PANGEA RESOURCES LTD v GENERAL CREDITS LTD [1992] NSWCA 178
NSW Caselaw
Full text
Select any passage to save a personal note with optional tags.
PANGEA RESOURCES LTD v GENERAL CREDITS LTD
SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL
KIRBY P, MAHONEY and CLARKE JJ
10 April 1992, 24 December 1992
[1992] NSWCA 178
CONTRACT — commercial agreement — condition or warranty — proper
construction of contract — alleged breach of term of — promise of "due
performance of its obligations" by one party to contract — compromise of legal
obligations upon default under lease and debt of almost $870,000 — promise to
discharge liability by taking certain steps — steps to be taken include payment of
$10,000 for certain equipment and plant — equipment and plant sold for nett sum
of $9,800 and such sum duly paid — default in payment of $200 — such sum later
tendered after proceedings commenced — whether default of $200 constitutes breach
of agreement avoiding compromise and rendering initial debt due and owing — no
equitable defences raised — held (1) The consequence of the default was to be
determined upon a proper construction of the agreement, being a commercial
agreement between the parties; (2) The promise of "due performance" was not
breached by a deficit in the performance of an appropriately minor nature.
Tramways Advertising Pty Ltd v Luna Park (NSW) Ltd (1938) 38 SR (NSW) 632
(FC); 61 CLR 286 applied;(3) The failure to pay $200 in time was, in the
circumstances, such a minor deficit as not to constitute a failure of "due
performance" of the promises of the contract. Bowes (Carrying on Business as the
British Company) v Chaleyer (Carrying on Business as J Chaleyer and Company)
(1923) 32 CLR 159 considered; (4) However, (Kirby P dissenting) the failure to pay
the full $10,000 by the date fixed and for some months thereafter did not constitute
"due performance" of the agreement as required; (5) Decision of Brownie J (upon
different grounds) affirmed; appeal dismissed.
CONTRACT — compromise of large debt upon conditions — conditions complied
with except for condition calling for discharge of liability by payment as moneys
raised on disposal of plant and equipment — proper construction of the condition —
whether condition imposed obligations primarily upon the party sued or upon a third
party — held: (1) The obligation was imposed upon a third party; (2) The failure by
that party to pay the relevant moneys by the date provided in the contract did not
represent a failure to provide "due performance" of its obligations under the
agreement for the compromise of its debt.
PRACTICE and PROCEDURE — Commercial Division — decision upon written
materials — interpretation of written contract — observations by Mahoney JA as to
the necessity to ensure that all facts relevant to the consideration of the interpretation
and construction of the written documents are placed before the court asked to give
such interpretation and construction.
WORDS and PHRASES — "due performance".
Electronic Industries Ltd v David Jones Ltd (1954) 91 CLR 288 applied.
Bowes (Carrying on Business as the British Company) v Chaleyer (Carrying on
business as J Chaleyer and Company) (1923) 32 CLR 159, 172 referred to.
Kirby P The facts and the relevant legal authorities are stated in the reasons
for judgment of Mahoney JA which I have had the privilege of reading in draft.
2 UNREPORTED JUDGMENTS
Challenge to "due performance" of a settlement agreement The issue before
the Court is whether the appellant gave "due performance" of the settlement
agreement which, by its previous name, it entered with the respondent.
Conformably with authority, such an agreement, being designed to terminate
litigation between the parties, would be given a rigorous construction according
to its terms designed, as they were, to upholding the surrender by the parties of
their strict rights at law. See Scott v English [1947] VLR 445 (VSC - Fullagar J)
at 454. Cf Ankar Pty Ltd v National Westminster Finance (Australia) Ltd (1987)
162 CLR 549, 561; Tricontinental Corporation Ltd v HDFI Ltd (1990) 21
NSWLR 689 (CA), 702, 704. On the other hand, the agreement between the
parties was a commercial document, between business enterprises. The Court
should not adopt a punctist's approach in giving meaning to the words which the
parties agreed upon, by which to express their mutual promises.
The respondent denied "due performance" by the appellant of the settlement
agreement, the terms of which are set out in the reasons of Mahoney JA. That
agreement laid down four requirements to be performed by the appellant. The
respondent did not contest the payment of the sum of $250,000 contemplated by
CL2(a) of the agreement. Although that sum was apparently paid about four
weeks late, no point of objection was raised by reason of this default. At least in
that respect, the respondent adopted an apparently sensible and commercial
approach to the meaning of the agreement. But that is where this attitude ceased.
It was then replaced by an approach of strictissimi juris which would have made
the lawmakers of the Medes and Persians proud.
So far as the second requirement was concerned (the issue of shares in
accordance with CL2(b)(i) of the agreement) there was no room for dispute. The
appellant had conformed strictly to this requirement. That stipulation was duly
performed.
The respondent contested that the appellant had complied with the fourth
requirement, viz the payment of moneys, by the date provided, as laid down by
CL2(b)(iii) of the agreement. For the reasons given by Mahoney JA, I agree that
there is no substance in this complaint. I adopt Mahoney JA's reasons in that
regard.
That leaves only the respondent's third complaint that the appellant failed to
give "due performance" of its obligation under CL2(b)(ii) of the agreement. That
clause provided:
"(2) Tantalex [the former name of the appellant] hereby agrees with GCL [the
respondent] to discharge that liability in the following manner:
(b)@)
(ii) by the payment of $10,000.00 for the purchase of absorption plant Item No
40 reagent shared No 41 client buildings ('item 40 and 41') and plant office item
No 43.
By CL3(b) of the agreement the payment of the $10,000 provided for in
CL2(b)(ii) was to be made "progressively upon realisation of the equipment".
Mahoney JA has described what occurred. There was a delay in the sale of the
equipment. At its eventual sale a sum of $10,500 was recovered. Clearly this sum
vindicated the approximate valuation which the parties had put upon the
equipment and the amount which they had anticipated would be recovered from
its sale. However, an amount for agent's commission was deducted from the sum
recovered. The nett amount remaining after that deduction was $9,800. That sum
was duly forwarded to the respondent by the agent engaged to sell the equipment,
URJ PANGEA RESOURCES LTD v GENERAL CREDITS LTD (Kirby P) 3
a specialist in mining and machinery supplies. The sum actually paid was thus
$9,800. There was, therefore, a default of $200 in the strict terms of the promise
by CL2(b)(ii) to pay $10,000. It was not revealed in the meagre evidence whether
the appellant knew of this default at the time of payment. It seems fairly likely
that it did not and assumed that this obligation of the agreement had been
properly complied with. However that may be, when, after the commencement of
the litigation, the default came to notice the balance of the sum of $200 was
tendered, promptly, on 21 March 1989. It was accepted, but without prejudice to
the legal rights of the respondent.
