WINROBE PTY LTD v SUNDIN'S BUILDING CO PTY LTD [No 2] [1992] NSWCA 278
NSW Caselaw
Full text
Select any passage to save a personal note with optional tags.
WINROBE PTY LTD v SUNDIN'S BUILDING CO PTY LTD [No 2]
SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL
KIRBY P, SHELLER and CRIPPS JJA
20 August 1992, 24 December 1992
[1992] NSWCA 278
PRACTICE and PROCEDURE — review of judgment before orders entered —
orders previously announced allegedly affected by procedural unfairness — claim
between proprietor and builder concerning erection of building partly on land of
third party — proprietor gives builder notice under contract — notice alleges failure
to proceed with project in a competent manner — particulars annexed to notice set
out alleged encroachment — notice fails to specify with particularity the action
required of builder — Court in earlier reasons dismisses proprietor's claim upon the
basis of inadequacy of the notice in specifying what builder must do to put matter
right — whether Court proceeded upon the basis of an erroneous legal principle or
a factual issue not in dispute at the trial — held: (Sheller JA; Kirby P and Cripps JA
concurring): (1) The legal principle stated by the Court was correct and the
judgment would not be reviewed upon that ground. Pauling vy The Mayor, Aldermen
and Burgesses of the Borough of Dover (1855) 10 Ex 753; 156 ER 644 followed. The
notice required specification of the action required by it; (2) However, it was now
clear that the validity and specificity of the notice was not in issue at the trial; (3) Had
such validity and specificity been in issue, evidence might have been called to help
resolve the suggested ambiguities of the notice. Codelfa Construction Pty Ltd v State
Rail Authority of New South Wales (1982) 149 CLR 337 applied; (4) Accordingly, the
claim having been dismissed upon the basis of the notice's lack of specificity, a
procedural unfairness to the appellant had occurred which required review of the
earlier judgment upon the footing that the validity and specificity of the notice was
not in issue. Coulton and Ors v Holcombe and Ors (1986) 162 CLR 1 applied; (4)
Original judgments and proposed orders withdrawn for the purpose of such review.
Smith v New South Wales Bar Association [No 2] (1992) 66 ALJR 605 (HC);
Wentworth v Rogers and Ors [No 9] (1987) 8 NSWLR 388 (CA) applied.
JUDGMENTS and ORDERS — withdrawal of judicial orders before entry —
avoidance of procedural unfairness — determination of appeal on a basis conceded
at trial — concession at trial not made clear during argument of appeal despite
questions from the Court on the issue — original judgments withdrawn for review of
the decision upon the footing of the issues contested at the trial. Smith v New South
Wales Bar Association [No 2] (1992) 66 ALJR 605 (HC) applied.
Supreme Court Rules, Pt40, R9(1).
Kirby P I agree with Sheller JA.
Sheller JA The Court delivered its judgment and made orders in this appeal
on 15 June 1992. On 30 June 1992, on the appellants' application by notice of
motion, we ordered that judgment not be entered pending the hearing of an
application by the appellants, in effect, for the Court to review and alter its
judgment. We have power to take this course; Pt40 R9 (1) of the Supreme Court
Rules and Smith v New South Wales Bar Association (1992) 66 ALJR 605 at 608.
In that case four members of the Court said:
2 UNREPORTED JUDGMENTS
"The power is discretionary and, although it exists up until the entry of
judgment, it is one that is exercised having regard to the public interest in
maintaining the finality of litigation (Wentworth v Woollahra Municipal Council
(1982) 149 CLR 672 at 674). Thus, if reasons for judgment have been given, the
power is only exercised if there is some matter calling for review (Marinoff v
Bailey (1970) 92 WN (NSW) 280 at 284; National Benzole Co Ltd v Gooch
(1961) 1 WLR 1489 at 1492-94) and there may be more or less reluctance to
exercise the power depending on whether there is an avenue of appeal (State Rail
Authority of NSW v Codelfa Constructions Pty Ltd (1982) 150 CLR 29 at 38-39,
45-46; Wentworth v Rogers (No 9) (1987) 8 NSWLR 388 at 394-5)."
