the jurisdiction of the
Court. Indeed, it recognizes that the Commonwealth must go
to the Court if it desires to establish repudiation and
recover damages therefor. Accordingly, if the Commonwealth
has shown two things - (1) that the defendant failed to make
progress with, or carry out, the contract to the satisfaction
of the Board; and (2) that the defendant did not account for
that failure to the satisfaction of the Board - then there was
a breach of contract which amounted to its repudiation by the
defendant.
As to the first of these matters, the letter from
the Secretary, Contract Board, to the defendant dated
28th January 1959 and the notice enclosed - sent as they were
under the authority of the Board's decision recorded in its
minutes of 14th January 1959 - satisfies. me that the Board was
very much dissatisfied with the defendant's progress with, and
earrying out of, the contract. The principal contention on
behalf of the defendant was, however, that upon the evidence
I should not find that the defendant had failed, to the
satisfaction of the Board, to show cause as required by the
notice. This I will now consider,
By the statement of claim it was alleged that
"The defendant failed to show cause to the satisfaction of the
said Board why the said contract should not be treated as
having been repudiated by the defendant". This allegation
was not put in issue; what the defendant did was to refrain
from admitting that the truth of the allegation would entitle
the plaintiff to rescind the contract or treat it as having been
repudiated by the defendant. It was proved that on 18th
February the Contract Board considered the substance of the
defendant's letter of 10th February 1959, written in reply to
the notice that had been sent to it, and recommended approval
to forwarding to the defendant a letter drafted by the Assistant
Crown Solicitor and informing it as follows: "The Contract
Board has considered the representations contained in your
Company's letter but is not satisfied that the Company has shown
cause, as required by the Notice of the 28th January, 1959, why
the Contract should not be treated as having been repudiated by
your Company", Mr. Stephen's contention that the Contract
Board did.not exercise the discretion which it had, but
automatically adopted the opinion of the Assistant Crown
Solicitor that the company had failed to show cause, hardly does
justice to the Board which was, of course, entitled to
professional advice. Having regard to the matters to which I
have already referred, I am satisfied that the proper finding is
that the Board did consider the matter and concluded that the
defendant had failed to Show cause as required.
Looking at the evidence, however, independently of
the special provisions of clause 23(1)(C), I am still satisfied
that the defendant did repudiate the contract because it was
unable to fit the bogies with the "Athermos" axle boxes, which
the contract required, except by purchasing them from the sole
Australian manufacturer, Bradford Kendall Ltd., at what it
regarded as an extortionate price, Mr. Stephen argued that the
defendant could, and was ready to, carry out its contract by
fitting "Athermos" axle boxes supplied from abroad. Assuming,
4,
without deciding, that the contract did allow the use of
imported boxes, I am nevertheless satisfied that the defendant,
having been refused an import licence, was not in a position to
import them and, furthermore, if they could have been imported,
they could not have reached Australia in time for the completion
of the contract by the due date. Accordingly, the defendant's
only practicable way of carrying out its contract was to use
Australian-made boxes, and this it had firmly determined not to
do. In the circumstances, not being able to carry out its
contract except at a substantial loss, it refused to do so and
repudiated the contract. I therefore find the only issue left
to me in favour of the plaintiff.
Accordingly, there will be judgment for the
plaintiff for £26,726 11s. Od. and costs.
IN THE HIGH COURT OF AUSTRALIA
THE COMMONWEALTH OF AUSTRALIA
A.E. GOODWIN LIMITED
REASONS FOR JUDGMENT
Judgment delivered at Melbourne
on Monday, 15th March, 1965. .
THE COMMONWEALTH OF AUSTRALIA
Ve
A. EB. GOODWIN LIMITED
When the trial of this action began, it appeared
that there were three issues : (1) whether there was a contract
between the parties for the manufacture by the defendant of
154% railway goods wagon bogies at the price of £698 each; a
(2) whether the defendant had repudiated that contract; and i
(3) if so, whether the Commonwealth's claim for £26,726.1ls. Od.
damages was excessive. In the course of the trial, counsel for
the defendant, in the face of the strength of the plaintiff's
case, abandoned the first and third matters, leaving for
decision the one question whether it had been shown that the
defendant had repudiated the contract.
Whether there was repudiation may be considered {
(i) having regard to clause 23 (1)(C) of the General Conditions
of Tender and Contract - a document forming part of the
contract - and (ii) independently of that provision.