Before Brownie J, the respondent's successful argument was that the
under-payment by $200 put the appellant in breach of its obligation, by CL5 of
the settlement agreement, to give "due performance" of its obligations under the
agreement. Only by such "due performance" would the appellant be released
from its obligations at law. In default of such "due performance" the outstanding
amount of $869,655.31 (together with interest) would be payable. The
respondent, contending principally that the $200 under-payment amounted to a
failure of "due performance", commenced these proceedings. Brownie J,
adopting a strict approach to the meaning of the settlement agreement, upheld
this contention. In this Court, the appellant challenges his Honour's view, and the
judgment which followed it.
A trivial default is not a failure of "due performance"
For the reasons given by Mahoney JA, I agree that Brownie J's conclusions on
the primary argument should be rejected. The deficit by the appellant in its
performance of a requirement of an appropriately minor or trivial nature would
not deprive that performance of the character of "due performance", as that
phrase was used in CLS of the agreement. Looking at this settlement agreement,
in its context and between such parties, and viewing the appellant's compliance
with the four requirements which it accepted, it could not be said that default in
the payment of $200 by the due time would provide such a breach of the
agreement as to warrant its termination by the respondent. See Tramways
Advertising Pty Ltd v Luna Park (NSW) Ltd (1938) 38 SR (NSW) 632, 641 (FC);
61 CLR 286.
As the appellant pointed out, the amount of its default represented 0.004
percent of the alleged compromised obligations. It was only 2 percent of the sum
of $10,000 provided for by CL2(b)(ii) of the agreement which was paid to, and
accepted by, the respondent. It would be surprising indeed if such a minor
default, trivial in all the circumstances, had the consequence of depriving the
appellant's conduct of the character of "due performance" of its obligations under
the agreement, every other part of which was either accepted as, or held to be,
duly performed. The logic of the respondent's submissions drove its counsel to
accepting that even a one cent underpayment or a second's delay in payment
would, upon his view, represent a failure of "due performance" in the terms of the
agreement. The basic fallacy of this approach lies not only in its
misunderstanding of the law of essentiality of the conditions of contracts but also
in its unrealistically rigid construction of the phrase "due performance" in an
agreement of this character between these parties.
Brownie J made it plain that, in his view, it was only the default in the payment
of $200 which entitled the respondent to succeed. He said:
4 UNREPORTED JUDGMENTS
"Tt follows that the defendant would be entitled to succeed but for the fact that
the sum paid pursuant to CL2(b)(ii), within the time fixed by CL3(c) was $9,800
rather than $10,000.... On the proper construction of CL2 and CL3, I conclude
that the plaintiff should succeed on this issue..."
A belated application to raise a new contention should be refused When the
appeal was initially argued, the notice of contention filed on behalf of the
respondent did not refer to the basis upon which the majority of this Court has
now concluded that the respondent was entitled to hold its judgment. With
supplementary written submissions, made in response to an inquiry by this Court,
the respondent has now filed an amended notice of contention. By this, it seeks
to rely upon an "additional ground" with which to support Brownie J's judgment.
The additional ground proposed by the respondent is:
"That there was not due performance by the appellant of its obligation under
CL2(b)(ii) and CL3(c) of the agreement in that the appellant did not pay
$9,800.00 being part of the sum of $10,000.00 referred to in CL2(b)(ii), within
180 days from the date of the Agreement, that is to say, by 31 March 1987, and
in fact paid that amount of $9,800.00 on or about 20 January 1988."
This contention assumes (correctly as it turns out) that a default of $200 would
not, of itself and standing alone, amount to such a breach of a condition of the
agreement (and of the terms of CLS, properly construed) as to amount to a failure
of "due performance". But it says that the default is constituted not by the minor
sum involved but by the late time of the payment of the sum actually paid.
I would be disinclined to permit such a belated amendment of the notice of
contention to permit this issue to be raised in this Court. It is proper to say that
the transcript of argument reveals that the matter was orally argued but outside
the formal record of the Court which the respondent now seeks to put in order.
There is no demonstrated merit in the respondent's insistence upon its strict
rights, so rigidly insisted upon. On the contrary, at least on the basis of the
evidence adduced at the trial, the merits favour the appellant. With minor defaults
(one of them accepted, and one not) it conformed to its obligations under the
settlement agreement. It paid large sums. It sold and realised its equipment. It
issued shares. Just as it had promised. In these circumstances, I am not convinced
that this Court should grant the respondent the indulgence it belatedly seeks to
raise a different basis in its notice of contention with which to insist upon its
unrealistic and uncommercial construction of the agreement which it reached
with the appellant. No sense of justifiable grievance or injustice to the respondent
urges me to a different conclusion. Those who take wholly technical points must
not be surprised when courts respond in a like way.
Nevertheless, I shall assume against my inclination that leave to raise the new
contention would be permitted by the Court, the notice of contention amended
and the issue accepted, to be dealt with upon the present facts as a matter of
construction of the agreement.
The question before the Court is then whether the appellant's default of time
robs its actions, in purported compliance with CL2(b)(ii), of the character of "due
performance" of the agreement as required by CLS. I pause to reflect that it
would be curious if the failure to pay the sum of $200 by the due date would not
be of such a character but the payment of $9,800, accepted some time after the
suggested due date, would deprive the appellant's action of the character of "due
performance".
URJ PANGEA RESOURCES LTD v GENERAL CREDITS LTD (Kirby P) 5
Non-essentiality of contractual stipulations as to time In my view, the late
payment of the sum of $9,800 did not amount to a breach of the requirements as
to time for payment in the agreement such as to rob the appellant's purported
payment of the character of "due performance" of its obligations. CL3(b) of the
agreement governed CL2(b)(ii). That subclause provided, relevantly, that
payment of the money should be made "progressively upon realisation of
equipment". According to the evidence at the trial, the sum of $9,800 was
certainly paid promptly by the agent upon the realisation of the sale of the
specified equipment. The respondent has not argued to the contrary. The
appellant's only real default was the failure, initially, to pay the sum of $200
underpaid. The appellant accepts that that sum was not paid in accordance with
the requirements of CL3(b). However, as has now been held, that default is so
minor in character and trivial in amount that it does not mean that the appellant
has not given "due performance" for that reason.
A clue to the non-essentiality of time in compliance with the obligation
imposed by CL2(b)(ii) of the instant agreement may be seen in the structure of
CL2 itself. So far as the obligation imposed by CL2(a) a specific date, viz 31
December 1986, is nominated by the subclause. Similarly, in respect or CL2(b)(i)
a specific date, viz "the date of this agreement", is nominated. But in respect of
CL2(b)(ii) and (iii) no identified date is stated at all. Doubtless this was because
each of those subclauses contemplated action on the part of the appellant which
would necessarily take a little time, the completion of which could not be
determined in advance and with exact precision.