The appellants' complaint is directed to one part of my judgment, with which
the other members of the Court agreed. Two things are said of it; first that my
conclusion was contrary to authority which was not cited to us; second that it was
adverse to the appellants on an issue which had not been raised at the hearing
before the trial judge, Giles J. Since the matter involves, to a substantial degree,
what took place in argument before us on the appeal and bearing in mind that,
subject only to the High Court granting a party special leave to appeal from our
decision, we are the final Court of Appeal, the matter is one with which, for these
and other reasons, I think we should deal rather than leaving the appellants to
make application for special leave to the High Court. For reasons which will
appear, I think the appellants' application to review the judgment should be
granted. The respondent made no submissions to the contrary.
The application is directed to that part of my judgment which deals with a
notice purportedly given, pursuant to CL31 of the Building Contract, by the
appellants, the Principal under the contract. Para(a) of that clause provided that
if the Contractor, the respondent to the appeal, should make default in the
following respect, inter alia,
"(ii) If he fails to proceed with the Project with due diligence or in a competent
mannef,.........
AND if, in the face of a default that is capable of remedy, he shall continue that
default for ten (10) days after notice in writing has been given to the Contractor
specifying the default and stating the Principal's intention of determining the
Contractor's employment, THEN the Principal may, without prejudice to any
other rights or remedies, by notice by registered mail determine the employment
of the Contractor under this Contract."
The Principal gave a notice in a form which is set out in my judgment. The
notice recited that the Contractor had failed to proceed with the Project with due
diligence or in a competent manner. It then recited, in summary form, CL31 and
in its body stated:
" (1) That pursuant to CL31 of the Contract the Principal gives notice that the
Contractor has failed to proceed with the Project with due diligence or in a
competent manner particulars whereof are set out in the Schedule to this notice
AND FURTHER TAKE NOTICE that if the Contractor shall continue the default
for ten days after this notice has been given to the Contractor then it is the
intention of the Principal to determine the Contractor's employment under the
Contract."
The particulars given in the Schedule were as follows:
"The Contractor has failed to proceed with the Project with due diligence or in
a competent manner in that the Contractor has designed and constructed the
Works in such a manner that the same encroach upon the Rights of Carriageway
burdening the Site being Lots 4 and 5 in Deposited Plan 748030 so as to preclude
URJ WINROBE PTY LTD v SUNDIN'S BUILDING CO PTY LTD [No 2] (Sheller JA) 3
the Proprietors of Strata Plan No 34735 which is the registered proprietor of the
dominant tenement from having the benefit of such Rights of Carriageway. "
The appellants claimed that the Contractor was obliged to redesign and
construct or reconstruct the Works. It failed to take any steps to do so and,
accordingly, it is said that the notice effectively enabled the Principal to
determine the Contractor's employment. The Contractor's failure is said to be a
failure to proceed with the project with due diligence or in a competent manner.
In the course of his judgment of 18 December 1990, from which this appeal
was brought, Giles J said:
"Tt follows from the view which I have expressed that there was no failure on
the part of the contractor to proceed with the Project with due diligence or in a
competent manner. As the principal pointed out, the Project included the
contractor's obligation to design the Works as well as to construct the Works.
Implicit in the principal's notice given on 23 August 1990 was that the contractor
was obliged to redesign and construct or reconstruct the Works so that there was
no encroachment on the rights of carriageway interfering with the enjoyment of
the rights of carriageway by the owners of lot 3. The principal relied for this
obligation on an express obligation which it said was found in CLI (a) of the
articles of agreement and CL11 CL13 and CL20 of the conditions, and did not
contend for an implied obligation to correct a design (eg Equitable Debenture
Assets Corporation Ltd v William Moss Group Ltd (1984) Con LJ 74) or warn
of a defective design (eg Victoria University of Manchester v Wilson (1988) Con
LJ 416). Any such implied obligation may well have been inconsistent with the
express terms of the contract, but that did not arise. For the reasons I have given,
I do not think that in August 1990 there was any obligation on the contractor to
so redesign the Works.
