Select any passage to save a personal note with optional tags.
Movrow arc nov
V
Mananin
| heean
a
on
Ketierd 15 Nov 922
oth
MORROW and another vy, MANNING
53 7 . STABKE, DIXON, AND EVATT JJ.
'
The respondent employed the appellants as architects te prepare
Plans. and specifications for a large building in Sydney and to supervise
its erection. During the course of the work differences arose with the Fa
econtractcr which were ultimately submitted to arbitration. The arbitra~"
tors by their award founc that in addition to an amount of £49,500 al-
ready paid to the contractor under the appellants! prozress certificates,
there was payable by the respondent to the contractor a valange of £2,606 =
13 - Lid., of which £535-3-24. might be withheld as rotention moneys for a
speca fied period. In the arbitration various claims for allowances were
submitted by the respondent cn the ground of defective work by the con- i
tractor or failure to comply with the specifications, and in arriving at
their award these were considered by the arbitrators, who communtegsoa tay
the parties to the reference their decision upon each item. The 'respondent
however, appears to have been dissatisfied with the condition of the
building, and would not pay the architects, the appellants, the unpaid
balance of their remuneration, When the appellants sued him in the Supreme |
Court of New South Wales for their fees, he filed, as well as a plea of
never indebted, pleas by way of cross action alleging that the appellants,
as architects, had been negligent in the preparation of plans specifications
and bills of quantities and in supervision. The action was tried as a :
commercial cause without a jury by Halse Rogers J., who gave judgment fer |
the appellants upon the action and cross action. Spon apreal to the Full
Court consisting of James, Davidson and Stephen JJ., this judgment upon
the cross action was reversed ag to three items of negligence with respect
to which the Full Court entered judgment upon the cross action for the
sum Of £1,100. The juigment for the appellants upon the claim in the ac- t
tion was affirmed, and also uvon other items of negligence in the cross
action. From the judgment of the Full Court the arpellants, the architects,
now appeal to this Court; the resnondent algo cross appeals in respéct of
two of the items in referhoe to which the Full Court upheld the judgment
of Halse Regers J.
There are thus five matters to be dealt with in respect of which
the building owner, the respondent, claims that the architects have been
guilty of negligence resulting in damage.
ta
1. It is convenient to consider first a claim for the small sum of
£40. The specifications contain the requirement that at the level of each
Floor a 3 lb. lead damp course should be built in the brick work of the
walls. It appears that at the upper floor levels the contractor used 2 1b
end not 3 1lb-lead. The amount payable to the contractor was fixed in the
certificates and award as if he had used 3 1b. lead throughout, because
tthe fact that he had used 2 1b. lead was not discovered until later. It is
+ said that lead of the lesser gtuge serves the purpose of a damp course as
'well as that of the gauge specified . But the cost or value of the higher
gauge is greater. The sum of £40 is the amount whioh should have been de-
. dueted from the contract price in respect of all the smaller gauge lead
' used if the fact of ite use had been discovered before tae arbitration.
Tais amount, by the judgment of the Full Court, the respondent has recover —
ed from the appellants. Halse Rogers J. found that the failure of the archi-
tects to discover the use of 2 lb. lead amounted to negligence in super-
vision, and this finding has not been challenged. But he was of opinion
that the amount over-credited to the contractor had not in fact been paid
to him by the respondent and might be deducted from or set aside against
the retention moneys which remain in the respondent's hands. The general
conditions of the contract provide: :
"oy defects shrinkages or other faults which may appear within fifty four
.(54) weeks from the completion of the building and arising out of defective
or improper materials or workmanship shall upon the direction in writing
of the architect and within such reasonable time as shall be specified
therein be amended and made good by the builder at his own cost, unless the
architect shall decide that he ought to be paid for the same, and in case
of default the proprietor may recover from the builder the cost of making
good the works."
