Select any passage to save a personal note with optional tags.
WOODWARD PTY LTD v KELLEHER
SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL
GLEESON CJ, SAMUELS and PRIESTLEY JJA
20 April 1989, 30 May 1989
[1989] NSWCA 82
JURISDICTION OF DISTRICT COURT — action and cross-claim removed by
consent from Supreme Court to District Court proceedings litigated to completion in
District Court without any question as to jurisdiction being raised — attempt to raise
jurisdiction issue on appeal — HELD: the District Court being a Court whose
jurisdiction can be enlarged by the consent of the parties, a party can waive his right
to call the jurisdiction in question, and such waiver had occurred in the present case.
Eyres v Butt [1986] 2 Qd R 243 followed,
Farquharson v Morgan [1894] 1 QB 552;
Secretary of State for Defence v Warn [1970] AC 394;
Essex Incorporated Congregational Church Union v Essex County Council
[1863] AC 808;
Honnery v Smith 57 SR NSW 598 distinguished
Heron v Newell (Master Allen, unreported 28 June 1977) considered.
WAIVER - circumstances in which a party may waive a right to object to jurisdiction
considered. DAMAGES - proprietor's claim for damages for breach of a building contract
- work of rectification not done on date of hearing - no unreasonable delay on part of
proprietor. HELD: in the circumstances it was open to the trial judge to assess costs of
rectification as at date of trial - Radford v De Froberville [1977] 1 WLR 1262 followed.
BUILDERS LICENSING ACT 1971 - failure to comply resulting in builders inability
to sue for unpaid balance of amount due under building contract - HELD: In applying the
principles established by Bellgrove v Eldridge 90 CLR 613 as to measure of proprietor's
damages, the unpaid balance due under the building contract should be deducted from the
costs of rectification. Pavey and Matthews Pty Limited v Paul (1987) 61 ALJR 151
applied. Builders Licensing Act 1971 District Court Act 1973
Gleeson CJ This is an appeal from a decision of his Honour Judge Mahoney
in the District Court in relation to a building dispute. The issues raised on appeal
are considerably narrower than those which were litigated at first-instance, and
for that reason it is unnecessary to go into the full details of the original disputes
between the parties. It suffices to say that the appellants are a company which
carried out certain building work at a residential property near Tamworth and the
principal of that company. The respondents are the company which owns the
property and the principal of that company, who engaged the services of the
builders. The appellants propounded a claim for what was alleged to be the
unpaid balance due under the relevant building contract. During the course of the
hearing, and after argument, his Honour non-suited the appellants by reason of
the provisions of s13I of the Builders Licensing Act 1971, the work having been
carried out in contravention of s9 of that Act. The respondents propounded
cross-claims against the appellants, in damages and tort, on the basis of
deficiencies and defects in the building work. His Honour found in favour of the
respondents on the cross-claims and entered a verdict and judgment in favour of
both cross-claimants in the sum of $78,455.20 plus costs. For the purposes of this
appeal it is unnecessary to go into the detail of the relationship between the
2 UNREPORTED JUDGMENTS
cross-claims or to consider how it came about that there was a judgment in an
identical amount given in favour or both cross-claimants. Those matters are not
the subject of the appeal. For purposes of presentation and argument of the appeal
the matter has been treated in substance as though it were a dispute between a
builder and a proprietor in which the builder was non-suited in respect of his
claim for the unpaid portion of the contract price of the work and the proprietor
succeeded in his cross-claim for damages for deficiencies and defects in the
work.
There were three issues argued in the appeal, and it is convenient to deal with
them separately.