On the contrary, the contractor was obliged to execute the work shown upon
the Contract Drawings, and thus to construct the Works by building on the rights
of carriageway in such a way as to interfere with the enjoyment of the rights of
carriageway. The principal could vary the Works, but its remedy was in damages
for the breach of the warranty in CL20 of the conditions. Hence the principal was
not entitled to terminate the contract, as it purported to do by the notices of 23
August and 13 September 1990, pursuant to CL31 of the conditions."
In the course of my judgment I held, contrary to the conclusion reached by
Giles J, that the Contractor was by contract obliged to remedy any defect in the
design and stated that I was inclined to think that the nature of the contract was
such that it would be obliged to build in accordance with the redesign.
Accordingly I thought it necessary to determine whether the notice was
effective in the circumstances of the case to enable the Principal to determine the
contract. I considered it was not because it failed to specify the default and state
with reasonable explicitness what was required to be done about it.
I said that I did not agree that it was implicit in the notice that the Contractor
was obliged to redesign and construct or reconstruct the Works so that there was
no encroachment on the Right of Carriageway. "It certainly was not explicit." I
said:
"A notice given to a party in default under a contract that if something required
to be done is not done the contract will be put to an end must state with
reasonable explicitness what it is that is being required to be done; O'Brien v
Dawson (1941) 41 SR 295 at 304.
4 UNREPORTED JUDGMENTS
Tf as it was entitled to do the Principal required the Contractor to redesign and
demolish that part of the Works which interfered with the rights of carriageway
it was in my opinion bound to say so explicitly in the notice. The Works were 80
per cent complete. Properly understood the notice did not require the Contractor
in order to avoid termination to demolish within ten days so much of the Works
as interfered with the rights of carriageway and to redesign them so that they did
not so interfere. It is plain from the language the Principal used that it did not
intend this by its notice. This is also consistent with what had taken place
between the parties up to that time. In my opinion the notice was not effective
under CL31 to enable the Principal to determine the employment of the
Contractor under the contract."
The correctness of this conclusion is challenged by the appellants on this
application. In support of this challenge the appellants have referred to the
following cases: Pauling v The Mayor of Dover (1855) 10 Ex 753; 156 ER 644;
Re Stewardson Stubbs and Collett Pty Ltd and Bankstown Municipal Council
(1965) 2 NSWLR 1671; Hooker Constructions Pty Ltd v Chris' Engineering
Contracting Co (1970) ALR 821; Eriksson v Whalley (1971) 1 NSWLR 397;
Hounslow LBC v Twickenham GD Ltd (1971) Ch 233; Brenmar Building Co Pty
Ltd v The University of Newcastle (unreported, Court of Appeal, 12 December
1977); Brown and Doherty Ltd v Whangarei County Council (1988) 1 NZLR 33
and Yendex Pty Ltd v Prince Constructions Pty Ltd (1989) 5 BCL 74. Of these
all but three, Pauling, Brenmar and Yendex are decisions of single judges. None
detracts from the general principle that I stated in my judgment by reference to
O'Brien v Dawson nor indeed as a general principle do the appellants challenge
it. The appellants say two things: first that a reference to the default as described
in CL31 (a) (ii), that is to say by saying that the Contractor has failed to proceed
with the project with due diligence or in a competent manner, is a sufficient
"specifying" of the default; second that the contract did not require the Principal
to specify what must be done to put the matter right; compare Hounslow LBC v
Twickenham GD Ltd at 264G.