The Specifications contained the following provision:
i
"Maintenance: For six (6) calendar.months after the issue of final certifi-
cate the builders are to be resgonsible for and are to make good all shrink~
ages ease doors sashes etc overhaul all locks fittings and fastenings and
uake good any defects that may reveal themselves due to defective workman—
ship or materials. The architeots will atftheir discretion retain one per
cent (1) of the amount of tke contract for the duration of the maintenance
period". |
In their award the arbitrators said: "we find that of the above sum...the s
of £535-3-2 may be retained by the proprietor as retention money until 5th
June 1931". Now the amount of the retention money fixed by the award is
14 of the price smd» named in the contract. The date, 5th June 1931, is !
exactly six months from the date of the award, although it appears to be olro,
{
{ 54 weeks approximately - six days more - from the date when the building |
4b
i
t
ete eR ASSES OA EL ESERIES
~
wag handed over, which, accoriing to the ar
nitects. was 16th May 1930.
The award seems to mean that the building owner must pay the full sum de-
termined,unless under the maintenance clause in the specifications or
possibly the clause in the contract, the retention money may be applied
for the owner's benefit, and to treat the amged for that as equivalent to
the final certificate.
In these circumstances, the respondent could not retain the £ho out
of the retention money if he were sued by the cogtractor upon the award
unless he could establish fraud in the contractor o&% that the deficiency
in the gauge of the lead was a defect that before 5th June 1931 revealed
itself due to defective materials or that the deduction is authorised by
the clause in the general conditions. We cannot assume that the resnondent
can establish fraud against the contractor. The provision in the general
conditions looks rather to the remedy of defects and faults than to ae
compensation, and it needs some direction in writing from the architect
"and none has been given. The maintenance clause in the speoificationsis
expressed in language not appropriate to the case of a discovery that the
contractor has used materials inferior to those specified, although no
defect in the building has resulted or is likely to occur. The respondent,
therefore, appears to have no direct answer to an action by the contractor
upon the award. Possibly he might succeed in a cross action against the
contractor for unliquidated damages for breach of contract, Put, as it
appears that es a result of the architects' default, he has incurred a
direct liability to the contractor of an amount greater by £40 than wasp
proper, the burden is upon the architects of disnlacing their prima facie
liability te recoup him this amount by way of damases, and this burden is
not discharged by suggesting the existence of a collateral remedy against
the contractor of a controversial nature. It follows that the Full Court
wereiright in reversing the judgment of the learned nrimery Judge unon
this item,
2. The Full Court awarded £600 damages against the appellants for
failure in due care to see that the conerste floor was provided with a
ped of rubble filling laid uron the excavated surface of the ground. The
site of the building had been excavated before it was put into the control
of the contractor. The building went much below the ground level and in-
cluded a basement. The floor of the basement was specified as 3 inches J
1 Aa eae remsemessi 2!
of concrete with a layer of bitumen or Seysul asphelte 3/4ths of an inch
thick and a layer of 2 inches of metal topping finished with red oxide.
Under this floor a number cf weeping Brains of porpus pipe were provided
to carxy away soakage. The specificetionsclearly required that where
these Grains were laid beneath the floor they should -be filled over with
rubble. But it appears that the member of tee oor tient firm whe was
resgonsible for the specifications intended todand considered that he
had specified a rubble filling as the bed of the whole flocr of the base-
ment. Expressions occur in the specifications which sugcest that the
drafteman probably intended to specify a rubble bed, but they contain
nothing definitely requiring it, and the plans do not indicate it, elthough
according to some oral testimony, the bill of quantities Ancluées the
necesa@ary rubble. The Full Court were of opinion that the specifications
did + call for a rubble bed. Halse Rogers J. was of opinion that they
failed to do so, and in the arbitration between the reapondent and the
contractor the arbitrators held that they did not require the contrector
to lay @ bed of rubble for the floor.
Upon this question of construction we find ourselves in agreement
with Halse Rogers J. and the Arbitrators. The truth aprears to be that
the draftsman of the snecifications omitted to include-in them, as he
intended to do, an express provision requiring such a bed, but in one or
two other parts cf the specifications employed language upon the assump-
tion that such a provision had in fact been waite, Although a critical
reader of the specifications might suspect or believe that some error had
been made and might reasonably conjecture that the errer consisted of the
omissior of a clause specifying rubble, the references to be found in the
specifications are in our opinion insufficient to supply the omission.