The agreement between the parties did not explicitly state that the time for
compliance with the obligations imposed by CL2 was of the essence. To the
contrary, the fact that time was not regarded as of the essence is demonstrated by
the acceptance of the sum of $250,000 paid pursuant to CL2(a) nearly a month
after the due date without any complaint on the part of the respondent. Even at
trial no complaint was made in that regard and none was voiced on the appeal.
The very nature of the obligations accepted by CL2(b)(ii) and (iii) of the
agreement made it inappropriate that time should be of essence for compliance
with the requirements of those sub-clauses.
In the history of our legal system, a difference arose between the approach of
the common law and of equity as to the manner in which each regarded breaches
of stipulation as to the time for the performance of contractual obligations. There
being no relevant equitable defences in this case, it is appropriate to consider the
rule at common law. That rule in its original form was stated by Barwick CJ and
Jacobs J in Neeta (Epping) Pty Ltd v Phillips (1974) 131 CLR 286 at 298:
"At law a failure to carry out the contract on the day stipulated, if the failure
was not due to any default on the part of the other party in performance of his
obligations, was a breach of the contract in one of its essential terms. In other
words, time was of the essence of the contract."
Equity adopted a quite different position. A stipulation as to time was not
regarded as essential unless the contract expressly, or by necessary implication,
made it so. Only if the contract so provided would equity follow the law.
Sometimes essentiality would be implied from the nature of the contract, viewed
in its surrounding circumstances. See eg Neeta, 298.
The Conveyancing Act 1919, s13 changed the common law in this State. It
provided that:
6 UNREPORTED JUDGMENTS
"13 Stipulations in contracts as to time or otherwise, which would not before
the commencement of this Act have been deemed to be or to have become of the
essence of such contracts in a court of equity, shall receive in all courts the same
construction and effect as they would have heretofore received in such court."
The stipulation as to time in the subject agreement was not essential
It is therefore the duty of this Court to approach the suggested time default on
the part of the appellant, in conforming to the requirement of CL2(b)(ii) as
elaborated by CL3(c) of the agreement, in accordance with the beneficial
approach of equity as now mandated by statute. Neither by CL3(c) itself nor
otherwise in this agreement did the respondent expressly purport to make a
stipulation as to time essential. Before the sum of $9,800 was paid to it, the
respondent did not purport to terminate the agreement with the appellant for
breach of any such stipulation as to time. Accordingly, when the appellant
tendered to the respondent the sum of $9,800 it tendered substantial, sufficient
and relevantly timely performance of its obligations under the agreement. In the
terms of CLS of the agreement it gave "due performance" of its obligation
thereunder. It was thereupon, by that clause, "released and forever discharged"
from its obligations to pay the respondent the balance of the sum outstanding. It
was entitled to have the benefit of the settlement and of the "due performance"
of its part in the agreement by which that release was achieved. See Halsbury's
Laws of England, 4th ed, Vol 9, para479ff; Citicorp Australia Ltd v Hendry and
Ors (1985) 4 NSWLR | (CA) 30ff.
Conclusions and orders
Like Brownie J, then, I am of the view that, but for the default in the payment
of $200, under-payment of the sum of $10,000 promised, the appellant was
entitled to succeed at trial. Unlike Brownie J, I agree with the conclusion which
Mahoney JA has expressed: that the default in the under-payment of $200 was of
such a minor or trivial nature in the circumstances as not to constitute a failure
of "due performance" by the appellant of its obligations under the settlement
agreement. But, unlike Mahoney JA, I would not give leave to the respondent to
amend its notice of contention to raise its meritless point as to the suggested time
default in the payment of the sum of $9,800. If, however, the majority of the
Court would give that leave, I would determine the point against the respondent.
Neither by the terms of the settlement agreement nor by necessary inference
arising from the circumstances, was the stipulation as to time for compliance with
CL2(b)(ii) of the agreement strict so as to make the suggested time default of the
appellant such as to rob its conduct of the character of "due performance" of its
obligations. The appellant therefore gave "due performance". This conclusion, by
the application of the relevant legal principles, produces a result which is neither
unjust nor surprising. Indeed, it is the contrary result which is surprising. With
respect, it involves an apparent departure from commonsense in the resolution of
a commercial dispute between business enterprises. The common law normally
reflects commonsense. It does so here.
The orders which I would favour are:
1. Appeal allowed;
2. Set aside the judgment entered by Brownie J;
3. In lieu thereof, order that the plaintiff's proceedings in the Commercial
Division of the Supreme Court be dismissed with costs; and
4. Order that the respondent pay the appellant's costs of the appeal and have,
in respect of such costs, if otherwise so qualified, a certificate under the Suitors'
Fund Act 1951.
URJ PANGEA RESOURCES LTD v GENERAL CREDITS LTD (Mahoney JA) 7
Mahoney JA The main issue in this appeal is the meaning of "the due
performanceby Tantalex of its obligations hereunder". The plaintiff's contention
is that all but two of those obligations may be accepted as performed: two of them
were not. The learned judge held that one of such obligations had not been
performed and gave judgment for the plaintiff.
The defendant has appealed to this Court against his Honour's judgment.
Before the judge and before this Court, counsel for the parties have reduced the
facts to their essentials. They may therefore be stated briefly. [In stating the facts
I shall drawn no distinction between Australian Guarantee Corporation Ltd and
General Credits Ltd ("GCL"). I shall refer to the defendant Pangea Resources Ltd
by its former name Tantalex Ltd ("Tantalex")].
Tantalex had leased certain mining plant and equipment from GCL. It
defaulted under the lease and, as at 2 October 1986, it owed GCL $869,655.31.
On 2 October 1986, an agreement was made between GCL and Tantalex
providing for the discharge of that indebtedness. The relevant clauses of that
agreement were as follows:
"2. TANTALEX hereby agrees with GCL to discharge that liability in the
following manner:
(a) by payment of the sum of $250,000.00 on or before 31 December 1986.
(b) (i) by the issue upon the date of this agreement of one million 20 cent fully
paid shares in its capital
(ii) by the payment of $10,000.00 for the purchase of absorption plant Item No
40 reagent shared No 41 client buildings ('Item 40 and 41') and plant office Item
No 43
(iii) by payment of the whole of the moneys raised by the disposal of the major
remaining plant and equipment the subject of the lease less the costs of disposal
properly paid to third parties (such costs of disposal however in no case to exceed
15% of the gross sale price) (such sale estimated to realise $260,000) payable
progressively upon the same of such remaining major plant and equipment such
sale to be effected by Mr N Seckold, a director of Tantalex acting as agent for
GCL.
3.(a) All offers for the purchase of remaining items of major equipment
received in pursuance of the arrangements referred to in the last sub-clause of the
preceding clause shall be submitted to Australian Guarantee Corporation Ltd for
approval before acceptance.
(b) Payment of the sums of money to be paid pursuant to CL2(b)(ii) and
CL2(b)(iii) be made progressively upon realisation of the equipment.
(c) Unless otherwise agreed by GCL all payments and actions required to be
made by Tantalex shall be made or done (as the case may be) on or before the
expiration of 180 days from the date hereof.