1. JURISDICTION
The appellants contended, for reasons that will appear below, that the verdict
and judgment entered in favour of the cross-claimants was "ultra vires and of no
force or effect." This claim was based upon a contention that, by reason of the
relevant provisions of the District Court Act 1973, and in the events that
occurred, the cross-claims, and indeed the entire proceedings (including the
appellants' own claim) were beyond the jurisdiction of the District Court. It was
submitted on behalf of the respondents, correctly in my view, that such an
argument could not properly be made the subject of an appeal, and should be the
subject of a challenge to jurisdiction by way of an application either for
declaratory relief or for an order in the nature of prohibition or certiorari (City
Finance Co Limited v Mathew Harvey and Co Limited 14 SR NSW 438, 21 CLR
55). Thereupon senior counsel for the appellants sought leave to file in Court,
returnable instanter, a summons seeking a declaration "that the verdict and
judgment of his Honour Judge Mahoney in the action numbered 139 of 1984 in
the District Court for an amount of $78,455.20 plus costs is ultra vires and of no
force or effect." The Court reserved its decision on that application, but heard full
argument both on the procedural and substantive issues. I am of the opinion that
leave to file the summons as requested should be granted although, as will appear,
I am also of the opinion that the summons should be dismissed.
In order to understand the jurisdictional point that is taken it is necessary to
refer to the relevant provisions of the District Court Act 1973 and to the
somewhat complicated history of the matter.
The District Court is a Court of limited statutory jurisdiction in the sense that
the jurisdiction of the Court to hear and determine civil claims is, subject to one
important qualification, limited by reference to the quantum of the claim being
propounded. The actual limits, expressed in money terms, have varied from time
to time. The present limitations are contained in s44 of the Act which is in the
following terms:
"44. (1) Subject to this act, the Court shall have jurisdiction to hear and dispose
of
(a) any personal action at law where the amount claimed does not exceed
$100,000, whether on a balance of account or after an admitted set-off or
otherwise; or
(aa) any action to recover goods that have been detained, or to recover the
assessed value of such goods, where the value of the goods together with the
amount of any consequential damages claimed for the detention of the goods
does not exceed $100,000; or
URJ WOODWARD PTY LTD v KELLEHER (Gleeson CJ) 3
(b) any action brought to recover an amount not exceeding $10,000, which is
the whole or part of the unliquidated balance of a partnership account, or the
amount or part of the amount of the distributive share under an intestacy or of a
legacy under a will.
(2) Where the amount claimed in an action includes interest (being interest
which the Court could, under s83A(1), order to be included in the amount for
which it could give judgment), that interest shall be disregarded for the purposes
of
(a) determining whether the maximum amount for which the action is
authorised by this Act to be brought has been exceeded or not; and
(b) determining whether or not the Court has jurisdiction to hear and dispose
of the action.
(3) Where -
(a) an amendment to subs(1) which is enacted after, or was enacted before the
commencement of Schedule 3 to the District Court (Procedure) Amendment Act,
1984, has or had the effect of increasing the amount specified in paragraph (a) or
(aa) of that subsection; (b) an action in which an amount of money is claimed is
pending at the time when the amendment has effect or, as the case may be, an
action in which an amount of money is claimed was pending at the time when the
amendment had effect and has not been finally determined, the Court may, on the
application of the claimant, make an order altering the amount specified in the
claim to an amount not exceeding that specified in paragraph (a) or (aa) of that
subsection, as in force immediately after the amendment has or had effect."
Prior to 1 April 1983 the relevant money sum was $20,000. It was increased
from $20,000 to $100,000 on that date.
The important qualification earlier referred to arises by reason of the
provisions of s51 of the District Court Act 1973 which, at all times material to
this appeal, were in the following terms:
"51. (1) In this section "memorandum of consent" in relation to an action or
cross-claim means a document signed by each party to the action or cross-claim,
or his solicitor, in which it is stated that each of those parties consents to the
action or cross-claim being tried in the Court and is aware that, unless the
document is filed, the Court will not have jurisdiction to dispose of the action or
cross-claim.
(2) Where, but for this subsection, the Court would not have jurisdiction to
hear and dispose of an action or cross-claim by reason only of the fact that the
amount claimed exceeds $100,000, the Court shall have jurisdiction to hear and
dispose of that action or cross- claim if a party to the action or cross-claim files
a memorandum of consent in respect of the action or cross-claim.
(3) This section does not apply in relation to an action referred to in s44(1)(b)."
