District Court New South Wales
Medium Neutral Citation: Robust Builders Pty Ltd v Barai & Anor (No.3) [2023] NSWDC 373 Hearing dates: 22-24 August 2023 Date of orders: 24 August 2023 Decision date: 24 August 2023 Jurisdiction: Civil Before: Abadee DCJ Decision: See paragraph 32 Catchwords: CIVIL PROCEDURE – application to adjourn to allow party to prepare further evidence in reply – application opposed – discretionary considerations Legislation Cited: Evidence Act 1995 (NSW) ss 136, 144 Cases Cited: Nil Texts Cited: Nil Category: Procedural rulings Parties: Robust Builders Pty Ltd (plaintiff/cross-defendant) Mr P Barai (defendant/cross-claimant 1) Mrs F Mahjabeen (defendant/cross-claimant 2) Representation: Mr D Lambley (solicitor) for the defendants/cross-claimant Mr R Mehndiratta (as director of and for the plaintiff/cross-defendant) File Number(s): 2018/00259451 Publication restriction: Nil
JUDGMENT
Background 1. The plaintiff applies for an adjournment of this hearing. The purpose of the adjournment is to provide him with the opportunity of preparing evidence in reply to the lay and expert evidence relied upon by the owners. The owners oppose the application. 2. The circumstances surrounding this application are as follows. This proceeding, which features a builders claim against owners and an owners' cross claim for alleged incomplete and effective works relates to a construction contract entered at some point in the latter half of 2016. The proceeding commenced on 23 August 2018 - now over five years ago. The hearing was scheduled to commence in the May 2023 sittings at Parramatta, but that hearing date was vacated on 8 May 2023 and the matter was re-scheduled to commence in the Court's August 2023 sittings. I note that on 8 May 2023, Mr Mehndiratta appeared for the builder. On the same date, the Court made an order granting leave for the owners' building expert, Mr Paul O'Donnell, to give evidence by audio visual link. An early hearing date (apparently in June 2022) was also vacated. 3. The hearing came before me as the Judge presiding over the Parramatta Civil List in its August 2023 sittings of the District Court. There was a callover of this matter, along with other hearings, on 14 August 2023, at which Mr Mehndiratta appeared for the builder. On that day, and on the following day, issues were identified regarding Mr Mehndiratta's authority to act for the plaintiff and an application he wished to raise about calling a person as a witness. No other impediment was identified as to the commencement of the case. 4. I dealt with the two matters raised in that callover. Mr Mehndiratta provided an affidavit of his authority. I dispensed with the requirement that he state his awareness or his potential liability to some or all of the costs ordered against the builder. I also rejected an application by Mr Mehndiratta to call another person to give evidence orally.
We try to embed the page this law was scraped from. If the site blocks framing, you still get the link and a local excerpt.
Last checked with source on —
Checking whether the official page can be embedded…
Plain-English simplify of this law: a short summary, key points, and both sides of the argument. Generated on first view via Replicate, then cached. Vote on what helps your study.
No study brief is cached for this law yet. Sign up to generate a plain-English brief.
Sign up to generate