The respondent referred to Leros Pty Ltd v Terara Pty Ltd (1992) 66 ALJR 399
at 405 where, in the context of the requirements for the form of a caveat to protect
an estate or interest in land under the West Australian Transfer of Land Act 1893,
three members of the High Court said that it seemed to them "that 'specify'
should be understood in the sense of 'mentioned definitely or explicitly' ".
For the reason, as will appear, that I consider that, had the appellants taken
objection to its doing so, this Court would not have entertained an argument that
the notice under CL31 was defective, I do not think it appropriate to do more
than, in deference to the arguments and researches of counsel, express a tentative
view about the arguments now put on behalf of the appellants.
As to the first, the cases relied upon by the appellants were all concerned with
claims by the proprietor that the builder had failed to maintain an appropriate rate
of progress and, in that sense, not complied with its general obligations under the
contract. To adapt the language of Baron Park in Pauling's case the work in
general had been done in a negligent and sluggish manner. They were not cases,
such as the present, involving, if the defect was to be put right, redesign and
demolition. As Moffitt J, as he then was, pointed out in Stewardson Stubbs at
1674, lack of reasonable diligence or competence may be capable of remedy in
two possible senses, that is repairing the results of the lack of past diligence or
URJ WINROBE PTY LTD v SUNDIN'S BUILDING CO PTY LTD [No 2] (Sheller JA) 5
competence or, alternatively, merely by proceeding in the future with reasonable
diligence and competence. In Pauling's case Baron Park, sitting as a member of
the Exchequer Court said:
"T think, that, if the engineer had wished the plaintiff to do some particular
piece of work, as, for instance, to pull down and rebuild some portion of the
work, the notice should have specifically stated to what extent he required the
particular work to be done. But here the objection of the engineer is, that the work
in general is done in a negligent and sluggish manner. It is, therefore, sufficient
for him to give a general notice of this description. He tells the plaintiff he is
proceeding in a negligent and slow manner, and requires him to do the work
better, and with more expedition. Such a notice is good."
So far as I am aware this statement has never been doubted. It is argued on
behalf of the respondent that it applies to the present case and demonstrates the
notice to have been defective.
As to the second point, a clause such as CL31 may well be regarded as
intended, if possible, to provide an opportunity to avoid the necessity for
termination and to allow the contract to be completed in accordance with its
terms. That being so, I incline to the view, in the circumstances of the present
case, that the expression "specifying the default", if what is required is
rectification rather than future performance, (compare per Samuels JA in
Brenmar Building Co Pty Ltd v The University of Newcastle), calls for the notice
to state with reasonable explicitness what it is that is required to be done. None
of the authorities now cited suggests otherwise.
The appellants, however, submit that the effectiveness of the notice under
CL31 was not an issue at the hearing before Giles J. The respondent denies that
the point was conceded. But the appellants' argument is that the issue was
whether the Contractor was in breach of an obligation entitling the Principal to
give the notice it did. Giles J held that it was not in breach of such an obligation.
I took the contrary view. During the course of argument in this Court the
effectiveness of the notice was raised by the Court. It is desirable to set out in full
the passages from the transcript of argument. The hearing of the appeal extended
over two days and the matter was raised in the course of both the appellants' and
the respondent's submissions on the first day and again in the appellants'
submissions in reply on the second day.
A. In the course of the appellants' submissions on the first day of the hearing
of the appeal:
"SHELLER JA: Your notice does not say - Produce a proper design. It seems
to be attacking the fact the initial failure entitles you to terminate? COLES: One
would get that impression. That should be read, in my submission, as referring to
the initial, or original, failures to proceed in the sense that the design was flawed
from inception, and it also should be read as a failure, therefore, to amend or
rectify that design as a progression as the works got under way.
SHELLER JA: CL31 (a) (b) seems to be talking about some ongoing process.
The contract has been made, and the contractor fails to proceed with the project.
The trouble I have at the moment is that 177 (this is a reference to the page in
the appeal book where the notice was, in part, set out) seems to be talking about
some pre-contract failure to do something? I do not understand the principle upon
which you say that entitles you to terminate in accordance with that notice,
because you depend upon that notice?