It is to be noted that, as a consequence of the provisions of s51, the District
Court is not a Court whose jurisdiction is the subject of intractable limitations
which are incapable of being expanded by the consent of the parties. On the
contrary, the jurisdiction of the Court can be affected by the consent of the parties
to proceedings before the Court. That circumstance serves immediately to
distinguish the present case from cases, including cases concerning the District
Court under legislation prior to 1973, relating to tribunals of strictly and
unalterably limited jurisdiction. In cases of the lastmentioned kind it is correct to
say that jurisdiction cannot be conferred by consent. The corollary of that
proposition, where it applies, is that a party cannot, by acquiescence or estoppel,
find himself in a position in which he is unable to assert want of jurisdiction (cf
4 UNREPORTED JUDGMENTS
Farquharson v Morgan [1894] 1 QB 552; Secretary of State for Defence v Warn
[1970] AC 394; Essex Incorporated Congregational Church Union v Essex
County Council [1863] AC 808; Honnery v Smith 57 SR NSW 598). By contrast,
the District Court, under the District Court Act 1973, is a Court upon which in
certain respects jurisdiction can be conferred by consent.
It should also be noted that the District Court Rules lay down a procedure by
which a party may challenge the jurisdiction of the Court, and such a challenge
has to be made within a certain time after commencement of the proceedings
(District Court Rules Pt 10 13).
$143 of the District Court Act 1973 provides:
"143. (1) Where the Supreme Court is of opinion that any proceedings that are
pending in the Supreme Court could properly have been commenced as an action
in the Court, the Supreme Court may, if it thinks fit, on the application of any
party or of its own motion, order that those proceedings be transferred to the
Court sitting at such proclaimed place as the Supreme Court thinks fit. (2) Where
the Supreme Court is of opinion that any proceedings that are pending in the
Supreme Court could properly have been commenced as proceedings under
Subdivision 2 of Division 8 in the Court, the Supreme Court may, if it thinks fit,
on the application of any party or of its own motion, order that those proceedings
be transferred to the Court sitting at such proclaimed place as the Supreme Court
thinks fit."
It is to be observed that the power to make an order under s143 depends, not
upon the existence of a certain state of affairs, but upon the holding by a Supreme
Court Judge of an opinion as to the existence of such a state of affairs. No doubt
an opinion formed pursuant to s143 may be shown, on an appeal against the
making of an order, to be erroneous. However, an order made under s143 is an
order of the Supreme Court and as such stands unless and until it is set aside on
appeal. (cf Peacock v Bell and Kendal (1667) 1 Wms Saund 73 at 73-5, 85 ER
84 at 84-8; Re Ross-Jones ex parte Green (1985) 59 ALJR 132 at 141)
In an unreported decision in 1977 (Heron v Newell 28 June 1977) Master
Allen, in dealing with an application made to him under s143, held that, upon its
true construction, the words "where any proceedings...could have been
commenced as an action in the (District) Court..." related to the time at which the
Supreme Court proceedings in question were in fact commenced and that,
therefore, the test to be applied at the time of an application under s143 was
whether, having regard to the jurisdictional limits of the District Court as they
stood at the time of the commencement of the Supreme Court proceedings, those
proceedings could have been commenced in the District Court.
That is the background against which the following events fall to be
considered.
The proceedings were commenced in the Supreme Court by the appellants in
April 1981. At that time the amount referred to in s44 of the District Court Act
1973 was $20,000. The claim propounded by the appellants was for $21,491.27
plus interest. As was noted above, on | April 1983 the amount referred to in s44
of the District Court Act was increased to $100,000. On 27 January 1983 the
respondents filed a defence and cross-claim. It is of some importance to observe
that the amount claimed in the cross-claim was not then, and has not since, been
specified. From time to time various particulars of individual items included,
either cumulatively or in the alternative, in the cross-claim, have been provided.
By far the largest element in the cross-claim was a claim for damages in the form
of the estimated costs of carrying out certain rectification work in respect of the
URJ WOODWARD PTY LTD v KELLEHER (Gleeson CJ) 5
relevant building, but that rectification work has not yet been carried out, and, as
will appear in relation to the second issue the subject of the present appeal, his
Honour gave judgment on the basis of an estimate of costs as at the date of the
hearing. If the cross-claim had been brought originally in the District Court the
failure to specify an amount claimed would have constituted an irregularity (see
District Court Rules Pt 20). The District Court Rules require a party propounding
a claim to specify the amount of the claim. This requirement is related to the
scheme of the District Court Act concerning the monetary limits on the Court's
jurisdiction.