An intenticn te require rubble cannot be spelt out of the documents them—
selves with enouch clearness to call upon a contractor to provide it.
Evidence was directed to the questior whether a rubble bed was in fact a
necessary or desirable part of the design of the basement floor. From
this evidence we gather that it is . proper practice to specify such a
ved for a concrete floor in such circwrstances unless the erchitect is
assured of the suitability and shfficiency of the surface vpon which the
floor would otherwise be laid. It further appears that if rubble is 80
specified, a demp proof course in the floor is often omitted. In the B
wt
present case the excavated surface consisted of clay end sandstone and
there wag much conflicting evidence tren the question of its wetness and
as to the manner in which water would percolate into the porous pipes an
as to other matters affecting its suitability. It is not easy to say what
part of this evidenoe the learned primary Judge thought religable , and
some of it amounted only to speculative arguments from probabilities. But
probably all that can be said is that a wise precaution usually taken to
guard against dangers which cannot be estimated satisfactorily in advance
has been omitted, and that an accurate estimate of these dangers is no
easier when the surface is concealed @#em by the floor itself. It was not
until after the concrete had been put down that the architect discovered
that his intention of having a rubble bed had not been carried out. The
Seysul asphalte had not been laid and the exnense of reotefying the error
was not then so great as it is now. But it was greater than the cost would
originally have been of including rubble. Indeed, the additional cost of
the rubble if put down first would have been only £53. The architect dis~
covered also that a proper rubble filling had not been laid cver-the porous
drains. He at once called vron the contractor to lay rubble under the floor
everywhere, but the contractor disputed that the specifications called for
rubble. He required an arbitration, and proposed that one or other of the
following courses should be adopted: .
(1) that he would prooced to complete the floor, giving a guarantee to
pay assessed damages if in the arbitration the contract should be inter-
preted as calling for a rubble bed;
(ii) that he should, under the architects' direction, cut up the coherete
slab then laid, put in the rubble, and lay the floor complete, the responds
ent agreeing, if the contract should be interpreted against the respondent,
to pey the cest of doing so as an extra.
The architects on behalf of the respondent chose the firat alternetive and
the floor was completed without rubble. The resnondent evbwitted his claim
against the contrector under this arrangement in the
eral arbitration
uron the completion of the work, and, except for the rubble immediately
ever the drains, in respect of which £117 was awarded, the claim failed
because of the interpretation of the specifications adépted by the arbitra-
tors. In the present action against the architects, the apoellante, the
respondent presents his claim to damages upon an alternative. He says that
tee
ttn mameA SEO a RRA ECS
if rubble was not called for by the specifications, the omission arose
from want of jue care in the preparation of the plens end specifications,
and if it was called for by the specifications, the feilure of the con-
tractor to supply it occurred through a want cf due care in sunervision .
Halse Rogers J. in some measure adopted the first alternative. He did
not find that to design such a concrete floor without a rubble bed was
te adopt a negligent form of construction, but he considered that when
the architects had formed an intention of requiring a rubble bed, the
failure so to draw the specifications as te call for it amounted to
negligence. He found, however, that the respondent had suffered no dam-
age, or no demage beyond that allowed for in the aum awarded against
the contractor by the arbitrators. This finding was baséd upon the con-
clusion that in the result a good and sufficient floor had been provic-
ed end that it was netther necessary at present nor likely to become
necessary to take up the floor and put down a rubble bed. The Full Court
alopted the second alternative, and awarded £600 against the appellants?