5. GCL hereby agrees that upon the due performance by Tantalex of its
obligations hereunder, Tantalex shall be released and forever discharged from all
obligations to pay GCL the balance of the then(sic) outstanding of the said sum
of $869,655.31 and from actions proceeding claims or demands whatsoever
which GCL then has or can or may have against Tantalex for or in respect of the
default recited above or any other matter or thing whatsoever concerning such
default of the said lease."
CL2 contemplated four things: the payment of $250,000, the issue of shares by
Tantalex, the payment of $10,000, and the payment of the moneys raised by the
disposal of the plant and equipment referred to in CL2(b)(iii).
8 UNREPORTED JUDGMENTS
$250,000 was paid by Tantalex to GCL. It was paid not by 31 December 1986
but on 28 January 1987. It is accepted that, in this regard, Tantalex was not in
breach of its obligations under the agreement because the time for payment was
extended.
Tantalex issued shares in accordance with CL2(b)(i): no issue arises in that
regard.
As to the sales of Items 40, 41 and 43 of the Tantalex property, the position was
more complicated. The plant and equipment referred to in CL2(b)(ii) and (iii)
was, it is agreed, not owned by Tantalex. It was leased by it from GCL. It was,
in my opinion, contemplated by the agreement that the plant and equipment
referred to in CL2(b)(ii) would be purchased from GCL by Tantalex: that
sub-clause, in providing "for the purchase of..." the relevant items, contemplated
the purchase of them by Tantalex from GCL. It contemplated in addition that the
purchase by Tantalex from GCL would be in the context of or with a view to the
"realisation of the equipment": CL3(b); by the sale of it to other parties. The
payment of the $10,000 provided for in CL2(b)(ii) was, by CL3(b) to be "made
progressively upon realisation of the equipment".
In fact, arrangements were made for the sale of that equipment by a Mr Wilson.
Mr Wilson appears to have been a "principal" of a company or firm Minemach,
suppliers of mining and machinery supplies.
The 180 day period referred to in CL3(c) expired on 31 March 1987. The plant
and equipment referred to in CL2(b)(ii) and (iii) was not sold by that time.
Subsequently, following consultation with GCL, Mr Wilson achieved a sale of
the plant and equipment referred to in CL(2)(b)(ii) in 1988. The sale was for
$10,500. After deduction of commission, the net proceeds of the sale were
$9,800. The Minemach company accounted to GCL for $9,800 accordingly.
Subsequently, in or about February 1990, GCL commenced proceedings
against Tantalex to recover $379,441.42, being the balance of $869,655-31
which, it claimed, had not been received by it. It acknowledged that on 20
January 1988 it had received $9,800 in accordance with the agreement but
suggested that the balance of the $10,000 referred to in CL2(b)(ii) had not been
received. By a letter dated 21 March 1989 Minter Ellison, the solicitors for
Tantalex, tendered $200 plus interest of $74 "being the difference between
$10,000 referred to in the Settlement Agreement and the amount received by your
client". That amount was received by GCL: it is agreed that the receipt of it does
not affect the rights of GCL otherwise in respect of the agreement.
In relation to the plant and equipment referred to in CL2(b)(iii), it is accepted
that the sale or sales took place in the early part of 1987. Sums were received by
Tantalex in respect of those sales and subsequently payments were made by
Tantalex to GCL in respect of them. As I understand the final position and
contentions of the parties, the dispute which GCL now raises relates to a net
amount of $13,500, being the proceeds of sale of plant and equipment in March
and May 1987. The contention of GCL is that though it received some of the
proceeds of the various sales of plant and equipment, the amount of $13,500
remained outstanding. Minter Ellison, in the letter of 21 March 1989, conceded
that amounts "received from Minemach in March and May 1987... have
apparently not been accounted to your client". A tender of payment was then
made and presumably accepted.
It is from these facts that the present dispute arises. GCL claims that, at the
time of the agreement of 2 October 1986, Tantalex owed it $869,655.31; that it
agreed to discharge that liability "upon the due performance by Tantalex of its
URJ PANGEA RESOURCES LTD v GENERAL CREDITS LTD (Mahoney JA) 9
obligations" under the agreement; that Tantalex did not do so; and that therefore
GCL is entitled to the balance in fact unpaid of the $869,655.31. Tantalex
contends that what occurred constituted "the due performance by Tantalex of its
obligations" under the agreement and that accordingly it was released from that
balance.
It is conceded by Tantalex that the discharge of its indebtedness was to take
place, not by virtue merely of its promise to do what the agreement obliged it to
do, but by virtue of the performance of the obligations which, by the agreement,
it undertook to perform. The appeal has proceeded on that basis. In the
circumstances, the matter should be decided accordingly.
I shall consider in turn what happened in respect of CL2(b)(ii) and CL2(b)(iii).
1. CL2(b)(ii):
It is necessary to consider two things: (a) what were the obligations of Tantalex
under the agreement in this regard; and (b) whether there was "the due
performance" by Tantalex of those obligations.
(a) The obligations of Tantalex involved (I shall put the matter in a neutral
sense at this stage) the payment of $10,000 on or before 31 March 1987. The
obligation in this regard was for the payment of $10,000, not merely the sum or
the net sum received upon the "realisation" of the relevant equipment by
subsequent sale by it. However, the payment of $10,000 was, by CL3(b) to be
made "upon realisation of" the relevant items. But, as GCL has contended, the
"payments and actions required to be made or done by Tantalex" on or before 31
March 1987: CL3(c); included the purchase of the relevant items by it and the
realisation of them within CL3(b).
GCL contends that Tantalex was in default in respect of these obligations in
two respects: what was done was not done on or before 31 March 1987; and the
payment made to it by Tantalex was not for $10,000 but only for $9,800.
There has been doubt as to the reliance placed upon these and in particular
upon the first of them, the non- payment within the specified time. The basis on
which the matter was dealt with before the trial judge is, from the terms of the
judgment, not completely clear. His Honour said:
"Tt follows that the defendant would be entitled to succeed but for the fact that
the sum paid pursuant to CL2(b)(ii), within the time fixed by CL3(c), was $9,800
rather than $10,000, remembering that the defendant paid and the plaintiff
accepted the further sum of $200, plus a further $74 in respect of interest upon
that sum in March 1989. On the proper construction of CL2 and CL3, I conclude
that the plaintiff should succeed on this issue, subject perhaps to consideration of
the circumstances in which $274 was paid, and accepted."
His Honour appears to have found that the $9,800 was paid "within the time
fixed by CL3(c)" and to have decided the claim against the defendant upon the
basis of the non-payment of $200. However this is, as I have said, not completely
clear: it may be that his Honour acted upon the basis that no portion of the
$10,000 was paid "within the time fixed by CL3(c)".