On 10 August 1984 by the consent of all parties an order of the Supreme Court
was made transferring the proceedings (that is, the claim and the cross-claim) to
the District Court. No point was taken by either party at that stage, or at any later
stage of the proceedings in the District Court, either as to the circumstance that
the appellants' claim exceeded the amount of $20,000, which, at the date of the
commencement of the Supreme Court proceedings (although not at the date of
the making of the order for transfer), was the sum which appeared in s44 of the
District Court Act, or as to the circumstance that the cross-claim did not specify
the amount of the claim and that it was therefore impossible, by looking at it, to
tell one way or the other whether the claim fell within the prima facie monetary
limits of the District Court's jurisdiction. Furthermore, neither party filed any
notice of objection to jurisdiction in accordance with the District Court Rules
and, of course, any such notice would have been inconsistent with the original
consent to transfer of the proceedings.
Both parties thereafter proceeded to litigate the matter in the District Court as
though the only relevant limit on the Court's jurisdiction was the amount of
$100,000. That the parties assumed that the jurisdiction was, in the events that
occurred, limited, but that the limit was $100,000, is evident from their conduct
at a stage prior to the final hearing when the respondents gave further and better
particulars of the financial details of their cross-claim. There was an exchange of
correspondence between the solicitors of the parties which makes it clear that
both sides were proceeding on the basis just mentioned, and this was expressly
stated by counsel in the course of certain interlocutory proceedings before his
Honour Judge Flannery. The action and cross-claim in due course came on for
hearing. The first hearing had to be aborted when, after it had been going for
some days, the presiding judge resigned from office. Subsequently there was a
lengthy hearing before Judge Mahoney, the outcome of which has already been
stated.
Having been unsuccessful at the hearing, the appellants appealed to this Court
and then, for the first time, called in question the jurisdiction of the District Court.
The history recited above makes it clear that, if it is legally possible for the
appellants by their conduct to have become disentitled to take the jurisdictional
point, they should be treated as having put themselves in that position.
In Eyres v Butt [1986] 2 Qd R 243 the Full Court of the Supreme Court of
Queensland dealt with a case that raised a similar, although not identical, issue.
The District Court Act 1967 of Queensland contains, in s73, a provision to the
same effect as s51 of the New South Wales legislation. In that case the parties to
an action in the District Court agreed to an enlargement of jurisdiction but never
signed the necessary memorandum of consent. In due course judgment was given
for an amount which was beyond what I have called the prima facie jurisdiction.
The appellants contended that the judgment was beyond jurisdiction and relied
upon the principle stated in Spencer Bower and Turner, "Estoppel by
6 UNREPORTED JUDGMENTS
Representation", 3rd Ed at 144 in the following terms: "Not even the plainest and
most express contract or consent of a party to litigation can confer jurisdiction on
any person not already vested with it by the law of the land, or add to the
jurisdiction lawfully exercised by any judicial tribunal; it is equally plain that the
same results cannot be achieved by conduct or acquiescence by the parties. Any
such attempt to create or enlarge jurisdiction is in fact the appointment of a
judicial officer by a subject, and as such constitutes a manifest usurpation of the
Royal prerogative."
Connolly J distinguished that principle, and the cases which support it, on the
basis that, by reason of the provisions of s73 the District Court was not a Court
of fixed jurisdiction. His Honour said:([1982] 2 Qd R 243 at 250) "To say in a
case such as this that jurisdiction cannot be conferred by consent is apt to confuse
the nature of the problem. Enlarged jurisdiction can indeed by conferred by
consent because the statute so provides. The true question here is whether the
parties having consented in fact and the learned trial judge having approved their
consent, and the action having thereafter been tried to judgment on the footing of
that consent the appellants are not estopped by their conduct from denying that
s73 was strictly complied with."
His Honour went on to hold that there was an estoppel, the case being one
where the effect of the estoppel was not to extend the jurisdiction beyond the
legislative boundaries (bearing in mind s73) and where the representation was set
up merely as a remedy for an irregularity in procedure. De Jersey J agreed. The
judgment of Thomas J was to like effect, although it involved a somewhat
different (but not inconsistent) process of reasoning.