6 UNREPORTED JUDGMENTS
COLES: We do not for the general right. All we say is we have asserted a state
of affairs in that notice, namely, that the contractor has failed to proceed with the
project with due diligence and in a competent manner. Then we particularise that.
He has designed and constructed the works in a manner that they encroach.
Accepting what your Honour says the clause contemplates, by use of the word
'proceed' - the progressive steps involved in the project, we say, those are the
steps the contract provides for. We say, if there was at the outset a faulty design,
then proceeding with the project in accordance with that design was not
proceeding with the project with due diligence.
We say, inasmuch as it was incumbent upon the contractor to continue to
design, and to redesign, from time to time, that he failed to proceed with that
aspect with diligence, competence or at all, and the proof of that position was that
there was constructed the building in the way referred to in the schedule, that is
to say, encroaching. We say that is right, that is what happened.
Be that as it may, quite apart from any other provision of the contract apart
from CL1(a) and CL13, there was a state of affairs clause, CL31 (a) (ii), which
describes, namely, failure to proceed with the project in a diligent or competent
manner.
We say that can be identified, really, throughout the course of the works from
the inception of the plans up to and including the whole of the period before May
but the principal was ignorant of the infringing quality of the design, and, upon
becoming aware, there was a continuing failure to proceed between May and
August - notice was given. There was then a failure to comply with it. His
Honour took the notice - and we do not shrink from the accuracy of the
description - as being a notice requiring the contractor to redesign or reconstruct
accordingly. He took no steps as to that. After 10 days no intimation of the course
to be embarked upon by the contractor in remedy had become apparent.
SHELLER JA: The problem I have in this case is what the contractor was
asked to do was contribute to the amount of settlement that had to be paid to the
neighbour. This is not a case in which the contractor was asked to fix his design
up?
COLES: He was required to remedy the breach, and his Honour took that to
mean a requirement that he redesign and, so far as necessary, reconstruct.
SHELLER JA: There was never the slightest suggestion that would happen.
The idea was they would pay out the neighbour? COLES: No doubt the principal
hoped that some accommodation could be reached with the owner in due course,
no doubt for the payment of money if necessary. The renunciation of the
obligations is to be found, in all the circumstances, page 4 of my outline of
submission.
SHELLER JA: The contractor refused to contribute?
COLES: Not only that, he denied it was his responsibility. Upon receipt of a
notice saying - Fix it - he did nothing, against the background of having already
initially furnished a design which was - we say - in breach of his obligations of
skill and care and, secondly, having had drawn to his attention what he should
have already suspected, that the design he had tendered resulted in serious
consequences, he, of his own initiative, did nothing affirmative about it.
SHELLER JA: Where do we find a request from the proprietor that the design
be put right, or fixed?
COLES: One finds it in the notice of 23 August.
SHELLER JA: I have some difficulty reading that as saying that?
URJ WINROBE PTY LTD v SUNDIN'S BUILDING CO PTY LTD [No 2] (Sheller JA) 7
COLES: The notice was at 176 volume 1. His Honour said - page 738.6 (read).
That is not to say that other recipients might have read the notice differently.
Certainly, we would see the notice conveyed that meaning. We understand the
submissions put against us on that question tend to assume that his Honour's
reading of the notice was the reading for which we contend, because it is said that
has other consequences, so far as the characterisation of breach is concerned, as
being an anticipatory one.
I read to your Honours the passage a moment ago that assimilated within the
repudiation the evincing of the intention to perform substantially in a manner
inconsistent with the obligations, or to perform in a manner more or less
dependent upon the promisor's own discretion.
We place considerable reliance on the express intimation coming from Mr
Sundins in the passage at 270, that is to say, Mr Sundins' assertion - we are not
responsible for the problem with the right of way. We had the earlier
conversation, where he stated he did not regard it as appropriate, at least at that
stage, for the appellants to be paying any money, indicating that he himself was
not going to contribute."
