IPOH GARDEN BERHAD (AUST) PTY LTD v AW EDWARDS PTY LTD [1989] NSWCA 104
NSW Caselaw
Full text
Select any passage to save a personal note with optional tags.
IPOH GARDEN BERHAD (AUST) PTY LTD v AW EDWARDS PTY LTD
SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL
MAHONEY, PRIESTLY and MEAGHER JJA
24 August 1989, 19 October 1989
[1989] NSWCA 104
BUILDING CONTRACT — CONSTRUCTION OF CL405(h) OF AUSTRALIAN
STANDARD METHOD OF MEASUREMENT OF BUILDING WORKS —
"ALLOWANCE FOR WORKING SPACE"
Mahoney JA This appeal concerns the payment to be made the respondent
builder in respect of the construction of a pedestrian tunnel from the Queen
Victoria Building to the Grace Bros Department Store. It concerns, in particular,
the payment to be made for excavation of pits for footings. Under the contract the
payment to be made in respect of each cubic metre of excavation was specified
and, subject to adjustments permitted by the contract, the quantity of the
excavation was also specified. In the present case, the cubic metres to be
excavated in respect of the matters here in question were specified as 98 cubic
metres and 83 cubic metres.
However, it is agreed that payment is to be made in addition to this. The work
to be done fell literally within the terms of CL405(h) of the Australian Standard
Method of Measurement of Building Works, authorised by agreement between
The Australian Institute of Quantity Surveyors and The Master Builders'
Federation of Australia. (The court has been referred to the fourth edition of that
Standard, January 1980).
The appeal has proceeded upon the basis that the amount to be paid to the
builder for such excavation is to be increased by adding to the quantity to be
excavated as provided in the contract an amount, at the contract rate, for an
additional space calculated in accordance with CL405(h) of the ASMM.
It is agreed that CL405(h) applies because the work in question required
formwork exceeding one metre high and because the work required workmen to
operate from the outside, within the terms of that clause.
The only question to be determined on this appeal is whether the extra quantity
for which payment is to be made is to be calculated in accordance with par (ii)
or par (iii) of CL4.05(h).
The facts have been detailed in the judgment of Meagher JA which I have had
the advantage of reading. I agree with his Honour's analysis of the relevant
documents.
In particular, I agree with his Honour's construction of CL405(h). That
paragraph provides for "allowances for working space". The allowance is, as the
clause indicates, hypothetical. But, being an allowance for working space, it
would be expected that, as CL(ii) allows for working space of 0.60 metres and
CL(iii) allows for one metre, the allowance for working space where both are
satisfied is to be the greater of the two, viz, one metre.
However, Mr Staff QC, for the proprietor, submitted that this construction
should not be adopted. For this submission, he relied upon the meaning of
"work" and the provisions of CL408(b).
2 UNREPORTED JUDGMENTS
I do not think that CL408(b) requires a different construction of CL405(h).
CL408(b) deals with the position where "basement or similar walls" are in
question. The present work is not such. It may be that where basement or similar
walls are in question, it will be necessary to consider the application of the
general provisions for allowance of working space contained in CL405(h). That
question does not arise in this appeal.
Mr Staff suggested that the learned judge, in adopting the construction to
which Meagher JA has referred, misconstrued the word "work". Upon the
assumptions on which this appeal has proceeded, I do not think that that
submission should be accepted. At least, there is no reason why the ordinary
construction of CL405(h) should not be adopted in this case.
I agree with the orders proposed by Meagher JA.
Priestley JA For the reasons given by both Mahoney JA and Meagher JA I
agree with the orders proposed by Meagher JA.
Meagher JA This is an appeal by Ipoh Garden Berhad (Aust) Pty Ltd
concerning the construction of a written agreement dated 14 June 1985 whereby
it as proprietor engaged the respondent AW Edwards Pty Ltd to construct a
pedestrian tunnel complete with shops from the Queen Victoria Building to the
Grace Bros Department Store passing beneath the intersection of George and
Market Streets Sydney.
The excavations required by that agreement included those for ten pad footings
on which were to be built reinforced concrete columns supporting the overlying
roads. The case concerned the correct allowances to be made for working space
in constructing those pad footings and columns.
The specified Bill of Quantities (which fulfilled the function of both a
Specification and a Bill of Quantities), which formed the basis for the respondent
builder's pricing for the work for which he was to be paid, was drawn up
pursuant to the General Conditions of Contract. CL1019 of those General
Conditions required that where any "item of quantity" was omitted from the
Specified Bill of Quantities which should have been included in it an amount
designed to reflect the extra work involved should be added to the Contract Sum.