Connolly J referred to the case as one in which the appellant was to "be
allowed to waive the defect, or to be estopped by conduct from setting it up",
although his ultimate resolution of the issue was couched in terms of estoppel
rather than waiver.
In the present case there is some difficulty in identifying a specific
representation of a kind which would found an estoppel. There would have been
a problem in invoking s51 as the direct solution to the problem if the point had
been raised because s51(2) does not precisely fit the case. The lack of jurisdiction
arose not because the amount of the claim or cross-claim exceeded $100,000, but
because (assuming the correctness of Heron v Newell) it exceeded $20,000.
Whether the matter could have been dealt with under s44(3) is far from clear,
because the amendments which increased the prima facie jurisdiction to
$100,000 were made before the action became one which was pending in the
District Court. One thing, however, is quite plain. If any problem had been raised
prior to the hearing before Mahoney DCJ it could have been overcome simply by
the filing of fresh originating process. That course would undoubtedly have been
available if an objection to jurisdiction had been taken by the appellant within the
time limited by the District Court Rules. By the time the point was ultimately
raised, however, all the expense of the proceedings had been incurred and,
moreover, the cross-claim was probably statute-barred.
The consent of the appellants to the transfer of the claim and cross-claim to the
District Court, their failure to object to jurisdiction in the manner and within the
time limited by the District Court Rules, or at all, and their participation in the
proceedings right through to final judgment on the express basis that the Court
had jurisdiction to deal with the matters before it all occurred in a situation where
the jurisdiction of the Court, although prima facie limited, could be enlarged by
consent and where, if the point had been taken, the problem could easily have
URJ WOODWARD PTY LTD v KELLEHER (Gleeson CJ) 7
been solved. When Mahoney DCJ came to try the claim and cross-claim and to
give judgment on the cross-claim even the prima facie jurisdiction of the Court
comprehended the amounts claimed and the amount for which he ultimately gave
judgment. If, as was argued in this Court by the appellants, the steps which had
previously been taken were inadequate to secure the result that could otherwise
have been achieved, and that was intended by all parties, that is to say, that the
Court should have jurisdiction up to $100,000 then that, in my view, is properly
to be treated as an irregularity which the appellants have waived. (London
Chatham and Dover Rail Co v South Eastern Rail Co (1888) 40 Ch D 100; Lloyd
v Great Western Dairies [1907] 2 KB 727; Eyres v Butt (supra)).
It thus becomes unnecessary to examine the validity of the premise upon
which the entire argument for the appellants is based, that is to say, the
correctness of Heron v Newell. It is a decision on an important matter of practice
which has stood for twelve years. It turned upon a point of construction which,
it might be thought, could easily have gone the other way. If one is considering
the meaning of the words "could properly have been commenced" in relation to
an action which is about to be transferred from the Supreme Court to the District
Court it is difficult to see why the legislature would have intended to direct
attention to the jurisdiction of the District Court, not at the time the action is
transferred to it, but at the time when the action was commenced in the Supreme
Court. One would have thought that the logical question to ask would be: "Does
the District Court now have jurisdiction to deal with this matter?" However, the
question posed by the section as construed in Heron v Newell is: "Did the District
Court (at some otherwise irrelevant past time) have jurisdiction to deal with this
matter?" The words "could properly have been commenced" are wide enough to
cover any time up to the date of transfer, and I am, with respect, far from
convinced of the correctness of Heron v Newell. However, as it is not necessary
to decide the point in this appeal I express no concluded view on the matter.
2. TIME FOR ASSESSING COSTS OF RECTIFICATION The appellants'
second complaint is that the learned trial judge, in assessing damages in respect
of the cross-claim, based his award on estimates of the cost of carrying out the
work of rectifying defects and remedying deficiencies in the building as at the
date of the trial.
In my view his Honour's reasons for judgment disclose no error of principle.
