EDEN CONSTRUCTIONS (NSW) PTY LTD v HAINES [1991] NSWCA 86
NSW Caselaw
Full text
Select any passage to save a personal note with optional tags.
EDEN CONSTRUCTIONS (NSW) PTY LTD v HAINES
SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL
KIRBY P, SAMUELS and CLARKE JJA
25 and 26 February 1991, 18 October 1991
[1991] NSWCA 86
CONTRACT — collateral contract negligent misrepresentation contract avers
reliance on own enquiries — contract upheld. CONTRACT — contract for removal
of rock from sewer outfall — contract reduced to writing — written specifications
contain agreement that contractor has examined drawings etc, information relevant
to risks and site and surroundings — warranty that failure to do 80 will not relieve
contractor of liability to perform contract in accordance with terms — quantity of
rock discovered to be in excess of estimate — contractor argues entitled to recover
additional sums on grounds of (a) collateral contract; (b) warranties made to induce
it to enter into the contract; and (c) failure to exercise reasonable care in supplying
information — held: (Dismissing appeal from Giles J) (1) The information conveyed
in the contract was not warranted as true and correct; (2) There was no collateral
contract; (3) The claim in negligence in supplying incorrect information was not
established. Cutts v Buckley (1933) 49 CLR 189 considered.
Kirby P I agree with Samuels JA.
Samuels JA On 16 October 1986 the Minister for Public Works accepted the
appellant's tender made on 9 September 1986 for the removal of rock from the
seaward end of the Norah Head Outfall Tunnel of the Wyong Shire Sewerage
Scheme. The respondent is the nominal defendant appointed pursuant to the
provisions of the Claims Against the Government and Crown Suits Act 1912. No
formal document of contract was executed, but there is no dispute but that there
was a contract between the parties which consisted of the tender and its
accompanying schedules, some further correspondence which passed prior to
acceptance and need not be noted further, the letter of acceptance, the general and
special conditions and the specification and drawings. In addition I note that the
respondent contended, and the learned trial judge held, that the contract had been
varied by a letter of 10 March 1987 sent by the Public Works Department ("the
Department') to the appellant.
The appellant claimed substantial damages of the order of $1.3 million upon
four different and alternative bases, the last of which was added by amendment
granted on 23 March 1989 during the course of the trial, was ultimately rejected
by Giles J, and was not pursued on the appeal.
The evidence is dense rather than extensive perhaps, although the four appeal
books contain upwards of 1000 pages of oral testimony and written material,
which, since the appellant challenged a number of critical findings of fact made
by the learned trial judge, it was necessary to examine in some detail. However,
once analysed, the evidence and the issues can be summarised tolerably
concisely; and the labour involved has been very much lightened by Giles J's
lucid and careful judgment with which, I may say at the outset, I am in general
agreement. It seems to me that the best way of approaching the matter is first to
indicate the general nature of the works which the appellant undertook; then to
note the contractual provisions upon which the parties rely, and finally to indicate
2 UNREPORTED JUDGMENTS
the way in which the appellant put its claim. In explaining the nature of the work
and the circumstances in which it was to be carried out, I have drawn freely upon
the judgment.
A tunnel constructed as part of the Wyong Shire Sewerage Scheme terminated
at Norah Head in three nozzles spread in a fan-like formation, slightly short of
a roughly vertical cliff face and at a position below sea level. In introducing the
work, which was the subject of the contract, Giles J turned first to two drawings
known as 26 and 27, both included in the contract documents, the first being a
longitudinal section and the second a plan view. I will adopt the same course
because it is necessary, not merely to indicate in general the conventional
dimensions, both horizontal and vertical, which the drawings adopted, but also to
have regard to various notes and legends which the drawings contained.
Horizontal measurement was described as chainage, although actually in metres,
commencing at the seaward end of the nozzles at a point known as 'Chainage 0'.
Features to seaward were measured in positive metres from the nozzles and
features inland in minus quantities. Mean sea level was taken as Reduced Level
("RL") 100, and in the vertical scale features above that level were shown as
reduced levels in excess of 100 and features below that level as reduced levels
under 100. These vertical measurements were in metres too. Accordingly, as the
learned judge pointed out, RL 94.1 meant a position 5.9 metres below mean sea
level.