Before this Court, it was not clear from the argument whether the plaintiff
relied upon the contention that the $9,800 was not paid within the time fixed by
CL3(c). After the court had reserved its decision, the court directed the attention
of the parties to what was said in argument and invited further submissions upon
this matter. The plaintiff then filed further written submissions in which it was
contended that it relied, and was entitled to rely, before this Court on that matter.
10 UNREPORTED JUDGMENTS
That has not been substantially contested by the defendant. I shall therefore deal
with the matter upon the basis that the default alleged is in respect of each of
these two matters.
I shall deal first with the significance of the failure to pay the outstanding $200.
There are three aspects of the obligations of Tantalex under the agreement which
are relevant for present purposes. First, Tantalex's obligations extend to the
whole of the matters referred to in CL2, viz, the payment of $250,000, the issue
of one million 20 cent fully paid shares, the payment of $10,000, and the dealing
with "the disposal of the major remaining plant and equipment...". Second, its
obligations in relation to the matter directly in question, the payment of $10,000,
were conditioned by CL3(b) and (c). And, for present purposes, the discharge of
Tantalex's liability for $869,655.31 was conditional upon "the due performance
by Tantalex of its obligations hereunder": CLS.
It is relevant to have in mind the totality of the obligations of Tantalex under
the agreement: this will be relevant in considering whether there was "due
performance" of its obligations under the agreement. Tantalex was obliged to pay
$250,000 in cash, to issue one million 20 cent fully paid shares having at least
some value, to pay $10,000, and to allow or be concerned in the disposal of the
residue of the plant and equipment. It is not clear how the failure to pay the $200
now in question or to pay it by 31 March 1987 is to be measured against the
totality of these obligations. Counsel suggested in argument that the $200
represented.04 per cent of the company's total obligations. It is 2 per cent of the
sum of $10,000 provided for in CL2(b)(ii). How its significance in the context of
its obligation to dispose of one of its assets, its share capital, and the unquantified
price of the residue of the plant and equipment is to be calculated is, as I have
said, not clear. On any assessment, it constitutes a very small part of the totality
of Tantalex's obligations.
It has however been accepted that CL2(b)(ii) required the payment in cash of
$10,000. The agreement provided for the payment of that money "for the
purchase of" the items of plant there specified and it provided further that the
payment of that sum was to "be made progressively upon realisation of the
equipment". It was contemplated that, the plant and equipment having been
leased from GCL, Tantalex would "purchase" the relevant items of it as specified
in CL2(b)(ii). It was further contemplated that Tantalex would then itself sell
those items of plant to third parties. If and insofar as it be relevant, or admissible,
the evidence disclosed that negotiations for such a sale had in fact been
undertaken. But, in my opinion, the effect of these provisions was not to impose
an obligation merely to pay to GCL the proceeds of realisation of the particular
items: the obligation remained one to pay $10, 000. Therefore, the fact that
Tantalex received, as the net proceeds of the sale, only $9,800 did not relieve it
of the obligation to pay $10,000.
Reference was made in argument to the relationship between CL3(b) and
CL3(c).
It was submitted that the effect of CL3(c) was to qualify CL3(b) and that all
that had to be done by Tantalex had to be done within 180 days of the date of the
agreement, viz, by 31 March 1987. The result of this would be that the items had
to be realised by them and that if there had been no realisation of the relevant
items of equipment within CL2(b)(ii) by that time, it remained the obligation of
Tantalex to pay $10,000 by 31 March 1987. That, I think, is the correct
construction. CL3(c) operates to require that, as and when the equipment is
realised and the proceeds of realisation received, the proceeds are to be paid to
URJ PANGEA RESOURCES LTD v GENERAL CREDITS LTD (Mahoney JA) 11
GCL, even though that be before 31 March 1987. But CL3(c) put an overall time
limit upon the discharge of these obligations, including the obligation to realise
and to pay, inter alia, the $10,000.
I do not mean by what I have said that CL3(b) has no effect upon the nature
of the obligation imposed by CL2(b)(ii). It may be that the provision that the
amount payable under CL2(b)(ii) be paid "progressively upon realisation of the
equipment" operates to create an equitable assignment or security over the
proceeds of sale of the relevant equipment: see Palmer v Carey (1926) AC 703;
Robertson v Grigg (1932) 47 CLR 257 at 265. However, it is, in my opinion, not
necessary to pursue that matter: no issue has arisen by reference to it.
(b) I come therefore to the significance of the reference in CL5 to "due
performance". Tantalex owed $869,655.31. The agreement, by CL2, provided
that Tantalex would "discharge that liability in the following manner:...". And, by
CLS, GCL agreed that "upon the due performance by Tantalex of its obligations
hereunder" Tantalex should be "released and forever discharged from" the
balance of that amount.
The question to be determined is therefore whether there was a failure of due
performance of such obligation because, though the other obligations were
performed, the obligation to pay $10,000 was performed only to the extent of
$9,800.
Mr McDougall QC has, in his careful submissions, suggested in effect that it
would be strange if a failure to perform limited to the minor deficit here in
question should lead the court to the conclusion that the balance of the amount
of $869,655.31 remained to be satisfied. There is, I think, force in this
submission. It would be sad if the law required, at least in such a case as this, that
the object which Tantalex sought to achieve and GCL was prepared to concede
was defeated by a minor or even, as Mr Lindgren QC accepted, the smallest
deficit in performance. However, the agreement is to be given effect according to
the intention of the parties as appearing from its terms and it is necessary to
determine whether that result flows from the terms of it.
Before doing so, it is proper to record how that issue has been presented for
determination and what has not been raised. The court does not know why the
$200 was not paid: at least, the matter has not been dealt with in any detail.
Nothing has been established as to the circumstances in which the deficit of
performance occurred. It is open to a court, exercising equitable jurisdiction, to
mitigate the effect of an agreement if a deficit in performance has resulted from,
eg, mistake or accident. The jurisdiction of the court in this regard is well
established: see, eg, Storey on Equity Jurisdiction, 11th ed (1873), para78, at 84
(accident) and ch 5 (mistake); Halsbury's Laws of England, 4th ed, vol 16,
paral235. The extent of the court's jurisdiction in relation to accident and
mistake has not been argued: no application has been made for the exercise of it.
Therefore this Court should, in my opinion, deal with the present dispute upon
the basis that no case has been made out for the application of those principles.
It has not been established whether the deficit in performance resulted from,
eg, deliberate default by Tantalex or a misunderstanding of the requirements of
the agreement. It is therefore necessary to deal with this appeal upon the basis
that issues of this kind do not arise. It was on that basis that the matter was argued
before the trial judge.
12 UNREPORTED JUDGMENTS
What is in issue in relation to the non-payment of $200 is therefore the effect
of a minor deficit in the performance of obligations under an agreement. This has
been the subject of consideration in relation to, inter alia, the termination of an
agreement for default and the construction of the terms of the agreement.
