COMMONWEALTH OF AUSTRALIA v HOOPER [1992] NSWCA 44
NSW Caselaw
Full text
Select any passage to save a personal note with optional tags.
COMMONWEALTH OF AUSTRALIA v HOOPER
SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL
SAMUELS AP, PRIESTLEY and HANDLEY JJA
18 February 1992, 28 February 1992
[1992] NSWCA 44
CONTRACT — Pipeline Authority makes written agreement with Australian Gas
Light Company ("AGL") in which subCL7.8 says AGL shall have first refusal right
to acquire pipeline — Commonwealth proposes to transfer pipeline disregarding first
refusal right whether Commonwealth was a party to the agreement — if so, whether
Commonwealth was bound by subCL7.8 — Held: interpreting agreement against
background of commercial practicalities requires interpretation that in subCL7.8
Commonwealth joined Authority in binding promise to AGL.
Samuels JA I agree with Priestley JA.
Priestley JA This appeal deals with one issue in a dispute between the
Commonwealth of Australia and the Australian Gas Light Company ("AGL").
The proceedings began in late 1990. They were commenced by Mr Hooper the
Secretary and statutory agent of AGL as plaintiff against the Commonwealth and
the Pipeline Authority ("the Authority") when it appeared to AGL that the
Commonwealth was proposing to act in breach of what, in AGL's view, were
contractual obligations it had to AGL. The matter was regarded as urgent and the
issues were ordered to be tried separately. The separate trial was before Gleeson
CJ, who made a declaration, in regard to one of the issues, that AGL had a
contractual entitlement against the Commonwealth which the Commonwealth
had denied.
Before the Chief Justice, the Commonwealth argued a number of grounds in
support of its contention that it was not subject to contractual obligations asserted
by AGL. In dealing with those grounds, the Chief Justice set out in some detail
the circumstances surrounding two agreements made in 1974 between the
Authority, AGL and other parties, and Heads of Agreement dated 21 August
1985. The issue fought before Gleeson CJ was whether under subCL7.8 of the
1985 Agreement AGL had a binding contractual right against the
Commonwealth. That sub-clause reads:
"Subject to rights under existing agreements, AGL shall have first right of
refusal to acquire on terms no less favourable than those offered to any third
party, the pipeline, or any interest therein should the Authority decide to dispose
thereof."
(I will refer to the right claimed by AGL under this sub-clause as the first
refusal right.)
Before Gleeson CJ the Commonwealth submitted that the 1985 Agreement did
not create legal relations, that the Commonwealth was not a party to it, and that
in any event subCL7.8 did not refer to the Commonwealth, and for this and other
reasons could not be binding on it. Gleeson CJ found against the Commonwealth
on all these points.
2 UNREPORTED JUDGMENTS
In this court, the Commonwealth did not pursue the contentions that the 1985
Agreement was of no contractual effect or that the Commonwealth was not a
party to it. The question argued was whether the Commonwealth was bound by
subCL7.8.
The two 1974 agreements and the 1985 Agreement marked steps in the history
of a gas pipeline from Moomba in central Australia to Wilton in New South
Wales. Construction of this pipeline was begun by a wholly owned subsidiary of
AGL. In 1973 the Pipeline Authority Act (Commonwealth) was passed, which
established the Authority and gave it functions including the acquiring and
operating of pipeline systems. In 1974 the Commonwealth decided to take over
AGL's Moomba project. The Authority acquired the pipeline, entering into the
two 1974 agreements with AGL and also with the producers of the gas. Amongst
other things, by these agreements the Authority undertook to honour promises
which AGL had made to the producers before the Authority acquired the pipeline
and agreed to receive gas from, and transmit it through the pipeline for AGL. The
agreements also set out in detail the basis for calculating the payments to be made
by AGL for use of the pipeline. The agreements had a term of thirty years.
To protect AGL's position as a user of the pipeline and its position in regard
to the producers, the Authority in one of the agreements covenanted with AGL
that the ownership or control of the pipeline would not be transferred from the
Authority other than with the prior written consent of AGL unless the transferee
first covenanted with AGL in similar terms to the covenant then given, and in the
other agreement there was a provision that neither AGL nor the Authority could
assign its rights or obligations under the agreement without the consent in writing
of the other. Due performance of these agreements was guaranteed in writing by
the Commonwealth Minister for Minerals and Energy. The guarantees were
expressed to be for the benefit of AGL and the producers.
The charges to be paid by AGL under the 1974 agreements for the transporting
of the gas had been intended to be sufficient to recoup to the Authority, during the
term of the agreements, the cost of acquiring, completing and operating the
pipeline. By 1981 to Authority had come to the opinion that the charges fixed by
the agreements would not be sufficient for that recoupment. The Authority
negotiated with AGL for an alteration in the basis of the charges. These
negotiations continued from 1981 to 1985. There was room for negotiation
because, amongst other reasons, AGL wanted the Authority to make certain
improvements to the pipeline. Another thing that AGL wanted was the
opportunity to acquire the pipeline in the event that Government policy should at
some stage lead to its being privatised. There were indications that Government
policy of public ownership of the pipeline might be changed. The pipeline was
important to AGL which wanted to ensure that if it ceased to be publicly owned
AGL would have the opportunity of getting back into the position that it had
planned to be in in the first place, before the Authority had acquired the pipeline
from it.
