MITCHELL v JA BRADSHAW PTY LTD v MITCHELL [1991] NSWCA 202
NSW Caselaw
Full text
Select any passage to save a personal note with optional tags.
MITCHELL v JA BRADSHAW PTY LTD v MITCHELL
SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL
SAMUELS AP, MAHONEY and HANDLEY JJA
17 June 1991, 17 June 1991
[1991] NSWCA 202
CONTRACT — building contract or management contract — question of fact —
reasons of trial judge adopted — no question of principle.
Samuels JA We have had some opportunity of considering this appeal from
Mr Justice Giles and since we have each come to a firm view as to its disposal
there seems to be no reason why we should delay giving judgment.
The appeal raises two questions of fact. The first concerns the relationship
which existed at the relevant times between the appellant and the second
respondent. It was the second respondent's contention that it acted for the
appellant as construction manager under a contract the precise terms of which
were certainly somewhat obscure. Thus its view was that it was an agent for the
appellant as its disclosed principal. The appellant on the other hand contended
that there was between him and the second respondent an engagement which
seems at least very similar to a lump sum or fixed price building contract. The
differences which emerge from these two positions are, I would think, obvious.
The learned judge considered with care the evidence which had been led
before him, and this was very extensive, and, founding upon his view of the
credibility of the principal antagonists and upon such documentary evidence as
there was, concluded that the arrangement was that for which the second
respondent contended. In my view the learned judge was correct in arriving at
this conclusion. I think that there would be little point in my simply recapitulating
the evidence that was led before him and then expressing a conclusion which, in
all substantial respects, would be congruent with his reasons with which, so far
as it may be necessary to do so distinctly, I express my agreement.
The second question concerns the responsibility for the casualty, that is for the
damage caused by the collapse of the southern wall of the works. The appellant,
for whom Mr Fagan has put an earnest and complete argument, asserted that this
issue depended upon a short point. I will not repeat all the evidence but, in
essence, the point was this. The first respondent, which I call hereafter
'Bradshaw', was represented on the site by Mr Blazley - at least he was the senior
of two supervisors. To be more accurate he was the supervisor and Mr Kerr was
the site foreman. The representative of the second respondent, whom I call
'DHD', on the site was Mr Clarke. The learned judge found, and I think with
respect quite correctly, that, in the ordinary course of his work, Clarke directed
Blazley what was to be done and Blazley took his instructions from Clarke. No
doubt Bradshaw was under a duty to the appellant, Mitchell, pursuant both to the
contract between them and in tort, to carry out the work it was undertaking with
reasonable care and skill. It is unnecessary, however, to examine that concept
further. There was an engineer, who was Mr Arnott, whose job it was to supervise
the technical aspects of the excavation work and to warn if any danger seemed
likely to ensue as a result of what was being done. He was, therefore, to maintain
some technical engineering restriction upon the extent of the works and to advise,
2 UNREPORTED JUDGMENTS
from the engineering point of view, as to how they might best be accomplished.
Bradshaw, so the evidence ran, worked under the directions of an engineer on all
or at least most of their jobs. They did so on this job. Blazley, from the way in
which the work had been carried out and the practice adopted between him and
Clarke, took the view that any instructions from Clarke had previously been
cleared with the engineer and had his authority.
On 29 January 1986 when the wall collapsed Bradshaw was about to excavate
at the bottom of the piers which were part of the construction maintaining the
integrity of the southern wall. The underlying support for the southern wall was
affected by loose soil. Blazley thought that to excavate at that point was, as he put
it, "rather dicey". He conveyed that apprehension to Clarke, Clarke told him, in
short, to go ahead because the job had to be done. Blazley did so, and the wall
came down. He said that he had assumed that Clarke's instruction had the
imprimatur of the engineer. The point that is advanced, upon which this part of
the case turns, raises the question whether Blazley was reasonably justified in
making the assumption he made about the intervention, or advice, of the
engineer.