It and associated matters have arisen in cases where the court has considered
whether an agreement may be terminated for breach: see generally Tramways
Advertising Pty Ltd v Luna Park (NSW) Ltd (1938) 38 SR (NSW) 632; (1938)
61 CLR 286; Associated Newspapers Ltd v Bancks (1951) 83 CLR 322; DTR
Nominees Pty Ltd v Mona Homes Pty Ltd (1978) 138 CLR 423; and Citicorp
Australia Ltd v Hendry (1985) 4 NSWLR 1. Where there has been a deficit in the
performance of a party's obligation, the other party may be entitled to claim a
termination of the agreement. Without limiting the grounds on which a right to
terminate for default may arise, it ordinarily arises because what has happened is
a fundamental breach, a repudiation of the agreement or a breach of a condition
of it. A minor deficit in performance will ordinarily, by definition, not constitute
a fundamental breach and so provide the cause of termination: see Ankar Pty Ltd
v National Westminster Finance (Australia) Ltd (1987) 162 CLR 549 at 561-2.A
minor deficit in performance may constitute evidence of an intention to repudiate
an agreement but, in most cases, the question will not arise: see generally Carr
v JA Berriman Pty Ltd (1953) 89 CLR 327.
But such a question may arise where the non-performance, although minor,
involves a breach of a condition. A term which is a condition, either of the
contract coming into force or of its continuance may constitute a ground on
breach for termination of the contract. A term which is a condition merely of the
performance of some obligations of the contract may give rise to more difficult
questions: see generally Perri v Coolangatta Investments Pty Ltd (1982) 149
CLR 537. In the present case, the due performance by Tantalex of its obligations
under the agreement was a condition of the agreement by GCL that Tantalex
should be released and discharged from its obligation to pay the balance of its
indebtedness then outstanding: CLS.
The effect of a minor deficit in the performance of a condition has, in my
opinion, been considered in at least two respects: reference has been made to the
possibility that a breach of a condition which ordinarily would justify termination
of an agreement will not do so if the breach is minor; and the fact that the term
is a condition ordinarily grounding termination has, I think, been seen as relevant
to the construction of the term and to whether it should be read in such a way that
a minor deficit in performance is not seen as a breach of it.
In the first of these cases, the construction of the condition is not affected: the
obligation remains, to adapt the present case, to pay $10,000. But, the suggestion
has been, effect is given to the fact that the instant breach is minor by holding that
such a minor breach does not give rise to a right to termination. Such a
formulation of the principle does not, I think, appear in terms in the cases. But,
I am inclined to think, the reasoning of Jordan CJ in the Tramways Advertising
case was founded upon such a basis. The court was there required to consider the
breach of a term requiring that advertising be displayed on trams for "at least
eight hours". Two questions arose: whether the term was a condition of the
contract or merely a warranty; and if it was a condition, what rights flowed from
the breach of it. In considering the first question, Jordan CJ: at 38 SR (NSW) 632
at 641-2; said: "The question whether a term in a contract is a condition or a
warranty, ie, an essential or a non-essential promise, depends upon the intention
of the parties as appearing in or from the contract. The test of essentiality is
URJ PANGEA RESOURCES LTD v GENERAL CREDITS LTD (Mahoney JA) 13
whether it appears from the general nature of the contract considered as a whole,
or from some particular term or terms, that the promise is of such importance to
the promisee that he would not have entered into the contract unless he had been
assured of a strict or substantial performance of the promise, as the case may be,
and that this ought to have been apparent to the promisor.... If the innocent party
would not have entered into the contract unless assured of a strict and literal
performance of the promise, he may in general treat himself as discharged upon
any breach of the promise, however slight. If he contracted in reliance upon a
substantial performance of the promise, any substantial breach will ordinarily
justify a discharge."
It may be inferred from what the Chief Justice there said that a term may be
a condition if only "a substantial performance" of the obligation that it imposed
was expected. It would appear to follow from this that, if there was a performance
of it not in terms but only substantially, that deficit would not give rise to a right
to terminate for breach of the condition. Therefore, it would appear to follow, a
right to terminate for breach of a condition providing for the payment of $10,000
would not arise from the payment only of $9,800 if the intention discerned by the
court was that the payee "would not have entered into the contract unless he had
been assured of... a substantial performance of the promise".
When the matter was considered in the High Court, it was determined upon a
different basis. Latham CJ dealt with the matter upon a basis of construction to
which I shall refer. He held that, upon the basis of an extended construction of
the requirement for "at least eight hours" display, the condition had been broken:
at 304-5. Rich J gave the obligation a literal construction: at 306. McTiernan J did
the same: at 311-2. Dixon J dissented: his Honour leaned to a more extended and
less literal construction: at 309-310.
There is, in my respectful opinion, attraction in a view which accepts that, if
that which led the parties to see the term as essential was the necessity for not a
literal but only a substantial performance of it, then a performance which is
substantial only should not give rise to the consequence in law that the agreement
may be terminated for such a breach.
In the present case, the due performance of Tantalex's obligations was not, in
literal terms, made a condition of the operation of the agreement: it was, by
inference, a condition of the agreement of GCL that Tantalex should be released
and discharged from the balance outstanding of the debt. It is, I think, at least
arguable that, had GCL adverted to the matter, it would have accepted, in the
sense to which Jordan CJ referred, that the essential nature of the term depended
not upon the literal but upon a substantial performance of it.
However, it is not necessary to form a final conclusion upon this aspect of the
matter. I am of opinion that the agreement, properly construed, required only the
substantial performance of Tantalex's obligations and that what occurred
constituted such a performance. As I have said, it is to be accepted that the release
and discharge of Tantalex was conditioned upon "the due performance" of its
obligations. Those obligations involved, inter alia, the payment of $10,000. But,
where the intention of the parties is clear, it has been accepted that words
otherwise clear or precise may be construed as if "approximately" or
"substantially" were added to them. In my opinion, such a construction is to be
adopted in the present case.
In Bowes v Chaleyer (1923) 32 CLR 159 the commercial contract provided for
the sale of goods, to be shipped to Melbourne from Europe, "Half as soon as
possible. Half two months later". Knox CJ: at 168; construed the agreement as
14 UNREPORTED JUDGMENTS
requiring the shipment of one half of the goods ordered on each occasion but said
that "even assuming that the contract did not require the first half to be comprised
in one shipment, the admitted facts show that neither the first shipment taken
alone, nor the first and second shipments taken together, consisted even
approximately of one half of the goods ordered...".
Higgins J held that the contract required the plaintiff "to have the goods
shipped in halves, with an interval of two months" and that this had not been
done: at 190-1.