The negotiations at length resulted in agreement on a changed basis of
charging for transporting the gas, improvement of the pipeline facilities, and the
giving to AGL of the first refusal right to acquire the pipeline should it be
disposed of. This agreement was embodied in the 1985 Agreement earlier
referred to.
There was detailed evidence before Gleeson CJ of the negotiating history
preceding the making of the 1985 Agreement; the parties without objection laid
before him the various drafts that preceded the final form. His summary of this
URJ COMMONWEALTH OF AUSTRALIA v HOOPER (Priestley JA) 3
was: "Both the negotiating history of the document, and some of its terms,
indicate that it was intended that the parties to the Heads of Agreement would be
AGL, the Commonwealth, and the Authority. As between the Commonwealth
and the Authority, it was the Commonwealth that took the major role in the
negotiations for the Heads of Agreement. Certain of the terms of the Heads of
Agreement were matters that directly concerned the Commonwealth rather than
the Authority. CL1 provided that AGL would have a representative on the
Authority. That was something that could only be brought about by decision of
the Commonwealth. Furthermore, CL7.4 was in the following terms:
'7.4 The acceptance by the Commonwealth of this proposal shall be taken as
full settlement of the present dispute and the Commonwealth will not initiate any
further action to recover its costs over the life of the Agreement.""
Gleeson CJ then described how it was, that in his view, the 1985 Agreement
became binding on the parties. As I have indicated, it is now agreed by the
Commonwealth that it was a party to that Agreement and that it became legally
binding.
In 1988 it became clear that the Commonwealth Government was intending to
dispose of various public assets including the pipeline. It also became known that
the Commonwealth Government took the view that the Authority did not have
power under the Pipeline Authority Act to dispose of the pipeline system as a
going concern. At this point attention focused on the form of AGL's first refusal
right. (The text is at 2 above.)
The Commonwealth Government adopted the position that AGL's only right
under subCL7.8 was against the Authority and that since the Authority could not
dispose of the pipeline system as a going concern the promise was of no practical
effect.
The Commonwealth Government embodied this view in a document it
published on 22 August 1990 requesting proposals to purchase the pipeline
system. The document referred to the 1985 Agreement saying that it would be the
Government and not the Authority which would be arranging the sale of the
pipeline system on behalf of the Commonwealth and that that would be done by
legislation.
The document also referred to the covenant in the 1974 agreements. The
relevant part of the text of that covenant was:
"5. The Pipeline Authority covenants with AGL... that the ownership or control
of the pipeline will not be transferred from the Pipeline Authority other than with
the prior written consent of AGL... and unless the transferee first covenants with
AGL... in similar terms to... this clause..." (italics added)
The document of 22 August 1990 paraphrased the relevant words of this
covenant as:
"Covenant by TPA not to transfer ownership or control of the pipeline without
the prior written consent of AGL..." (italics added)
The difference between the words and the paraphrase of the covenant serves to
highlight the fact that in 1974 the Authority was making a wider promise than
that it itself would not transfer ownership of the pipeline without AGL's consent,
namely it was promising that neither it nor anybody else would do so. If it be
right that the Authority had no power to dispose of the pipeline system as a going
concern (a matter not raised for decision either before Gleeson CJ or in this court)
the promise nevertheless had a real practical point because it was in an agreement
guaranteed in writing by the Commonwealth, which, in a practical sense, would
have the ultimate say on any question of the disposal of the pipeline.
4 UNREPORTED JUDGMENTS
When the separate trial began before Gleeson CJ, the substance of AGL's case
was that there should be a declaration of its rights under the 1974 covenant and
guarantee and under subCL7.8 of the 1985 Agreement and ancillary relief by way
of injunction. However, late in those proceedings a new point was raised about
the 1974 covenant and guarantee. The Chief Justice took the view that this point
could not be properly litigated without a number of procedural steps being taken;
to enable matters to be put in proper form, he ordered that the part of the matter
dealing with the 1974 covenant and guarantee should be made the subject of a
separate trial. What then remained for him to decide was the argument about the
first refusal right in the 1985 Agreement.
In considering whether this sub-clause bound the Commonwealth, it is of some
importance to have in mind not only that in the appeal in this court the
Commonwealth conceded that it was a party to the 1985 Agreement but that that
concession was made for what in my opinion was very good reason. It is
sufficient to mention three matters. The first is that federal Cabinet agreed to the
1985 Agreement; the second is that the text of the agreement itself showed in
different places that the Commonwealth must be party to it: see for example
subCL7.4 (pp 4-5 above); third, the Commonwealth proceeded to carry out a
number of things that the agreement required.
