Select any passage to save a personal note with optional tags.
CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD
SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL
KIRBY P; MAHONEY and CLARKE JJA
3 and 4 April 1991, 7 August 1991
[1991] NSWCA 68
CONTRACT — financier promises "full funding to property developer — whether
binding contract — held: In the circumstances, there was. The Coal Cliff Collieries
Pty Ltd v Sijehama Pty Ltd, CA, unrptd, 5 July 1991 discussed — DAMAGES — loss
of profit — loss of chance — project of property development collapses for want of
funding by promised finance — proper approach to calculation of damages
considered.
CONTRACT — binding contract — partners propose property development —
suburban shops and residences — funding of $6.5 million required — financier A
offers "full funding" subject to "total satisfaction" of it and its solicitors of
"documentation" — financier B offers to "match" that offer accepts commitment in
terms of financier A's letter — inserts penalty provision — promises later letter
confirming "full funding" — developers accept offer of financier B and decline
financier A — proceed to various stages of development promised letter committing
"full funding" never supplied despite later undertakings to do so — financier B later
discloses "change of policy" — development collapses developers sues financier B for
breach of contract and for deceptive or misleading conduct under s52 Trade
Practices Act 1974 (Cth) — financier B sues developers for recovery of advances and
debt — developers plead estoppel asserting entitlement to relief on the ground of
financier B's unconscientious conduct — trial judge (Cole J) finds (a) breach of
contract; (b) breach of s52 Trade Practices Act; and (c) entitlement to rely on
estoppel — awards damages for (i) futile borrowings less value of land plus (ii) loss
of profits which would reasonably have accrued to the developers had "full funding"
been provided as promised appeal —
TRADE PRACTICES — deceptive and misleading conduct representations by
financier to property developers — whether conduct misleading and deceptive at the
time — Whether finding that it was is liable to appellate disturbance — held:
Unnecessary to determine having regard to the respondents' entitlement to damages
for breach of contract and conduct of the trial.
ESTOPPEL — reliance — whether reasonable for representee to act — financier
adopts brief letter promising "full funding" for $6.5 million property development —
further documentation clearly contemplated — whether reasonable for party to act
on letter — whether, when policy changed, party obliged to seek alternative funding
— held: Unnecessary to determine in the light of entitlement to recover for breach
of contract. The Commonwealth v Verwayen (1990) 170 CLR 394; Lorimer v State
Bank of New South Wales, Court of Appeal, unreported, 5 July 1991 considered.
DAMAGES — contract — breach of — promise to lend money financier promises
developer to provide "full funding" for property development — later modifies terms
on basis that policy has changed — proper approach to damages — held: (Kirby P
and Mahoney JA: Clarke JA dissenting) (1) The developer was entitled to the
consequential loss of profits which flowed from the failure of the financier to adhere
to its promise to provide full funding, which failure occasioned the collapse of the
2 UNREPORTED JUDGMENTS
development. Head v Kelk (1963) 63 SR (NSW) 340 distinguished; (2) It was open to
the trial judge to conclude that the developer could not readily later obtain
alternative funding and the onus of proving that it could have done so lay on the
financier; (3) Various complaints of factual error on the part of the trial judge were
not sustained.
Held:
(Dismissing appeal)
(by the Court) (1) Having regard to the conduct of the case at trial, it was not open to
the financier to raise for the first time on appeal a defence that the arrangement contained
in the letter promising "full funding" was "subject to contract" as this would involve a
procedural unfairness to the developers. Masters v Cameron (1954) 91 CLR 349, 360
considered; Coulton v Holcombe (1986) 162 CLR 1, 7 applied; (2) On the facts, it was
open to the trial judge to conclude that the parties intended to enter legal relations upon
the basis of the letter accepted by financier B. McCutcheon v David MacBrayne Ltd
[1964] 1 WLR 125 (HL); Codelfa Construction Pty Ltd v State Rail Authority of New
South Wales (1982) 149 CLR 337 applied; (3) The terms of the promise were not so
uncertain as to prevent enforcement. Biotechnology Australia Pty Ltd v Pace (1988) 15
NSWLR 130; Austotel Pty Ltd v Franklins Selfserve Pty Ltd (1989) 16 NSWLR 582, 587;
The Cool Cliff Collieries Pty Ltd v Sijehama Pty Ltd, Court of Appeal, unreported, 5 July
1991 distinguished; Godecke v Kirwan (1973) 129 CLR 629, 641; Axelsen v O'Brien
(1949) 80 CLR 219, 225; Charalambous v Ktori [1972] 1 WLR 951 applied; (4)
Accordingly, the judgment based on breach of contract would be upheld and damages
calculated on that basis sustained. Discussion by the Court of the desirability of giving
legal effect to the commercial expectations of business people.
Trade Practices Act 1974, s52, s52A, s87.
Kirby P This appeal comes from a judgment entered by Cole J. It raises two
difficult questions.
The issues and course of the proceedings
The first is whether a finance company will be held liable to provide "full
funding" for a multi-million dollar property development scheme upon the basis
of a promise said to have been made in oral representations and evidenced in a
brief letter. Where it was clearly contemplated that, to give effect to the "deal" (to
use a neutral expression), a multitude of detailed, complex interrelated security
documents would have to be prepared, approved and executed by the parties, will
the law enforce the 'deal' or decline to do so because it lacks the necessary
certainty? Will such uncertainty be taken by the law As an indication that the
parties lacked the intention necessary then to enter into legal obligations?
Contingently upon an affirmative answer to the first question (whether found in
the law of contract, estoppel or in rights arising from the Trade Practices Act
1974 (Cth), (the Act) (s52 and s52A) a subsidiary question is posed as to the
calculation of the damages or determination of the other relief to which the
disappointed parties are entitled when the finance company failed to provide such
"full funding".
Other questions, including one addressed to the procedural fairness of the
appellant's principal argument on the appeal, took the Court into an examination
of the way in which the respective cases of the parties were pleaded,
particularised, presented and argued before Cole J.
His Honour dealt with the contentions of the parties in two stages. By reasons
given on 15 November 1990, he concluded that a legally binding contract had
been made and breached. He went on to conclude that the appellant had also
misled and deceived the respondents in breach of s52 of the Act. This entitled the
respondents to relief under s87 of the Act. In response to a cross claim by the
URJ | CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (kirby P) 3
appellant against the respondents, Cole J concluded that the appellant, as cross
claimant, was estopped from denying that it had entered into a legally binding
agreement to provide "full funding" and was thereby prevented from relying on
the terms of the securities taken by it.
By reasons given on 14 December 1990, his Honour gave judgment for the
respondents in the sum of $4,079,359.88. Upon the cross claim he gave judgment
in favour of the appellant, as cross claimant, in the sum of $3,164,050.58. He
stayed the execution of the judgment on the cross claim until the judgment in the
principal action had been satisfied by payment to the respondents.
Against the judgment giving effect to those orders, the appellant has appealed
to this Court. Originally, the respondents, by notice of contention, sought to
uphold the judgment upon bases different from those advanced by Cole J.
However, during the hearing of the appeal, without objection by the appellant, the
Court gave leave to the respondents to file a cross appeal to claim relief of a kind
different from that provided to them by Cole J. This related to relief based upon
the provisions of s87 of the Act or, alternatively, upon the principles governing
the grant of equitable relief against unconscionable conduct.
From this sketch of the general issues raised by the appeal and cross appeal,
it is necessary now to descend into the detail of the facts concerning the "deal"
between the parties. It is then necessary to examine the respondents' contention
that the appellant, on the appeal, had raised an entirely fresh basis to resist its
suggested liability. The respondents argued that, at trial, the appellant had
presented quite a different case. To permit it now to change its contentions would,
so it was said, involve a procedural unfairness of the kind forbidden by the
requirements of due process as explained in Coulton v Holcombe (1986) 162
CLR 1, 7f.
Findings on credibility: failure to call witnesses
The primary facts were not in dispute either before Cole J or in this Court. At
the trial, this point was emphasised (as his Honour noted) by the failure of the
appellant to call the evidence of its officers. The significance of this omission will
become obvious. His Honour accepted as truthful the evidence given by Messrs
William Jamieson and Glenn Pearson (the second and third respondents). They
were the principals of Cenepro Pty Limited (the first respondent) (Cenepro). This
was a shelf company to be used for a property redevelopment. Cole J did not
leave the acceptance of the testimony of Messrs Jamieson and Pearson to
inference. He expressly affirmed his acceptance of the evidence of Mr Pearson
upon the basis of his impression from the witness box. He concluded that he
could accept that evidence, and that of Mr Jamieson, as "the undenied evidence
of truthful witnesses". The appeal must be approached, therefore, upon the basis
that the respondents' evidence was truthful. Jones v Hyde (1989) 63 ALJR 349,
351; Abalos v Australian Postal Commission (1990) 171 CLR 167, 179.
So much was accepted by the appellant. Its counsel conceded that there was no
challenge to any of the facts found by Cole J on the issue of liability. All of his
Honour's findings, as to what was said by the respondents and to them by the
officers of the appellant, were unchallenged. It was also conceded that a prime
actor in the appellant's employ (Mr Stephen Bembrick) was not uniformly
"consistent" in what he had said to the respondents. Neither Mr Bembrick, nor
his superior, Mr Bruce Anderson (the New South Wales manager of the
appellant) testified. Whilst their absence from the witness box does not provide
affirmative material for the respondents' case, it does give rise to the inference
that nothing they could have said would have denied any of the material
4 UNREPORTED JUDGMENTS
testimony given by Messrs Jamieson and Pearson; that nothing they could have
said would have advanced any substantial evidence favouring the appellant (for
otherwise they would have been called); accordingly that inferences which would
otherwise reasonably arise from the testimony given in the respondents' case
might more comfortably be drawn because contradictory testimony was not
called to correct or qualify such inferences. See Jones v Dunkel (1959) 101 CLR
298, 302; Clayton Robards Management Ltd v Siu (1988) 6 ACLC 57; QANTAS
Airways Ltd v SS Pharmaceutical Co Ltd, Court of Appeal, unreported, 20 July
1990; (1990) NSWJB 78.
In a case of this kind, it is desirable to incorporate in these reasons, by
reference, all of the findings of fact made by Cole J. The great bulk of his
Honour's first reasons is taken up in a review of the protracted dealings between
the appellant and the respondents. In a sense, the legal conclusion emerges only
from an understanding of the detailed facts, as found. Whilst taking into account
all that his Honour said in his reasons, I will content myself with the following
exposition of the facts, taken from those reasons. It is convenient to adopt the
same course as his Honour did. I will deal first with the issues concerning the
liability of the appellant.
Proposal for property development
Mr Jamieson owned one of a complex of properties at the corner of Bellevue
Road and Riddell Street, Bellevue Hill. His property, number 27A Bellevue
Road, comprised a butcher shop with a residence above it. Other shops in the
complex were number 23A (a newsagency), 2S (an electrical store), 25A (a fruit
shop) and 27 (a laundry). Adjacent to the newsagency were premises owned by
the Commonwealth Bank of Australia (number 23). At the rear of the bank's
premises was a carpark. A right of way in favour of the Woollahra Municipal
Council ran at the rear of numbers 25 to 27A.
In 1988, Mr Jamieson conceived the idea to redevelop properties 23A to 27A
inclusive and to acquire the bank carpark and the right of way in order to
incorporate these in the redevelopment. He approached his friend, Mr Pearson, an
architect with experience in the development of properties, to join in the
enterprise. Mr Jamieson was to contribute his interest in number 27A and Mr
Pearson his expertise and skill in drawing up the plans and proposals. Plans
showing five commercial premises with five three-bedroom residential units
above were duly prepared. Messrs Jamieson and Pearson had discussions with
the owners and tenants of the premises. In late July 1988, Mr Pearson approached
Mr Bembrick, an officer of the appellant with whom he had had previous
dealings. A meeting took place in early August 1988 at the appellant's offices. Mr
Bembrick indicated that the appellant would be interested to fund the project. But
he suggested a number of alterations to the plans, including the substitution of
eight two-bedroom units for the five three-bedroom units originally proposed. Mr
Pearson later drew amended plans to conform to Mr Bembrick's suggestion.
During this initial discussion Mr Bembrick explained different modes of
providing finance: either a joint venture with another developer or a 100%
finance figure for redevelopment exclusively by the respondents. Mr Pearson
expressed a preference for the latter. But it was agreed that Mr Bembrick should
discuss the proposal with other clients of the appellant who were involved in
participating in joint property ventures.
URJ | CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (kirby P) 5
On 12 August 1988, Cenepro entered into a contract to purchase number 23A.
Soon thereafter it took an option over 25. Both of these arrangements were
subject to time clauses. Adding Mr Jamieson's interest in 27A, the respondents
therefore had, by this stage, a capacity to secure three of the five allotments.
Pursuant to Mr Bembrick's instruction, Mr Pearson gathered financial data. On
1 September 1988, Mr Bembrick inspected the site. He indicated that he had all
the information required to prepare a submission to the appellant. It was
understood that this was to be on the basis of full funding of the respondent's
proposal for both acquisition of the allotments not yet owned and for construction
of the redevelopment proposed.
On 6 September 1988, Mr Bembrick, on a letter which described him as
"Senior Property Finance Manager: NSW", wrote to Cenepro advising that the
appellant had approved a facility of $880,000 for specified acquisitions. This was
guite different from that sought. It led Mr Pearson to telephone him. He protested
that it was:
"\.. not for full funding as we discussed."
Mr Bembrick explained that the intention of the letter had been to tide the
respondents over "for the moment". But Mr Pearson said: "... We're not
interested in just purchasing one property and there is no guarantee that Custom
Credit give us funding for The whole deal.
Having reached this imposse, the respondents looked around for finance
elsewhere. By way of a broker, they were put in touch with Devreal Capital
Limited, (Devreal), a company engaged in financing projects of this nature in
competition with the appellant. The proposal submitted to Devreal by the broker
was for a facility of $6.32 million for total acquisition and construction costs,
together with capitalised interest. This proposal was put to Devreal on 8
September 1988. Soon afterwards, Mr Bembrick telephoned Mr Pearson to
inform him that he wanted the nomination of a valuer. This was provided. On 14
September Mr Bembrick proposed a meeting with a client of the appellant, Scotts
Developments Pty Ltd (Scotts). This company was put forward as a joint
venturer. Mr Pearson asked whether there was any problem with "doing the
project with us only".
Mr Bembrick replied:
"No, this is just another avenue, and because of Scotts existing line of credit
may be easier. I'm just looking at all the possibilities. I'm trying to help you
guys."
The meeting went ahead. The proposal was for Scotts to receive 60% of the
profits, 40% going to the respondents. Eventually the respondents' agreed to the
proposal. Heads of agreement were to be prepared by Scotts.
Meanwhile, the broker for Devreal advised Mr Pearson that: "Subject to final
checks and investigation being satisfactory we have been assured that Devreal J
will give a commitment to proceed with the full project... The Devreal offer will
be based on total funding and they are developing a proposal based on a mixture
of fees and profit share. The end results will be a substantial savings on what
Custom Credit have suggested." By 21 September 1988, the respondents had still
not received the heads of agreement signed by Scotts. That morning, the broker
sent a letter by facsimile to the respondents enclosing an offer from Devreal. This
offer is a key document.
Offer of finance from a competitor
The letter, dated 21 September 1988 was addressed to the Directors of
Cenepro.
6 UNREPORTED JUDGMENTS
It began:
"we are pleased to confirm our offer of finance on the following terms and
conditions."
It then set out details of the name of the borrower (being Cenepro and Messrs
Jamieson and Pearson as directors); the amount (being $6.5 million to be drawn
by an initial tranche with further advances):
"... subject to completion of Devreal's project feasibility, an external valuation
of the total development scheme, check costings, and DA approval from the local
council, proving satisfactory in all respects." The loan purchase was then defined
as was the term of 18 months, with an initial tranche for 90 days; the amount of
an establishment fee ($15,000), the specification of the interest rate (15.95%)
"reviewable at Devreal's discretion", the specification of security, and the
identification of the respective lawyers for the parties. The following key
provition was then included:
"Documentation
Subject to Devreal and its lawyers total satisfaction."
There then followed items, all likewise expressed in summary form, detailing
arrangements as to costs. The letter closes with the following provisions:
"Material Adverse Change:
Devreal reserves the right to withdraw the facility should anything transpire
that renders its completion undesirable.
Insurance:
A comprehensive policy noting Devreal as mortgagee must be provided with
cover for the replacement value of the improvements.
Special Conditions: Initial Tranche
Satisfactory valuation of 23A Bellevue Road, Bellevue Hill.
"Acceptance:
To confirm you acceptance of the terms and conditions please sign the attached
copy of this letter and return same with your cheque for $5,000. This sum will
be reimbursed on drawdown. This offer is open until 23 September 1988.
Yours sincerely
DEVREAL CAPITAL LIMITED"
(Signed by the Joint Managing Directors)
Armed with this letter, Mr Jamieson telephoned Mr Bembrick on behalf of the
respondents to inform him of the offer of "full funding from another financier".
Devreal's broker had warned him by letter:
"T would reiterate comments... that you would be unwise to go forward with
Custom Credit on the verbal assurances of an officer of that company who does
not have decision making power."
Mr Jamieson confronted Mr Bembrick with his need to make an urgent
decision on Devreal's offer. As found by Cole J, the following conversation
ensued:
MR BEMBRICK: Look, at least give me a chance to see if I can get it together
before you do anything. As you know I've put lots of work into this and so has
Scotts. Do you think you can hold off?
MR JAMIESON: Scotts were supposed to have signed up on this deal already
and I don't want to jeopardise the deal with Devreal.
MR BEMBRICK: Leave it with me and I'll get back to you straight away."
There followed a flurry of meetings with representatives of Scotts and with Mr
Bembrick. Agreement was reached on the heads of agreement of the joint venture
with Scotts as previously proposed. At Mr Bembrick's suggestion, Mr Pearson
URJ | CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (kirby P) 7
then telephoned Devreal's broker to advise that Cenepro had made "alternative
arrangements" and would not now be proceeding to accept Devreal's offer of full
financing of $6.5 million. Messrs Jamieson and Pearson duly attended at Scott's
solicitor's.
But Mr Bembrick arrived at 6 pm with the news that Scotts had decided not
to proceed with the project after all. The following conversation ensued: "MR
BEMBRICK (Scotts):... have pulled out of the deal.... ' ve spoken to my superior,
Bruce Anderson about it and in the circumstances Custom Credit would be
prepared to fund the project.
JAMIESON: I have been told... that you don't have the authority to approve
this deal. In fact I have o fox saying just that.
MR BEMBRICK: I don't have authority. But Bruce Anderson does. He is the
New South Wales State Manager. I've spoken to him about it already. He's back
at the office playing cards. We can go across there now and talk to him but we
have to hurry."
A deal clinched with the Appellant
With Mr Bembrick, Messrs Pearson and Jamieson thereupon returned to
Custom Credit's offices. They met Mr Anderson. At his request, they showed him
a letter of approval from Devreal. Mr Bembrick referred to the problem of
authority. Mr Anderson said:
"Of course I've got authority, I'm the State Manager for New South Wales."
Having read the Devreal offer there ensued the following conversation:
"MR ANDERSON: Steve, I can't see why I can't do the same deal as Devreal.
MR BEMBRICK: I can't see why not either.
MR JAMIESON: Can you do a better deal than Devreal? There was then some
discussion pursuant to which Mr Anderson agreed to reduce the profit share taken
by the appellant from 20% to 15% and to reduce interest marginally to give a rate
of 2% above the bank bill rate. Security was then discussed. Mr Jamieson
outlined difficulties in raising security on his property mortgaged to the
Commonwealth Bank. This led to the following exchange:
MR ANDERSON: Okay. How about we structure in this way. Ill prepare
documentation so that you give Cenepro an opinion over your property and then
Cenepro can change the opinion in favour of Custom Credit. But in the meantime
we want a lien over your bills.
MR JAMIESON: But you've took my personal guarantee as well as (Glen
Pearson's) and there's $100,000 equity in the property anyway - 23A is worth
$450,000 and we took it for $350,000. that should be enough.