Starke J took a somewhat different approach. His Honour: at 192-3; said:
"The written order contained these words: "Goods to be shipped per
sailer/steamer. Half as soon as possible. Half two months later.' As a matter of
construction, these words mean, in my opinion, that the goods are to be shipped
in equal parts, the first part as soon as possible, and the second part two months
after the first part has been shipped. A stipulation for shipment in half parts does
not warrant a piecemeal shipment of those parts; the shipment of the half part
must be in one parcel. 'In carrying out a commercial contract such as this, some
slight elasticity is unavoidable; no one supposes that' that shipment must be
mathematically one half of the goods purchased; it must, however, be
substantially of the quantity specified (cf Harland and Wolff v Burstall and Co
(1901) 6 Com Cas 113 at 116). The words 'as soon as possible' in this contract
mean 'within a reasonable time', regard being had to the ability of the vendor to
obtain the goods from the manufacturers and to despatch them to the
purchaser...". His Honour concluded that on that construction, there had been a
breach.
Isaacs and Rich JJ dissented. Their Honours: at 170-1; said: "In all cases of
contract the supreme function of the court is to see that the real intention of the
parties is enforced, so far as that can be ascertained or deduced from the language
they have used with reference to the circumstances in which they have used it.
Particularly is this so in mercantile contracts; since merchants are habitually less
formal than lawyers, and trust to terse and often elliptical modes of expression
that need close attention to surrounding circumstances in order to appreciate their
true meaning. The court must be careful to maintain the spirit of the bargain so
far as that is consistent with the language employed, neither neglecting the
materiality of stipulations expressly assented to, nor blindly adhering to form at
the expense of substance whereby either party may slip out of an honest
bargain...".
Subsequently, at 174-7, their Honours examined the meaning of, inter alia, the
two phrases referred to. They held that "business efficacy" indicated that the
terms did not strictly impose a condition but allowed appropriate flexibility in the
performance of the obligations.
In the Tramways Advertising case Latham CJ considered the requirement
imposed by the words: "we guarantee that these boards will be on the tracks at
least eight hours per day throughout your season". The Chief Justice: (1938) 61
CLR at 304; said:
"But it is still necessary to consider what default will amount to a breach of the
clause. The clause used the words "at least eight hours' but, in my opinion, such
a phrase should not be interpreted with absolute mathematical exactitude in a
commercial contract of this class. In some contracts it may be proper to construe
references to time with absolute and precise accuracy down to minutes and
seconds, but in a contract dealing with the display of roof boards on trams for at
least eight hours per day the words 'eight hours per day' should be understood as
URJ PANGEA RESOURCES LTD v GENERAL CREDITS LTD (Mahoney JA) 15
meaning substantially eight hours per day. The clause would not, in my opinion,
be broken by small occasional deficiencies. I give to this clause the same kind of
construction which was given in Bowes v Chaleyer (1923) 32 CLR 159 to such
phrases as 'half' the goods and 'two months later'. The court read these
provisions as conditions but interpreted them as if the word 'substantially' had
been introduced into them. I take the admission that each board was not exhibited
for at least eight hours a day as an admission that it was not the case that each
board was exhibited for substantially eight hours each day. I am accordingly of
opinion that the defendant was entitled to determine the contract by reason of the
past breaches of the plaintiff."
Such an approach to the construction of "due performance" may, in my
opinion, properly be taken in the present case. It was not, I think, the intention
of the parties that if Tantalex performed all but the most minor part of its
obligations the object of the agreement should yet be defeated. Thus, for
example, the agreement provided that Tantalex should "use its best endeavours to
have the shares" provided in CL2 "listed with the Australian Associated Stock
Exchanges". That was part of the obligations to be performed by Tantalex under
the agreement. It could not have been the intention of the parties that, if Tantalex
failed to use its best endeavours to have the shares listed on one stock exchange,
the release and discharge should not take place and that even though, in the event,
the shares were listed on all stock exchanges. They intended, I think, more
elasticity than that.
In my opinion, therefore, the operation of CL5 was not prevented if there was
a deficit in its performance of an appropriately minor nature.
Was Tantalex's non-performance of that nature? I have referred to the
significance of the failure to pay $200. It was, as I have indicated, a minor matter
in the context of the total obligations of Tantalex under the agreement. Mr
Lindgren QC accepted that his argument that any deficiency in performance
would defeat the operation of CLS would apply even if the deficit involved a
payment short by only $1. I do not think that submission should be accepted.
The agreement is a commercial agreement. It does not spell out in terms all of
the obligations of the parties or lay down the letter of what is to be done. It covers
some matters and leaves others to be implied. There are apparent omissions: cf,
for example, CL3(b). The obligations of Tantalex under the agreement range
from the large (the payment of $250,000) to the small (the payment of $10,000).
And the obligation to issue the one million shares "upon the date of this
agreement': CL2(b)(i); was, I think, intended to be interpreted in substance and
with some flexibility. It was not, I think, contemplated that a deficit in
performance of some of the minor obligations undertaken would constitute a
failure of "due performance" of all of them. I do not think that there was such a
failure in the present case.
T have to this point dealt with the effect of the failure to pay $200 in due time.
I have dealt with this separately because of the way in which the failure to pay
the full $10,000 by 31 March 1987, the time required by CL3(c), has been dealt
with and against the possibility that a different view may be able to be taken in
respect of this obligation. I come now to deal with the failure to pay the full
$10,000 in time.
As I have said, the sale of the relevant equipment was not completed, and so
the sum from which the $10,000 was paid was not received, until some time in
1988. It was therefore after that date and from the net proceeds of that sale that
the $9,800 was paid to GCL.
16 UNREPORTED JUDGMENTS
If the obligation of Tantalex was to pay $10,000 by 31 March 1987, there was
a breach of that obligation. I am not able to conclude that, in the sense to which
I have referred, that was "a minor matter" or that there was a substantial
performance of the obligations of Tantalex. It may be that the default was minor
and that the performance was substantial. But those matters must be decided on
the evidence before the court and that evidence, as far as it extends, does not
satisfy me that it was so. I have considered whether, in view of the terms of the
judgment of the trial judge, I am constrained to decide otherwise. I do not think
that I am.
On that basis, I am not satisfied that there was "due performance by Tantalex
of its obligations hereunder". I shall, in favour of the defendant, assume that "due
performance" does not require the performance of all of its obligations literally
in accordance with the terms of the agreement. As I have indicated, the terms of
the agreement indicate that the parties contemplated - I put the matter generally
- some flexibility in the performance of it. Accordingly, there could be "due
performance" notwithstanding that there were minor or incidental
non-compliance with the literal terms of the agreement. But I am not able to say
that that flexibility extended to a default in the payment of $10,000 over the
period of months here in question. I am satisfied that it did not.
I am conscious that in fact other obligations were not performed strictly in
accordance with the terms of the agreement and that no point has been taken in
relation to that non-performance. But nothing has been urged, or at least
established, to show that that can lead to a construction of the present obligation
different from that which the terms of it require. And it has not been argued, or
established, that the delay in payment was excused, by the conduct of the parties
or otherwise or that it resulted from a misunderstanding of the terms of the
agreement which might be relied upon for the defendant. The rights of the parties
have been argued by reference essentially to the terms of the agreement.