It was argued for the defendant that no regard can
be had to clause 23(1)(C) because it constitutes an wmlawful
attempt to oust the jurisdiction of the courts, That argument
I reject. My reason for doing so will become apparent from my
statement of my understanding of the effect of the provision
itself,
Not every breach of a contract amounts to tne
repudiation of that contract, A breach, to be so regarded,
must be one going to the root of the contract, But the parties
to a contract may, if they wish, stipulate that a particular
breach should be regarded as amounting to the repudiation of the
whole contract. See the statement of law by Jordan C.J. in
Tramvays Advertising Pty, Ltd. v. Luna Park (N.S We) Ita.
38 S.R, (N.S.W,) 632, at pp. and 642, Such a p
2.
constituted pursuant to the Supply and Development Act 1939-
1948 (hereinafter called "the Board"), inter alia, a breach
going to the root of the contract and amounting to its
repudiation unless the contractor shows cause, to the
satisfaction of the Board, why it should not have that effect,
So much of this provision as is relevant here is obviously not
concerned in any way with ousting the jurisdiction of the
Court. Indeed, it recognizes that the Commonwealth must go
to the Court if it desires to establish repudiation and
recover damages therefor, Accordingly, if the 6ommonwealth
has shown two things - (1) that the defendant failed to make
progress with, or carry out, the contract to the satisfaction
of the Board; and (2) that the defendant did not account for
that failure to the satisfaction of the Board - then there was
a breach of contract which amounted to its repudiation by the
defendant. .
As to the first of these matters, the letter from
the Secretary, Contract Board, to the defendant dated
28th January 1959 and the notice enclosed ~ sent as they were
under the authority of the Board's decision recorded in its
minutes of 14th January 1959 - satisfies me that: the Board was
very much dissatisfied with the defendant's progress with, and
carrying out of, the contract. The principal contention on
behalf of the defendant was, however, that upon he evidence
I should not find that the defendant had failed, *o the
satisfaction of the Board, to show cause as required by the
notice. This I will now consider.
By the statement of claim it was alleged that
"The defendant failed to show cause to the satisfaction of the
said Board why the said contract should not be treated as
having been repudiated by the defendant." This allegation
was not put in issue; what the defendant did was to refrain
from admitting that the truth of the allegation would entitle
the plaintiff to rescind the contract or treat it as having been
3.
repudiated by the defendant, It was proved that on 18th
February the Contract Board considered the substance of the
defendant's letter of 10th February 1959, written in reply to
the notice that had been sent to it, and recommended approval
to forwarding to the defendant a letter drafted by the Assistant
Crown Solicitor and informing it as follows: "The Contract
Board has considered the representations contained in your
Company's letter but is not satisfied that the Company has shown
cause, as required by the Notice of the 28th January, 1959, why
the Contract should not be treated as having been repudiated by
your Company." Mr, Stephen's contention that the Contract
Board did not exercise the discretion which it had, put
authomatically adopted the opinion of the Assistant Crown
Solicitor that the company had failed to show cause, hardly does
justice to the Board which was, of course, entitled to
professional advice. Having regard to the matters to which I
have already referred, I am satisfied that the proper finding is
that the Board did consider the matter and concluded that the
defendant had failed to show cause as required.
Looking at the evidence, however, independently of
the special provisions of clause 23 (1)(C), I am still satisfied
that the defendant did repudiate the contract because it was
unable to fit the bogies with the "Athermos" axle boxes, which
the contract required, except by purchasing them from the sole
Australian manufacturer, Bradford Kendall Ltd,, at what it
regarded as an extortionate price. Mr. Stephen argued that the
defendant could, and was ready to, carry out its contract by
fitting "Athermos" axle boxes supplied from abroad. Assuming,
without deciding,that the contract did allow the use of
imported boxes, I am nevertheless satisfied that the defendant,
having been refused an import licence, was not in a position to
import them and, furthermore, if they could have been imported,
they could not have reached Australia in time for the completion
of the contract by the due date, Accordingly, the defendant's
Le
only practicable way of carrying out its contract was to use
Australian-made boxes, and this it had firmly determined not to
do. In the circumstances, not being able to carry out its
contract except at a substantial loss, it refused to do so and
repudiated the contract, I therefore find the only issue left
to me in favour of the plaintiff.
Accordingly, there will be judgment for the
plaintiff for £26,726.11s, Od. and costs.
Related laws
No related documents linked yet.
You've got 21 of 22 free Acts left this visit. Sign up anytime for Facts, Related, and study briefs too.