MR ANDERSON: You were willing to give a lien over the bills in The Devreal
offer.
MR JAMIESON: Well I really need the money now. Anyway in the Devreal
offer it was agreed that the lien is going to be released on substitution of security
over 27A and that it is going to happen quickly. I was going to get paid up front.
ANDERSON: Well that's what's going to happen here. The lien will only be
there until final documentation is completed and an option on 27A in favour of
Cenepro is documented. Then your bills will be returned.
JAMIESON: Okay, I'm happy with that.
MR BEMBRICK: Are you happy with that Glen?
MR PEARSON: Yes."
Drinks were then brought in to celebrate the "deal". Mr Anderson explained
that all the secretaries had gone home so that it was not possible to prepare the
documentation that evening. As found by Cole J the following exchange ensued:
8 UNREPORTED JUDGMENTS
MR BEMBRICK: we could use our previous offer just to defer the immediate
settlement so we can have a cheque ready for that on Friday. we could also at the
same time prepare a letter for The full funding for Cenepro to sign on Friday.
MR ANDERSON: Fine.
MR JAMIESON: So all this can be ready on Friday?
MR BEMBRICK: Yes.
It was then that the letter of 6 September 1988 offering the facility of $880,000
was amended to constitute a facility for $480,000. The earlier letter was changed
to show that it related only to the acquisition of number 23A. Mr Anderson
expressed his determination to ensure that the respondents were "on the hook" to
the appellant:
MR ANDERSON: "...I want to make this clear. If we can't get the whole deal
there's no basis for us simply to fund the first settlement. We want to lock you
in so that you don't go back to Devreal.
MR PEARSON: Well, since you are giving us full funding and a bit better
deal, we don't want to do any deal with anyone else.
MR ANDERSON: We want to make sure that you don't.
MR BEMBRICK: What if we put in a discharge fee of $50,000?"
MR ANDERSON: Good idea."
Mr Bembrick then wrote onto the amended letter the following additional
term:
"Discharge Fee:
Should this facility be discharged at the expiration of the term a fee of $50,000
is payable on discharge." The respondents agreed to that change. As found by
Cole J, they left the meeting with Messrs Anderson and Bembrick confident in
the belief that the appellant had accepted the obligation of full funding; that it
would signify this in writing on the following Friday; that the only reason it did
not do so there and then was the Absence of typing staff; and that as a measure
of the commitment required and given for this arrangement, a penalty of $50,000
was inserted, as Mr Anderson had said, to 'lock' the respondents into the
appellant and to prevent them going back to Devreal.
It was not argued that Mr Anderson lacked authority to make this arrangement,
whatever its legal effect. It was argued that Mr Bembrick lacked authority and
could make no representations for, or binding promises on behalf of, the
appellant. But there is a difference between Mr Bembrick's ostensible authority
before the meeting with Mr Anderson on 21 September 1988 and thereafter.
There after, it is clear that Mr Bembrick was acting with whatever authority Mr
Anderson had lent to the "arrangement". That authority was, by his own
assertion, ample, as one would expect in the case of the State Manager of the
appellant. As neither Mr Anderson nor Mr Bembrick gave evidence to deny
authority, the suggested want of it can therefore be rejected.
The parties' conduct after the 'deal'
Like Mr Anderson, the respondents were interested only in "the whole deal"
and not with the purchase of individual allotments. Just before the meeting on 21
September, recounted above, Cenepro had obtained an option over number 27. It
thus had control over four of the five frontage allotments. Agreement had also by
that time been achieved, in principle, both with the Commonwealth Bank and the
local council respectively for the sale of the car park and extinguishment of the
right of way, although in both cases the price had still to be finalised.
URJ | CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (kirby P) 9
It was expected that arrangements relating to number 25A would be resolved
shortly. Armed with their "agreement" with the appellant, the respondents could
have been excused for thinking that at least foreseeable problems were behind
them and full funding for their redevelopment would be provided by the
appellant, substituting for Devreal. Both Mr Pearson and Mr Jamieson gave
evidence, which Cole J expressly accepted, that neither of them would have
accepted the facility for $480,000 for the settlement on 23 September unless they
believed that the appellant had agreed to fund the total acquisition and
construction costs of the whole development. His Honour found that, had they
believed that it was otherwise, they would have reapproached Devreal on the
following morning for a revival of its $6.5 million financing offer on a "full
funding" basis. It may be inferred that his Honour believed that that offer would
have been forthcoming from Devreal. There is no reason to conclude otherwise.
When, however, 23 September 1988 arrived, no letter from the appellant
confirming the full funding arrangement, made on 21 September 1988 with Mr
Anderson, was forthcoming. Mr Jamieson protested this fact. The appellant's
solicitor telephoned Mr Bembrick. Mr Jamieson confronted him with the promise
to provide the letter "for full funding" and a refusal to sign the document for the
settlement of 25A without the letter. According to Cole J's findings Mr Bembrick
replied:
MR BEMBRICK: I haven't had time to finish it. ''ve been busy doing the
paper work for 23A. But be done. You' ve got nothing to worry about. The deal
is done. It's just a matter of putting together paperwork."
Further reassurance was given that the respondents had nothing to worry
about. That they would get their letter. That the deal was done. And that the letter
would be ready 'in a week'. It was only then, and, as Cole J found "acting upon
those assurances", that the loan documentation was executed for Cenepro and the
personal guarantees and indemnities executed by Messrs Pearson and Jamieson
in connection with the purchase of 23A. Cole J accepted the evidence that the
guarantees were only executed:
"... based upon the representations and assurances of Mr Bembrick on 23
September 1988 confirming the arrangement mode between Cenepro and Mr
Anderson on behalf of Custom Credit on 21 September 1988 that Custom Credit
would provide full acquisition and construction funding."
It would be tedious to recount the tale of prevarication, fobbing off and interim
arrangements which thereafter ensued. The detail of it is set out in Cole J"
reasons of 15 November 1990. Mr Bembrick, for a time, continued to assure the
respondents that "the letter will be out soon". For their part, they frequently
requested a letter confirming "full funding". Each time they received a fresh
promise from Mr Bembrick. However, when on 5 December 1988 a letter was
finally received, it was not in the terms of "full funding". Instead, it offered a
facility of $2.9 million, being for some of the acquisition costs and capitalised
interest. It also contained a new provition for a "participation fee" of $100,000
or 20% of the profits whichever was greater.
Cole J concluded that this letter was not a fulfilment of the promise made by
Mr Anderson at the meeting on 21 September 1988 and repeated thereafter on
numerous occasions by Mr Bembrick. The letter led to a confrontation between
Mr Pearson and Mr Bembrick. The latter contended that it was "easier to do it
this way". He again put off the provision of the letter for full funding. When
asked for another meeting with Mr Anderson, he was assured by Mr Bembrick
that Mr Anderson was:
10 UNREPORTED JUDGMENTS
"\..Aware of all this and this is the best way to do it... Don't worry, you will
get your full funding. I'm doing this for you and I am personally getting nothing
out of it." Cenepro declined to accept the offer of 5 December because it did not
regard it as consistent with the agreement of 21 September 1988. Meanwhile,
despite his soothing words as recounted by the respondents, Mr Bembrick was
writing internal memoranda which came to light in the litigation, at variance with
the repeated promises of commitment for full funding. By mid-December 1988,
Mr Bembrick advised the respondents that he had another client of the appellant
to offer as a joint venturer. Nothing eventuated. On 3 February 1989, at a meeting
between Messrs Jamieson, Pearson and Bembrick, Mr Bembrick finally
acknowledged that the appellant had changed its policy:
"MR PEARSON: What the hell is doing on? What happened with our funding?
Things aren't going the way you said they would. Custom Credit seems to be
changing its mind all the time...
MR BEMBRICK: I'm with you guys but Custom Credit has altered its
position. With the downturn in economy they're only dealing with existing
clients and I think it's going to get worse.
MR PEARSON: Yes, but we agreed to do this back in September.
MR BEMBRICK: Custom Credit doesn't think you and Mr Jamiesons are
strong enough. Maybe you should consider bringing in a third party. that would
give them some comfort down the road
MR PEARSON: Look, we don 't agree with it. Everything is just about done.
It's only got to be built... we think the project can stand on its own. Custom Credit
must have agreed this in September then reconsidered.
MR BEMBRICK: Custom Credit's policy has changed.
MR PEARSON: That is fine for new clients but not for us.
Cole J was not convinced that Custom Credit's policy had actually changed.
He stated that the internal documents made it clear that Mr Bembrick had never
submitted an application for approval of full acquisition and construction
funding.
Instead, Custom Credit pressed its revised offer of 5 December 1988. But
Cenepro never took up the $2.9 million facility proposed in that letter. Further
fruitless discussions took place and still more joint venturers were introduced but
declined. The date for the settlement of number 25 on 6 April 1989 approached.
The approach of that date ultimately required Cenepro to accept an interim
arrangement with the appellant. As found by Cole J, the respondents could not
find finance elsewhere. They could not afford litigation. Their only option was to
take up the offer of finance which the appellant made. They signed a variation of
the facility agreement and then secured funds to purchase No 25.
Indeed, a total of fourteen separate offers were made by the appellant.
All of them were particular to the specific acquisition and other costs. None of
them fulfilled the obligation which the respondents kept asserting that the
appellant had promised to "provide full funding". In April 1989 Mr Bembrick
answered the repeated protestation of Mr Jamieson with these words:
"Policies have changed again. The facility to value ratios and security
requirements have changed and this is the best that I can do... we need comfort
in the form of a going venturer or equity."
In May 1988 the appellant offered Cenepro a letter of finance with a facility of
$3.61 million. To Mr Jamieson's protest, Mr Bembrick replied:
URJ | CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (kirby P) 11
"T've spoken to my superiors about it and in the current economic
circumstances this is the only way it can be done. My superiors don't think
Cenepro is strong enough." Again the respondents were in a precarious position.
The settlement of No 25 was approaching on 9 June 1989. Time had been made
of the essence. In a conversation shortly before that date, Mr Jamieson expressed
concern about the "extremely precarious position" of the respondents if they
could not settle. Mr Bembrick replied:
"As I told Glenn, because of the downturn in the economy our loan to value
ratios have changed and we need more security. We want a mortgage over your
property." This presented difficulties for Mr Jamieson as he had already explained
to the appellant.
Further negotiation ensued. Ultimately Cenepro had no real or commercial
alternative. As found by Cole J it was faced with accepting the appellant's offers
or abandoning the project. In July 1989 Cenepro therefore sought to introduce a
third party to the appellant to become a joint venturer on terms similar to those
earlier proposed for Scotts. However, the appellant insisted on personal
guarantees of the directors which, it had previously been made clear, would not
be provided. The settlement of 25A then fell due on 16 October 1989. Again Mr
Jamieson requested the letter of "full funding" which he at least expected would
be forthcoming with the participation of a viable joint venturer. Mr Bembrick,
consistently with his earlier stance, said:
"Look, approval for the full facility should issue soon. We'll give you on
interim facility to settle 25A. We'll make the term for one month. That should be
enough time for us to get the approval for the full project costs."
As earlier, so now. The letter of approval for full funding did not ensue. By
December 1989 Mr Bembrick had explained that the matter was out of his hands.
At the same time, the last of the prospective joint venturers withdrew. The project
collapsed. At the time of its collapse, Cenepro had acquired 23A, 25, 25A and 27.
Mr Jamieson owned 27A. The purchase of the car park and acquisition of the
laneway had not been completed. In all, the appellant had advanced the
respondents $2.635 million. With accumulated interest to the date of trial, the
amount outstanding by the respondents to the appellant exceeded $3 million in
debt and upon the personal guarantees which the appellant had insisted upon. The
appellant held mortgages over the properties purchased by Cenepro. It also held
a charge over Mr Jamiesons bank bills and over number 27A.
It was in these circumstances that the respondents, as plaintiffs commenced
proceedings in the Supreme Court. Those proceedings were heard in the
Commercial Division. By their summons, the respondents sought damages for
breach of contract and relief under of the Act. The appellant defended and by a
cross claim sought to recover the debt alleged to be outstanding to it. In defence
to the cross-claim the respondents asserted that the appellant was estopped from
claiming repayment, on the ground that it was unconscionable for it to seek to do
so. In the alternative, they sought to offset against any sums found to be owing
the amounts to which they were held to be entitled.
Cole J found for the respondents upon the three legal bases relied upon by
them. In his second reasons, published on 14 December 1990, he resolved the
issue of damages. As earlier stated, he awarded the respondents damages. On the
cross-claim, Cole J found the appellant entitled to judgment in a smaller sum. He
stayed execution of the judgment on the cross-claim until the damages were paid.
12 UNREPORTED JUDGMENTS
The result of the litigation was the nett recovery by the respondents of
$915,301.30 in damages and costs. It is this outcome which the appellant
challenges in the appeal.
Issues in the appeal
In summary form, the issues argued in the appeal were as follows:
1. Whether, consistently with the matters litigated at the trial, it was open to the
appellant on appeal to argue that no legally enforceable agreement was reached
on 21 September 1988 upon the basis that any such "agreements" was, expressly
or by implication, to be subject to subsequent formal documentation, and
consequent negotiation and further express agreement. If such defence were
available to the appellant, it contended that it answered the claim of an agreement
to provide "full funding" and that, under the "agreement", so understood, it had
fully performed its side of the bargain by proceeding, at each successive stage,
to negotiate, and when agreed, to document, the provision of funds in furtherance
of the agreement, so understood;
2. Alternatively, within the case presented at the trial, the appellant contended
that there was no legally enforceable promise As a result of what was "agreed"
on 21 September 1988. This was argued upon the basis that the suggested
"agreement" was not one to which the parties intended legal consequences to
attach or was one, the terms of which were so uncertain that the law would
withhold legal enforcement of it;
3. The appellant contested the finding that it had engaged in misleading or
deceptive conduct within s52 of the Trade Practices Act and suggested that there
was no evidence from which such a finding could be made;
4. The appellant also contended that it was not open to the respondents to
succeed on estoppel if a contract was not found. Alternatively, it argued that the
requirements of estoppel had not been established by the facts as found;
5. The appellant attacked the conclusions on the respondents' entitlement to
damages, if liability were established. If there were any liability, it contended that
the damage suffered was limited to the cost of securing alternative finance in
January 1989 when it must have become plain that the "full funding", as
understood by the respondents, would not be provided. Alternatively, the
appellant contended that the respondents had provided evidence which would
only support a claim for damages on the basis of breach of contract. Such
evidence was not available to support the different form of relief (more akin to
tort) sought under s87 of the Act or the different relief against unconscionability
provided upon proof of an estoppel. Cf Lorimer v State Bank of New South
Wales, Court of Appeal, unreported, 5 July 1991. Upon this basis, the appellant
contended that, if the respondents failed in their claim in contract, but succeeded
under s52 of the Act or on the estoppel, they would be denied relief, having
forfeited the opportunity to provide evidence by which such relief could be
fashioned; and
6. Finally, the appellant criticised a number of factual finding made by Cole J
in his reasons on damages and thereby sought to undermine at least the
quantification of the damages, if all other arguments failed. It is convenient to
deal with these arguments in turn.
Conduct of the trial
In this Court it was the primary submission of the appellant that Cole J had
attributed legal consequences to the "unenforceable arrangement" between the
parties on 21 September 1988 when it was clear that such arrangement was
"subject to formal contract". It was put that it was the clear intention of the
URJ | CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (kirby P) 13
parties that no binding contract would come into existence between them until
the formal documentation relating to the proposed loan and all of its many terms
have been executed by the parties. In this way, the appellant argued that the case
fell within the third class of cases in Masters v Cameron (1954) 91 CLR 353, 360.
It is worth remembering that catalogue of possibilities. Although very familiar
and now criticised as incomplete, it usefully identifies the respective positions of
the appellant and the respondents on the appeal. In Masters, Dixon CJ,
McTiernan and Ritto JJ (at 360) said:
"Where parties who have been in negotiation reach agreement upon terms of
a contractual nature and also agree that the matter of their negotiation shall be
dealt with by a formal contract, the cases may belong to any of three classes. It
may be one in which the parties have reached finality in arranging all the terms
of their bargain and intend to be immediately bound to the performance of those
terms, but at the same time propose to have the terms restated in a form which
will be fuller and more precise but not different in effect. Or, secondly, it may be
a case in which the parties have completely agreed upon all the terms of their
bargain and intend no departure from or addition to that which their agreed terms
express or imply, but nevertheless have made performance of one or more of the
terms conditional upon the execution of a formal document. Or, thirdly, The case
may be one in which the intention of the parties is not to make a concluded
bargain at all, unless and until they execute a formal contract."
Essentially, the respondents contended that the "arrangement" on 21
September 1988 fell into the first class. There was a concluded contract, although
documentation to give effect to the agreement (eg by mortgage, charge etc) was
clearly contemplated. On the appeal, the appellant contended that the case was in
the third class.
In support of that contention, the appellant pointed to a number of indicia in
the Devreal letter which it had accepted. It also relied on the very nature of a
complex financing transaction of the kind contemplated by the parties. So far as
the letter was concerned, the appellant laid emphasis upon the fact that it reserved
to the "total satisfactions of Devreal and its lawyers acceptance of
documentation". The latter retained in Devreal the right to withdraw the facility
should anything render its completion "undesirable". It clearly contemplated
further documentation; but did not contain precise agreement about their terms.
The letter also contemplated subsequent eventualities which were not defined
with precision but which envisaged the possibility of Devreal's withdrawal or
placing a limitation on its liability. Thus the provition for further advances was
stated to be subject to the completion of Devreal's project feasibility study.
Costings were to be "subject to independent assessment by Devreal's appointed
consultant". The letter did not deal with what would occur if the project cost
exceeded the total amount of the facility of $6.5 million, as subsequently
transpired. Various items certainly "blew out". Thus the cost of the purchase of
the laneway from the Council was budgeted at $25,000. In fact, the estimated
cost when the project collapsed was just short of $138,000.
In these circumstances, the appellant contended that the Devreal letter itself,
and the very nature of such a transaction between such parties dealing in such
sums, clearly envisaged further documentation of considerable complexity with
a multitude of terms upon any of which agreement could break down. This was
not a case where, upon any view, an informal arrangement would have been
contemplated by the parties. The appellant was a large finance company whose
internal procedures would, self-evidently, require security documents to be
14 UNREPORTED JUDGMENTS
executed. The subject of the loan was the acquisition and charging of land in
respect of which formal documents are ordinarily required as all parties would
have appreciated. In such circumstances the appellant urged that the proper
characterisation of the "arrangement" of 21 September 1988 was an agreement in
principle, but subject in the ordinary way to the preparation of the necessary
documents at the successive stages at which the provision of funding by the
appellant to the respondents fell due.
It was this "subject to a contract" argument which the respondents urged
involved an entirely new case; one different from that presented at the trial. An
appellate court may, and in appropriate circumstances should, allow a party to
raise a new case on appeal where all that is involved is the application to given
facts of principles of law not relied on at the trial. This arises from the character
of an appeal such as the present one, as a "rehearing", as s75A of the Supreme
Court Act provides. However, in a series of cases, the High Court of Australia has
made it clear that an appellate court may not permit an enlargement of the issues
on appeal if to do so would occasion procedural unfairness to the other party.
Thus in Coulton v Holcombe (1986) 16 2 CLR 1, 7, Gibbs CJ, Wilson, Brennan
and Dawson JJ said:
"Tt is fundamental to the due administration of justice that the substantial
issues between the parties are ordinarily served on the parties... The powers of an
Appellate Court in respect to amendment are ordinarily to be exercised within the
general framework of the issues so determined and not otherwise. In a case
where, had the issue been raised in the Court below, evidence could have been
given which by any possibility could have prevented the point from succeeding,
This Court has firmly maintained the principle that the point cannot be taken
afterwards: see Suttor v Gundowda Pty Ltd (1950) 81 CLR 418, 438; Bloemen
v The Commonwealth (1975) 49 ALJR 219."