On drawing 27, the plan view, there was shown to seaward of the nozzles a
fan-shaped area in rough prolongation of the fan formation of the nozzles
themselves. The boundaries of the 'fan' were formed approximately by an
hypothetical extension of the axis of the two flanking nozzles. The 'fan'
contained an inner portion, immediately to seaward of the nozzles to a distance
of 5.2 metres, which was designated Zone 1, and the outer portion extending to
about 20 metres was described as Zone 2A/2B. Flanking the outer portion of the
'fan' on either side were hatched areas forming lateral extensions and designated
as Zone 2A. I take the rest of the description of the area from the judgment. In
section, these zones were picked up with vertical dimensions. Zone 1 was
depicted with vertical dimensions by way of stopped top and bottom lines, from
RL 102.3 at the highest to RL 92.9 at the lowest. Zone 2A was given the added
description, "(Loose Rock)', and was depicted with a top line running
horizontally at RL 95.0 to approximately ch 15.0, and then sloping downwards
to ch 20.0 at RL 90.0, and an irregular bottom line from RL 92.25 to RL 90.0.
Zone 2B was given the added description, "(Solid Rock)", and was depicted with
a top line being the landward part of the bottom line of Zone 2A and a stepped
or alternatively sloping bottom line from RL 91.9 to RL 91.3 (stepped) or RL
92.25 to approximately RL 91.0 (sloped).
Thus there was depicted three 'envelopes'. Broadly speaking, Zone 1 could be
said to be solid rock above and below sea level being that part of the cliff face
at the seaward end of the nozzles which required excavation to expose the
nozzles to the sea; Zones 2A and 2B could be said to be the rock further to
seaward which had to be removed in order to allow the discharge from the
nozzles to flow freely into, mix with, and be carried away by the sea; and of
Zones 2A and 2B, Zone 2A was the upper and larger envelope with a greater plan
area said to contain loose rock and Zone 2B was the lower and smaller envelope
said to contain solid rock. The contract was described in the documents, which
were provided of course by the Department, as a "schedule of rates contract" and
CT-05 "description of contract" (that is, the fifth condition of tendering) said:
URJ EDEN CONSTRUCTIONS (NSW) PTY LTD v HAINES (Samuels JA) 3
"The Contractor shall be paid on a Schedule of Rates basis subject to cost
adjustment." As it will appear, the contract was not strictly a schedule of rates
contract but contained also lump sum stipulations. The works were described in
this way:
"The work to be carried out under this Contract is the removal of rock from the
seaward (outlet) end of the Norah Head Outfall Tunnel.
The works will form part of the effluent outfall system for Wyong Shire at
Norah Head and are briefly summarised as follows:
a) drilling of the rock between the tunnel discharge nozzles and the sea.
b) cracking/breaking up of that rock by non-explosive means.
c) removal and disposal of that material together with boulders (and some solid
rock) from the sea-bed to leave a fan-shaped opening in front of the discharge
nozzles.
The material to be excavated is within the Munmorah Conglomerate. The rock
types of this formation consist of sandstones, pebbly sandstones and
conglomerates with siltstone and claystone beds."
The description of the site stated that it was located "at the seaward edge of the
rock platform adjacent to the Norah Head Lighthouse" and that the rock to be
removed "generally lies between RL 102.0 and RL 90.0." The conditions of
tendering in CT-16 drew attention to investigation reports referred to in para 5 of
the description of the site and CT-O9 specifically informed tenderers that they
"may ask for clarification of anything in the Tender Documents."
The claim added by amendment at the hearing, to which I have referred, and
which is not now pursued, was based upon general condition ("GC") 3.3(c) to
which I need not further refer. But GC 12 is of importance and was in these
terms:
"The Contractor shall be deemed to have
(a) examined carefully and to have acquired actual knowledge of the contents
of the Drawings, Specification, Schedules, Bills of Quantities (if any), Conditions
of Tendering, these General Conditions of Contract and the Special Conditions (if
any) and any other information made available in writing by the Principal to the
Contractor for the purpose of tendering; and
(b) examined all information relevant to the risks, contingencies and other
circumstances having an effect on his tender and which is obtainable by the
making of reasonable enquiries; and
(c) examined the site and its surroundings; and
(d) satisfied himself as to the correctness and sufficiency of his tender for the
work and that his price covers the cost of complying with all his obligations
under the Contract and of all matters and things necessary for due and proper
performance and completion of the Contract.