It is clear that some days previously, and of course before the southern wall
had been reached, or at least before the bottom of the piers at the southern wall
had been reached, Blazley had complained to Clarke that that wall was dangerous
perhaps that is too strong a word - that work on or below that wall needed care
because the piers were honeycombed, or did not reach all the way down to the
excavation. Clarke said he would check that with the engineer and on Tuesday,
21 January, when work was resumed, Clarke told Blazley:
"The engineer is happy with the back wall. It is safe and does not require any
further attention at this stage."
He then told Blazley to proceed with the detailed excavation.
Eight days or thereabouts went by until the conversation which I have already
related took place and, as I also indicated, Blazley, having raised some
apprehensions about the condition of the footings along the southern wall, was
told by Clarke to get on with it, and did so. It is said by Mr Fagan that there is
no evidence that Blazley had seen Mr Arnott on the job between 18 January and
29 January, which is the case, so that he should at once have been on inquiry as
to whether Clarke's final instruction had been cleared by the engineer. However,
Blazley was not permanently on the site and, accordingly, it was perfectly
possible for the engineer to have been there, to have made an inspection, and to
have discussed the works with Clarke without Blazley being aware of it. The
practice on the job, in my view, was powerful support for the reasonableness of
Blazley's assumption.
It was also put that it was known that the southern wall might represent
difficulty. Indeed there was a notation on one of the drawings to the effect that the
engineer would give further final advice about how excavation under the wall
should be carried out, or whether - I presume - it should be attempted at all, when
the bulk excavation had exposed the bottom of the piers. So it was said with that
warning available to him Blazley should have been all the more reluctant to make
the assumption he adopted without expressly asking Clarke whether he had
spoken to the engineer.
To my mind the presence of that endorsement on the drawing and the final
instruction from Clarke might very well have appeared to Blazley to be an
indication that what the endorsement contemplated had in fact been carried out.
The stage had been reached at which the engineer had suggested consultation,
URJ MITCHELL v JA BRADSHAW PTY LTD v MITCHELL (Handley JA) 3
and the consultation had taken place. But perhaps more weighty is this
consideration. No cross-examination was directed to Blazley to challenge his
assumption or the ground upon which it rested. It is certainly true that he was
asked generally his reasons for obeying Clarke's instruction, and his answer was
that that was the way in which he had been working, that he was required, as he
understood it, to obey at least not unreasonable instructions given to him by
Clarke. And, of course, Blazley relied on Clarke to consult the engineer where
necessary. But the grounds of the assumption were not put to him and it seems
to me that he cannot be convicted of negligence in making the assumption unless
the basis of it had been explored. This was not done. It may be that if questions
of this kind had been put to him he might have offered reasons for the assumption
which do not appear in the evidence, which are quite unknown to the court, and
which might have amounted to a further powerful justification. At all events I do
not consider that the evidence as it stands establishes that Blazley acted without
reasonable care in assuming that Clarke's instructions had the backing of the
engineer.
I should add that the learned judge made it plain that he was not offering the
view, the firm view, that Bradshaw was under a duty to the appellant to question
"the safety or wisdom of what it was directed to do." Similarly, I will abstain
from deciding that matter. In my view the ground which the appellant took at the
trial and on the appeal was the most favourable battle field upon which it could
have conducted the engagement.
It seems to me that, despite Mr Fagan's able argument, the appeal must be
unsuccessful and that the learned judge's conclusions upon this aspect of the case
were right. I agree with them, and, accordingly, the appeal should be dismissed
with costs.
Mahoney JA I agree.
Handley JA I also agree.
The appeal is dismissed with costs. The security fund is to be retained in court
until taxation, when there is to be paid out enough to satisfy the taxed bill, any
balance to be returned to the appellant's solicitor.
Counsel for the Appellant: DJ FAGAN/DM LOEWENSTEIN
Counsel for the 1st Respondent: DD FELLER
Counsel for the 2nd Respondent: NCOTMAN
Solicitors for the Appellant: HEGARTY AND ELMGREEN
Solicitors for the 1st Respondent: CORRS CHAMBERS WESTGARTHS
Solicitors for the 2nd Respondent: TEECE HODGSON AND WARD
Related laws
No related documents linked yet.
You've got 21 of 22 free Acts left this visit. Sign up anytime for Facts, Related, and study briefs too.