The gist of the respondents' opposition was that this case, on appeal, was quite
different from the case presented at trial. There, it was contended, the appellant's
case was that it would not be bound until a letter was provided promising "full
funding"; that no such letter had been provided; and that in default of the
condition precedent the "arrangement" had never acquired the force of a binding
legal contract. In this sense, it was the respondents' submission that the
appellant's case at trial was more akin to the second of the classes mentioned in
Masters v Cameron rather than the third. Of course, the case may not fall readily
into any of the categories in Masters v Cameron.
The parties intended to be bound immediately and yet to have a letter
evidencing the agreement.
Precisely what had been the appellant's case at trial was the subject of a heated
contest in this Court. The respective positions were asserted. But as counsel had
changed and no agreement could be reached, the Court required the matter to be
dealt with in a formal way, ie either by the provision of an agreed statement or
by the taking of evidence. Cf Builders' Licensing Board v Mahoney (1986) 5
NSWLR 96, 98 (CA). Eventually, a statement, signed by counsel who had
appeared at the trial, was tendered. This contained the following agreement:
"The address on behalf of the appellant occupied approximately an hour and
a half, during which the submissions were developed.... It was submitted on
behalf of the appellant:
URJ | CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (kirby P) 15
(a) that the informality of the discussion on 21 September 1990, coupled with
the complexity of the transaction and the embryonic state of the project pointed
away from an objective conclusion the binding contract as made in the
discussion;
(b) that the parties contemplated a letter embodying the facility and the
respondent had nothing until a letter was forthcoming;
(c) That to hold otherwise would characterise Cenepro as bound to borrow the
money and to render Cenepro liable in damages if the development did not
proceed, which is wholly unrealistic considering the informality of the
circumstances in which the proposed financing as discussed."
The written submissions tendered at the trial were examined. Upon this point
they contained only the following paragraphs:
"27. The conversations on 21 December 1988 between Anderson representing
Custom Credit and Jamieson and Pearson representing Cenepro did not constitute
an offer and acceptable capable of giving rise to a binding contract.
28. There was no intention to create contractual relations unless and until an
offer is produced and accepted.
29. Further the terms of the foreshadowed facility were too uncertain to
constitute the basis for a binding contract."
It is difficult to resolve a dispute of this character. I start from a desire to ensure
that, so far as it is fair to do so, the appellant should have the benefit of any legal
arguments which are available to it. For a number of reasons, however, I have
concluded that it would involve a procedural unfairness to the respondents to
permit the appellant to rely here upon a "subject to contract" argument. It is not
clearly stated in the written submissions tendered at the trial. Nor is it clearly
contained in the note of counsel's recollection of the oral arguments. It is not
clearly pleaded in the defendant's Statement of Contentions by Way of Defence.
It was not clearly put to the respondents' witnesses during the hearing on liability.
It was not stated in Cole J's epitome of the issues presented at the trial as he
perceived them. It was not clearly raised in the grounds of appeal. Most
importantly, to permit the argument to be raised for the first time would inflict a
particular procedural injustice on the respondents. They had issued a subpoena at
the trial requiring the appellant to produce its operating procedures. As a
consequence, a substantial book was produced titled "Property Finance Division
- Operating Procedures". Having regard to the way the appellant presented its
case, the respondents did not tender this document. The Court was invited to infer
that standard operating procedures, and pro forma documents existed so that,
from this material, it would have been open to Cole J quite readily to construct
the series of security documents (and their terms) envisaged to give effect to the
"arrangement" for full funding of 21 September 1988. In short, from the
Operating Procedures it would have been possible to define with a high degree
of precision "the terms restated in a form which will be fuller and more precise
but not different in effect" from the agreement of 21 September 1988.
There is another consideration. As recorded in the evidence, Mr Pearson was
an architect with experience in the development of properties. Had it been clear
that the appellant's case at trial was that the "arrangement" of 21 September 1988
was "subject to contract", it would have been open to the respondents to seek to
elicit from Mr Pearson evidence concerning his experience of the way in which
agreements of the kind recorded in the Devreal letter are translated in the
marketplace by using standard form security documents. Mr Pearson gave
evidence that he had been involved in some fifteen developments. He was not
16 UNREPORTED JUDGMENTS
cross examined to suggest that financiers, such as the appellant, never made
commitment to provide finance without first obtaining the execution of formal
security documents. Instead, the line of cross examination adopted was that he
was waiting for a letter which, though promised, never came.
And there is a still further consideration. Had this been the appellant's case at
the trial, the respondents could have sought to explore, by evidence, the practices
normal in the business of financing property developments. Cf Air Great Lakes
Pty Limited and Ors v K S Easter (Holdings) Pty Limited (1985) 2 NSWLR 309,
332.
In the foregoing circumstances, Suttor and Coulton require this Court to refuse
to entertain an argument on appeal which was not the case fairly raised and
presented at the trial. Of course, it is still open to the appellant to contend, for
other reasons, that no legally binding contract was made. But it cannot do so
upon the basis that it was an agreed precondition to the achievement of such a
contract that the parties would first agree upon the precise terms of the security
documents which were expressly and impliedly contemplated by it.
No intention to contract or contract too uncertain The appellant certainly
argued at the trial that the evidence demonstrated that there was no intention, at
21 September 1988, to enter into a promise which would be legally binding on
it. It also clearly contested liability upon the basis that any "promise" then made
was too uncertain and would not, therefore, be enforced. These are alternative
ways of presenting the same idea. They bear and obvious relationship to the
"subject to contract" argument; but they are not the same as it.
Drawing upon many of the facts already referred to, both in the terms of the
Devreal letter which it accepted and in the very nature of such a transaction
between such parties, the appellant argued that the arrangements on 21
September 1988 fell far short of a concluded agreement. It was clear at that time
that a great deal of documentation would be required to evidence the security
arrangements in respect of such of the properties which form part of the
development. So much was not disputed by the respondents. In such
circumstances, so the argument ran, the law would withhold enforcement of an
agreement which the parties had themselves not yet concluded in appropriately
precise and detailed terms.
As is usual in cases of this kind, indicia exist in the evidence to support the
competing contentions of the parties. Take, for example, the following indicia
which support the appellant's arguments:
1. The terms of the Devreal letter have already been referred to. They contain
many provisions which appear to contemplate a requirement of "total
satisfaction" on the part of Devreal and its lawyers in documentation still to come
and a full right of Devreal to withdraw upon grounds rendering "its completion
undesirable". These and other terms suggest a provisional character for the letter,
lacking the precision, completeness and certainty normally found in a legally
binding promise to provide "full funding" in a multi-million dollar transaction;
2. Mr Pearson, at least, on behalf of the respondents, had been engaged in a
number of property developments. He would have known, and the other
respondents would therefore have known, of the detail typical of security
documents, mortgages, charges, options etc. The parties, as at 21 September
1988, would have been aware that their solicitors would have to negotiate the
detail of such security documents. Upon that detail there would be numerous
opportunities for legitimate differences of opinion. One security document
tendered contained 45 different clauses. Even allowing that many of them would
URJ | CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (kirby P) 17
be standard, some particular provisions could easily give rise to disputes. So
much would have been plain to the parties on 21 September 1988 if they had
turned their attention to it. Every person engaged in property development would
know (so it was said) that funds are not actually handed over until security
documents are completed. Even if such documentation was not a pre-condition
to liability, its necessity (as the parties would have realised) argued against an
intention to be bound where and when, before the documents were settled and
agreed;
3. On its face, the Devreal letter included only the principal terms of the
proposed "arrangement" between the parties. The reservation to the "total"
satisfaction of Devreal and its lawyers did not provide an independent arbitrator
who could resolve differences and fill in blanks. No reference was made to "usual
documents". No independent means was provided to settle disputes over terms
which caused later disagreement. Instead, one party only, the financier, reserved
to itself and its lawyers the necessity of "total satisfaction" and an unqualified
"right to withdraw the facility"; and
4. The right to withdraw the facility "should anything transpire that renders its
completion undesirable" was reserved by Devreal and, by inference, therefore,
also by the appellant. It is a commonplace that financiers operate in a financial
market which is subject to the swings of economic circumstances. So much, it
was argued, would have been known to the respondents, at least, by inference,
because Mr Pearson had extended experience in property development.
Accordingly, when economic circumstances changed, it was entirely normal that
the appellant would wish to reconsider its position. It was perfectly regular that
it should seek to improve its equity and to increase the price of its finance. This
was particularly so because the costs had increased beyond those contemplated
on 21 September 1988. Even upon the terms of the Devreal letter, the respondent
was not committed to extend "full funding" without documentation. It at was
entitled to have total satisfaction in the documentation provided and to withdraw
the facility should anything transpire which rendered its completion
"undesirable". This, in effect (so it was said) was what it had done.
As against these considerations, the respondents pointed to a number of
features of the "arrangement" which tended to confirm an intention to contract
and the achievement of terms which were sufficiently certain for the law to
enforce them:
1. The background to its acceptance of the Devreal letter demonstrated that the
appellant was keen to get the respondents' business. So much was even stated by
Mr Anderson who said:
"We want to lock you in so you dont go back to Devreal."
"Locking" in is the language of obligation. The conversations found by Cole
J, leading to the acceptance by the appellant of the Devreal letter also contain
language of promise. If all that had been involved as a "moral obligation" it
would seem curious to have celebrated it with drinks and to have promised a
letter committing the appellant to "full funding". The repetition of that promise
and the constant reassurance that the respondents need not be concerned because
the "deal" was "done" represented further evidence of obligation and
commitment;
2. Although the transaction envisaged a multi-million dollar facility, the
evidence of the Devreal letter (and other evidence of a letter from the Macquarie
Bank Limited) indicated clearly enough that this was the way in which, in the
world of finance, facilities of this magnitude are offered and accepted. In virtually
18 UNREPORTED JUDGMENTS
every case, such facilities contemplate further security documentation. If the law
were to withdraw its support from the enforcement of such promises, given and
accepted, a dangerous divergence would arise between legitimate commercial
expectations and legal protection;
3. As a further indication of the intention of the parties that they should be
legally bound by what they agreed on 21 September 1988, they specifically
concurred in the inclusion of a $50,000 discharge fee. This was designed to
provide a disincentive to the respondents going back to Devreal and to "lock
them in" to the appellant. It seems unlikely that, had the respondents in fact
returned to Devreal, that the appellant would have waived or ignored its claim on
this penalty. At least, no evidence was given for the appellant to suggest that it
would or to demonstrate that the penalty had no effect;
4. The discussion between the respondents and Mr Anderson about the
authority which he and Mr Bembrick enjoyed had no point except as it related to
the authority to bind the appellant. But binding the appellant is a matter of legal
obligation, not mere moral commitment. By exploring the respective authority of
Messrs Anderson and Bembrick, the respondents were disclosing their concern to
secure a legally enforceable right. By asserting his undoubted authority, Mr
Anderson was responding affirmatively to this inquiry. He did not say that,
although he had the authority to bind the appellant, its actual obligations would
not arise until the security documents were agreed. He simply made a "deal" and
asserted his right to do so on behalf of the appellant; and
5. The breakdown of the "arrangement" between the parties did not arise
because of any uncertainty in the Devreal letter, nor from the failure to agree on
any particular term of a security document proffered to give effect to that letter.
It was not as if the appellant or its lawyers failed to have "total satisfaction" in
the documentation designed to give effect to the "deal". Instead, as Cole J found,
the appellant continued to string the respondents along. Ultimately, it simply
changed its policy. Thus, it was not uncertainty of the commitment which
occasioned the dispute. The amount of the loan was clear. So were the interest
rates. So were the participation fees. The basic obligations assumed by the
prospective parties were clearly spelt out in the Devreal letter which the
appellant, with modifications agreed to by the parties, accepted. The appellant did
not even purport to act on the material adverse change clause. It did not withdraw
the facility citing anything which had transpired which rendered "its completion
undesirable". Instead, as found by Cole J, it prevaricated, repeatedly made false
promises that a letter for "full funding" would follow and only later announced
that it had changed its policy.
A shift in the approach of the law to the problem that is presented in this case
can be seen by contracting May and Butcher Ltd v Ring [1934] 2 KB 17n with
more recent English authority collected in D W Greig and J L R Davis, The Law
of contract, Law Book Co, 1987, 379 and J Paris, Making Commercial contracts,
BSP Commercial Books, Oxford, 1988, 30. Young J in Corpers (to 664) Pty Ltd
v NZI Securities Australia Ltd (1989) ASC #55-714 at 58-415 citingGreig and
Davis, has suggested that:
"... commercial pressures have moved commercial courts in The last 50 years
from that was logically correct to what is realistic. The logically correct view
reflected in such cases as May and Butcher Limited v King... so that if parties did
not direct their minds to vital terms of their contract, there was no contract. This
being a commercially unrealistic point of view, the judges in England were
within a few years made to reconsider the matter and the view was finally taken,
URJ | CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (kirby P) 19
as expressed by Williams J in York Air Conditioning and Refrigeration
(Australasia) Pty Ltd v The Commonwealth (1949) 80 CLR 11 at 26 that if the
Court:
"... comes to the conclusion that parties intended to make a contract, it will if
possible give effect to their intention no matter what difficulties of construction
arise.""
There are, of course, limits. They arise where, to an unacceptable extent, the
parties have themselves failed to agree upon essential terms. See Biotechnology
Australia Pty Limited v Pace (1988) 15 NSWLR 130, 133; ANZ Banking Group
Ltd v Frost Holdings Pty Limited [1989] VR 695; noted (1991) 65 ALJ 59. The
matter debated in this Court is not beyond argument as the elements in the
evidence listed by the parties clearly indicate. I remind myself that the intention
to enter into legal relations is to be determined not by reference to the actual
intentions of each party but by reference to what each was reasonably entitled to
conclude from the words and attitude of the other. Cf McCutcheon v David
MacBrayne Limited [1964] 1 WLR 125, 128 (HL). See also Codelfa
Construction Pty Limited v State Rail Authority of New South Wales (1982) 149
CLR 337; Summit Investment Inc v British Steel Corporation [1987] 1 L1 L Rep
230, 233 (CA); Australian Broadcasting Corporation v XVIth Commonwealth
Games Limited (1988) 8 NSWLR 540, 549. As pointed out in the lastmentioned
case, it is the obligation of Australian courts to have regard to the commercial
circumstances surrounding the exchange of communications and to the subject
matter of those communications. Allen v Carbone (1975) 132 CLR 528, 531f.
See also R Lewison, The Interpretation of Contracts, Sweet and Maxwell,
London, 1989, 1.02.
Many of the considerations which must be taken into account in deciding cases
such as the present are collected by me in my reasons in The Coal Cliff Collieries
Pty Ltd Anor v Sifehomo Pty Ltd and Anor, Court of Appeal, unreported, 5 July
1991. I will not extend these reasons by repeating what I said there.
In the result, I have not been persuaded that Cole J was wrong to conclude that
the appellant and the respondents by their agreement on 21 September 1988
intended to enter into legally binding relations. Nor am I persuaded that his
Honour was wrong to reject the contention that the terms of such agreement were
so uncertain that the law would not enforce it. Whilst it is true that there was a
clear contemplation that numerous security documents would be required to flesh
out the agreement which the parties there made, I consider that these were, in the
circumstances, of the kind contemplated by the first class in Masters v Cameron.
To the extent that differences arose upon the terms of the documentation
necessary to give effect to the binding promise, a formula was provided by which
the "total satisfaction" of the appellant and its solicitor would determine the
matter. Cf Godecke v Kirwin (1973) 129 CLR 629, 641f. This would not mean
that the appellant, as one party to the contract, would be at liberty to insert any
provision whatever. The satisfaction, total or otherwise, was limited to
"documentation" of the agreement already reached. I believe that this is the kind
of formula which courts will accept as machinery to resolve uncertainties. Cf
Axelsen v O'Brien (1949) 80 CLR 219, 225. To the extent that total satisfaction
was unreasonably withheld, a court would itself be able, in a matter such as a
security document, to settle the appropriate terms of a conveyance, lease,
mortgage or other instrument by which the contract was to be completed. It
would do to, normally, by referring the matter to a Master. See Charalambous and
Another v Ktori [1972] 1 WLR 951, 953 (Golding J). Doubtless in the instant
20 UNREPORTED JUDGMENTS
case, had such disputes arisen, they would have been resolved by reference to the
Operating Procedures Manual of the appellant, which was brought to Court on
subpoena but not tendered in the way the case developed.
These facilities provided in this case adequate means of resolving disputes
about the machinery documentation necessary to give effect to the agreement of
the parties achieved on 21 September 1988 and substantially set out in the
Devreal letter which the appellant accepted.
Their availability distinguishes the case from such earlier decisions as
Biotechnology Australia Pty Limited v Pace (1988) 15 NSWLR 130; Austotel
Pty Limited v Franklins Selfserve Pty Ltd (1989) 16 NSWLR 582, 587 and The
Coal Cliff Collieries case (above). In none of those cases did the Court have the
relevant expertise for, or means of, resolving the omission in the agreement on
vital terms which the parties had left.
In coming to the conclusion which I have reached, I confess to being
influenced by the same movement towards a more practical approach to this
question as is noted by Young J, approving the analysis of Professors Greig and
Davis. If, as seems obvious from correspondence from three financial sources,
large and important commercial agreements are effected substantially upon short
letters which contain the essence of the parties' promises, it would be a great
misfortune if the law refused to enforce such promises where the business
community organises its affairs upon the assumption that such promises would be
fulfil led and, if necessary, enforced. Such a disparity between commercial
expectations and legal principle should be avoided if at all possible. Cf The
Eurymedon [1975] AC 154, 167 (HL) (per Lord Wilberforce). In the commercial
context, there is a presumption that parties in the position of these parties do
intend legal relations. This presumption does not answer the question whether the
parties actually entered into a contract undertaking. See Kleinwort Benson
Limited v Malaysia Mining Corp Berhad [1989] 1 WLR 379, 383 (CA). What is
required is sufficient evidence of a clear commitment to permit the inference to
be drawn that the parties intended their agreement to be legally enforceable. Cf
Gibson v Manchester City Council [1979] 1 WLR 294, 297 (HL). See also
discussion A de Moor, Intention in the Law of contract: Elusive or Illusory?
(1990) 106 LQR 632, 636.
The better interpretation of the dealings between these parties is that, on 21
September 1988, a reasonable observer would have understood that they had
given a clear commitment and were bound to an agreement. That agreement, in
plain terms, from the letter which was incorporated, obliged the appellant to
provide the respondent Cenepro with "full funding", as stated, for a significant
property development. The conduct of the respondents thereafter was entirely
consistent with that interpretation of the promise of the appellant. The conduct of
the appellant did not initially deny that promise; but rather affirmed it, in the facts
found. In such circumstances, the law holds the appellant to that promise. Belated
endeavours to reinterpret or qualify that promise should be rejected. I consider
that this is the more commercially realistic conclusion. That opinion has brought
me to the same result as Cole J reached.
Misrepresentation and estoppel
The foregoing opinion sustains the judgment in favour of the respondents and
Cole J's approach to their claim for relief, by way of their entitlement to damages
for breach of the contract found. The conclusion obviates the necessity to explore
at length the alternative bases upon which the respondents sought either to claim
against the appellant (under the Trade Practices Act) or to fend off its claim for
URJ | CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (kirby P) 21
recovery from them (by estoppel). The respondents would be entitled to secure
that measure of relief most beneficial to them. I did not understand them to argue
that if they succeeded in contract, and recovered damages under that head, they
additionally or alternatively sought relief under s87 of the Trade Practices Act or
to prevent damage being suffered to them by the unconscientious conduct of the
appellant. See The Commomwealth v Verwayen (1990) 170 CLR 394 and
Lorimer v State Bank of New South Wales (above). I will, nevertheless, note
briefly the appellant's arguments in regard to these heads of claim.