Failure by the Contractor to do all or any of the things he is deemed to have
done under this clause will not relieve the Contractor of his liability to perform
and complete the Contract in accordance with the terms and conditions thereof."
There are two special conditions which must be specifically mentioned. SC-14
provided:
"The Principal does not represent that information made available shows
completely the existing site conditions. The Principal is not responsible for any
interpretation, deductions and conclusions made by the Contractor from the
information made available and the Contractor shall accept full responsibility for
any such interpretations, deductions or conclusions."
SC 21 was in these terms:
4 UNREPORTED JUDGMENTS
"The Contractor must check and must ensure that any sub-contractor checks
all relevant dimensions on site before proceeding with the work under the
Contract. In no circumstances shall dimensions be scaled from drawings. The
layout of plant and equipment as shown on the Drawings shall be taken as
diagrammatic only and all measurements and other information required to carry
out the work specified shall be obtained by the Contractor on the site. No claim
for extras arising from failure to obtain measurements and other information on
site will be allowed."
Several paragraphs of the Specification should be referred to. S-01.1 described
the works in this way:
"The work to be carried out under this contract involves the removal and
disposal of rock from in front of the tunnel, which has been constructed by others,
in order to expose the outlet nozzles (which will be uncapped (by others) when
the system is commissioned).
Rock shall be removed to the specified profile, either stepped or sloped as
shown on Drawing 82272-26. Disposal shall be further out to sea and/or around
the headland at Norah Head as specified in 5-07.1.1."
The "specified profile" was congruent with what is later described as "the
minimum clearance line" and appears in drawing 26 either as a stepped or sloped
line as the lowest boundary of Zone 2B.
S-06 dealt with rock breaking, and 06.1 provided:
"Zone | (Refer Drawings Nos 82272-26 and 27)
The Contractor shall break the rock by non-explosive means into pieces with
size compatible with the disposal methods to be used (Refer 5-06.3.)"
5-06.2 provided:
"Zone 2B (Refer Drawings Nos 82272-26 and 27)
The Contractor may use explosives for breaking of sea bed solid rock (if any)
seaward from line AD to the minimum clearance line shown on Drawing No.
82272-26." and S-06.4 said: "Payment for breaking and removal of sea bed solid
rock (if any), that is Zone 2B, will be made as described in 5-08.4."
I find it necessary, as the learned judge did, to set out in full the provisions of
S-08.4, but its terms must be prefaced by indicating the provisions made in the
Schedule of Rates of which Item 4 is the relevant portion. It was in these terms:
"4. (a) Breakup, removal and disposal of rock from Lump Item Sum 68,785.00
Zone 1 as specified and shown on Drawings
82272-25, 26 and 27 (S-06, 07, 08.4)
(b) Removal and disposal of rock on the sea bed in
Zone 2A; and breakup, removal and disposal of
rock in Zone 2B; as shown on the drawings and as
specified. (S-06, 07, 08.4, SC-23)
(i) Zone 2A - in situ loose rock 1070 cu.m 347.85 372,199.50
(ii) Zone 2B - in situ solid rock 100 cu.m 587.45 58,745.00"
S-08.4 then provided as follows:
"08.4 Item 4
08.4.1 The amount tendered for Item 4(a) will be paid for rock removal from
Zone | that is, broken up, removed and disposed as specified and shown on
Drawings 82272-25, 26 and 27. The amount shall be deemed to include all
necessary additional drilling, over and above that specified and paid for under
URJ EDEN CONSTRUCTIONS (NSW) PTY LTD v HAINES (Samuels JA) 5
Item 3, as well as removal of the timber formwork from around the nozzles,
details of which are shown on Drawing No 8227-27.
Based on survey measurements and mathematical calculations, the quantity of
solid rock within Zone | has been estimated at approximately 290 cubic metres.
Refer calculations on Drawing 8227-27. This quantity is not for contract
purposes, but for information only.
For purposes of this contract, Zone 1 will not be re-surveyed, other than in
accordance with S-09, nor its estimated quantity re-calculated The Contractor
will be deemed to have made his own assessment of the totality of work required
within Zone 1 and of the sufficiency of his tender amount for Item 4(a) for
performance of such work.