B. In the course of the respondent's submissions on the first day of the hearing
of the appeal:
"DONOHOE.............4+ My friend, when he came to CL31, had to grapple with
questions from Mr Justice Sheller on the inelegance of the notice, which appears
at 176 and the apparent incongruity between the language of CL31 - CL31 (a).
We submit that CL31 (a)(ii) is prospective in its natural sense, and it is, in its
terms, quite inappropriate to describe an error found in the design undertaken by
the contract - so entered into.
We point to 'fails to proceed' and we say those words contemplate, and are
appropriate to, the getting on with the detailed design after the contract had been
entered into.
When one looks at the task faced by the draftsman at 176 it becomes apparent
(read). No particulars were furnished, and the moment one attempted to furnish
them they would have been of events pre-contract. One searches in vain for any
indication of when this occurred.
SHELLER JA: If this design was defective and required to be fixed up why
was it not your obligation to fix it up?
DONOHOE: Because we had not been given a direction by the principal as to
what to do. The principal said - Give me some money to buy off the neighbours.
SHELLER JA: In a sense that is what the case is all about - the effectiveness
of that notice? That is central? DONOHOE: Yes, we say that.
SHELLER JA: In a broad sense you acknowledge that there was an obligation
under the contract to continue a design process of some sort which would have
involved fixing up a defective preliminary design. The point you make is that you
were never asked to do that?
DONOHOE; Yes, and we say the whole of the appellant's case has to be based
on this tortured construction point to get a result if the construction is, as Mr
Justice Giles found it to be, and it really is not a repudiation case. The building
was 80 per cent complete and ahead of schedule. That was said in the first
affidavit. This was a job that was going well. The builder claimed a bonus and
recovered bonus on the basis he would have finished early - page 11.K. The only
reason work stopped was because payments stopped. While it may be said - Here
was a case, if the construction of the contract that Mr Justice Giles held to be the
correct construction, is not the correct construction then my clients ought to have
8 UNREPORTED JUDGMENTS
understood that they had an obligation. The reality is they were confused. They
were not saying - We do not propose to complete this job. This is a case where
they wanted to get on, finish and get their bonus. It really is artificial to try and
construct these arguments of repudiation based upon appreciation of points of
law and construction because the Court would not readily find an intention to
repudiate."
C. In the course the appellants' submissions on the second day of the hearing
of the appeal:
"COLES........ My friend said yesterday the designer in the present case was
not asked to fix the design. Once he became aware of the problem he ought to
have set about fixing it or evincing an inclination to fixing it whether asked or
not. Secondly, he was asked albeit in a somewhat different context, that is, the
notice of 23 August. Inasmuch as there might be an express or implied
requirement to notify on our part the contractor that he ought to - if there is to be
implied an obligation to ask him before there was implied a duty to act - it is
dispensed with by the contractor's inclination that such an implication would be
- by washing his hands of the matter, that meant the contractor was maintaining
an untenable construction of the contract. He never ventured a design or anything
toward the solution of the problem.
We understood it to be suggested yesterday firstly it might be conceded by the
contractor that there was a continuing design duty. If there be conceded such a
duty independently to be inspired by the variation clause such a concession
which is a correct one suggests the processes adopted by Giles J to resolve the
matter were not the correct ones. Apart from that what was then said was one
should accept the inference of repudiation should not lightly be drawn. The
repudiation in the present case comprised the evincing by the contractor of an
intention not to perform at all or only to continue performing on his own terms.
We rely upon his express avowal 'It is not my responsibility'. We rely on his
failure to do nothing to address his mind to anything when we sent him the notice
and we rely upon his response, issuing a notice suspending the works, a notice
was not one he was entitled to issue, but which evinces an intention not to
perform any further design obligations at all including reconstruction obligations
necessary pursuant to that design in the events which happened.