The work in question still has not been carried out. There was no unreasonable
delay on the part of the proprietor either in failing to have the work done prior
to the date of the hearing or in prosecuting the cross-claim. Where there is a
complaint of breach of a building contract and the proper measure of damages is
the cost of reinstatement, and where the defects have in fact been put right, the
cost is to be assessed as at the time of the rectification work, provided there has
been no unreasonable delay (East Ham Corporation v Bernard Sunley and Sons
Ltd [1966] AC 406; Johnson v Perez (1988) 63 ALJR 51 at 52, 57, 60). Where
at the date of the trial the defects have not yet been put right, then the essential
question becomes one of fact as to the time in which, acting reasonably, the
proprietor should have carried out the rectification work. If the proprietor has
behaved reasonably, both in prosecuting his claim for damages and in delaying
the carrying out of the work, then there is normally no reason why damages
should not be assessed as at the date of the trial.
8 UNREPORTED JUDGMENTS
The judgment of Oliver J in Radford v De Froberville [1977] 1 WLR 1262 at
1287 makes it clear that in the ultimate analysis the question that arises in a case
such as the present turns upon the reasonableness of the plaintiffs' actions or
inaction. His Lordship said:
"once proceedings have been commenced and are defended, I do not think
that the defendant can complain that it is unreasonable for the plaintiff to delay
carrying out the work for himself before the damages have been assessed, more
particularly where his right to any damages at all is being contested, for he may
never recoup the cost. If, therefore, the proceedings are conducted with due
expedition, there seems to me to be no injustice if by reason of the time that it
takes for them to come to trial, the result of inflation is to increase the pecuniary
amount of the defendant's ultimate liability."
I consider that, in the circumstances of this case, it was perfectly proper for
Mahoney DCJ to assess damages by reference to building costs which were
current at the date of the trial.
3. DEDUCTION OF UNPAID BALANCE OF CONTRACT PRICE
The final question argued on this appeal arose in the following manner. The
respondents' cross-claim for damages for the builder's various breaches of
contract was based substantially upon the estimated cost of carrying out the work
necessary to repair the defects and remedy the deficiencies in the work performed
by the builder. In Bellgrove v Eldridge 90 CLR 613 the High Court laid down the
measure of damage to be applied in an action for damages for breach of contract
brought by a building owner against a builder where the builder had departed
substantially from the specifications with the result that the foundations were
defective and the building was unstable. The Court held that the measure of
damage was the cost, in excess of any amount of the contract price unpaid, of
reasonable and necessary work to make the building conform to the contract plus
consequential losses, if any. It is to be noted that the issue in Bellgrove was not
as to the deduction of the unpaid balance of the contract price but as to whether
a quite different basis of calculating damages was appropriate. In the present
case, the trial judge non-suited the plaintiffs and held that the unpaid balance of
contract price (which was agreed in this Court to amount to $11,652) could not
be recovered by reason of the provisions of s13I of the Builders Licensing Act
1971. The question is whether the plaintiffs are nevertheless entitled to have that
amount deducted in calculating the damages on the cross-claim. The learned
judge answered that question in the negative. It is common ground that if his
decision on that point is reversed then the damages should be reduced by
$11,652.
In Bellgrove the High Court cited with approval the following statement in
Hudson on Building Contracts 7th Ed (1946) at 343:
"The measure of the damages recoverable by the building owner for the breach
of a building contract is, it is submitted, the difference between the contract price
of the work or building contracted for and the cost of making the work or
building conform to the contract, with the addition, in most cases, of the amount
of profits or earnings lost by the breach."
The corollary of that proposition was stated in H Dakin and Company Limited
v Lee [1916] 1 KB 566. In that case the matter was considered from the point of
view of the builder, who had performed work which was defective, but not so
defective as to produce the result that he could not recover anything for his
services. He was held to be entitled to recover the unpaid balance of the contract
price, less the cost of rectifying the defects.
URJ WOODWARD PTY LTD v KELLEHER (Gleeson CJ) 9
In many cases, perhaps most, cases of a claim for damages for breach of a
building contract made by a proprietor against a builder on the basis of defective
work, there will be no doubt that the unpaid balance of any contract price is
recoverable by the builder from the proprietor subject always, of course, to the
possibility that it might be exceeded by the proprietor's claim for damages.