Against this background, Gleeson CJ considered two methods of interpretation
of subCL7.8. The first involved observing that, granted the Commonwealth was
a party to the 1985 Agreement, and reading it literally, the Commonwealth began
by agreeing that AGL should have the first refusal right, but that the sub-clause
then concluded with a condition which made illusory the opening grant of the
first refusal right. The Chief Justice regarded the opening part of the sub-clause
as undoubtedly furnishing its primary subject matter. The appropriate way of
resolving the repugnancy therefore was by disregarding the concluding words of
the sub-clause.
The alternative method of interpretation was to read the concluding words of
subCL7.8 as dealing with the commercial practicalities of the matter rather than
being directed to legal or conveyancing technicality. On this basis, the Chief
Justice said the words might be read: was referring to, and being satisfied by, a
plan of the Commonwealth, in which the Authority acquiesces or participates,
that the pipeline will be sold. The evidence makes it plain that the Authority has
been involved in, and has cooperated with the task force concerning, the
proposals to 'privatise' the pipeline."
He then mentioned some other factual matters showing the close cooperation
of the Commonwealth and the Authority, under the Commonwealth's
supervision, in the efforts to sell the assets of the Authority.
On this latter approach, the Commonwealth, as a party to the 1985 Agreement,
was joining in a promise to AGL that in the event of disposal of the pipeline, AGL
should have the first refusal right.
The Chief Justice said that whichever of the alternative constructions was
adopted the Commonwealth's view of the sub-clause must fail.
Before this court counsel for the Commonwealth vigorously assailed both
methods of interpretation. It is not necessary to discuss whether his criticism of
the first method has any validity, because it seems plain to me that the Chief
Justice's commercial practicality interpretation should carry the day irrespective
of the fate of the repugnancy approach. The surrounding circumstances point
strongly towards that view and the language itself, understood in the overall
context of its coming into existence, seems to me to support it.
URJ COMMONWEALTH OF AUSTRALIA v HOOPER (Handley JA) 5
If it is right that the Authority does not have the power to dispose of the
pipeline as a going concern as the Commonwealth contends, then the commercial
practicality interpretation is strengthened. The Commonwealth was participating
in the making of the 1985 Agreement in the most active way, it was pressing AGL
to confirm that it assented to it (as AGL eventually did), so that if the Authority
did not have the appropriate power it must follow that the Commonwealth was
promising that should the Authority decide, in a commercial way, to dispose of
the pipeline, not being in law empowered to do so, the Commonwealth would see
to it that by some appropriate method AGL's first refusal right would be available
to
In my opinion the Commonwealth's attack upon the Chief Justice's
construction of subCL7.8 fails.
The final argument relied on by the Commonwealth in challenging the Chief
Justice's conclusions was one that, so far as I can see from the transcript of the
argument before him, he was not asked to consider. This argument was to the
effect that if subCL7.8 was interpreted in the way found by the Chief Justice, it
imposed a fetter on the Commonwealth, discouraging it from considering
legislation of a certain kind (that is, which would enable the contractual
obligation to be avoided) at pain of being liable in damages or possibly having
to comply with s51(xxxi) of the Constitution if it did not. It was said that there
is an established principle that the Crown cannot make such fettering contracts.
For this proposition counsel relied upon "The Amphitrite" (1921) 3 KB 500;
Commissioners of Crown Lands v Page (1960) 2 QB 274 and West Lakes Ltd v
South Australia (1980) 25 SASR 389. Neither of the first two decisions has
attracted much approval: see the discussion in Aronson and Whitmore; Public
Torts and Contracts at 194-7, and Ansett Transport Industries(Operations) Pty Ltd
v Commonwealth (1977) 139 CLR 54 at 74-8 (Mason J) and 113 (Aickin J). The
criticism is that the proposition for which the two English cases stand is much too
widely expressed. In the WestLakes case, the second paragraph in the reasons of
King CJ would seem to negate the possibility of the doctrine, if it has any effect
in Australia, being of any help to the Commonwealth in the present case.
However, there is no need in the present appeal to consider whether the
doctrine exists in Australia and if so what its content is, because, assuming its
existence here in favour of the Commonwealth, I do not see that it can be said
to have any application to the instant facts. In the circumstances of the present
case the Commonwealth's submission can only mean that the "fetter" would
discourage either the Commonwealth executive from considering the
introduction of the particular legislation to Parliament, or Parliament from
considering its passage. I cannot see how it can be said that the existence of the
contractual obligation which in my opinion the Commonwealth undertook when
the 1985 Agreement was made, could, as a matter of fact, have any such effect.
I do not think it is accurate to say that the contractual obligation is in any real
sense a fetter, or exerts any pressure, upon either the Commonwealth executive
or the Commonwealth Parliament or any of their members in regard to legislation
which may be proposed to Parliament.
In my opinion this appeal fails, and should be dismissed with costs.
Handley JA I agree with Priestley JA.
Appeal dismissed with costs.
Counsel for the Appellant: D Jackson QC/Mrs M Beazley/ M Rudge
6 UNREPORTED JUDGMENTS
Counsel for the Respondent: (1) AR Emmett QC/AA Bell (2) G. Curtis (Sol)
(Submitting appearance)
Solicitors for the Appellant: Australian Government
Solicitors for the Respondent: (1) Minter Ellison (2) Australian Government
Solicitor