One can test the matter by asking what does the principal do when he has a
defective design, an exposure for a large amount of money or great
inconvenience to third parties, the possibility of enormous cost and on the other
hand the person to whom he should be looking for assistance, his builder, says it
is not my responsibility and I am not prepared to do anything. What should have
been done? We do not say it was the obligation of the builder there and then to
demolish the right of access ramp, he needed to evince some readiness to go on
with the contract to accommodate the consequences of his breach. It was not
good enough to do nothing. It got worse. We have, in giving notice on 23 August
saying please do something, responded with a notice to say 'We are downing
tools' but at 67 we are sent a notice of demand under the Companies Code
threatening to wind up. The notice is not in evidence but the solicitors for the
principal wrote a letter about it and from p 67 it appears there was sent on 31
August 1990 a notice of demand under s364 of the Companies Code which is a
section which provides if one does not pay within 21 days one is deemed to be
insolvent and may be would up accordingly.
URJ WINROBE PTY LTD v SUNDIN'S BUILDING CO PTY LTD [No 2] (Sheller JA) 9
One is entitled to issue a demand if one is unequivocally entitled to be paid an
amount. The builder was saying he was entitled to an indefeasible title which the
principal would either pay him or be deemed insolvent,. The threat to wind up the
principal was not going to coerce it but if brought to fruition would deprive it of
the intention of litigating with the owners of Lot 3. Where is any evidence or
demonstration of the evidence to go on with the contract in its terms. We did not
in sending the notice of 23 August want the ramp to be demolished one would
have thought
SHELLER JA: What did you want.
COLES: Some indication by a builder in the difficult circumstances in which
we found ourselves he was to perform the obligations in the context of proffering
as soon as practicable a demonstration by way of some further design of
something that if in the worst of all worlds we were obliged to demolish we could
at least have under way in point of gaining council approval and the like
something from the builder pursuant to his design obligation which would have
been a comfort in the position in which we found ourselves.
CRIPPS JA: Was that aspect explored at the trial, what you should have done?
COLES: Was there evidence of these various opportunities?
CRIPPS JA: Yes or what you should have or should not have done in response
to all this.
COLES: Someone being cross examined as to what he should have done, I
don't think so. I really can't say.
SHELLER JA: You asked for money, then issued a notice which on my reading
really does not say what you want at all. You are just moving away from the real
thing. If you wanted this to be redesigned it was easy enough to say so, but you
didn't say that.
COLES: His Honour read it that way.
SHELLER JA: I find it difficult to read that as a requirement that the contractor
prepare a new design and make the building conform with it.
COLES: One would ask how does one rule out if one does not read it as
requiring some action?
SHELLER JA: Evasive. What strikes me at the moment is that you wanted
money if you had really written to them and said what you wanted it would be
"We wanted a contribution.... *.
COLES: There was no point. Even when the sum was $10,000 -
SHELLER JA: In any event that is the impression I had and that is not said and
I find it very difficult to get out of this language a plain statement you really
wanted what you now say, namely, a redesign.
COLES: We were entitled to a redesign.
SHELLER JA: The question is whether you asked for it.
COLES: By drawing the attention to the identified deficiency in the old one we
flagged the desirability of a conforming one. The notice did not ask for money.
The last thing we wanted was to pull the access ramp down unless that was a
matter of the
SHELLER JA: You didn't really want the contractor to redesign it.
COLES: Yes we did. Supposing we are in the position we have to pull it down.
We will need to have something in its place. That was the position at the time we
gave the notice. We either leave things in limbo and submit to a contractor who
only demands payment of money or bring things to a head and say 'Against the
day we must pull this down you must have a conforming plan available to satisfy
your obligations'.
