Select any passage to save a personal note with optional tags.
CJ AND R LIESCHKE v BR TURNER
SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL
KIRBY P, MAHONEY JA and Hope AJA
9 March 1992, 9 March 1992
[1992] NSWCA 135
ARBITRATION — BUILDING DISPUTE — ARBITRATOR'S AWARD — DATE
OF "PRACTICAL COMPLETION" — MEANING OF — CLAIM FOR LOSS
AGAINST BUILDER — FINDING BY ARBITRATOR ON FACTS — HELD:
LEAVE TO APPEAL REFUSED.
ARBITRATION — commercial arbitration — appeal to Supreme Court — appeals
limited to leave in cases of manifest error of law on face of the award — building
dispute between proprietors and builder — whether builder liable for water damage
— whether builder liable after determined date of practical completion — date
thereof — Giles J refuses to grant leave — proprietors apply by summons for leave
to appeal to Court of Appeal — held (dismissing summons): The case was not one
suitable for leave. Observations by Kirby P on the "purpose of Parliament that leave
should not be granted except in the comparatively rare circumstances of a manifest
error of law".
Commercial Arbitration Act, 1984 s38(5).
ORDERS Summons dismissed with costs.
Kirby P By s38(5) of the Commercial Arbitration Act, 1984 Parliament has
provided for cases to which this summons for leave to appeal applies. The
subsection provides, relevantly: s38(5) The Supreme Court shall not grant leave
under the subsection unless it considers:
(b) there is
(i) a manifest error of law on the face of the award"
Giles J, before whom the summons for leave to appeal first came from the
arbitrator, concluded, for reasons stated by him on 14 February 1992, that there
was no such error of law. Two such errors were alleged by the claimants who
were the proprietors in the subject building dispute before the arbitrator. The
summons before us is an application for leave to appeal from his Honour's
decision, wherein he decided that the summons before him should be dismissed
with costs. The claimants have reargued in this Court the contentions which they
unsuccessfully urged upon Giles J.
Of the two suggested errors of law argued before his Honour, the first was that
the arbitrator, on the face of the reasons given and attached to his award, had
erred in the way he dealt with a claim of the proprietors in respect of the repair
or replacement of the claimants' chattels arising from water damage resulting
from a storm in December 1988. At that time the subject premises were in the
course of construction by the opponent, the builder.
It is true that the reasons given by the arbitrator on this point are somewhat
confusing. There is a comparatively lengthy discussion by him of the issue of
insurance. This was irrelevant to the issue to be decided. However, at the end of
his reasons on this point, the arbitrator came to what Giles J felt to be his real
reason for dismissing this aspect of the proprietors' claim. The arbitrator said:
2 UNREPORTED JUDGMENTS
"The Respondents initial refusal to allow the chattels to be stored elsewhere;
their inaction when they observed water pouring into the house, and their
inattention to the water damaged items when finally stored in an outbuilding,
discloses a lack of concern for their property. In addition I have noted the
Claimants obligation to prevent water penetration to the building but this is met
by the unforeseeable and violent nature of the storm".
It is pointed out that in the specifications agreed between the claimants and the
opponent the builder promised to "at all times [keep] existing buildings
watertight". It may also be pointed out that, by CL14.1 of the subject building
contract, the builder was rendered liable by the contract to indemnify the
proprietor "against any legal liability, loss, claim or proceeding... due to the
negligence, omission or default of the builder". The claimants' case was that the
water damage suffered by them was a loss due to the builder's negligence.
Giles J interpreted the arbitrator's award to mean that the "true cause" of the
loss which the claimants suffered was the unforeseeable and violent nature of the
storm and the failure of the proprietors to take steps to protect their own property.
I agree with his Honour's interpretation. I accept this interpretation as the true
construction of what the arbitrator said. But if this is so, it represented a finding
of fact and nothing more. It does not constitute a "manifest error" on the face of
the award, still less an "error of law" which would attract leave to appeal from
Giles J, particularly given the imperative instructions of Parliament in s38(5)(b)
to which I have referred.
For this reason, there is no such error on the part of Giles J as would attract
leave in this Court. On the contrary, I consider that on this point his Honour's
approach was correct. It is clearly the purpose of Parliament that leave should not
be granted except in the comparatively rare circumstances of a manifest error of
law.
That leaves the second argument for the claimants. This relates to the date of
"practical completion" of the contract, after which the claimants' relevant
entitlements terminated. This point concerns CL16.1 of the contract. That clause,
put generally, provides a mechanism whereby, in the event of a dispute, the date
of practical completion can be determined by a procedure of written notice. In
this case, it was common ground that no such written notice was ever given. Nor
was a decision of the architect made. Accordingly, the "date of practical
completion" was a question of fact to be decided by the arbitrator. It was not
determined by the exceptional procedure envisaged by CL16.1.
The arbitrator approached the resolution of the question by referring to matters
such as the laying of carpet in the premises, the cleaning of the premises and the
painting of the premises. Clearly, these were matters relevant to his
determination. They do not indicate an error of law in the approach which he
adopted. Nor do they indicate a manifest misapplication of CL16.1 in the
contract, assuming that to constitute an error of law. It was not for the proprietors,
by the date of their actual re-occupation of their premises, to determine
conclusively when the premises was "reasonably fit for use", as the contract
provides. To the extent that the proprietors' assertion is that they were entitled to
have the actual date of their occupation accepted uncritically as the date of such
"reasonable fitness", I would reject their argument, as the arbitrator did and as
Giles J did as well.
Accordingly, the two errors of law which were urged upon this Court are not
such as to attract the intervention of the Court. In my view, Giles J was correct
in the decision which he made. Accordingly, his decision must stand.
URJ CJ AND R LIESCHKE v BR TURNER (Hope AJA) 3
The order in this Court should be: the summons for leave to appeal should be
dismissed with costs.
Mahoney JA In my opinion, this is not an appropriate matter for leave to
appeal. I would dismiss the summons for leave to appeal with costs.
Hope AJA I agree.
The orders of the Court are: KIRBY P:
1. Summons dismissed; and
10 2. The claimants to pay the opponent's costs.
Counsel for the appellant: OG Watt
Solicitors for the appellant: Fleming Muntz
15 Counsel for the respondent: EM Olsson
Solicitors for the respondent: Gibney and Gunson
Related laws
No related documents linked yet.
You've got 21 of 22 free Acts left this visit. Sign up anytime for Facts, Related, and study briefs too.