Irrespective of the accuracy of the said estimated quantity and irrespective,
also, of the actual quantity of solid rock broken up and disposed from Zone 1, the
contract amount for Item 4(a) will be paid upon completion of rock
removal/disposal from Zone 1 in accordance with the contract.
For purposes of progress valuation and payment for item 4(a), regard will be
had for: * the amount of rock drilling within Zone 1 (other than that along lines
ABCD for which payment will be separately made against Item 3) * the assessed
quantity of solid rock which has been broken up but not yet removed to disposal
* the assessed quantity of solid rock which has been broken up and removed to
disposal all as an assessed proportion of the totality of work covered by Item 4(a).
However, the Superintendent reserves the right which right will not be
exercised unreasonably to make no progress payment under Item 4(a) except in
respect of the assessed proportion of the total quantity of solid rock from Zone
1 which has been removed to its final disposal.
08.4.2 Based on survey measurements and mathematical calculations, as
shown on Drawings 82272-25, 26 and 27, the total quantity of rock - whether
loose or solid on the sea bed within Zones 2A and 2B - has been determined at
1170 cubic metres.
For all purposes of the contract, the said total quantity will apply unless it be
challenged by the Contractor.
Should the Contractor wish to challenge this total quantity of 1170 cubic
metres for Zones 2 and 2B, he shall do so prior to any removal of rock from Zone
2 and prior also to any deposition of broken rock from Zone | into or onto Zone
2A. Otherwise, no challenge will be entertained.
Upon a challenge by the Contractor to the total quantity of Zones 2A and 2B,
the surface of Zone 2A will be resurveyed, and the total quantity within Zones 2A
and 2B will be recalculated. Such a re-calculation shall be by mathematical
formulae equivalent to those shown on Drawings 82272-26 and 27 or such other
mutually agreed formulae.
The re-survey and re-calculation of quantity shall be undertaken jointly on
behalf of the Principal and the Contractor, with each party initially bearing its
own costs. For all contract purposes, the revised quantity determined by
re-survey and re-calculation whether greater or lesser than 1170 cubic metres will
supersede and supplant the previously determined quantity of the 1170 cubic
metres.
In the event of the revised quantity being different (greater or lesser) from the
1170 cubic metres by 5% or more, the Contractor's reasonable costs for re-survey
and re-calculation will be reimbursed by the Principal. Should the revised
6 UNREPORTED JUDGMENTS
quantity be different (greater or lesser) from 1170 cubic metres by less than 5%,
the Principal's costs for re-survey and re-calculation shall be met by, or
recoverable from, the Contractor.
In like manner, should the revised quantity be different from 1170 cubic metres
by 5% or more, the Contractor will be entitled to an extension of time for
completion in respect of any delays to progress caused by the re-survey and
re-calculation; but, if the difference be less than 5%, then no claim for extension
of time will be entertained.
The Principal has not attempted to measure the separate quantities in Zones 2A
(loose) and 2B (solid). For purposes of Item 4(b)(i) in the Schedule of Rates, it
has been assumed that 1070 cubic metres of the total quantity is in Zone 2A and
the remainder (100 cubic metres) is in Zone 2B.
Attention is directed to Clause SC-23 which deals with the guaranteed
accuracy of those assessed quantities and to sub-clause 3.3(c) of General
Conditions of Contract which deals with the impacts of departures from such
guaranteed accuracy.
Attention is further directed to Clause S-07.2, which provides for a survey of
the surface of Zone 2B after removal of all loose rock from Zone 2A.
From that survey, the quantity of solid rock remaining within Zone 2B will be
calculated, using mathematical formulae similar to those shown on Drawing Nos
82272-26 and 27.
This calculated quantity for Zone 2B will be the total quantity for which
payment will be made against Item 4(b)(ii), provided always that the
Superintendent shall have directed removal of rock from Zone 2B. Refer S-07.3
The calculated quantity for Zone 2B will be subtracted from the total quantity
for Zones 2A and 2B (ie 1170) cubic metres or as revised in accordance with the
foregoing) to determine the quantity for Zone 2A, which will be deemed to be the
actual total quantity for which payment will be made against Item 4(b)(i).