That additional work was, it was agreed by both parties, to be quantified and
valued by reference to the Australian Standard Method of Measurement of
Building Works.
Items c/36 and c/37 of the Specified Bill of Quantities provided: "C/36
Excavating pits exceeding 1m sq on plan down to existing railway tunnel roof for
pad footings; exceeding 7m but not exceeding 8m total depth. (No 5) (SB) m3 98
C/37 Ditto; exceeding 8m but not exceeding 9m total depth. (No 5) (SB) m3 83"
It was common ground that neither of those items made any allowance for
working space and such an allowance should have been made. One had therefore
to turn to the Standard to see what that allowance was.
CL405(h) of the Standard provided:
"Allowances for working space (which shall not be subject to adjustment if
more or less space is actually required) shall be made in the measurements of
excavations as follows:
i. 0.15 metre from the face of any work which requires formwork not
exceeding | metre high;
ii. 0.60 metre from the face of any work which requires formwork exceeding
1 metre high;
URSOH GARDEN BERHAD (AUST) PTY LTD v AW EDWARDS PTY LTD (Meagher JA) 3
iii. 1 metre from the face of any work to be covered externally with a
damp-proof covering which is not described as executed overhand or from the
external face of any work which requires workmen to operate from the outside."
The appellant proprietor contended, both below and in this Court, that the
allowance should be computed in accordance with sub-paragraph (ii) and the
respondent builder contended that it should be computed in accordance with
sub-paragraph (iii). In the former case the allowance should be $30,526.14; in the
latter case it should be $138,700.96. On this issue Smart J found for the
respondent builder, and it is this finding which was reagitated before this Court
on appeal.
However, the bulk of the hearing at first instance concerned another question,
viz the purely factual issue whether the work defined in the contract required
workmen to operate "from the outside" within the meaning of the second leg of
sub-paragraph (iii). This issue was also decided by his Honour in favour of the
respondent builder, the issue being decided in the affirmative. There was ample
evidence for his Honour so to decide and the correctness of his Honour's finding
in this regard was not challenged on appeal.
Therefore, the sole question with which this appeal is concerned is the proper
construction of 4.05(h) the Standard.
Mr Staff QC, leading counsel for the appellant proprietor, in a powerful
submission argued that the Court should hold that each of the sub-paragraphs (i)
(ii) and (iii) were meant to be independent of the others, and further that
sub-paragraphs (i) and (ii) between them constitute a code covering all situations
in which formwork is required. In effect this means that the word "other" has to
be used before the word "work" whenever it appears in sub-paragraph (iii).
In my view these arguments should be rejected and Smart J's decision on the
point is correct. The whole clause should be construed according to the ordinary
meaning of the language used; and whilst it is clear from the terms of that
language that sub-paragraph (i) and (ii) are mutually exclusive, there is no reason
why either of those paragraphs may not overlap with sub-paragraph (iii). The fact
that the appellant's argument necessitates the interpelation of extra words into
sub-paragraph (iii) of itself demonstrates the inappropriateness of the argument.
As Mr Walker, for the respondent builder, pointed out, if the situations
involved in either sub-paragraph (i) or sub-paragraph (ii) also involve the
application of sub-paragraph (iii), the result is that allowances of 0.15 metres (or
0.60 metres) should be allowed for working space as well as 1 metre. This would
not involve cumulative allowances, because each allowance is measured from the
same point, viz "the face of the work", the greater including the lesser.
Thus, the ordinary canons of construction yield the result that sub-paragraph
(iii) will always apply (inter alia) whenever there is a "work" which "requires
workmen to operate from the outside". Moreover, the purpose of the clause yields
the same result. His Honour found as a fact that, as a matter of ordinary
engineering and quantity surveying expression in the industry, it would be
unreasonable and inappropriate to restrict working space to less than 1 metre, and
the Standard, whilst dealing with conventional and not actual situations, should
not be construed as dictating a merely arbitrary conclusion.
For these reasons I am of the opinion that the appeal should be dismissed with
costs.
Counsel for the Appellant: DA Staff QC and A Lakeman
4 UNREPORTED JUDGMENTS
Solicitors for the Appellant: Clayton Utz
Counsel for the Respondent: BW Walker and P Larkin
Solicitors for the Respondent: Wesygarth Baldwick
Related laws
No related documents linked yet.
You've got 21 of 22 free Acts left this visit. Sign up anytime for Facts, Related, and study briefs too.