So far as the claim for relief on the basis of s52 of the Act is concerned, Cole
J found that the evidence made it clear that the appellant:
"\.. did not intend to, and did not in fact, honour the representation." This was
the representation to provide full funding to the respondents made at the meeting
on 21 September 1988, including by the acceptance of the Devreal letter, and
repeated thereafter by Mr Bembrick, including on 23 September 1988 when the
promised letter Containing the confirmation of "full funding" was not
forthcoming.
The appellant argued that Cole J had erred in attributing to the appellant the
conduct of Mr Bembrick. Even if his conduct was misleading and deceptive or
likely to mislead and deceive, he was not authorised to make representations and
the respondents were aware of this from the alert they received from Devreal's
broker. This argument has no merit. There was no contest but that Mr Anderson,
as State Manager for the appellant had authority. After the meeting on 21
September 1988, it was open to reasonable inference that Mr Bembrick's
representations were made in furtherance of the "arrangement" then made by the
appellant with the respondents. Accordingly, whatever had been the position
before that date the representations after that date were made with authority. No
evidence was given for the appellant to gainsay this conclusion.
Then the appellant contended that Mr Anderson's representations had to be
construed as they would be by a reasonable person in the position of the
respondents in the relevant context. From this it was argued that the
representation of "full funding", in terms of the Devreal letter, amounted to a
representation "subject to formal contract". For the reasons already stated, this
argument cannot be admitted as it was not the way in which the appellant
conducted the trial. As Cole J's treatment of this issue again demonstrates, the
appellant's case at trial was simply that a letter would be forthcoming, and it
never was. This argument was rejected, rightly in my view, as lacking
commercial reality.
Then the appellant argued that the respondents would know that they could not
rely upon any such representation as was made to them without agreement on the
relevant formal documentation. Being subject to documentation which required
the total satisfaction of the appellant and its solicitors, a reasonable person in the
position of the respondents would not have been misled by an "in principle"
commitment to "full funding". Such a person would know that such a
commitment was always subject not only to documentation but to the vicissitudes
of the economy, particularly in the case of a facility for $6.5 million involving the
acquisition and mortgage of land.
This argument can be rejected upon the same basis as the equivalent argument
by which the appellant sought to defeat the claim in contract. There was no clear
specification that the agreement on 21 September 1988 was provisional only. In
the words used, and in what the parties thereafter did and said, it was clear that
22 UNREPORTED JUDGMENTS
the promise of full funding was made in order to get the respondents committed
to the appellant so that they would not return to Devreal which had offered them
such a commitment.
The appellants next argued that they had never refused to provide funding.
They had made fourteen separate offers of funding, each of them adjusted to the
circumstances of the time, the equity of the respondents and the economic
situation generally. This may be so. But, as Cole J found, the offers, successively
made, fell short of the promise of "full funding". That is what the appellant,
through Messrs Anderson and Bembrick, represented to the respondents they
would receive. Cole J concluded, by reference especially to internal memoranda
but also to the whole conduct of the appellant and its officers, that it had never
intended to provide "full funding". It did not so intend when it agreed as it did
on 21 September 1988, and this despite the use in the Devreal letter which it
adopted of that very phrase.
The respondents did not have to go so far as to establish that the
representations made on behalf of the appellant were false when they were made.
It was enough, for the respondents to succeed under s52 of the Act, to establish
that when it made its representations, the appellant did not have reasonable
grounds for making them. See the Act, s51A. The appellant complained that a
case amounting to fraudulent misrepresentation had not been pleaded, as it
should. It urged that, at worst, the facts simply supported a conclusion that it had
changed its policy. Such a conclusion fell far short of positive deception at the
time the promise" of "full funding" was made. My own interpretation of the facts
differs somewhat from that reached by Cole J. The internal memoranda casting
doubts upon the viability of the respondents as borrowers did not appear until
many months after the representation on 21 September 198B that "full funding"
would be provided. If necessary, I would prefer to conclude that the appellant, at
that meeting did intend to provide full funding. But it rapidly went cold on the
idea. And then, instead of frankly informing the respondents of the change of
policy, continued, through Mr Bembrick, to spin the respondents along with
what, by then, was the false promise that full funding would be afforded and
confirmed by the much delayed letter. Such prevarication and lack of candour
may be reprehensible. But it is not clear that they amounted to a deliberately false
representation.
In view of the conclusion which I have reached on the claim in contract, it is
not necessary for me to resolve this issue. The relief to which the respondents
would be entitled under the Trade Practices Act involves the application of the
measure of damages applicable in tort. Cenepro would be thus entitled, if it
succeeded under the Act, to be put in the position that it would have been in if
the representation of full funding had not been made. See Gates v The City
Mutual Life Assurance Society Limited (1986) 160 CLR 1, 12f. However,
although the respondents never abandoned their claim to relief under s87 of the
Trade Practices Act, I will confine my attention to the relief afforded them by
Cole J. This was in contract.
I can adopt a similar approach to the challenge to Cole J's finding that the
appellant was estopped from denying that it was bound to provide full funding to
Cenepro. Because I have concluded that the respondents were entitled to succeed
in contract, it is unnecessary to explore the appellants' submission that an
estoppel cannot arise which would prevent a party from denying the existence of
an "agreement" which was not a legal agreement at all. Cf Austotel Pty Limited
and Anor v Franklins Selfserve Pty Ltd (1989) 16 NSWLR 582, 584. If, as I have
URJ | CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (kirby P) 23
found, the contractual obligation was proved, it is unnecessary, in the way the
respondents presented the appeal, to explore the alternative relief to which they
would be entitled to prevent unconscionable conduct and to do justice between
the parties. See Verwayen, (above) and Lorimer (above). Cf Amalgamated
Investment Property Co Ltd (In Liq) v Texas Commerce International Bank Ltd
[1982] QB 84, 103.
I see no reason to doubt Cole J's conclusion that an estoppel was proved, given
his Honour's findings of the representations made by the appellant to the
respondents, their reliance on those representations, and their actions, as a
consequence, resulting in detriment to them.
It was open to the respondents to choose any form of relief available to them
upon any basis in law upon which they could succeed. As they have succeeded
in contract, they are entitled, if they so elect, to have their damages assessed in
contract. That was the course adopted by them before Cole J. I therefore turn to
the complaints about what his Honour did in that regard.
The trial Judge's assessment of damages
Cole J had before him a claim for damages based upon loss of the expectation
of profit on the development. He had a cross claim by the appellant for the
amounts owing to it for the sums extended to the respondents upon various
security documents. There was no dispute about the total amount owing to the
appellant in this way. The sum was agreed at $3,284,359.88. From that sum credit
had to be given in respect of the charge enjoyed by the appellant over Mr
Jamieson's bank bills. This credit of $120,309.30 reduced the sum owing to the
appellant to $3,164,050.58. It was in that sum that his Honour entered judgment
on the cross claim in favour of the appellant. That component of the adjustment
of the entitlement of the parties has not been disputed.
Cole J then turned to calculate the amount owing to Cenepro for the breach of
the promise which he had found the appellant had given that company to provide
"full funding" for the Bellevue Hill property development. He had before him a
claim for loss of profits on the development. Most of the reasons given 14
December 1990 are devoted to testing the various hypotheses by which the loss
of profit could be calculated in the events which had occurred. It was
acknowledged that proceeding to the calculating involved making a number of
assumptions about what would have happened if the appellant had adhered to its
contractual promise. To assist him in his task, his Honour had expert evidence
which utilised alternative computer programmes. Into these was fed the data
upon the essential variables from which a profit or loss on the venture would be
derived. His Honour acknowledged the necessity to determine five variables,
acting on the assumption that the appellant had provided Cenepro with "full
funding. These variables were:
1. The date of the completion of the development and sale of the component
parts;
2. The pre-sale of some of the components off the plan prior to such
completion;
3. The value of the development at completion
4. The cost of completing the project, including land consolidation costs,
development expenses, construction expenses and interest and, if, as seemed
likely, those costs went beyond the $6.5 million agreed between the appellant and
Cenepro, whether additional finance would have been obtainable and if so upon
what terms; and
5. Cenepro's ability to raise finance.
24 UNREPORTED JUDGMENTS
As to the date of completion, by reference to the evidence Cole J concluded
that it was probable that Cenepro would have been in a position to complete sales
by 31 March 1990, had the appellant not breached its agreement. By reference to
the evidence of an experienced real estate agent, which he accepted, Cole J
concluded that sales of the units could have been achieved off the plan. This
reinforced his view that settlement of all the sales by 31 March 1990, as
suggested by Cenepro, would have been achieved.
There was a dispute between the experts called for the respective parties as to
the value which would have been placed upon the project on completion and
upon the assumption of sales of all units by 31 March 1990. The appellants'
expert gave an estimation of $10.4 million. Cenepro's expert estimated $11.09
million. Cole J preferred the latter. He did to by reference to unsatisfactory
features of the appellant's witnesses evidence. In the appeal, the appellant did not
challenge the gross realisation of $11.09 million.
There was a similar dispute concerning the costs of construction.
Upon this matter too, Cole J had expert evidence and various quotations.
The figure he preferred was $3.3 million, being the top range of a figure
contained in a report of Mr Fisher, an experienced quantity surveyor, prepared in
February 1989. That report had been prepared at the request of Cenepro for
incorporation in a valuation report requested by the appellant. It was therefore
accepted by Cole J as an estimate:
"\.. which all of the parties relied upon for their commercial purposes in
circumstances free of litigation."
In addition to the acquisition and construction costs, it was necessary to add
various other minor costs, such as for selling, advertising, leasing commissions,
insurance, rates and taxes and sundry expenses. The amounts allowed for these
have not been disputed, most of them being allowed in the sums contained in the
computer programme.
When to the costs of acquisition and construction, the sundry costs were
added, and the resulting product deducted from the gross realisation of $11.09
million as agreed, the result for nett profit was found by Cole J to be $2,740,709.
His Honour rounded this for unforeseen contingencies to $2.7 million. Under the
Devreal letter, as varied by it, the appellant was entitled to 15% of this nett profit.
Accordingly, the residual profit to which Cenepro was entitled, upon these
premises was $2,295,000. Cole J acknowledged that the foregoing calculations
assumed that the project would have proceeded to completion notwithstanding
the cost over-runs beyond the $6.5 million which the appellant had, as found,
agreed to lend.
His Honour had before him evidence led for Cenepro from Mr Leon Bovaird.
He was an person with an extensive background in financial organisations,
having for a time worked with Equity Pacific Finance Limited. He gave evidence,
which Cole J accepted, that it was his experience that financiers, faced with cost
over-runs, provided additional finance to enable the development to be completed
and sold as a completed project. Only by doing so did they avoid the low returns
invariably involved in partly completed projects. Faced with an absence of
contrary evidence from the appellant, Cole J concluded that on the balance of
probabilities the additional funds required to complete the project could have
been obtained on the same terms as the appellant had agreed in the modified
Devreal terms.
URJ | CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (kirby P) 25
The result of these calculations led to the orders which Cole J then made. The
parties were agreed that the value of the land acquired by Cenepro and still held
by it was $1.5 million. It was therefore necessary for credit to be given for this
substantial asset. When from the residual profit of $2,295,000 the value of the
land of $1.5 million was deducted, the nett sum owing to Cenepro as its final loss
of profit on the development, which it would have recovered had it gone ahead
as agreed, was $795,000. Cole J then concluded that Cenepro was entitled to
recover as damages this sum together with the amount of principal and interest
owing on the existing loans.
It was in that way that Cenepro recovered against the appellant judgment in the
sum of $4,079,359.88. The judgment on the cross-claim for $3,164,050.88
represented the amount agreed to be recoverable by the appellant under the terms
of the mortgage without taking into account the sum of $120,309.30 on Mr
Jamieson's bank bills.
The appellant mounted two attacks on these orders. The first contended that
Cole J had adopted the wrong principle in calculating Cenepro's damages. The
second, whilst accepting his Honour's approach, challenged a number of the
assumptions upon which he reached his final figure.
The cost of securing finance
The primary argument for the appellant was that the proper measure of
damages for breach of contract was any additional cost of finance which Cenepro
suffered by reason of the failure of the appellant to provide it with the "full
funding" which it was found it had promised. The appellant argued that, by 5
December 1988, or alternatively by January 1989, Cenepro was fully aware that
the appellant would only proceed to provide funding on a stage by stage basis.
At least by that time, the earlier hopes of the provision of a letter would confirm
the earlier promise of "full funding" must have faded in the mind of any
reasonable observer.
The appellant pointed out that the respondents themselves must have come to
this conclusion. Certainly, Mr Pearson gave evidence that by January 1989 it was
clear to him that the appellant had repudiated "whatever assurances they had
given". The appellant relied upon the respondents' approach to the Macquarie
Bank. A letter from that bank was admitted in evidence. Bearing date 23 March
1989, addressed to Cenepro and written to Messrs Jamieson and Pearson, it
confirmed that bank's:
"\..interest in considering an application for a Facility to be structured as
follows:" The facility envisaged the provision of an amount of $7,650,000 to
Cenepro to provide funds to meet the cost of the Bellevue Hill development. It
is worth noting (by contract to the Devreal letter which the appellant, with
modifications, accepted) that the letter from the Macquarie Bank bore the stern
warning at its head:
"please note that this letter does not represent confirmation of formal approval
of a facility. macquarie Bank Ltd reserves the right to amend, add or delete any
terms or conditions contained in this letter. This letter does not impose an
obligation on Macquarie Bank Ltd. A formal letter of offer containing all terms
and conditions to be forwarded once formal approval has been obtained."
Neither this letter, nor any other, resulted in a firm commitment of a financier,
other than the appellant, to take over the financing of the Bellevue Hill
acquisition and development. Cenepro was a shelf company. Various attempts
had been made to secure a joint venturer for it. The attempts by the appellant
itself had come to nothing. The economy had, after the promise of 21 September
26 UNREPORTED JUDGMENTS
1988 become more difficult. The very fact that the appellant, unlawfully as it has
been held, endeavoured to extricate itself from its promise and to add further
terms and conditions, provides material from which Cole J was entitled to
conclude that the possibility of obtaining alternative finance, equivalent to that
which the appellant had promised, was insignificant. When the respondents
witnesses were cross-examined, it was not put to them for the appellant that they
could have obtained alternative finance. Cole J specifically found that in the
circumstances in which they found themselves the respondents had no real
alternative but to go along with the successive proposals of the appellant. The
suggestion that Cenepro should have sought out and obtained alternative sources
of finance comes rather unconvincingly from the appellant, given that at no stage
did it make that suggestion to the appellant. Its submission amounts to a
contention that Cenepro failed to mitigate its loss because it could have obtained
funding elsewhere and there by reduced its damages. The onus of establishing
such a contention lies upon the appellant.
In support of its contention on this issue, the appellant relied on Head v Kelk
(1963) 63 SR (NSW) 340.
There it was held that, under a contract for the loan of money, where the breach
alleged was the acceleration of the demand for repayment contrary to the terms
of the loan, the only contemplated loss suffered by the plaintiff was his loss, if
proved, occasioned by the raising of a loan of similar amount on less
advantageous conditions and the expenses of doing so where he had been forced
to repay the loan earlier than he otherwise would. However, that finding was
offered in a context quite different from the present. The loan in Head was to
provide housing and a settled income to the borrower. The loan was for 12,000
pounds. None of the difficulties would have stood in the way of raising an
equivalent sum as would have been presented to Cenepro in this case. There was
clear evidence before Cole J of the difficulties typically experienced in a half
completed development in raising alternative finance. The very difficulties which
the appellant experienced in its numerous attempts to secure a joint venturer
speak eloquently of the obstacles of belatedly securing alternative finance. The
viability of the project had, by reason of the delay, become quite marginal. This
is plainly demonstrated by the nett residual profit ultimately found by Cole J and
challenged in this appeal. In there circumstances, it is reasonable for Cenepro to
say that, if the appellant suggested that it should have sought alternative funding
elsewhere, it neither said so at the time, nor did it call evidence at the trial to
establish that it would have been as possible to obtain it as it now contends.
It was open to Cole J to conclude that, realistically, no other source of funds
was available to Cenepro in early 1989 other than from the appellant. In such
circumstances it was open to his Honour to approach the calculation of damages
as he did: seeking to ascertain the losses which flowed from the breach of
contract. In the United States it has been held on a number of occasions that so
long as a financier has notice of the purpose, for which funds were desired by a
borrower, it will be liable for damages caused by the borrower's inability to carry
out its purpose if the performance by the financier of its promise would have
enabled the borrower to do so. See eg W C Shepherd Co Inc et al v Royal
Indemnity Co (1951) 192 F 2d 710, 717; Avalon Construction Corp v Kirch
Holding Co Inc (1931) 175 NE 651, 653; Bond Street Knitters Inc v Peninsula
National Bank (1943) 42 NYS 2d 744: Here the borrower's losses included the
obligation to pay the loans, secured in futility, from the appellant, together with
the nett loss of profit which would have been derived by Cenepro if the appellant
URJ | CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (kirby P) 27
had adhered to its promise. I see no error in the general approach which Cole J
adopted to calculating the respondents' loss of profit. I agree with what Mahoney
JA has written on this general point.
Specific complaints on damages calculations
This conclusion leaves only the particular heads of complaint by which the
appellant attacked a number of the assumptions upon which Cole J's conclusions
had been based. Specifically, the appellant contested his Honour's conclusions
that:
(a) The construction of the development would have been completed by
mid-February 1990;
(b) The registration of the strata plan would have been achieved by 31 March
1990;
(c) The cost of construction was $3.3 million; and
(d) The strata units would have been sold in their entirety by 31 March 1990.
The thrust of the attack on items (a) and (b) rested upon the contrast between
the timetable of dates assumed by Cole J and the evidence of the actual date upon
which the event occurred. The contrast was advanced in order to establish that,
even had the appellant complied with the contract as found, the programme of
acquisition and development lagged a long way behind that assumed by Cole J.
It thus took the respondents into a period when, on the evidence, the costs of
construction were higher and the economic downturn threatened the prospect of
sale of the units, whether on the plans or otherwise. As these variables affected
the calculation of nett residual profit, it was legitimate for the appellant to take
the Court to the detail of the evidence in order to test the factual premises upon
which Cole J's conclusions rested. The utilization of a computer programme does
not improve the calculation of damages if the factual variables fed into it as data
are not sustained by the evidence.
The following table was relied upon by the appellants:
" Event Found Actual
Lodgment of development application 8.8.88 8.8.88
Development consent Dec 88 14.3.89
Lodgment of building application Jan 89 9.6.89
Building consent Apr 89 3.11.89
Commencement of construction 1.5.89 Nil
Completion of construction mid-Feb 1990 Nil
Approval of stata plan 31.3.90 Nil
Settlement of Sales 31.3.90 Nil
The appellant argues that the delay in securing development consent was
occasioned by the difficulty which the respondents experienced in securing the
written consent of the tenant of the fruitshop to vacate his shop. The evidence
showed that at one stage the tenant asked for $100,000 consideration. Later he
even asked for $280,000. Originally, the local council stated that it would not
give development consent until the written consent of the tenant was produced to
it. Later, it agreed to proceed upon the basis of a promise by Cenepro that it
would treat the tenant fairly. But the point made by the appellant was that it was
not responsible for the delay occasioned by this controversy. It disputed that the
promise of "full funding" included moneys to be paid to the tenant of the fruit
shop. No item for that purpose had been specifically disclosed in the respondents'
28 UNREPORTED JUDGMENTS
feasibility proposal. Nor was it allowed for in the application for finance
presented by the respondents to Devreal, which resulted in the Devreal letter.
On the other hand, whilst acknowledging in cross-examination that the
appellant would be "expected" to act upon his statement that "there would be no
problem with any of the tenants", Mr Pearson asserted that the appellant was
"fully aware of the situation". By this I infer that it was "fully aware" of the
difficulty being experienced in securing the consent of the tenant of the fruitshop.
It was open to Cole J to infer that it was the lack of funds provided by the
appellant to Cenepro which occasioned the somewhat languid dealing with the
fruitshop tenant and the Council. Had "full funding" been available, as promised,
it is relatively easy to infer that Cenepro would have accelerated its efforts to
obtain development consent upon just the kind of undertaking which was later
offered and accepted by the Council. In reaching his view, Cole J took into
account the evidence of the average time taken to obtain such building approvals.