The progress quantity of loose rock removed to final disposal from Zone 2A
for which progress payments will be made against Item 4(b)(i) will be as
mutually agreed, or as determined by the Superintendent in the event of
disagreement.
Such progress quantities will be assessed by whatever means are appropriate
to the circumstances, including visual observation of the sea bed and/or
assessment of quantities transported to disposal, and/or underwater survey.
Similar principles will apply for progress measurement and payment, if
required, for removal from Zone 2B against Item 4(b)(ii).
08.4.3 The rate tendered for Item 4(b)(i) will be paid for each cubic metre of
loose rock pre-existing in and removed from Zone 2A but not material from Zone
1 as specified and as shown on Drawings Nos 82272-25, 26 and 27 as might be
moved from Zone | into/onto Zone 2A. The rate tendered shall be deemed to
include disposal.
Refer S-08.4.2 and SC-23 regarding quantities and limits of accuracy for Item
4(b)(i).
08.4.4 The rate tendered for Item 4(b)(ii) will be paid for each cubic metre of
solid rock broken up, removed and disposed from Zone 2B as specified and
shown on Drawings Nos 82272-25, 26 and 27.
Refer S-06.2, S-06.4, S-07.3, S-08.4.2 and SC-23. 08.4.5 Where disposal is
wholly or in part on land the rates for Items 4(a), 4(b)(i) and 4(b)(ii) shall be
deemed to include the cost of carrying out the work in accordance with the
particular requirements of 5-07.1.1(b)."
URJ EDEN CONSTRUCTIONS (NSW) PTY LTD v HAINES (Samuels JA) 7
As the learned judge pointed out, in S-08.4.2 there were references to SC-23,
GC 3.3(c) and S-07.2 and 5-07.3. The first and second of these provisions were
of relevance to what Giles J treated as the first ground of the plaintiffs claim,
which was added by amendment, and which is not pursued in the appeal, and I
need not therefore refer further to these stipulations. However, S-07.2 and S-07.3
remain material and were in the following terms:
"07.2 Underwater Survey after Completion of Zone
07.2.1 After the removal of all loose rock from Zone 2A (whether pre-existing
or disposed there from Zone 1) a joint underwater survey shall be carried out in
order to ascertain the surface of Zone 2B. Notice of such survey shall be given
by the Contractor to the Superintendent at least two weeks before the sea bed is
expected to be in readiness for it, in order that the necessary arrangements can be
made and to allow for suitable diving access.
07.2.2 The time for completion of the survey will be two (2) weeks from the
date notified by the Contractor. The Contractor shall be entitled to an extension
of time and reasonable costs should the survey not be able to be carried out within
the time specified.
07.3 Rock Removal from Zone 2B
The Principal reserves the right to direct the removal of solid rock from Zone
2B or to leave it in-situ.
Attention is directed to S-08.4.2 and SC-23 regarding the limits of accuracy for
work under Item 4(b)(ii). No payment will be made arising from the non
performance of work under Item 4(b)(ii) should the Superintendent direct that
solid rock on the sea-bed be left in-situ."
The time for practical completion of the works was thirty weeks from 16
October 1986, the date upon which the tender was accepted, and was thus 13 May
1987. It is unnecessary, I think, to traverse in any detail the performance of the
works. It is enough to say that, ultimately, a certificate of practical completion
was issued on 8 June 1988, and in a cross-claim the respondent claimed
liquidated damages for the over-run of fifty six weeks in the sum, including
interest, of $130,779.18.
Before turning to the way in which the appellant presented its case at the trial
and on the appeal, I must refer to a variation of the contract which was effected
by a letter of 10 March 1987 written by the Department to the appellant and the
subject of considerable contention at the trial. However, although the notice of
appeal disputed the conclusion to which the learned judge came in respect of it,
the appellant no longer presses those grounds of appeal. Accordingly, the
provisions of the contract, that is, in S-08.4.2, and, of course, in the drawings,
which "determined at 1170 cubic metres" the total quantity of rock to be
removed, stood unaffected by the possibility of the challenge contemplated by
S-08.4.2; and, secondly, the variation recorded in the letter abolished any
distinction between loose rock or solid rock within the total determined quantity
of 1170 cubic metres. Hence, a further consequence was that the provision for a
survey in S-07.2 could thereafter be put aside.