as the estimated cost of rectifying the defect after deducting £53, the
additional cost of putting in rubble in the first instance. Their Honour s
covsidered that, notwithstanding the finding of the learned primary
Judge, the floor was unsatisfactory; because they were satisfied upon
the evicence that it admitted damp from the subsoil. The evidence uson
the question whether it did in fact admit damp was fully discussed be-
fore us, and we are of opinion that the finding that it did net do so,
which the judgment of Halse Rozers J, clearly implies, oucht not to
have been disturbed. Trere is no reason te suppose that he did not take
into account all the evidence relied unon by the Full Court, including
an experinient to which their Honours attached much weight. Te ourselves
de not find thet experiment so convincing, and we think that Helse Rogers
J., who not only heard end saw the witnesses but viewed te premises,
waa in a better position than en apnellate Court can be to form an
opinion uyon this question of fact. But we think thet there was a -fail-
ure of cue care on the part of the anvellants in preraring the plans «x
and specifications in such a way that rubble was not called for, and in
not discovering earlier by supervision that the contractor was not
putting down a rubble bed. But we are of opinion that on the one hand
the finding of the Full Court that the present condition of the floor
a
RAR Ae Oe RCN NR RAINE EEE EINE SNES SERNA
:
w
called for remedy should not be supoorted, and on the other, .hand the
finding of Halse Rogers J. in favour of its comphete sufficiency goes
too far. We accept his finding to this extent namely that the floor is
apparently good and sound and that there is no praesent reason for taking
it up and ne immediate likelihood of it becoming necessary or desirable
to do so. But the very purpose of requiring rubble is to cive a greater
degree of security against the action of water and possible failures of
the weeping drains adequately to perform their function. The evidence
does not show that all reasonable apprehension unon these matters is
excluded. The resnondent's position is that he has less security than he
ought against possible difficulties which may or may not have tecome
actual. The seourity is not so diminished that a reasonable man would now
set about obtaining it by a costly alteration of the floor. He would do
nothing unless and until the floor actually fails in some way. But at the
same time, can it be said that for this reason a building omer who was
entitled to the exclusion or reduction of this risk ig entitled only to
nominal damages? The situation is,we think, one which calls for the as-—
sessment of damaces for exposure to mischance. Such en assessment must
necessarily be attended with difficult¥ . and be not made as a matter
of calculation but almost as an exercise 6f discretion. On the whole, we
think that the resnondent should receive £100 damazes upon thie item of
negligemce.
3. The Full Court avarded to the resnondent a further sum of £460
ag damases for negligence on the part of the erpellants in the supervision
of the work of rendering the external face of the southern wall in cement.
The damages were calculated as the estimated cost of painting the southern
wall in order to give a protection against weather which the cement ren—
dering had, in the opinion cf the Court, feiled to give completely. An
expert witness of experience called by the respondent upon being asked:
"What sort of a job ig the external rendering in the building?" answered —
"As far as thickness goes, it is slightly under usual, nothing very
"serious; it appears to be a weak mixture roughly put on". The specifica—
tions required a mixture of five parts of sand to two of cement gauged
with toxicement in the proportion of 3 lbs. to one bag cf cement, and they
called for a rendering full 5/8ths of an inch thick. The atatement of
ehhe
accounts and demands put before the erbitrators propared by the architects
contained a olaim for damages for xork not carried cut to the specifica-—
tions in resnect of external rendering. In forwarding this document to
the solicitors for the respondent, the appellants wrote:
"As regards the thickness of cement rendering, we have carefully measurea
gaue at twenty two (22) positions on the various walls, and find that the
thickness varies from 7/16ths" in three (3) places to 3/4ths" in three
(3) places, other measurements being averaged in between these two thick-
nesses. We must point out that from a practical point of view it is ® im-
possible to obtain a uniform thickness throughout , as the bricks them-
selves vary in size. The sketch in the margin will indicate the thickness~
es referred' to herein. We are of opinion that as far as practicable the
specified thickness has been provided, and accordingly we do not advise
any action in this connection",
The arbitrators appear to have considered that the contractor had made
some saving in cement, for upon the claim relating to the external ren-
dering they allowed against hiv the sum of £14. The award was dated 5th
November 1930. In the following March wet weather patches of damp appear-
ed through the southern wall. In July much more water shewed. Possibly
this might have been treeted as a defect to be made cood cut of the re-
tention moneys. But apparently this was not done and the architects have
now been saddled with a liability for the cost of remedying it. Much
evidence vas given in relation to the thickness cf the rendering upon
the wall and as to the probable nature of the mixture. On the whole, the
evidence tended to shew that cwing to unevenness in the surface of the
wall, the thickness of the rendering varied in different places and.»