Whether or not it is technically accurate to describe what is involved as a set-off,
there is no conceptual difficulty involved in such a case in deducting the unpaid
balance of the contract price from the cost of rectification and consequential
damages. There may, however, be, for a number of possible reasons, cases in
which the unpaid balance of the contract price could not be recovered in an action
brought by the builder. For example, the contract may have been repudiated by
the builder. The building work may be so radically defective as to disentitle the
builder to sue. The building contract may, for one reason or another, be void. Or,
as in the present case, the building contract may be unenforceable at the suit of
the builder.
The ultimate object of the rule as to damages earlier quoted is simply to apply
to the particular case of a building contract the general principle of measurement
of damages for breach of contract established in Hadley v Baxendale (1854) 9 EX
341 which is that the injured party is entitled to be indemnified against any loss
likely to arise in the usual course of things from the breach, and also such other
loss as was in the contemplation of the parties at the time of the contract as the
likely result of the breach of it. Where a builder contracts to construct a building
of a certain kind and to a certain standard of workmanship, and fails to do so,
prima facie the loss sustained by the proprietor is the difference between what it
will cost him to have the promised work carried out by somebody else and the
price he agreed to pay to have it done by the builder in question. If, for some
reason or other, the builder could not have enforced the contract against the
proprietor, that does not mean that the proprietor was entitled to have the building
erected for nothing.
S131 of the Builders Licensing Act 1971 provides as follows:
"131 (1) A person who carries out any building work in contravention of s9(1)
or (2) or 13A(1) or (2) is not entitled to damages or any other remedy in respect
of a breach of any contract for the carrying out of the work committed by another
party to the contract but is liable for damages or any other remedy in respect of
a breach of any-such contract committed by him.
(2) Nothing in subs(1) affects the liability of a person for an offence under s9
or 13A. As the decision of the High Court in Pavey and Matthews Pty Limited
v Paul (1987) 61 ALJR 151 demonstrates, contravention of the Act produces only
the specific and limited consequence referred to in the relevant provisions. The
builder may still sue on a quantum meruit. He may retain any instalments paid
on account of the purchase price. And, of course, the contract may be enforced
by the proprietor. If the builder fails to perform his contractual obligations in
some respect there seems to be no reason in principle or logic why the
proprietor's damages should be measured on the basis of the hypothesis that the
proprietor was entitled to have the work performed, under the contract, but at no
cost to himself. The considerations as to unjust enrichment underlying the High
Court's decision in Pavey and Matthews Pty Limited v Paul point in the same
direction.
In some respects the case of Mertens v Home Freeholds Company [1921] 2
KB 526 is the converse of the present case, and makes the point contended for
by the appellants. That was a case in which the defendant builder entered into a
10 UNREPORTED JUDGMENTS
contract to build a house for the plaintiff for a fixed sum. Some months after the
contract was entered into wartime regulations were promulgated making it
unlawful to commence or carry on building or construction work without the
licence of the Minister of Munitions. The defendant applied for a licence to
proceed but then so conducted himself as to procure, deliberately, the result that
a licence would not issue. The Minister of Munitions refused to grant the licence,
and the proprietor sued the builder for damages for breach of contract. The Court
of Appeal held that the defendant could not take advantage of the failure to issue
the licence, which was brought about by his own act, and that the proper measure
of damages was what it cost the plaintiff to complete the house substantially as
it was originally intended and in a reasonable manner when he was ultimately
allowed to proceed with the work, less any amount that would have been due and
payable to the defendant by the plaintiff had the defendant completed the house
in accordance with the terms of the original contract. The Court of Appeal
approved and applied a statement of principle as to the measure of damages
which had appeared in an earlier edition of Hudson on Building Contracts than
that cited above to sue to like effect.
The appellants were, in my view, entitled to the deduction from the damages
awarded on the cross-claim of the sum of $11,652.
The appeal should be allowed in part. The verdict and judgment on the
cross-claims should be varied by substituting $66,803.20 the judgment to date
from the same date as that pronounced below. The appellants should pay the
respondents' costs of the action. The appellants should pay half the respondents'
costs of this appeal.
Counsel for the Appellant: V Bruce QC and R Cameron
Solicitors for the Appellant: Patterson Byfields and Bryan, Tamworth, City
Agents: Dibbs Crowther and Osborne
Counsel for the Respondent: J Spigelman QC and G Underwood
Solicitors for the Respondent: Sly and Russell