This explanation of the terms of the contract now enables me to state
succinctly the fundamental issue between the parties. Following the variation
effected by the letter of 10 March 1987 (or, indeed, according to the respondent's
contention accepted by the learned judge, even before that variation in the
absence in fact of any challenge to the "determined" quantity of rock), the
contract was one in which the appellant was to be paid at the agreed rate for the
removal of 1170 cubic metres of rock. As the learned judge put it: "For all
8 UNREPORTED JUDGMENTS
purposes of the contract that total quantity would apply unless it be challenged
by the plaintiff." And I cannot do better than state the ultimate interpretation of
the contractual provisions in his words: "The result of these provisions was that
the total quantity of rock removed for which payment would be made was not the
actual quantity of rock removed but either 1170 cubic metres or some other total
quantity calculated consequent upon challenge."
As I have pointed out, there was not only no challenge in fact but the provision
for challenge was in effect removed from the contract. I should add that, in any
event, by 10 March 1987, removal of rock having already begun from Zone 2, the
time limited for any challenge pursuant to S-08.4.2 had probably expired. Hence,
the appellant's case was that it had entered into a contract to remove 1170 cubic
metres of rock disposed in certain formations, but found that the amount of rock
which had to be removed, and which the plaintiff did remove, was very much in
excess of that figure in circumstances of considerable difficulty. This case was put
at the trial in four different ways, but now only three remain for consideration.
First of all, it was alleged that there were contractual warranties -
(a) that there was no more than 1,170 cubic metres of rock in Zone 2;
(b) that Zone 2 consisted of the rock shown in the drawings;
(c) that the rock in Zone 2 was below RL 95.2;
(d) that there was no solid rock in Zone 2 seaward of ch 13.5;
(e) that the sea floor seaward of ch 16.7 was at RL 89.3 and consisted generally
of sand and shingle."
These warranties were made, it was contended, expressly or by necessary
implication by the Schedule of Rates Item 4(b)(ii), S-01.1, S-08.4.2 (para 1 and
para 2) and by Drawings 26 and 27. However, in breach of these warranties
(a) there was approximately 2,500 cubic metres of rock in Zone 2;
(b) Zone 2 did not consist of the rock shown in the drawings but consisted of
rock generally two to three metres higher than the rock shown in the drawings,
and almost all solid, not loose, rock;
(c) the rock in Zone 2 rose as high as RL 97.5;
(d) there was solid rock 2.6 metres deep in Zone 2 seaward of ch 13.5 as far
as ch 20 and beyond;
(e) the sea floor seaward of ch 16.7 as far as ch 20 and beyond was at RL 92
and consisted of solid rock.
Secondly, the plaintiff asserted that "in order to induce the plaintiff to tender
for, and thereafter to enter, the contract, the Department" made the warranties
upon which the first cause of action depended.
Finally, (I am taking these claims in the order in which the learned judge dealt
with them and not in the order in which they appear in the amended statement of
claim) the plaintiff contended that the respondent failed to exercise reasonable
care in supplying the information which made up the warranties to which
reference has already been made. This information was said to have been
conveyed by those portions of the contractual documents in which the so-called
warranties were said to reside. The acts and omissions relied upon were
(a) failing to carry out proper underwater survey of the site;
(b) failing to follow proper underwater survey procedure;
(c) failing to obtain accurate survey data;
(d) failing to process survey data accurately (alternatively to (a)-(c));
(e) failing to plot survey data accurately (alternatively to (a)-(d));
(f) providing information which contained gross errors (the errors being the
respects in which the information was said to have been incorrect).
URJ EDEN CONSTRUCTIONS (NSW) PTY LTD v HAINES (Samuels JA) 9
I turn first to the claim that the contract contained the contractual warranties
which I have set out above. His Honour rejected that submission, taking the view
that reading the contract as a whole, the representations (a word his Honour used
to comprehend the substance both of the contractual counts and the count in
negligence) were not, on its proper construction, to be found in it. The appellant
repeated before us the same submissions which he had advanced to the judge
below.