I do not believe that this Court would be entitled to disturb his Honour's
conclusion that:
"Tf Custom Credit had honoured its contract, greater diligence would have
been exhibited in pursuing Woollahra Council to issue the building approval
more promptly than in fact it did after lodgment."
The appellant then attacked Cole J's conclusion that the cost of the
construction would have been $3.3 million - a figure which he based upon the top
range estimated by a quantity survey, Mr Fisher, called for the appellant. The
appellant's complaint was that this estimate was based upon sketch plans, not
fully detailed, which were the only plans available to Mr Fisher when he gave the
estimate. Subsequently, those plans were amended. Two quotations were
obtained from builders who received the amended plans. Mr Fisher made a later
estimate of the construction costs of $4.078 million based upon one of the two
builders' quotations (Sid Greaves Shopfitter). However, Cole J rejected this
adjustment. He did not accept Mr Fisher's evidence. He rejected it as nothing
more than an adaptation of the Sid Greaves quotation.
Cole J had before him the evidence of Mr Pearson (whole testimony on
liability he had accepted unreservedly). He asserted that the estimate given by Mr
Fisher in February 1989, before litigation had commenced, provided a proper
estimate of the building costs associated with the project. Mr Pearson was an
architect with experience in property development. The February 1989 estimate
by Mr Fisher had been provided on the basis of the commencement of
construction on | June 1989 with costs escalating at 10%. The evidence showed
that the respondents were seeking a fixed price tender to protect them against
increases in construction costs. By adopting the upper limit expressed in Mr
Fisher's February 1989 estimate, Cole J provided a margin for Cost increases
resulting from amendment of the plans. Mr Fisher's report of February 1989 was
an unbiassed contemporaneous opinion of likely costs upon which it was
intended that the parties should rely. The later figures secured for the litigation
were unaccepted quotations which envisaged a commencement date many
months after that which Cole J found upon the hypothesis that "full funding" had
been provided to Cenepro.
In these circumstances, I do not believe that Cole J was wrong to revert to Mr
Fisher's earlier estimate. As his rejection of Mr Fisher's later "recantation" in
evidence depended in part upon his rejection of that evidence (and implied an
opinion that it lacked impartiality), this Court would not be authorised to reverse
such rejection. In any case, the reasons given for returning to the top of the range
URJ CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (Mahoney JA) 29
estimation at the time the project was viable are convincing. His Honour's
conclusion in this regard should not be disturbed.
That leaves finally the appellant" complaint about Cole J's conclusion that the
units in the development would be pre-sold "off the plan" during construction
(issue (d)). That finding depended, as the appellant acknowledged, upon the
evidence of two witnesses, Messrs Meredith and Robingon. The appellant called
their evidence "speculative". It pointed out that Mr Meredith, in his written
reports, had allowed a period of sale after completion of construction. However,
that left the evidence of Mr Robinson. He was the proprietor of the Bellevue Hill
real estate agency which carried on business close to the development. He gave
evidence that it was a project well able to be sold off the plan. He testified to a
number of enquiries regarding the development. Cole J stated that he was
impressed by Mr Robinson as "an experienced real estate agent".
He accepted his evidence. That evidence included the following passage:
"Well, we received enquiries up there. Bellevue Hill is a different area to a lot
of other areas. Bellevue Hill - the top end of Bellevue Hill, which are the areas
we are mainly concentrating in, they have a lot of older style units there. There
are very few modern units. When they do come up they do sell well. Bellevue
Hill, as everyone knows, has a very high Jewish fraternity, with quite a few
synagogues in the immediate vicinity with level walks. The Bellevue Hill area is
an older aged group area where we have a lot of home owners whose kids have
grown up wanting to move out of their house, get into a security unit, less
maintenance and looking for units." Upon the basis of this evidence it was
certainly open to Cole J to conclude that the sale of all units could have been
achieved off the plan. Upon the timetable which his Honour hypothesised this
sustained the conclusion that the sales would have been completed by 31 March
1990. It permitted the calculation of the profit which Cenepro would have made
upon those assumptions.
Conclusions and orders
In the foregoing reasons I have dealt with those grounds of the notice of appeal
which were argued before the Court, either in written submissions or in oral
argument. I will assume that those grounds of appeal which have not been the
subject of argument are not pressed. Within the matters argued none of the
criticism of Cole J's order has been sustained. The cross appeal was filed
defensively. No significant additional time was taken in disposing of it. The
orders which I would therefore propose are: 1. Appeal dismissed with costs; and
2. Cross appeal dismissed. No order as to costs.
Mahoney JA I agree with the judgment of Kirby P. In view of the arguments
which have been submitted I shall add some observations of my own upon two
matters: the uncertainty issue and the issue of damages.
1. The uncertainty issue:
I agree with the conclusions of Kirby P and of Clarke JA that the parties,
during the conversation with Mr Anderson on behalf of the defendant, reached an
agreement and that agreement was sufficiently certain to constitute a legally
binding contract.
The parties were, I think, agreed as to what the plan of the plaintiffs was for
the development of the relevant land and as to what the defendant should do in
and about the financing of that plan. I do not desire in this regard to add to what
has been said by Kirby P and Clarke JA.
30 UNREPORTED JUDGMENTS
The parties, in my opinion, thought that what they had done constituted a
legally binding contract. I do not mean by this that subjectively Mr Anderson or
Mr Pearson adverted precisely to the legal requirements of contract or the
application of those requirements to what had been agreed. But it was, in my
opinion, their belief that what they had done by way of agreement was such that
neither party could, at will, legally withdraw from it. Each understood, I think,
that the other was "locked in" for this purpose.
But such a belief by the parties does not as such mean that their agreement is
valid and enforceable as a contract. And it is to this matter to which, in the main,
the submissions have been directed in this appeal. The issue to be determined is
whether, though there was an agreement, it is not enforceable as a contract
because of uncertainties affecting it. The defendant has submitted that the present
agreement is affected by such uncertainty.
The law should not hold uncertain a contract which the parties believe to be a
valid and enforceable contract unless it is necessary to do so. To say that is to add
little to the store of legal knowledge: what is to be determined is, of course,
whether it is necessary to do so. But to say it is to help in focusing upon what is
the issue which must be determined. It helps because it leads to the consideration
of what the law should or should not see itself as able to do in rendering certain
that which allegedly is too uncertain to be enforced.
As has been pointed out: see, eg, Greig and Davis "The Law of Contract" at
363 et seq; there are various kinds of uncertainty. A contract may be uncertain
because there has been no agreement at all: there is merely an agreement "to
agree": Masters v Cameron (1954) 91 CLR 353 at 362-4. It may be uncertain
because the agreement arrived at leaves undetermined one of the terms which the
law requires to be specifically agreed in order that the contract be valid and
enforceable: there may, for example, be no agreement on the date of the
commencement of the term of a lease: see Halsbury Laws of England, 4th ed, Vol
27, par 204. One of the terms of the agreement may contain words which are so
vague as to be for this purpose meaningless: a promise to pay "a substantial cut
on all work done" has been held to be such: Stevenson v Ellis (1912) 29 WN
(NSW) 52; cf a different view of "pay you handsomely" in Kina v Ivanhoe Gold
Corporation Limited (1908) 7 CLR 617. Or one of the terms of the contract may
assume something which does not in fact exist: it may provide for "the usual
terms" where there are in fact no usual terms: see G Scammell and Nephew Ltd
v Ouston (1941) AC 251, eg, at 268-9.
In the present case, the attack upon the certainty of the agreement as a contract
is not limited to one particular matter. A number of submissions have been made:
these are referred to in the judgments of Kirby P and of Clarke JA. I desire to add
some observations of my own in relation to two of these matters: provisions
providing for documentation by third parties; and the settlement of the detail of
obligations agreed upon in general terms.
Reference was made in the agreement made with the Davreal company for the
agreement to be the subject of "documentation" and for such documentation to
be "subject to Davreal and its lawyer's total satisfaction". Such a provision does
not, in my opinion, mean that necessarily there is no binding ana enforceable
contract or that there is no agreement because that which is agreed is, eg, "an
agreement to agree". The significance of provisions of this kind must be
determined in the context of the surrounding circumstances of the particular
agreement. A provision that the parties or their lawyers shall produce
documentation obviously involves that a discretion or a choice will be exercised,
URJ CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (Mahoney JA) 31
for example, in the selection of the terms to be embodied in the relevant
documents. But that discretion or choice may be of at least two kinds: I shall
describe them as operative and ministerial. It may be the intention of the parties
that what the third parties are to do in the process of documentation will involve
the creation of or the variation of the obligations of the parties: that involves an
operative discretion. In other cases, the intention to be drawn from the transaction
is that the terms chosen to constitute the documents are not to vary but to give
effect to the obligations upon which the parties have already agreed: that involves
merely a ministerial discretion. There will no doubt be, in this second case, a
discretionary choice between different kinds of provisions: thus, in the
documentation of a provision requiring a party "to give an equitable charge
over...", there may be a discretionary choice by the lawyers as to the
circumstances in which the equitable charge is to crystallise or the receiver is to
be appointed. Experience shows that provisions of this kind may take many
forms and many pages may be used in their documentation. But the fact that there
is no universally accepted clause of this kind does not mean that, unless the
precise terms of such a clause is agreed upon by parties in advance, a clause in
an agreement providing for "an equitable charge over..." will result in a contract
too uncertain to be enforced.
If necessary, the court will settle the documentation necessary to give effect to
the parties' intention. It is not beyond the law's capacity to do so.
Therefore, the fact that such a matter is left to documentation in this way does
not necessarily produce the result of uncertainty.
It will not produce that result if, as I have said, the discretion in documentation
is ministerial. Whether it will be so will, as I have indicated, depend upon the
intention of the parties. There may, of course, be cases in which the intention of
the parties was that the discretion was to be not ministerial but operative; in such
cases, there will be no final agreement and so no binding contract. What is this
intention is to be derived from the context and surrounding circumstances and, no
doubt, the nature and significance of the obligations which the documentation is
to detail.
That leads to the second matter to which I have referred. This is related to the
first but, I think, raises a distinct matter, namely, how far the courts can and
should go in formulating the detail of the parties' rights and obligations.
In some cases, the agreement made by the parties may provide for one party
to have a right or be subject to an obligation the terms of which are to be specified
in writing but may make no provision for the settlement of those terms. Thus, in
the present case, it was contemplated in the conversation between Mr Anderson
and Mr Jamieson that the defendant should have "a lien over your bills" and that
Mr Pearson and Mr Jamieson should give a "personal guarantee". And it was
contemplated that there should be a mortgage or charge security given to secure
the finance to be provided for the project by the defendant. It was obviously
contemplated that a document would be drawn for these purposes, but no
provision was made as to who should draw it.
A party taking objection to the certainty of clauses such as these sometimes
asserts that "the law is not capable of" giving effect to provisions of this kind in
that they clearly contemplate that an appropriate document will be drawn and that
it will be in a form going beyond what has been adverted to by the parties or has
been specified in the parties' agreement.
32 UNREPORTED JUDGMENTS
I do not think that the law should be held to be incapable of giving effect to
terms of this kind. In earlier times, it was not beyond the capacity of, eg, the
Court of Chancery to give effect to an agreement for "a marriage settlement" or
"a mortgage". The court would refer to the relevant Master or Conveyancing
Counsel the settlement of the detailed terms of the relevant document. In a decree
for specific performance of a conveyancing transaction, the court frequently
settles documents the terms of which create obligations which the parties have
not, in detail, specified in their agreement. There are, no doubt, matters which are
beyond what a court may do in this regard. But in cases of the kind here in
question many of the matters to be settled are, in the relevant sense, interstitial
and the fact that they impose specific obligations on parties in terms not adverted
to in the agreement does not, in my opinion, mean that the terms of them cannot
be settled in this way.
The law will not, of course, make an agreement for parties where they
themselves have not done so. But where they have made an agreement which
they believe to be enforceable within the law, the courts should not refuse to do
what the parties expected them to do, at least where what is involved is interstitial
rather than substantial.
2. The measure of damages: It is, in my opinion, proper to adopt the "loss of
profits" basis as the basis for calculation of the plaintiffs' damages. There was a
clear breach of the plaintiffs' contract with the defendant. It was a complicated
contract and, as the judgments of the other members of the Court have indicated,
it was not possible for the plaintiffs to obtain alternative finance of the kind which
the defendant had promised to provide. In such a case as this, damages are, in my
opinion, available for the breach of a contract to provide finance.
In such a case, a plaintiff is entitled to be put, by an award of damages, in the
position in which he would have been if the contract had been performed:
Livingstone v Rawvards Coal Co (1880) 5 App Cas 25 at 39; Butler v Egg and
Egg Pulp Marketing Board (1966) 114 CLR 185 at 191. That position was the
position of parties who would have been provided "full funding" in the terms of
the agreement that had been made. It is therefore necessary to ascertain the loss
which the plaintiffs suffered because they were not, by performance of the
contract, put in that position.
The plaintiffs had intended, if that funding had been provided, to proceed with
the development project to which the agreement related. They contemplated that
they would have made profits from the completion of the project. But the law
does not assume, for the purposes of assessing the plaintiff's damages, that that
project would have been completed according to its terms. The cases establishing
the measure of damages require that the injured party be put in the position he
would have been had the promise been performed but no more. Therefore the
plaintiffs in the present case are not entitled to have, as such, the profits which
they would have derived had their plan gone well: they are to be treated merely
as if, by the provision of the agreed full funding, they would have had the
opportunity to make those profits. And the loss which they have suffered and for
which they are to be compensated by damages is essentially the loss of the
advantages of that chance.
In Levi Strauss (Aust) Pty Ltd v Mayne Nickless Ltd (Court of Appeal, 17
December 1976, unreported) I referred at length to the considerations relevant to
the ascertainment of damages for the loss of a chance. I shall not extend this
judgment by incorporating in terms what I there said: I remain generally of the
opinion set forth on pages 4-10 of my judgment in that case.
URJ CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (Mahoney JA) 33
It is, then, necessary to determine the compensation appropriate for the loss by
the plaintiffs of that chance. There is, in my opinion, no single approach which
must be adopted for the purpose of assessing the damages for such a loss. The
court will adopt the mode of calculating the loss which will give the true, or at
least the best, reflex of the plaintiffs' loss: see, eg, in the context of a building
case, the adaptation of the processes for assessment of damages to achieve a just
result in the context of building or repair contracts in Bellgrove v Eldridge (1954)
90 CLR 613 at 616-9.
In some cases, the assessment of damages will best be made by valuing, as
such, "the chance" which the plaintiff would have had if the defendant had
performed its contract. In the present case, that would be the chance of making
profit from the development of the land with the benefit of such finance as the
contract provided for. Chances of this kind and even more contingent possibilities
are capable of valuation: see, eg, Chaplin v Hicks (1911) 2 KB 786; Davies v
Taylor (1974) AC 207 at 220, per Lord Simon of Glaisdale. In other cases, the
appropriate approach may be to calculate the profits which would have been
derived if the plan had been carried into operation according to its terms and then
to discount the amount of profits so arrived at to take account of the contingencies
which, at the date of breach or other the relevant date, affected the chance of the
plaintiffs to make those profits.
This latter process of assessing loss is, in my opinion, essentially the process
adopted in assessing damages in many personal injury cases, eg, for the loss of
the capacity to work. What there is done is, in principle, to determine what,
uninjured, the plaintiff would have done in working at his chosen employment:
the wages to be earned, the period of employment, and the discount for present
value are calculated in conventional ways. And a discount is then applied to take
account of the possibility that, by reason of loss of employment, other accidents,
or the like, the plaintiff uninjured would not have derived such a sum. This is
conventionally seen as a proper reflex of the loss of the plaintiff's capacity or
chance of earning income.
That, I think, is essentially what was done by Cole J in the present case. His
Honour calculated the profits which the plaintiffs would have derived if the
plaintiffs' plan of development had been carried out according to its terms and the
events on which it was posited had occurred as the plan contemplated.
The learned judge then took into account what, conceptually, were the
contingencies apt to affect the carrying out of the development plan, that is, the
contingencies which, as at the date of the defendant's breach of contract, would
have been seen to exist. His Honour examined the main contingencies which had
been referred to in argument, expressed his conclusion as to what would have
been likely to be the outcome of each of them, and arrived at a conclusion as to
the extent to which each of them, so assessed, should be seen to affect the profit
to be derived from the development scheme as the appropriate measure for
assessment of damages in this case. His Honour did not, I think, spell out each
of these matters in detail but what he did involved in principle such a procedure.
The submissions which have been made to this Court in this regard require, I
think, that the matter be spelled out in more detail than it was necessary for the
trial judge to do and that the significance of the various contingencies be
considered.
As I have said, the plaintiffs' contention was that, had full funding been
provided as agreed, the development plan would have been carried out and they
would have earned the profits detailed in their submissions. The defendant's
34 UNREPORTED JUDGMENTS
argument in this regard was that the carrying out of the development plan was
affected by such contingencies that, at the date of the breach of contract and at
the present date, the outcome of the plaintiffs' plan was so uncertain that it was
no proper basis for the assessment of the plaintiffs' damages. It is therefore
necessary to examine the nature of those contingencies. The learned judge took
into account what, conceptually, were the contingencies affecting the successful
carrying out of the plan for development of the land. Those contingencies were
essentially of two kinds: contingencies inherent in the development plan itself;
and contingencies arising from factors outside that plan.
The inherent contingencies: It was recognised by the parties and by the trial
judge that, in a plan of development of the kind here in question, there were a
number of contingencies which might adversely affect the outcome of the
development plan. Thus, for example, the outcome of the plan and the profits
contemplated to come from it would be affected by costs incurred in carrying out
the work and those costs could be affected by, eg, adverse weather, strikes, and
the like. The calculation of profit was, according to the plan, contingent upon the
state of the market for land at the relevant times: it was seen as affected by
whether units in the development could be sold "off plan prior to completion" and
by what would be the market price of units to be sold upon completion of the
development.
Inherent contingencies such as these are, as it may be put, contingencies which
a developer would ordinarily take into account in calculating what would be the
likely outcome of the development. The learned judge, in his judgment in respect
of damages, referred to five matters as the "principal matters" to be taken into
account in this regard. He examined each of them and arrived at conclusions as
to what, absent breach of the contract by the defendant, would probably have
been the outcome of each of them. His conclusion was, generally I think, that the
outcome of these contingencies would not have affected the plaintiffs' calculation
of the profit to be derived from the development programme, at least to such an
extent that the projected profit was an unsafe basis for the calculation of damages.
His Honour outlined, briefly but sufficiently, the outcome of each of the
contingencies. I do not think that he erred in this regard. There are, no doubt,
different approaches to each of the contingencies and different ways of analysing
them but, in the end, the result would, in my opinion, be no different.
The outside contingencies: There were, in addition to those contingencies
inherent in the development programme, other contingencies which might affect
the financial outcome of the development. Submissions were addressed by the
parties to these contingencies.
Factors of this kind potentially affect any development programme. The
programme itself may be sound but the developer may lack, eg, the energy or the
expertise to carry it out according to its terms. Other things may go wrong: in the
present case, the difficulty involved in achieving a consensus with the tenant of
part of the land was an example of this.
It is, I think, important to understand the way in which the evidence relating
to these contingencies was used in the present case. Properly understood, the
defendant's argument was, or at least involved, that, with the benefit of the
knowledge of what actually happened following the defendant's breach, it should
be inferred that, had the contract not been broken, the development programme
would yet not have proceeded as planned and that therefore it is wrong to use the
profits which would have come from the carrying out of the programme as
planned as the basis for assessment of damages. Over-simplified, the suggestion
URJ CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (Mahoney JA) 35
is that, however good the plan, it would not in fact have proceeded because, as
subsequent events have shown, outside contingencies of this kind would have
defeated it.
Such an approach as this raises at least two questions: whether, if full funding
had in fact been provided, what did occur would have occurred; and, if it would
have occurred, how it would have affected the outcome of the plaintiffs'
development programme.