Therefore, with some reluctance, I conclude that there was not due
performance of Tantalex's obligations in this regard.
2. CL2(b) (iii):
GCL relied also upon the failure of Tantalex to perform its obligations under
CL2(b)(iii). Some at least of the failure alleged is referred to in the letter dated
21 March 1989 from Minter Ellison, the solicitors for Tantalex. That letter refers
to substantial amounts which, even at that time, had not been paid to GCL. Upon
any view, the amounts there referred to were, it was submitted, not paid to GCL
either "upon realisation of the equipment" or "on or before the expiration of 180
days from the date" of the agreement.
In order to consider this submission, it is necessary first to determine the extent
of the obligations of Tantalex under CL2(b)(iii). The plant and equipment was
owned by GCL. There had been a lease of it to Tantalex. In this case, the items
were not to be purchased by Tantalex and resold. The clause provided that the
sale should be "effected" by an agent for GCL, albeit one who was a director of
Tantalex. Prima facie it might be thought that the "effecting" of the sale included
the receipt of the proceeds of it and that therefore those proceeds would be held,
not by Tantalex, but by Mr Seckold as the agent of GCL. Subject to what I shall
say, CL2(b)(iii) on a strict reading imposed no direct obligation on Tantalex in
respect of the sale: at most, it imposed indirect obligations involving that it not
interfere with the sale or the like: Electronic Industries Ltd v David Jones Ltd
(1954) 91 CLR 288. Such indirect obligations are not here in question.
URJ PANGEA RESOURCES LTD v GENERAL CREDITS LTD (Mahoney JA) 17
However, the clause involves an agreement by Tantalex "to discharge that
liability" "by payment of" the moneys raised by the disposal of the remaining
plant and equipment. It might be thought that such payment could not be made
by Tantalex unless Tantalex itself received the proceeds of the sale. But prima
facie it was the obligation of Mr Seckold, as agent for GCL, to pay those
proceeds not to Tantalex but direct to GCL. He would prima facie be in breach
of his fiduciary duty to GCL if he did otherwise.
How, then, was CL2(b)(iii) to operate and what obligation did it impose on
Tantalex? The words of clause 2(b)(iii) could perhaps be given effect by reading
"by payment of" as "by ensuring payment of'. But I do not think that that
construction should be adopted. It is, in my opinion, better to treat the clause as
badly drafted and as involving the attempt to impose upon a person not a party
to the agreement, Mr Seckold, an obligation which, in law, he would not have,
unless, at least, he accepted it. CL3(a) gives rise to an analogous problem. It
requires "all offers for the purchase of remaining items of major equipment" to
be submitted to Australian Guarantee Corporation Ltd for approval before
acceptance. As the sale of that equipment was to be effected by Mr Seckold as
agent for GCL, that obligation prima facie would lie not on Tantalex but on Mr
Seckold: unless, at least, CL3(a) be limited to only such offers as were received
by Tantalex and not by Mr Seckold. That, I think, is a limitation which was not
what the parties had in mind.
In the end, I am not satisfied that the obligation to pay the moneys raised by
the disposal of the relevant plant and equipment was an obligation primarily upon
Tantalex "hereunder", ie, under the agreement. Tantalex may have acquired
obligations as the result of the receipt of such moneys from Mr Seckold if, in
breach of his fiduciary duty to account or otherwise, he paid them to Tantalex.
But those obligations were not obligations "hereunder" within CLS.
In my opinion, therefore, the failure of the persons responsible to pay the
relevant moneys to GCL at an earlier date than they were paid does not represent
a failure duly to perform the obligations of Tantalex under the agreement.
Before parting with this appeal it is proper to record that, in my opinion, the
basis upon which the appeal falls to be decided is unsatisfactory. The matter was,
the court has been informed, dealt with in the Commercial Division upon limited
evidence. The judge was, it has been said, provided with certain affidavits and an
agreed bundle of documents. His Honour himself referred to the limitations of
what was before him and the manner in which the issues fell to be decided: the
trial, his Honour said, "took an unusual course'.
It is, of course, proper that the parties, particularly in the Commercial Division,
reduce the issues to be determined to those genuinely in dispute and that the
evidence be presented in a form which reduces to the minimum disputes as to the
facts. This is not merely proper but also necessary. But, in the end, it is necessary
also that the parties ensure that there is before the judge all material necessary to
make clear not merely the issues in dispute but the matters which will be of
assistance in the decision of those issues. And, in the end, where the
interpretation of a written contract is in issue, the court must ensure as best it can
that the relevant material is before it. In Bowes v Chaleyer, Isaacs and Rich JJ at
172; said:
"The learned trial judge, Macfarlan J, says that 'no evidence was given as to
the precise nature of a contract to indent, both parties preferring to treat it as in
effect a contract by plaintiffs to purchase themselves and resell to defendant'. His
Honour adds: 'I had some doubts whether this was the proper view of it'. The
18 UNREPORTED JUDGMENTS
construction of the written contract being for the court, it is a question of law...
It is therefore impossible, when appealed to for its judicial opinion, that the court
in authoritatively declaring the rights of the parties should accept an erroneous
construction of the very nature and effect of the contract, even though suggested
by both parties. A court is bound to dispense the King's justice according to law...
Parties may so conduct their case as to conclude themselves as to the existence
or non-existence of facts, where the truth does not appear; but they cannot relieve
the court from its duty of legal interpretation of documents before it, or of giving
the true legal effect to facts as ascertained. The common law is as binding on the
court as any statute."
I confess to coming from the facts of this case with the feeling that, in the
construction of the agreement, the court has been required to consider questions
of interpretation and construction of the agreement and of what the parties did,
without having all of the facts which would be of assistance to it for those
purposes.
However, the parties have joined in asking the court to give effect to the
agreement strictly according to its terms. The result is, in my opinion, that the
appeal should be dismissed with costs.
Clarke JA I agree with Mahoney JA that the appeal should be dismissed with
costs and, subject to one matter on which I would wish to reserve my opinion, I
agree with the reasons which led his Honour to that conclusion.
The one aspect of the case on which I would wish to reserve my position
concerns the failure of the appellant to pay the sum of $200 within the
contractually agreed time. While the observations of Mahoney JA on this point
are persuasive it is unnecessary to deal with the point for the purposes of
disposing of the appeal and I would prefer not to do so.
The appeal should be dismissed with costs.
Appeal dismissed with costs.
Counsel for the Appellant: RC McDougall QC with S Donaldson
Instructed by: Minter Ellison
Counsel for the Respondent: KE Lindgren QC with J Parsons
Instructed by: Corrs Chambers Westgarth
Related laws
No related documents linked yet.
You've got 21 of 22 free Acts left this visit. Sign up anytime for Facts, Related, and study briefs too.