First of all, it was contended that support for the argument was to be found in
the various notes, legends and descriptions on the drawings, in particular
numbers 26 and 27. It was said, for example, that they contained a description
that Zone 2A consisted of loose rock and Zone 2B of solid rock; and that the
longitudinal section on drawing 26 of Zone 2A showed "rocks both large and
small not filling the envelope entirely." Reference was made to the position of
survey marks on drawing 26, particularly the note in the area of RL 89.3
"generally 89.3 (sand/shingle bottom)", and to various other legends and
depictions on the drawings, the calculations of the volumes of the "envelopes",
especially those on drawing 27, and to the survey notations on the plans.
Secondly, some support was sought from the diver's report, not arising from
any detailed information which it contained, but said to be provided merely by
the indication that there had been an underwater survey undertaken.
Thirdly, the argument relied upon various provisions of the contract, in
particular, as I have already mentioned, S-6, S-08.4.2 and the Schedule of Rates.
I have only summarised these contentions because they are very fully set out
in the judgment under appeal and may be categorised in this way. The contention
that the Department promised that there was no more than 1170 cubic metres of
rock in Zone 2 was essentially based upon Items 4(b)(i) and (ii) of the Schedule
of Rates and 5-08.4.1 and S-08.4.2; and the representations, to adopt the learned
judge's word, which were said warrant the topographical condition of the area of
the works, were said to be established as promises by what appeared on the
drawings.
It is plain, of course, that the contract must be construed as a whole. When it
is considered in this way it seems to me, with all respect to the argument of
counsel for the appellant, that it is very clear indeed that language was chosen
which was intended to indicate, and fairly did so, that the amount of rock to be
removed, and its precise disposition, were essentially uncertain. It was submitted,
for example, that the appellant could draw some comfort from the confrontation
between the word 'estimated' in S-08.4.1 and the word 'determined' in S-08.4.2.
If the suggested conflict between them is in fact realised, and I do not think that
it is, it would be extremely difficult in any event to assign any precise or certain
meaning to the information which each word was designed to convey. The use of
'estimated' obviously indicates something short of certainty, and there is no
certainty to be got from 'determined' when regard is had to the context in which
the word appears. It, in effect, introduces the provision for challenge, to which
reference has already been made, by pointing out that the determination of 1170
cubic metres based on survey measurements and mathematical calculations as the
total quantity of rock within Zones 2A and 2B will apply "for all purposes of the
contract.... unless it be challenged by the Contractor." There follow the detailed
provisions of challenge which I need not repeat. Further, later in the formula, this
is said: "For all contract purposes, the revised quantity determined by re-survey
and re-calculation [that is, following upon a challenge].... will supersede and
supplant the previously determined quantity of 1170 cubic metres."
10 UNREPORTED JUDGMENTS
In those circumstances, I find it impossible to see how the quantity of 1170
cubic metres can be regarded as in any way a promise of how much rock was
actually there. Again, towards the end of S-08.4.2, it is specifically provided that:
"The Principal has not attempted to measure the separate quantities in Zones 2A
(loose) and 2B (solid). For purposes of Item 4(b)(ii) in the Schedule of Rates, it
has been assumed that 107 cubic metres of the total quantity is in Zone 2A and
the remainder (100 cubic metres) is in Zone 2B." The emphasis appears in the
original document. The way in which S-07.2 contemplated an underwater survey
after the work had been completed in Zone 2A and the references to this exercise
in S-08.4.2 tend, in my opinion, to reinforce the respondent's answer to the
appellant's argument and the learned judge's conclusions. The provisions to
which I have just referred make it plain that the quantity 'determined' was not
intended to be a prediction of what the contractor would encounter, but was a
conventional figure adopted as an essential ingredient in the formula for payment.
Similarly, the notes and legends on the drawings abound in examples of what
can reasonably be regarded only as intimations of lack of certainty and definition,
«6
for example, phrases such as "theoretical bottom profile", "approximate extent of
boulder covered area", "approximate limit of boulder covered area (varies)", with
no indication of course as to the precise dimensions of the variation. I add the use
of the description "cliff (nominally vertical)", and the reference on drawing 27 to
the volume in the hatched areas on either side of the main portion of the fan area
as being "based on an assumed depth of loose material of 1.5 metres"; and the
appearance on drawing 26 of the profile decorated with question marks.