The matter may, I think, be tested sufficiently by considering the delay which
in fact occurred in carrying out the development programme. As Clarke JA has
pointed out, the plaintiffs development programme contemplated that a building
application would be lodged with the council in or about December 1988 or
January 1989 and that building approval would be given within three or four
months from that time. In fact, the application was not lodged until much later.
This, the argument suggested, would have delayed the programme, would have
affected the sale of units "off plan" and would have produced the result that the
units after completion would have been sold on a market more adverse than was
contemplated by the development plan. Therefore, the argument suggested, it
should be inferred that, had there been no breach of contract by the defendant, the
development plan would not in any event have been carried out.
But that, of course, depends, inter alia, upon whether what in fact happened
would have happened if the defendant had provided full funding and otherwise
carried out its contract. The plaintiffs accepted that there were such delays but
contended that those delays resulted from the defendant's failure to provide
finance as it promised to do.
The trial judge, in my opinion, accepted the thrust of the plaintiffs' submission
in this regard. The matter was dealt with in the evidence of Mr Pearson, an
architect and a director of the plaintiff company. In relation at least to the matters
here in question, the learned judge accepted the evidence of Mr Pearson and, in
accordance with established principles, this Court should, I think, accept Mr
Pearson's basic evidence. The conclusions or inferences to be drawn from that
evidence are, of course, for this Court to determine: Abalos v Australian Postal
Commission (1990) 65 ALJR 11.
Mr Pearson dealt with these matters in his evidence and the learned judge
accepted what he said. I shall not extend this judgment by setting out the detail
of his Honour's findings: they appear at pp 2445-8 of the appeal papers. His
Honour's conclusion was:
"The consequence is that the delay in obtaining the development approval was,
in truth, due to Custom Credit's breach, and the delay in finalising building
application plans was also due to Custom Credit's breach. I am satisfied that had
Custom Credit properly honoured its promise made on 21 September 1988,
development consent could have been obtained by December 1988 with the
consequence that building approval could have been obtained by April 1989
permitting construction to commence in May 1989."
In arriving at that conclusion, his Honour referred to the effect of the
defendant's failure to honour its agreement to provide full funding and the
consequences of that. He referred in particular to the fact, as it was suggested,
that "the plaintiff was unable to engage engineering consultants to provide the
engineering input to permit completion of the building application" and that
"additionally during that period Mr Pearson was heavily involved in dealings
with Custom Credit and was not able to attend to the architectural work on the
project". The submission for the defendant suggested that the reason why the
36 UNREPORTED JUDGMENTS
plan was, in the event, not adhered to, was not the unavailability of funding: it
submitted that the plaintiffs could have engaged engineering consultants earlier
than it did notwithstanding that funding was not to be provided by the defendant.
There is force in these submissions. But, as I have said, the basic relevance of
what happened in the absence of full funding is to assist in deciding what would
have happened had full funding been provided. I do not think that it should be
inferred from what happened following the defendant's actions that, had it
honoured its promise and supported the programme, the programme would not
have been carried through. The effect upon the plaintiffs of what the defendant
did and the way it did it must, I think, have been great. It is not surprising that
Mr Pearson saw himself as "heavily involved in dealings with Custom Credit"
and "not able to attend to the architectural work on the project". What a person
would do in the context of treatment such as the defendant afforded the plaintiffs
is, I think, not a reliable guide to what they would have done had the plaintiffs
had what the defendant promised. The likelihood is that, had money been
available or had the plaintiffs been able to assure those to be involved in the
programme that the defendant was committed to the full funding of it, the matter
would have proceeded and finance would have been available to carry it forward
as the development programme envisaged.
On that basis, it is in my opinion proper to use the profits basis adopted by the
trial judge as the basis for calculation of damages in the present case. I agree with
the orders proposed by Kirby P.
Clarke JA The first question which arises on this appeal is whether a
contractwas concluded between the parties. The trial judge, Cole J, held that a
contract had been concluded. The appellant submits that he was in error. Its
argument is that in their discussions the parties remained in negotiation. Although
counsel for the appellant accepted that the hallmarks of a concluded agreement
were to be found in the critical discussion which took place between the parties
on 21 September 1988 he submitted that outstanding matters on which there had
been no agreement negated the existence of a binding contract.
His submissions focused on three aspects of the discussion. First, the
respondents requested, and the appellants agreed to provide, a letter evidencing
the terms of the agreement discussed on 21 September.
In the particular circumstances of this case the consequence of the appellant's
promise to provide a letter was, according to the appellant's counsel, that the
parties should be taken to have agreed that no contract would come into existence
until that letter had been supplied.
Secondly, statements in a letter, the terms of which had been incorporated in
substance into the agreement discussed on 21 September, to the effect that
security documents in a form satisfactory to the appellant and its solicitors were
to be prepared properly led to the conclusion that there was no concluded
agreement until that documentation had been executed by the parties.
Thirdly, and because a number of matters were left outstanding, the agreement
which was said to have been negotiated on 21 September was too uncertain to be
enforced.
Cole J rejected the first and third submissions of the appellants. He did not deal
in his judgment with the second argument. The reason which the respondents (I
will in the main speak generally of the respondents although it was the first
respondent which was the developer) assigned for this omission was that the
appellant had failed to raise it at the trial. Accordingly, the appellant should not,
according to the respondents, be permitted to raise the question in this appeal.
URJ CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (Clarke JA) 37
This area of contention between the parties is covered in detail by the learned
President and I content myself with saying that I agree with his Honour that the
appellant should not now be entitled to raise the point. Nonetheless, it is
convenient to deal with this point, upon the assumption that the appellant had
been allowed to raise it, in association with the other two questions raised.
The relevant facts, which are fully recounted in the judgment of the learned
President, can be summarised as follows.
The second and third respondents wished to develop some property in
Bellevue Road, Bellevue Hill. They approached the appellant seeking finance for
the whole development. This occurred in August 1988 and negotiations
continued between the second and third respondent, who intended that the first
respondent actually carry out the development, and Mr Bembrick of the
appellant. The negotiations did not proceed as the respondents wished and the
respondents sought finance elsewhere. On 21 September 1988 they received an
offer of finance from Devreal Capital Limited which was in these terms:
"We are pleased to confirm our offer of finance on the following terms and
conditions.
BORROWER: Cenepro Pty Ltd
Registered Office
91 Military Road,
Neutral Bay
Directors
Jamieson, William
Pearson, Gregory
AMOUNT: $6,500,000, to be drawn as follows:
Initial Tranche $430,000 reducing to $420,000 in the event the valuation on
23A Bellevue Road, Bellevue Hill is less than $365,000.
Further Advances
Will be subject to completion of Devreal's project feasibility, an external
valuation of the total development scheme, a check costing, and DA approval
from the local council, proving satisfactory in all respects.
The pricing of the total facility will be as follows:
Upfront Fee: 1.75%
Profit Share: The higher of 20% of net project profit or $450,000
Interest Rate: Bank Bills + 2.75% pa
Security will comprise a mortgage over the total development together with
joint and several guarantees of W Jamieson and G Pearson.
Costings will be subject to independent assessment by Devreal's appointed
consultant.
This consultant will also authorise project draw downs.
LOAN PURPOSE:
Initial Tranche
(1) Provide purchase moneys for acquisition of 23A $350,000
Bellevue Road, Bellevue Hill
(2) Acquisition Costs 25,000
(3) Consultants Fees 15,000
(4) Option Fees 15,000
(5) Establishment Fee - (Devreal) 15,000
(6) Fee to Equity Pacific Limited 10,000
38 UNREPORTED JUDGMENTS
$430,000
Further Advances
Will be in respect to the development of a mixed commercial, retail and
residential project at 23A to 27A Bellevue Road, Bellevue Hill. It is contemplated
funding will cover 100% of project costs, including capitalised interest.
TERM: 18 months, with the initial tranche for 90 days.
ESTABLISHMENT FEE: $15,000
INTEREST RATE: Initial Tranche
15.95% pa, reviewable at Devreal's discretion from the date hereof. Any
adjustments generally reflect a change in Devreal's cost of funds. Interest is
payable at the end of the term.
SECURITY: Initial Tranche
(1) Registered First Mortgage (by Cenepro Pty Ltd) over 23A Bellevue Road,
Bellevue Hill.
(2) Charge over Option Agreements in relation to 25, 25A and 27 Bellevue
Road, Bellevue Hill.
NB It is recognised that the option on 25A may not be available at settlement
but will be provided as soon as executed.
(3) Unregistered second mortgage over 27A Bellevue Road, Bellevue Hill. It
is agreed no caveat will be lodged prior to the expiry of the loan term for the
initial tranche.
(4) Lodgement/assignment of Bank Accepted Bills of Exchange ("Bills") with
face value of $140,000.
(5) Joint and several guarantees of:
W Jamieson and G Pearson.
It is agreed the Bills will be released by Devreal, at its discretion, upon the
substitution of satisfactory alternative security.
DEVREAL'S Gadens, 175 Pitt Street, Sydney.
LAWYER: Phone: 232-5566
(Mr Jon Denovan)
BORROWER'S LAWYER: Hanley Cameron and Goold, 350 Oxford Street,
Sydney (Mr Garry Cameron)
DOCUMENTATION
Subject to Devreal and its lawyers total satisfaction:
COSTS:
All legal and related professional costs are to the Borrower's account. If paid
by Devreal they will be re-imbursed whether or not the facility is drawn down.
MATERIAL ADVERSE CHANGE:
Devreal reserves the right to withdraw the facility should anything transpire
that renders its completion undesirable.
INSURANCE:
A comprehensive policy noting Devreal as mortgagee must be provided with
cover for the replacement value of the improvements.
SPECIAL CONDITIONS: INITIAL TRANCHE
Satisfactory valuation of 23A Bellevue Road, Bellevue Hill.
ACCEPTANCE:
URJ CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (Clarke JA) 39
To confirm your acceptance of the terms and conditions please sign the
attached copy of this letter and return same with your cheque for $5,000. This
sum will be reimbursed on drawdown. The offer is open until 23 September,
1988."
Following receipt of this letter the second and third respondents met with
Bembrick and two officers of an organisation known as Scotts Developments Pty
Ltd ("Scotts") in order to negotiate a joint venture between the first respondent
and Scotts for the development of the properties which development was to be
funded by the appellant. At 1 pm on 21 September Draft Heads of Agreement
were settled. Following this occurrence the second respondent advised Devreal
that its offer was declined.
Later in the afternoon, however, Scotts pulled out of the deal. There then took
place a meeting between the second and third respondents and Bembrick at
which the latter said that in the circumstances of Scotts withdrawal the appellant
would be prepared to fund the project.
In response to a suggestion from the second respondent that Bembrick did not
have authority to commit the appellant he suggested a meeting with Mr Anderson
the appellant's New South Wales State Manager. At that meeting the following
discussion took place:
"BEMBRICK: 'Meet Bruce Anderson our State Manager. As I mentioned
earlier, Bruce, Bill and Glen were just about to sign up with Bob Scott who pulled
out. They had full financing for acquisition and development lined up from
Devreal."
JAMIESON: 'We knocked back our financing with Devreal because we had
shaken hands with Scotts. As you know, Custom Credit had introduced Scotts to
us."
ANDERSON: 'Yes I know..."
ANDERSON: 'Steve (Bembrick) has already told me about the offer from
Devreal.
Have you got a copy of the Letter of Approval from Devreal?'
JAMIESON: 'Yes, here it is.'
Mr Anderson was then handed a copy of the Devreal letter. Mr Bembrick then
said to Mr Anderson:
"Bruce, Bill and Glen have been told by Equity Pacific that the people they are
dealing with at Custom Credit don't have authority. They've got a letter from
Equity Pacific to that effect."
Mr Anderson then requested a copy of the letter to which I have previously
referred. It was handed to him. He responded:
"What would he know. Of course I've got authority, I'm the State Manager for
New South Wales.'
Having read the Devreal letter of offer, the following conversation occurred.
ANDERSON: 'Steve, I can't see why we can't do the same deal as Devreal.'
BEMBRICK: 'I can't see why not either.'
JAMIESON: 'Can you do a better deal than Devreal? We can still go back and
see them tomorrow morning though I would feel embarrassed doing so at this
stage."
ANDERSON: 'Well what do you have in mind?'
JAMIESON: 'What about the profit share?'
ANDERSON: 'We're prepared to take 15% instead of 20% and that will be
taken on completion of the end of the project. That's a better percentage than
Devreal."
40 UNREPORTED JUDGMENTS
JAMIESON: 'It's great, what about the interest rate? Devreal had offered
2.75% above bank bill rates. I'd prefer a fixed interest rate because I've had bad
experiences with foreign currency transactions.'
ANDERSON: 'I can't do a fixed interest rate for the whole term to match
Devreal's offer because our rate at the moment is 17%. What we can do is fund
acquisition costs at our normal rate of 17% and fund the construction using a
percentage over bank bill rates. It is not our practice to use bank bill rates, but in
this case, I think we could do it. The project is good enough. We can do better
than Devreal and give you 2% above the bank bill rate. Bank bills will work well
for the construction part of the project. What Custom Credit does is to draw the
bills for a term of six months from its fund, deposit them into another account
from which you can draw as the funds are required. That way the rate is fixed as
best we can. The term for the whole project will be for 18 months as in the
Devreal offer.'
Security was then discussed.
JAMIESON: 'I don't want my property tied up as security for the project. As
you know my property is mortgaged to the Commonwealth Bank. What I am
looking at is for Cenepro to purchase my property for $750,000 then I can pay
out the Commonwealth Bank and Cenepro can give Custom Credit the mortgage
it requires. As I told Steve, I want to make it clear to you that Cenepro and I are
to be kept separate as far as this project is concerned. Also I don't want to take
any risks. I've got some litigation on at the moment with the bank in relation to
a foreign currency transaction and I don't want to do anything to ruin my position
in relation to that litigation. That's why Bob Scott's offer was so good. He was
going to give me an extra $370,000 on top of the $750,000 on my property and
Glen was going to get his architectural fees up-front.'
ANDERSON: 'OK. How about we structure it this way. We'll prepare
documentation so that you give Cenepro an option over your property and then
Cenepro will charge the option in favour of Custom Credit. But in the meantime,
we want a lien over your bills.'
JAMIESON: 'You' ve got my personal guarantee as well as Glen's and there's
$100,000 equity in the property anyway - 23A is worth $450,000 and we got it
for $350,000. That should be enough.'
ANDERSON: 'You are willing to give a lien over the bills in the Devreal
offer.'
JAMIESON: 'Well, I really need the money now. Anyway, in the Devreal offer
it was agreed that the lien was going to be released on substitution of security
over 27A and that was going to happen quickly. I was going to get paid out
upfront.'
ANDERSON: 'Well that's what is going to happen here. The lien will only be
there until final documentation is completed and an option on 27A in favour of
Cenepro is documented. Then your bills will be returned.'
JAMIESON: 'OK I'm happy with that.'
BEMBRICK: 'Are you happy with that Glen?'
PEARSON: 'Yes.'
In celebration of the 'deal' drinks were obtained. The conversation continued:
BEMBRICK: 'Bruce, what are we going to do about the settlement on 23A this
Friday?'
ANDERSON: 'All the girls have gone home so we can't get documentation
prepared this evening.'
URJ CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (Clarke JA) 41
BEMBRICK: 'We could use our previous offer just to deal with the immediate
settlement so we can have a cheque ready for that on Friday. We could also at the
same time prepare the letter for the full funding for Cenepro to sign on Friday.'
ANDERSON: 'Fine.'
JAMIESON: 'So all this can be ready for Friday?'
BEMBRICK: 'Yes.'
The letter of 6 September 1988 offering the facility of $880,000 was then
amended to constitute a facility for $480,000. The purpose of the facility shown
in the letter was changed so that it related only to the acquisition of No 23A. After
discussion, the interest capitalisation facility was deleted, then reinstated.
Provision was inserted for rental on 23A to be forwarded to Custom Credit. There
was then a discussion about Custom Credit's fees. The following was said:
JAMIESON: 'You are not going to charge anymore than Devreal's $15,000
establishment fee.'
ANDERSON: 'No.'
JAMIESON: 'When do you get your participation fee?'
ANDERSON: 'On Friday when you get the cheque for 23A, we'll draw down
the participation fee. Also, I want to make this clear. If we can't get the whole
deal there is no basis for us simply to fund the first settlement. We want to lock
you in so you don't go back to Devreal.'
PEARSON: Well, since you are giving us full funding and a bit better deal we
won't want to do any deal with anyone else.'
ANDERSON: 'I want to make sure that you don't.'
BEMBRICK: 'What if we put in a discharge fee of $50,000?'
ANDERSON: 'Good idea."
Bembrick then wrote onto the amended letter the following:
'Discharge Fee Should this facility be discharged at the expiration of the term,
a fee of S50,000 is payable on discharge.'
Bembrick then read those words out to Pearson and Jamieson and asked: "How
does that sound?'
JAMIESON: 'OK.'"
Thus, according to the respondents an agreement was struck. That agreement
was partly in writing (the Devreal letter) and partly oral. The question which
confronts the court is whether in the light of surrounding circumstances an
agreement was concluded. The question depends "upon the intention disclosed
by the language the parties have employed" (see Masters v Cameron, 91 CLR
353, at 362). I have adopted those words from the judgment of the majority in
Masters for the reason that it poses accurately the test which should be applied
in the circumstances of the present case.
Where there is a disputed contention that a contract, which is partly in writing
and partly oral, is concluded between the parties the court is required initially to
determine what was said in the relevant conversations and to identify the
document or documents constituting the writing. Once the court has resolved
these factual questions it moves to the second stage in which it considers whether
the words, which it has found were spoken on the relevant occasion, and the
documents it has identified, establish the alleged contract.
In this task the court's attention is concentrated upon two questions, first,
whether the necessary intention is established and, secondly, whether the terms
of the alleged agreement are sufficiently certain. If it concludes that the parties
42 UNREPORTED JUDGMENTS
did intend to conclude a contract - that is, that they were ad idem - and that the
terms of the contract were not uncertain then it will uphold the existence of the
contract.
It should, however, be pointed out that when the court embarks on a
consideration of this issue questions invariably arise as to the admissibility, and
relevance, of evidence of surrounding circumstances. Evidence of this nature will
clearly be admissible in relation to the first stage of the enquiry. Where the court
is confronted with conflicting evidence as to what was said, and which
documents were discussed, at the critical meetings it will necessarily turn its
attention to those indicators which support one or other version advanced in
evidence. Those indicators will generally include the surrounding circumstances
- being events which occurred after, as well as before or simultaneously with, the
conversations in issue.
This is because the fact that one version of the critical conversations is more
consistent with other events clearly established by the evidence will tend to
suggest that it is more probable that that version is the correct one. Once,
however, the first issue is resolved or where there is no dispute as to what is said,
and which documents form part of the alleged contract - as in this case - there
may be a question whether evidence of surrounding circumstances (including
subsequent events) is relevant to the second stage of the inquiry. I think it can be
taken that as a general rule it will be but before I expand on that statement it is
convenient to say something about the intention of the parties.
I can be brief on this topic for while there has been debate on the question
whether the court seeks to ascertain the subjective intention of the parties or
applies an objective test the authorities have come down firmly in favour of the
latter. That is that the court looks to what was said and done and not to the
subjective intention of the parties. As Holmes J said in "The Common Law" (p
309):
"In contract, as elsewhere, it must go by externals and judge parties by their
conduct".
Or, as it was put by the majority in Taylor v Johnson, 151 CLR 422, at 428:
"The law is concerned, not with the real intentions of the parties, but with the
outward manifestations of those intentions".