upon the average was somewdat under the requirement of the specifica—
tions. Some seven samples were taken from the southern wall, and an analy -
sis was. wade of them in the
regate. The result was said to shew a_weak -
er mixture than thet snecified. But evidence was given on tue part of the
appellents that a proper practice was puraued by the plasterer to obtain
the due thickress, and that their clerk of works had irsisted that some
of the work should be done twice. Evidence was also
ce
ven of some guper-
vision and, check cf the mixi
to be
of the cement. Further, the inference
otherwise/drawn from the analysed samples was weakened by an annarent
incongruity between snother analysis, that of the mortar, and the con-
\o
dition and quality of the mortar revealed by inspection. Explanations were
offered of the failure of the wall to exclude the water, Witnesses said
that until a walltwas painted it would not exclude water eltogether in
very heavy driving rain . The specifications had provided for a coating of
lime and oil to make the wall quite water procf, at any rate until painted,
but with the concurrence of the respondent this provision hed bevn excised
iH
to reduce expense, Again, it was said that slight cracks in the wall of
such a building inevitably ocourred at the beams or girders and these 30°
were resyonsible . Upon the whole evidence, Halee Rogers cd. was not satis—
i fied that the architects had been guilty of any n@tigence resultine in we
admission of water. He found definitely that there was ho negligence in
respect of the nature of the mixture. The letter finding the Full Court
felt unable +6 interfere with, but their Herours cénsidered that negli-
gence in supervising the thickness ef the rendering was made out. Although
the simple fact that water did gain admission in substantial quantities
through the wall built uhder the direction of the appellants cannot but
impress us , on the whole of the evidence we think there is no sufficient
round for disturbing the finding of the primary Judge. The matter
'Largely turned unon his opinion of the accuracy of the witnesses, and also
upon the impression which an inspection of the premises produced. The de~
gree to which the average thickness of the rendering fell below that speci -
fied was very difficult to estimate, and in eny case the deficiency could
not be a matter obvious to the most experienced eye. Some failure in the
exercise of thdoare and skill reasonably required must positively appear,
and we do not think that the refusal of Halse Rogers J. to infer it from
the circumstances can be held erroneous. For these reasons we think" the
award of damages ty the Full Court upon this item should be reversed.
i
\, By a cross appeal the respondent etebme complains that the Full
Court should have awarded him damages against the architects in respect
of a deficiency of cement content in the cement mortar. This question de-
pended in the main upon analyses of samples. The finding of the primary
Judge was against the claim, and this was upheld ty the Full Court. fe
think it depended altogether on inferences from evidence which he was in
a much better position to deal with than an appellate Court, and we are
of opinion that his finding should not be disturbed. 2S
5. Lastly, @ similar question is raised by the cross appeal in
Tespect of the cement content of the internal rendering and the conorete
floors. We think the same reasona lead to the failure of this part of the
cross appeal also.
The appeal is allowed.
Tae judgment of the Full Court is discharged. In lieu thereof it
is ordered that the judgment of Halse Rogers J. on the cross action be
eet aside and that in its place judgment be entered for the defendant res—
pondent for the sum of £140. sc
And it is ordered that the respondent, the defendant, pay the plain -
tiffs, the appellants, their costs of the action and cross action, except
the costs of the findings raised by the cross action in respect of the base-,
ment floor and the deficiency of the gauge of lead in the damp course in
the walle; and that the coste of these findings be paid by the plaintiffs
appellants. And that the respondent pay the eee+ appellants their costs
of the appeal to thie Court.
No costs of the appeal to the Full Court from the judgment of
Halse Rogers J.
Costs to be set off.
ay
Related laws
No related documents linked yet.
You've got 21 of 22 free Acts left this visit. Sign up anytime for Facts, Related, and study briefs too.