Finally, overall must stand the opening sentence of SC-14: "The Principal does
not represent that information made available shows completely the existing site
conditions." In my opinion, the learned judge was perfectly correct to conclude
that the information conveyed in the contract documents, including the drawings,
was not warranted as true or correct.
The second submission put to the learned judge and rejected, and run again
before us, was that there was, in the alternative, a collateral contract to the effect
that in consideration that the appellant would enter into the contract, the
Department warranted the truth of the various representations alleged. This is a
curious argument because, in essence, it amounts to this; that in consideration
that the appellant would enter into a contract upon certain terms the Department
warranted that those terms were true. A collateral contract of the kind which the
appellant is seeking to erect is ordinarily to be found in the provisions of some
antecedent contract or promise, the consideration for which was the claimant's
entering into a main or principal contract, and "intended to be collateral, extrinsic
or supplementary to the main contract as distinguished from being part of it":
Cutts v Buckley (1933) 49 CLR 189 at 198 per Dixon J. In the present case there
is no such antecedent or independent contract. The consideration for the promises
allegedly made can only be the entry into the contract in which those promises
are, as the appellant contends, to be found. There was, therefore, no collateral
contract. The argument was, no doubt, stimulated by an endeavour to escape from
the very real difficulties perceived to lie in the way of the assertion of the
contractual warranties. To adapt Lord Brightman's words in Cinzano (UX) Ltd v
Customs and Excise Commissioners (1985) 1 WLR 484 at 488 I admired
counsel's ingenuity and tenacity but was totally unconvinced.
In any case, for the reasons which I have already given, the representations
were not warranties at all, so that the argument fails in limine. If, contrary to my
view, any collateral contract, that is to say, an engagement separate from this
URJ EDEN CONSTRUCTIONS (NSW) PTY LTD v HAINES (Clarke JA) 11
contract to execute these works could be found, its material terms, if they were
warranties, would be inconsistent with the terms of the principal contract which
are not: Esanda Ltd v Burgess (1984) 2 NSWLR 139.
That brings me finally to the claim in negligence which contends that the
respondent owed the appellant a duty to exercise reasonable care that "the
information supplied", that is what I have called, following Giles J's terminology,
the representations, was correct. Because, in my view, the information relied
upon was not supplied in the contract documents (for the reasons I have already
discussed) the claim must fail. Those documents (including, of course, the
drawings) did not assert or represent the facts, or convey the representations,
upon which this cause of action depends; and no other source of those
representations is suggested. The appellant seeks to rely on the judge's finding
that "the information was substantially incorrect", this being a reference to the
conclusion that, for example, more rock than 1170 cubic metres was in fact
removed from Zone 2. But that finding does not supply an affirmative answer to
the question whether the respondent represented that there was not more than that
figure.
It is unnecessary to consider the authorities, which were not in any case the
subject of dispute. But I think I should observe that I agree with the respondent's
contention that in Morrison-Knudsen International Company Inc and Anor v
Commonwealth of Australia (1972) 46 ALJR 265 it was assumed, in the absence
of a demurrer, that the statement of claim disclosed a cause of action.
There remains the cross-claim. Here the appellant's challenge must fail for the
same reasons as those which have proved fatal to its earlier contentions. The
appellant;s argument was that it was the respondent's acts and omissions that had
prevented the appellant from completing the works by the contractual date; so
that the respondent was not entitled to exploit the provision for liquidated
damages: see Percy Bilton Ltd v Greater London Council (1982) 1 WLR 794. I
entirely agree with Giles J's answer: "The plaintiff was obliged under the contract
to carry out the work of rock removal to the specified profile regardless of the
quantity of rock which it in fact encountered and had to remove, and (whether or
not in breach of duty) nothing the Department did prevented it from doing so."
It is unnecessary for me to express any views about Mr Fitzhenry's evidence,
and I do not do so. The appeal should be dismissed with costs.
Clarke JA I agree with Samuels JA.
Appeal dismissed with costs
Counsel for Appellant: R H Macready
Solicitors for Appellant: Colin Biggers and Paisley
Counsel for Respondent: D Cowan
Solicitors for Respondent: H K Roberts, State Crown Solicitor
Related laws
No related documents linked yet.
You've got 21 of 22 free Acts left this visit. Sign up anytime for Facts, Related, and study briefs too.