That is not to say, however, that evidence of actual subjective intention will
never be relevant. It is established that such evidence is of direct relevance where
it is said that a document which presents as a written contract is a sham. Or where
a party makes, or accepts, an offer in jest to the knowledge of the other party. The
subject is discussed in detail in the judgments in Air Great Lakes Pty Ltd v K S
Easter (Holdings) Pty Ltd, (1985) 2 NSWLR 220, but it is unnecessary to do
more than note that evidence of actual intention may be relevant in particular
cases for no reliance is placed on evidence of that nature in this case. Whether or
not evidence of actual intention is admissible it has long been established that
evidence of surrounding circumstances, and subsequent conduct, is admissible
upon the question whether a contract has been concluded between the parties
(Film Bars Pty Ltd v Pacific Film Laboratories, (1979) 1 BPR 9251; Australian
Broadcasting Corporation vy XIVth Commonwealth Games Ltd, (1988) 18
NSWLR 540; Barrier Wharfs Ltd v W Scott Fell and Co Ltd, (1908) 5 CLR 647,
at 669; Air Great Lakes Pty Ltd v K S Easter (Holdings) Pty Ltd, supra). In this
respect the question whether there is a contract between the parties is to be
distinguished from the one which arises when it is the construction of a written
contract which is in issue. In the latter case evidence of surrounding
URJ CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (Clarke JA) 43
circumstances, but not subsequent events, is admissible in cases where the
language used in the contract is capable of more than one meaning (Codelfa
Construction Pty Ltd v State Rail Authority of NSW, 149 CLR 337, at 352).
In this case the respondents contend that the conversation on 21 September,
particularly when understood in the light of the preceding events, clearly
constituted a binding contract.
The appellant however pointed to a number of features of the transaction in
support of the submission that it did not bind itself to the provision of 'full
funding' or, more accurately, to lend $6,500,000 to the first respondent upon the
terms of the Devreal letter as varied in the conversation of 21 September. Those
features could conveniently be divided into two categories.
The first containing various expressions in the Devreal letter which were said
to be inconsistent with a concluded agreement. The second concerning those
features of the transaction which rendered it inherently unlikely that the appellant
would, as a large finance company, bind itself to lend approximately $6,500,000
to the respondents for use in a staged development involving complex security
arrangements in the informal manner for which the respondents contended. In
support of this submission reliance was placed upon B Seppelt and Sons Ltd v
Commissioner for Main Roads, (1975) 1 BPR 9147, and Coogee Esplanade Surf
Motel Pty Ltd v Commonwealth of Australia, (1983) 50 ALR 363.
As I have earlier indicated the appellant submitted at the trial that the parties
did not intend that a binding contract came into existence until the letter referred
to in the conversation had been provided and signed. I am unable to accept this
submission. The circumstances in which the conversation occurred when
considered together with the terms of the conversation deny the validity of this
view. Let me amplify that statement.
The respondents were not interested in proceeding with their venture unless
they had secured a commitment from a financial organisation sufficient to fund
the full development. This is what was meant, I apprehend, by the expression
"full funding". They were not interested in securing a commitment for a lender
to lend the funds for the purchase of individual properties. Those properties were
of use to them only as part of the proposed development. They needed a
commitment from a financier to lend all the moneys required for the
development.
It was for this reason that after receiving a letter dated 6 September from the
appellant offering funds only for the purchase of 23A Bellevue Road the
respondents looked elsewhere for financial assistance.
The offer contained in the Devreal letter met their requirements. Devreal
offered a commitment to provide $6,500,000 which constituted full funding and
the respondents understood this to be an offer which would, upon acceptance,
form the basis of a contract. Although they had rejected the Devreal offer before
their important discussions with Bembrick and his superior, Anderson, they still
believed that if no satisfactory arrangement could be secured from the appellant
they could revive it.
In this context they were interested only in securing a commitment, or, to put
it another way, a binding obligation, from the appellant to provide full funding.
This view is fortified by the respondents insistence that as Bembrick did not have
authority to bind the appellant, they deal with someone who could bind it. Hence
the conversation with Anderson whose authority was not in question. During the
discussion agreement was reached on each point which arose and at the
conclusion the participants enjoyed celebratory drinks. While these were being
44 UNREPORTED JUDGMENTS
enjoyed there were further discussions which descended into greater detail.
During these Anderson proposed an additional term to "lock" the respondents in.
This term was also agreed. Following these discussions the respondents lost
interest in Devreal. They had, or believed they had, a binding commitment for
"full funding" from the appellant. Their belief was, as it seems to me, reasonable.
The words of Blackburn J in Smith v Hughes, [(1871) LR 6QB 597, at 607] are
apt:
"Tf, whatever a man's real intention may be, he so conducts himself that a
reasonable man would believe that he was assenting to the terms proposed by the
other party, and that other party upon that bellef enters into the contract with him,
the man thus conducting himself would be equally bound as if he had intended
to agree to the other party's terms."
Neither Anderson nor Bembrick gave evidence so the court was never apprised
of their subjective intentions. What they said and did, however, induced a
reasonable belief in the respondents that they were entering into a contract. The
terms of that contract were described by Cole J in these terms:
"Thus, the agreement reached that evening was that Custom Credit would
provide full funding. The arrangement was that it would be on the same terms as
that offered by Devreal except that the profit percentage would be less and the
interest rate slightly less. The letter for full funding was to be prepared and
available on Friday 23 September.
As an interim measure to ensure funds were available for settlement of No 23A
on Friday 23 September, a letter relating only to those funds was prepared, being
a handwritten amendment of the previous letter of 6 September. To ensure that
Cenepro was bound to take the full funding from Custom Credit, it being
contemplated the full funding letter would be ready for signing on 23 September,
a provision was inserted to the effect that their failure to do so would result in an
obligation to pay an additional $50,000."
I see no reason to differ from the substance of his Honour's conclusions.
The arrangement then concluded was not expressed to be subject to the letter
which Bembrick promised (and which could not be furnished on 21 September
because all the staff had gone home before the discussion).
Nor, in my opinion, was there anything said during the conversation which
gave rise to the implication that the agreement reached by the parties should be
regarded as provisional until a formal letter confirming its terms was provided.
There is, however, more substance in the uncertainty argument which it is
convenient to consider at the same time as the "subject to contract" argument.
Broadly, the submission was that there were so many aspects of the transaction
left for future discussion and decision that the so-called contract lacked requisite
certainty and was regarded by the parties merely as providing the fundamental
bases for their arrangement, the full details of which were to be spelt out in a later
agreement or agreements. These aspects included, but were not limited to, those
sections of the Devreal letter dealing with "Further advances", "Documentation",
"Material adverse change" and the terms of the mortgages which were to be
executed.
These terms were said to indicate that all of the details necessary for the
implementation of the arrangement had not been worked out. In determining
whether these features robbed the arrangement of the requisite certainty it is
important to bear in mind that in situations where it appears that the parties
intended to make a contract the courts will strive to give effect to that intention
(see, Upper Hunter County District Council v Australian Chilling and Freezing
URJ CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (Clarke JA) 45
Co Ltd, 118 CLR 429, at 437; York Air Conditioning and Refrigeration (A/asia)
Pty Ltd v The Commonwealth, 80 CLR 11, at 26, Corpers (No 664) Pty Ltd v
NZI. Securities Australia Ltd, 1989 ASC 55-714)In Biotechnology Australia Pty
Ltd v Pace, 15 NSWLR 130, Hope JA said, at 143:
"All these decisions show how far courts are prepared to go in order to find that
there is an enforceable contractual promise where that is what the parties have
intended. There are of course limitations. I have already referred to the case
where the promisor has a discretion, not only as to what he shall do, but also as
to whether he shall do anything. Such a promise is illusory. Furthermore it
appears that the promise will not be enforceable if the manner of performance,
including the amount of money to be paid or, if relevant, the number of shares to
be offered, is a matter entirely in the discretion of the promisor and no criteria by
which the performance required of the promisor can be measured, or the
minimum of that performance can be measured, is expressed or can be found to
be implied."
In this case I have already indicated my view that in their discussion on the
evening of 21 September the parties intended to conclude a contract. In these
circumstances the court should strive to give effect to the parties' intentions.
Furthermore neither the fact that the terms of the mortgages had not been settled
nor that the precise implementation of the arrangement had been spelt out in
detail should, in my view, necessarily lead to the conclusion that the contract
lacked certainty. One of the questions which concerned the court in Godecke and
Anor v Kirwan, 129 CLR 629, was whether a contract containing the following
term"
"6. If required by the Vendor/s I/we shall execute a further agreement to be
prepared at my costs by his appointed Solicitors containing the foregoing and
such other covenants and conditions as they may reasonably require." lacked
certainty. The court concluded that it did not. Walsh J was of opinion that the
clause permitted the insertion of covenants "not inconsistent with those contained
in the offer" and which were objectively reasonable. If the parties could not agree
on reasonableness the court could resolve their differences. Gibbs J agreed,
pointing out that parties to a contract may leave terms, even essential ones, to be
settled by the solicitors for one of the parties. Although Gibbs J left open the
question whether the fact that the power to determine outstanding matters was
vested in a party, rather than its solicitor or a third party, should lead to a different
result Walsh J (and Mason J agreed with him) thought it should not. Of course
there was no express requirement in this case that the terms of the documentation
should be reasonable. The requirement was that they should be to the "total
satisfaction of the appellant and its lawyers". In this respect it was similar to the
contract considered by Bray CJ in Powell v Jones, 1968 SASR 394, whose
judgment was approved by Walsh J in Godecke. His Honour held that subject to
the qualifications expressed at p 398 there is no reason in principle for holding
that there cannot be a binding contract if some matter is left to be determined by
one of the contracting parties (see also Axelsen and Ors v O'Brien, 80 CLR 571;
Hillas and Co v Arcos, Ltd, (1932) All ER Rep 494, at 507-8).
That result would not flow if it was left to one party to determine not only the
terms of documentation but whether it should proceed with the transaction itself.
In the present case it was submitted that the terms relating to further advances
under the heading "Amount" did leave that decision to the appellant. In my view,
46 UNREPORTED JUDGMENTS
however, the better view is that the parties had made a contract a term of which
enabled the lender to reconsider its position if, for instance, a DA approval was
not objectively satisfactory.
The submission that the case fell within the third category identified in Masters
v Cameron (supra, at 300) raises a slightly different question. It assumes that the
contract did not fail for want of certainty and propounds a consensual intention
that no contract would come into existence until the execution of a formal
agreement.
In this case it was said that the discussion concerning the provision of a formal
letter by the appellant when regarded in the light of the statements in the Devreal
letter, such as the provisions regarding documentation which I have identified,
evidenced a clear intention that no contract would come into existence until the
letter was provided.
I have already indicated my inability to accept that the parties intended that
they remain in a state of negotiation until the letter was provided but there
remains the contention that the provisions in the letter demonstrated that no
contract had been concluded.
The term concerning documentation would not lead me to that conclusion. It
was simply a term of the contract reserving to the appellant and its lawyers a
discretion as to the terms of the security documents. The provision headed
"material adverse change" is more difficult for it reserves to the appellant the
right to withdraw from the transaction.
That right is not an unqualified one. Its exercise is dependent upon a material
adverse change. Having regard to the whole of the letter I would regard this
provision as a term of the contract permitting the appellant to withdraw from the
facility (as it is described in the letter) upon the occurrence of what was
objectively a materially adverse change. Whether any change was objectively
materially adverse would fall to be judged upon the terms of the contract and its
surrounding circumstances.
Accordingly, I would reject this submission of the appellant and I would
uphold his Honour's judgment on the existence of a contract.
DAMAGES
Cole J proceeded upon the basis that the respondents were entitled to maintain
a claim for the loss of the profits which the respondents might have earned if the
appellant had not breached its contract to provide "full funding". In his judgment
he said that the respondents' right to maintain that claim was not in dispute. As
his Honour pointed out the assessment of the amount of profit or loss which
would have been occasioned had the breach of contract by the appellant not
occurred and the project been completed and sold involved the consideration of
various assumptions.
Furthermore his Honour considered that it was necessary to determine at least
four principal matters in order to arrive at conclusions on which to base an
assessment of the likely position at the end of the hypothetical development.
Those four matters were:
(1) The date of completion and sale of the development. In this respect the
respondents alleged the development would have been completed and sold by 31
March 1990. On the other hand the appellant alleged it would have been
completed later resulting in additional costs, including construction and interest
costs, and lower realisations due to a depressed market.
(2) Could the units in the development be pre-sold off plan prior to
completion?
URJ CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (Clarke JA) 47
(3) The value of the development upon completion.
(4) The costs of completing the project including land, consolidation costs,
development expenses, construction expenses and interest.
His Honour concluded that the development would probably have been
completed by 31 March 1990 and that the units would have been pre-sold off plan
prior to that date. Having assessed competing evidence he then determined that
the value of the development upon completion would have been $11,090,000 and
that the cost of completing the development (including construction costs of $3.3
million) would have been $8,795,000 leaving a profit to the developers of
$2,295,000.
The appellant challenged the fundamental basis on which the assessment was
made and also the findings on the four principal matters which I have earlier set
out.
Its first submission was that his Honour was in error in proceeding to award
damages upon a consequential loss basis. The proper measure of damages for
breach by a lender of its contractual obligation to advance moneys was the
additional cost of borrowing the moneys from elsewhere. If, according to this
argument, the substitute funds could be secured from sources other than the
defaulting lender then it was wrong in principle to award consequential losses
flowing from the failure of the development which was dependent upon
borrowed funds. That is because it remained within the borrowers capacity to
complete its development albeit that it was required to pay additional interest to
secure the substitute funds. If, on the other hand, other funds could be secured for
no additional cost then the borrowers damages would be limited to the additional
expenditure incurred in raising the substitute finance.
In any event, the argument proceeded, where it had not been shown that the
borrowers were unable to secure substitute funds it was quite wrong in principle
to allow consequential losses by way of damages. There is, in my opinion, a great
deal of substance in these submissions. Where a finance company declines to
honour a contractual obligation to provide funds to a developer different
consequences may flow. The developer may be able to obtain substitute finance
and if he does so it would follow that its damages would be limited to the
additional cost of the substitute finance together with incidental matters such as
the expense of obtaining the alternative finance and, perhaps, damage flowing as
a result of any delay occasioned by the breach of contract. It would, it seems to
me, be contrary to principle to hold that a developer who could secure alternative
finance should be treated as though it was incapable of completing the
development and awarded consequential losses (See Head v Kelk, 63 SR 340).
On the other hand if the evidence demonstrates that no alternative finance was
available to the innocent borrower no reason would appear why, in appropriate
cases, it should not be able to maintain a claim for consequential losses. In
addition there may be cases where, although a borrower may theoretically be able
to obtain alternative finance, the circumstances in which the breach occurred, or
particular features of the case, lead to the factual conclusion that alternative
finance would not, in a practical sense, be available to the borrower for the
completion of the development.
This, I think, is what was suggested by the respondents in this case. They
claimed that after the initial promise by the appellant its officers not only decided
not to honour the promise but led them on by making offers of much more limited
finance in circumstances where it was not a sensible commercial alternative for
them to seek the finance elsewhere. Indeed his Honour found that in all the
48 UNREPORTED JUDGMENTS
circumstances of the case the respondents had no real alternative but to go along
with the successive proposals of the appellant.
Be that as it may the major difficulty with the appellant's present submission
is that it would seem clear it was not made at the trial. Certainly his Honour's
judgment on damages does not mention the point now under consideration. On
the contrary his Honour stated that it was not in dispute that if a defendant is
aware of the purpose for which the plaintiff enters into a contract of loan then,
upon the defendant's breach of that contract, the plaintiff is entitled to
consequential losses flowing from the consequential incapacity to effect that
purpose.
Further, reference to the written submissions of the appellant at the trial makes
it clear that the appellant's sole concern with the principle that damages were
recoverable in respect of the additional costs of securing alternative finance was
to demonstrate that on the evidence in this case those damages could only be
nominal. In effect its counsel raised the matter simply to show that no damages
were properly recoverable under that heading.
The written submissions then proceeded to deal with the claim for
consequential loss. At no stage does it appear that it was submitted that, in the
absence of proof that alternative finance could not be secured, a claim for
consequential loss could not be maintained. Hence, the point now under
discussion was not dealt with by his Honour at the trial. Not only did counsel for
the appellant not take the specific point but he did not seek to raise with the
respondents' witnesses whether they had found it impossible to raise funds
elsewhere or why they had not followed up an offer contained in a letter from the
Macquarie Bank dated 23 March 1989.
It seems clear to me that if the point now under discussion had been a live issue
at the trial then it would have been canvassed in the evidence and the respondents
may have sought to lead evidence of the difficulties of raising finance from other
sources. In all the circumstances I do not think it is now open to the appellant to
raise this point and I would reject this particular challenge. The appellant also
contested the findings in respect of each of the four principal matters earlier
mentioned. It will be recalled that the first finding was that the development
would have been completed by 31 March 1990. This finding depended, in turn,
on a number of other findings as to the likely course of events which would have
followed if the appellant had not breached its contract.
The appellant put before this court a table which compared the likely course
of events as found by his Honour and the actual course of events prior to the trial.
That was a telling document and I think it is appropriate to set it out in full:
" EVENT FOUND ACTUAL
Lodgment of DA 8(or 12)/8/88 8(or) 12/8/88
Development consent December' 88 14/3/89
Lodgment of BA January'89 9/6/89
Building consent April'89 30/11/89
Commencement of construction 1/5/89 Nil
Completion of construction mid-Feb'90 Nil
Approval of Strata plan 31/3/90 Nil
Settlement of Sales 31/3/90 Nil"
URJ CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (Clarke JA) 49
The appellant submitted that the hypothetical timetable under which a building
consent was obtained by April 1989 and construction commenced by 1 May
1989: (a) Could never have been accomplished, even if the appellant had not
breached its contract, because of delays with occupiers of the properties and in
the acquisition of the land which operated as independent causes of delay; and (b)
Made no allowance for the actual delay in development consent between
December 1988 and 14 March 1989 which could not be blamed on the appellant.
His Honour rejected similar challenges upon the basis that the delays
mentioned were consequential upon the appellant's breach of contract. In
particular his Honour found that the respondents were unable to honour an
agreement to pay one of the tenants $25,000 in December 198B because of the
appellant's failure to honour its obligation to provide full funding.
In addition his Honour concluded that the appellant's breach of contract had
prevented the respondents from lodging the building application in January 1989
which was a necessary pre condition to the commencement of work on | May
1989. According to his Honour the relevant consequences of the failure of the
appellant to honour its obligation to provide full funding were that the third
respondent, an architect, was unable to devote sufficient time to the project
because he was obliged to consult regularly with the appellant. This was of added
significance insofar as the respondents did not have the funds to engage a firm of
architects to do the work which the third respondent otherwise might have done
himself or to engage engineering consultants to provide the engineering input to
permit completion of the building application.
In this respect his Honour accepted the third respondent's evidence that had the
promised funds been available without prevarication the building application
would have been attended to in time to enable its lodgment in December 1988 or
January 1989. Of course the building application would not, in any event, have
been lodged until after the grant of development approval. This is because, as the
third respondent explained, there was a possibility that conditions would be
imposed upon the grant of development for which provision would need to be
made in the building application. Accordingly the lodgment of the building
application in January 1989 would necessarily have been dependent upon the
grant of development approval in December 1988.
There are a great number of difficulties with this approach which have led me
to the conclusion that it cannot be sustained. At the outset I am unable to accept
that the failure to engage engineering consultants between September and
December 1988 and architects earlier than January 1989 resulted from the
appellant's breach of contract. Nor am I able to accept that the appellant was
responsible for the delay in obtaining development approval. While I would
accept that it may be appropriate to proceed upon the hypotheses that these steps
had occurred as planned if the breach of contract had led to the initial delays in
obtaining development consent and lodging the building application I do not
think that there is any evidence that the breach did have these consequences.
In this context it is important initially to recall the terms of the contract
between the parties. It was not a contract under which the appellant agreed, in
terms, to provide full funding for the development, whatever that phrase might
mean. His Honour found that "The terms were those in the Devreal letter subject
to the agreed amendments concerning profit share, interest rates, lien on
commercial bills, rent directions and discharge fee".
