VAROO PTY LTD v MULTIPLEX CONSTRUCTION PTY LTD [1991] NSWCA 274
NSW Caselaw
Full text
Select any passage to save a personal note with optional tags.
VAROO PTY LTD v MULTIPLEX CONSTRUCTION PTY LTD
SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL
KIRBY P, PRIESTLEY CLARKE JJA
18 and 22 February 1991, 22 February 1991
[1991] NSWCA 274
KEY WORDS: Appeal — arbitration — leave to appeal — construction of
agreement — question not ripe APPEAL — leave to appeal — Court of Appeal —
grounds for allowing or declining — building arbitration case — held: (1) The Court
will not normally give leave to appeal to correct the reasons of the judge appealed
from but to correct the decision; (2) The Court in the present case would decline
leave as the issues were not concrete but largely hypothetical.
ARBITRATION — building arbitration — cost plus contract variation clause —
need for "substantial variation" to the "scope of the works" — arbitrator makes
interim award Cole J grants leave to appeal — confirms award — application for
leave to appeal to the Court of Appeal — held: (declining leave and dismissing
summons) (1) The Court will not normally give leave to appeal to review the reasons
of the judge appealed from but to correct the decision challenged; (2) In the present
case, the decision of Cole J, affirming the interim award of the Arbitrator, was not
shown to be incorrect; (3) Appellate review, if any, should be postponed until the
Arbitrator had determined the application of the variation clause to concrete claims.
Kirby P (expressing the reasons and orders of the Court): The Court declines
leave to appeal from the order of Cole J dismissing an appeal which was, in turn,
brought, by his Honour's leave, from an interim award of Mr G L Lumsdaine,
Arbitrator.
The Court will not usually grant leave to appeal to correct the reasons of a
judge leading to his or her decision. Leave to appeal is usually given to permit
the Court, on appeal, to correct the decision appealed from.
In this case, Cole J dismissed the appeal from the Arbitrator's interim award.
In providing his reasons for taking that course, his Honour made a number of
observations about the meaning of the contract between the parties which have
been criticised by the claimant. Some of his Honour's observations may have
gone beyond what it was necessary for him to say to reach the conclusion which
he reached. In dismissing the summons for leave to appeal, this Court is not
necessarily endorsing all of the reasons given by Cole J for the order which he
made. It may be necessary or desirable at a later time, to return to a consideration
of those reasons and the construction of the contract there stated.
The result of Cole J's order is to confirm the conclusion stated in para 1.15 of
the Arbitrator's interim award. In that paragraph the Arbitrator stated: "1.15 Tam
of the opinion that pursuant to CL29, a SUBSTANTIAL VARIATION can arise
from an agglomeration of changes to the scope of the works as shown in the
Drawings and referred to in Cost Plan 4A, beyond that contemplated by the
parties at the date of the Contract."
The Court understands "can" in this paragraph to mean "may" and not to
indicate that every variation is necessarily to be included in a relevant
agglomeration of changes to the scope of the works.
2 UNREPORTED JUDGMENTS
The Court does not consider that there is sufficient doubt about the correctness
of the Arbitrator's statement, so understood, as to warrant the grant of leave to
appeal from the order of Cole J in turn dismissing a challenge to it.
The parties will now return to the Arbitrator who has set aside three weeks,
re-commencing on Monday next, for the hearing of the arbitration. The Arbitrator
will proceed to consider the various claims by the builder in respect of variations,
measuring each of them against the requirements of CL29 of the contract. He will
reach conclusions in each case which will eventually result in a final award. This
may then present a decision which will pose questions concerning the
interpretation and application of CL29 which are concrete. Such questions would
be more susceptible of appellate review than the issue tendered by the claimant
on this summons which has required the meaning of the contract to be dealt with
largely on a hypothetical basis.
The summons is dismissed. The claimant must pay the opponent's costs.
Summons for leave to appeal dismissed with costs.
Counsel for the Claimant: BS J O'Keefe QC / I Faulkner
Counsel for the Opponent: RS Hulme QC / MG Rudge
Solicitors for the Claimant: Dunhill Maddern and Butler
Solicitors for the Opponent: Cowley Hearne
Related laws
No related documents linked yet.
You've got 21 of 22 free Acts left this visit. Sign up anytime for Facts, Related, and study briefs too.