The contractual obligation thus undertaken was to provide a loan of
$6,500,000:
50 UNREPORTED JUDGMENTS
"To be drawn as follows:
INITIAL TRANCHE
$430,000 reducing to $420,000 in the event the valuation on 23A Bellevue
Road, Bellevue Hill, is less than $365,000. (This term was varied in the
discussions by making the initial tranche $480,000 in accordance with the letter
of 6th September earlier provided by the appellant.)
FURTHER ADVANCES
Will be subject to completion of Devreal's project feasibility, and external
valuation of the total development scheme, a check costing, and DA approval
from the local council proving satisfactory in all respects." (My emphasis)
No doubt the parties contemplated that an advance of $6,500,000 was akin to
an advance of the whole cost of the development. That would appear from the
respondents' estimates of the total development cost which were submitted, inter
alia, to Devreal and which indicated a cost of $6,315.758. But the appellant did
not undertake an obligation to provide full funding to the respondents as and
when they sought instalments. Its obligation was clearly defined. It was obliged
to provide an initial advance of $480,000-00 and the later advances were to
become due upon the happening of the contingencies set out in the Devreal letter.
All advances subsequent to the first one were dependent upon those conditions
including, relevantly, the condition that the respondents obtain a development
approval satisfactory in all respects. In terms of that contract the respondents
could not have held out any expectation of obtaining further advances to enable
them to take steps in the development prior to the obtaining of the development
approval. In particular they could not realistically have relied on the provision of
funds prior to the grant of development approval for the retaining of architects
and engineers to carry out work which they then required performed. Certainly
they could have retained architects and engineers in the expectation that upon
obtaining development approval they may have funds to pay them but no breach
by the appellant of its contractual obligations deprived them of that opportunity
nor caused them to delay retaining those persons. In fact the engineer was
retained at the end of October and the other architect on 9 January - both events
occurring before the grant of development approval.
There is some difficulty in dealing with this point as his Honour did not define
with any particularity in either of the judgments the precise breach committed by
the appellant nor when it occurred. It was not suggested, however, that the
appellant defaulted in compliance with the obligation to provide the initial
tranche. If it complied with that obligation then the breach occurred in the failure
to provide later instalments, the first of which became due, at the earliest, after
the development approval had been granted.
I appreciate that the respondents claimed that Mr Bembrick put them in a
dilemma. He promised money to pay the tenant and failed to honour that
promise. And he also failed to provide the promised letter. But the appellant was
not contractually obliged to provide moneys before the grant of development
approval to pay out a tenant and promises by Mr Bembrick had no contractual
force. Additionally the appellant's failure to provide the letter may have made the
respondents uneasy but did not, as it seems to me, constitute a breach of contract.
The respondents had, as his Honour found (and they claimed), secured a
binding commitment from the appellant and any failure on their part to take
necessary steps before the grant of the development approval cannot, in my
opinion, be regarded as a consequence of a breach of contract. I might add I find
URJ CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (Clarke JA) 51
it difficult to conclude that the delay in the retention of the engineers, and even
the architect, was occasioned by an anticipated breach.
There are other problems with his Honour's conclusion that development
approval was delayed by the appellant's breach of contract. His Honour noted
that the development application was lodged in September 1988 and that
approval was not given until March because the respondents were unable to pay
the tenant of 25A Bellevue Road the sum of $25,000.
In fact an amended development application was lodged on 25 October 1988.
The occasion for the lodgment of an amended development application was the
revision of the original plans in order to provide for the development on the site
of eight two bedroom units.
Notwithstanding, the respondents expected the application to be considered at
the December meeting of the Woollahra Municipal Council but this did not occur.
This was not surprising for on 10 November 1988 the third respondent's firm had
provided additional information to the Council and on 14 December 1988
submitted floor plans showing a number of amendments. These were submitted
two days after the Council meeting but in view of the third respondent's evidence
that these were submitted in response to a requirement from Mr David Sung of
Woollahra Council it is a fair inference that the respondents knew that the
application would not be considered until the documents had been provided.
In early January the third respondent heard, for the first time, that the tenant of
25A was not prepared, contrary to earlier indications, to consent to the project.
This action on the part of the tenant led the Council to decline to deal with the
application in January 1989. Thereupon the third respondent spoke to the tenant
of 25A Bellevue Road who indicated that he was protecting himself until the
money which he was expecting had been received.
In evidence the third respondent stated that the respondents were unable to pay
the tenant because the appellant had not funded them. But, as I have sought to
point out, there was no contractual promise binding on the appellant to provide
that funding at that stage. This had apparently been recognised by the third
respondent for in a draft letter to the Council dated 8 March 19839 he stated, inter
alia, "and in the light of the fact that funding for acquisition and development is
subject to development approval...".
This letter is also relevant for it contains a statement that the tenant had
provided consent in the light of a letter of intent provided by the respondents
(despite not having been paid $25,000) and it was this information which led the
Council at its meeting on 14 March 1989 to consent to the development approval.
It follows that I am unable to accept the conclusion that if the appellant had not
breached its contract the development approval would have been granted in
December or January at the latest. In my opinion the failure to obtain consent
prior to 14 March cannot be laid at the door of a breach of contract by the
appellant and his Honour's finding to this effect cannot stand. Insofar as this
finding was fundamental to the later conclusion that completion of construction
would have taken place by mid-February 1990 and final settlement of all sales
would have been completed by the end of March of that year those conclusions
were also erroneous.
I should add that, quite apart from this matter, the six month difference
between the hypothetical date on which building consent was taken to have been
obtained and the actual date of the grant of such consent also presented a not
inconsequential obstacle to an acceptance of the respondents' case.
52 UNREPORTED JUDGMENTS
The third respondent gave evidence that it was normal after lodging the
development application to work on the building application documentation so
that upon receipt of the development approval any necessary amendments could
be incorporated in the building application. His Honour noted that and then said
"between September and December 1988 Custom Credit not having honoured
the agreement to provide full funding, the plaintiff was unable to engage
engineering consultants to provide the engineering input to permit completion of
the building application. That position maintained until at least May". There was
as I have pointed out no contractual obligation to provide funds prior to the grant
of development approval but in any event the third respondent's evidence
demonstrated that engineering consultants were engaged at the end of October
1988.
Although the respondents might not have given them the full go ahead until
later this could not, in my view, be sheeted home to the appellant.
The respondents' case was that if funds had been available they would have
been able to lodge the building application in December 1988 or January 1989.
According to the third respondent his opinion was that approval would have been
granted within three months, that is, by the end of April of that year. Leaving
aside the fact that the period between the application and grant of building
approval was longer than the third respondent had estimated there was simply no
basis for concluding that the application would have been lodged in December
1988 or January 1989 except for a breach of contract by the appellant.
The period between the grant of development consent and the lodgment of the
building application was slightly under three months which was a far greater
period than the few weeks which the third respondent thought would be needed.
The evidence suggesting that this was the fault of the appellant was restricted to
claims of impecuniosity delaying the efforts of the engineer and the additional
architect. But the evidence to this effect was vague in the extreme and in my
opinion, even assuming that there was a contractual obligation to provide funds
at that time for engineering and architectural services, was insufficient to lead to
a conclusion that the appellant was responsible for the delay. Furthermore the
Council itself took nearly six months to process the building application because
final amended plans were not submitted until 21 November 1989. I fail to see
how this delay can be laid at the appellant's feet.
Iam simply unable to accept that the evidence demonstrated that if there had
been no breach of contract by the appellant the respondents would have secured
building consent by April 1989 sufficient to enable them to commence
construction on 1 May 1989. As the commencement of construction on that date
was critical to a completion of the project in mid-February 1990 it must follow
that I am unable to accept that, if the project had proceeded unimpeded by any
breach of contract, the buildings would have been completed by that time. In my
opinion the respondents failed to establish that if there had been no breach of
contract they would have been in the position to commence construction prior to
December 1989. Even if the construction is assumed to have taken only the 42
week period allowed by his Honour this would mean that the buildings would not
have been completed until the end of July 1990, at the earliest, a date by which,
on the evidence, the property market had substantially collapsed.
It follows from this conclusion that his Honour's assessment of damages
cannot stand and the judgment must be set aside. Although it would be highly
desirable for this Court to reassess damages in the present circumstances in order
to save the parties additional cost and delay I fear that the court is not in a
URJ CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (Clarke JA) 53
position in this case to carry out that exercise. This was, I think, accepted by the
parties who did not put before the court any calculations based upon assumptions
different from those accepted by his Honour. Accordingly, in my opinion Cole J's
judgment should be set aside and the case referred for a new trial on the issue of
damages.
The appellant also challenged his Honour's conclusions that the cost of
construction of the development would have been $3,300,00 and that all sales of
strata units would have occurred by 31 March 1990 (that is, before the market
deteriorated). Insofar as I have indicated the damages ought to be reassessed it is
not desirable that I deal with these claims. My silence on these aspects of the case
should not, however, be regarded as any indication of my views.
Finally, I observe that if this court had been able to re-assess the damages it
would have been required to assess in accordance with appropriate legal
principles. The application of those would, I tend to think, have required the court
to adopt an approach different from that followed by his Honour. What is readily
apparent is that the assessment of the damages depended upon answers being
given to a significant number of hypothetical questions concerning the likelihood
of specific events, a number of which were dependent upon the volition of third
parties, occurring. For instance, the assessment depended essentially upon the
hypothesis that, absent breach, construction would have been completed by
mid-February 1990 and all sales settled by the end of March of that year. Those
hypotheses depended in turn upon hypothetical findings that, breach apart,
development and building consents would have been obtained at much earlier
dates than they actually were and that construction commenced by 1 May 1989.
The assessment also depended upon the acceptance of evidence given by Mr
Robinson, a real estate agent, that it was probable that all units would have been
sold off-plan by mid-February 1990. This evidence was, at best, an educated
prediction of what might have occurred.
There were other contingencies. That there would be no delay in construction
that would lead to additional costs; that the construction costs would be as
originally estimated by Mr Fisher the quantity surveyor in February 1989 with a
minimal allowance for contingencies; and that (and this was most important)
insofar as the cost of the project was far in excess of $6.5 million the respondents
would have been able to raise additional funds on precisely the same terms as the
original promised advance of $6,500,000 in order to achieve completion. All of
these matters were highly speculative yet his Honour reached findings on the
probabilities as to the likelihood of each of the contingencies occurring and
having made findings treated each occurrence as certain. Indeed he went further.
He decided that as each of these events would have occurred if there had been no
breach it was probable that the respondents had lost profits in excess of
$2,000,000.
There is a real question in my mind whether this was a correct approach.
Assuming that a loss of potential profits was capable of assessment it seems to
me wrong in principle to assess the damages on the basis that a particular result
would have occurred when the conclusion is based on evidence which could
properly be described as speculative.
I tend to the view that the claim in this case should more properly be regarded
as a claim for the loss of an opportunity or chance to make profits than a claim
for loss of actual profits. The principles concerning such a claim are discussed in
Chaplin v Hicks, (1911) 2 KB 768, and Howe v Teefey, 27 SR 301. (See also
Auburn Municipal Council v ARC Engineering Pty Ltd, (1973) 1 NSWLR 513,
54 UNREPORTED JUDGMENTS
at 525.) Although in McRae v Commonwealth Disposals Commission, 84 CLR
377 (see also Hutley JA in Levi Strauss (Australia) Pty Limited v Mayne
Nickless Limited, (Court of Appeal, 17 December 1976, unreported), it was
suggested (at 412) that the principle in Chaplin v Hicks might be limited to the
breach of a contract to give a party a chance to make a profit or gain a benefit the
authorities seem to me to establish that the principle has a wider operation and
applies in situations where a party seeks to establish a loss which is, in the light
of a number of contingencies, properly categorised as one of an opportunity to
gain a benefit. After all the second and third respondent, who were not
experienced developers, were embarking on a speculative development at the end
of which they may have made a profit or loss. While developers may have
laughed at the suggestion that they might make a loss on a property development
in the mid 1980's the extent of the property boom in 1987 and 1988 pointed to
a possible collapse in the property market in later years. And this is what
occurred. In assessing damages in civil actions the law observes a distinction
between cases in which the question is whether a particular act has occurred and
those in which the question concerns what will occur, or what might otherwise
have occurred, in the future. This distinction was adverted to by Lord Diplock
with Lord Diplock's statement in Mallett v McMonagal, 1970 AC 166, at 176.
His Lordship said:
"The role of the court in making an assessment of damages which depends
upon its view as to what will be and what would have been is to be contrasted
with its ordinary function in civil actions of determining what was. In
determining what did happen in the past a court decides on the balance of
probabilities. Anything that is more probable than not it treats as certain. But in
assessing damages which depend upon its view as to what will happen in the
future or would have happened in the future if something had not happened in the
past, the court must make an estimate as to what are the chances that a particular
thing will or would have happened and reflect those chances whether they are
more or less than even, in the amount of damages which it awards."
To like effect was the statement by Lord Reid in Davies v Taylor, 1974 AC
207, at 212-3. In Malec v J C Hutton Pty Ltd, 64 ALJR 316, Brennan and Dawson
JJ said (at 316):
"By contrast, earning capacity can be assessed only upon the hypothesis that
the plaintiff had not been tortiously injured: what would he have been able to earn
if he had not been tortiously injured? To answer that question, the court must
speculate to some extent. As the hypothesis is false - for the plaintiff has been
injured - the ascertainment of earning capacity involves an evaluation of
possibilities not establishing a fact as a matter of history. Hypothetical situations
of the past are analogous to future possibilities: In one case the court must form
an estimate of the likelihood that the hypothetical situation would have occurred,
in the other the court must form an estimate of the likelihood that the possibility
will occur."
(See also the majority judgment at p 318; "Evidence, Proof and Probability"
(and Ed) Eggleton pp 210-212.)
It is true that these statements were made in the context of torts. But I find it
difficult to believe that there can be a distinction in principle in the manner in
which the law deals, relevantly, with hypothetical situations depending upon
whether the case is one of contract or tort. If, for instance, a patient sued a doctor
claiming that he had been blinded as a consequence of the doctor's breach of
contract and thereby lost the opportunity to become a concert pianist would the
URJ CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (Clarke JA) 55
facts be dealt with differently depending upon whether the claim was advanced
in contract or tort. I think not. In Hardware Services Pty Ltd v Primac Association
Ltd, (1988) 1 Qd R 393, Thomas J expressed the same opinion at 401 and
supported the opinion with reference to authority.
It may be that in particular cases the court is able to make a finding that a
certain event will probably occur in the future or, for example, that a present
disability will, as a matter of probability, continue permanently. In those cases the
law treats the event as certain and awards damages accordingly. Further the
weight of authority would appear to support the view that in contract cases no
discount is allowed for the possibility that the probable event may not occur. See
for instance, Levi Strauss (Aust) Pty Ltd v Mayne Nickless Ltd, (New South
Wales Court of Appeal, 17 December 1976, unreported, per Mahoney JA; TCN
Channel 9 Pty Ltd v Hayden Enterprises, (1989) 16 NSWLR 130, at 151-6, 159;
Sykes v Midland Bank Executor and Trustee Co Ltd and Ors, (1971) 1 QB 113,
at 129-130 and Amann Aviation Pty Ltd v The Commonwealth, 22 FCR 527, at
538 and 539, 566, cf at 546. There is, however, something to be said for the
opposing view and I would wish to reserve my own opinion on the question.
But there is a clear distinction between those cases in which a court is able to
conclude that a particular event would probably have occurred in the future if
there had been no breach and those in which there is a contingency, or there are
a number of contingencies, which rendered it quite uncertain whether the event
in question would have come to pass. The former category would include cases
where, to use the words of Best CJ "the plaintiff is entitled to have a
compensation for being deprived of that which almost certainly happens in those
cases" (Richardson v Mellish, (1924) 2 Bing 229, at 239) although it may not be
limited only to those cases (see the valuable discussion of the subject by
Mahoney JA in Levi Strauss).
This case was, however, more complicated than a simple claim for loss of
chance to make a profit on a venture. Properly analysed the respondents claim
included two elements expenditure in the venture wasted as a result of the breach
and the loss of prospective profits.
They claimed that if the contract had not been breached they would have
recouped their expenditure and made a profit. As their expenditure was far greater
than the value of the assets (real property) obtained for use in the development
their claim for damages could not accurately be described solely as a claim for
loss of profits.
Although there are statements in the authorities to the effect that an innocent
party is obliged to elect between a claim for recoupment of expenditure and a
claim for lost profits (eg Cullinane v British "Rema" Manufacturing Co Ltd,
(1954) 1 QB 292, at 303) those statements should be understood as applying in
those cases where to allow both claims would result in over compensation. In
cases where it is necessary to make an award of damages including expenditure
and lost profits in order to comply with the basic rule according to which
damages are awarded for breach of contract then principle demands that the
award made cover both elements. The judgment of Burchett J in Amann (supra,
at 568 et seq) provides a convincing rebuttal of the contrary argument.
In a case where claims for both heads of loss are maintained the court is
required to determine, first, what expenditure has been wasted and, second, what,
if any, profits were likely to have been received if the contract had been observed.
56 UNREPORTED JUDGMENTS
The first task is a simple exercise in fact finding. The second involves
consideration of the possible course of the innocent party's venture upon the
assumption that a breach had not occurred. Except in those relatively rare cases
in which a court is able to say that it is clear that a profit would have resulted the
court will need to determine whether the evidentiary material is sufficient to
support a finding as to the most likely of the possible courses which the venture
could have taken. In some instances the uncertainties may be so great, or the
contingencies may be so numerous, that the court will simply be unable to say
whether a profit or loss was the likely result. In other words, any prediction would
be no more than guesswork or speculation.
In such a case it would seem to me that the innocent party would be confined
to expenditure wasted. Where there is sufficient evidentiary material to enable the
court to conclude that there was a reasonable possibility, say 40 per cent chance,
that a profit of $X would have been earned then the damages should include an
amount to reflect the loss of that chance.
Where, however, the court concludes that if the contract had been observed the
chances are that the innocent party would have suffered a loss it may well be that
the claim for expenditure should be reduced to reflect the fact that all expenditure
would not have been recouped if the contract had been fulfilled. However, neither
this question nor an allied one concerning the onus of proof should be regarded
as settled. (See generally Amman, supra p 570-1; McRae, supra p 414; CCC
Films Ltd v Impact Quadrant Films Ltd, (1985) 1 QB 1, at 40.) There are two
outstanding issues - breach of s52 of the Trade Practices Act and Estoppel -
which received very little attention during the appeal.
His Honour found a breach of s52 of the Trade Practices Act but did not assess
the damages flowing from the breach for the simple reason that his assessment on
the respondents' primary claim was more favourable to the respondents. The only
challenge to the finding of breach was essentially the same as the appellants
mounted on breach of contract. That is, that the representations made on 21
September 1988 would have been understood as having been conditioned on
formal contracts. I have already rejected that submission and, accordingly, his
Honour's finding on the s52 point should stand.
The same comments apply in respect of the finding on estoppel which should
stand. The importance of this finding was that it led to a judgment for the second
respondent in the claim for possession of a mortgaged property. Although I am
somewhat troubled by this aspect of the case it seems to me that once the only
argument which was presented is rejected the judgment must stand.
In the light of these conclusions the following orders should be made:
(1) The appeal should be allowed;
(2) That O.1 and O.3 made by Cole J in proceedings No 50199/90 be set aside.
(3) Order a new trial in matter No 50199/90 before the Commercial Division
of the issue of damages;
(4) The appellant to pay the respondents' costs of the trial;
(5) The respondents to pay the appellant's costs of the appeal and, if qualified,
to have a certificate under the Suitors Fund Act thereof.
ORDERS
1. Appeal dismissed with costs; and
2. Cross appeal dismissed. No order as to costs.
Counsel for Appellant: T Simos QC and JM Ireland QC and PR Whitford
URJ CUSTOM CREDIT CORPORATION LTD v CENEPRO PTY LTD (Clarke JA) 57
Solicitors for Appellant: Gadens Ridgeway
Counsel for Respondent: TM Jucovic DP Robinson and D Pritchard
Solicitors for Respondent: Freehill Hollingdale and Page