10 UNREPORTED JUDGMENTS
The validity of the repudiation argument does not depend on any question of
construction of the contract but on the principles to which we have referred. If the
notice is inoperative for CL31 purposes which we deny, it takes its position as
part of the position that one views these things, from the standpoint of the
innocent party. Not the party who knowing of the error persisted in it. From the
standpoint of one who is confronted with what has gone on one looks at his
expectations. One readily infers from there being no response, but a notice to
suspend and a demand under the Companies Code, he was not going to perform
this contract other than in the way he wanted himself. What is an innocent person
to do when he finds himself in this dilemma? The first thing he could do is pay
out and hope. He can hope in paying up the builder will carry on, and he can hope
the builder will remain solvent long enough for the proprietor to recover
damages. It would be pointless to issue a variation order because he has already
said no to the request. He is going to assert an entitlement to be paid for it. In the
present case there could have been no question that Sundin would refuse to
recognise the right which his Honour suggested existed to set off the expense of
complying with the variation order against what we denied as his responsibility.
What was the proprietor to do? At least by sending his notice he flushed out from
the proprietor the very answer to the question what is the contractor going to do
and the answer was a resounding nothing. That the principal can stew."
In answer to the suggestion that the notice under CL31 was defective, it was
not submitted by the appellants either on the first day of the hearing of the appeal,
when it was first raised, or on the second day, that the matter was not in issue at
the trial nor were the cases now relied upon referred to. In fact no authority was
referred to. Rightly or wrongly after the matter had been reserved this left the
Court in the position where it assumed that the validity of the notice was an issue.
Prior to judgment, which was delivered over two months after the hearing of the
appeal, no application was made to deal with these matters.
The appellants now seek on this application to rely upon cases not previously
referred to but, more importantly, to argue that on the basis of well-known
principle, it was not open to us to treat the notice as ineffective. This latter
submission was not initially relied upon in the application to review the judgment
but emerged as a basis for doing so during the course of oral argument which
took place on 20 August 1992.
In their written submissions dated 26 August 1992 the appellants say:
" (a) The point on which the Court has pronounced against the Notice was not
the subject of any Notice of Contention, nor of any application to amend the
Notice of Contention, nor of any specifically formulated arguments by the
respondent in either its written or oral submissions;
(b) The appellants failed to appreciate the significance of the interchanges in
argument on the question of the content or effect of the Notice. It was not the
appellants' understanding that the Court would necessarily be disposed ultimately
to take a view of the Notice different to that of the trial judge. More importantly,
it was not made apparent that even if the Court so differed from the trial judge,
the result would be that the Notice should be condemned as ineffective for the
purposes of CL31, with the consequence that the appellant by later relying upon
it to terminate the contract became itself a repudiator. The specific proposition
that the principal was bound in law explicitly to stipulate for redesign and
demolition (as opposed to the observation that it had failed so to provide) under
penalty of having its Notice pronounced against was not canvassed in argument,
the debate on the run being limited essentially to the contention that Giles J was
URJ WINROBE PTY LTD v SUNDIN'S BUILDING CO PTY LTD [No 2] (Sheller JA) 14
correct in his view. The possible application of the general proposition illustrated
in other contexts by O'Brien v Dawson was not raised nor dealt with.
(c) Thus, when the question of the correct reading of the Notice arose at 20 of
the transcript of argument (preceded by some discussion at 17) the appellant said
at 20.8: 'We understand the submissions put against us on that question tend to
assume that his Honour's reading of the Notice was the reading for which we
contend....'.
(d) The respondent, for its part, simply took on board the suggested
'inelegance' of the Notice (page 28.6) without seeming to develop any
submission thereon. Likewise (at transcript page 29A) it embraced without
elaboration the propositions put to it, but in the context of its own arguments
(appearing from 29.8 et seq) on other aspects of the case.
(e) However, it may be acknowledged that the remarks of Giles J at AB 738
were open to interpretation as representing a conclusion on a matter which the
Court might have thought had been in issue. In the course of argument the
appellant failed clearly or at all to inform the Court expressly that there had been
no such issue. Equally, the respondent, inasmuch as it embraced matters put from
the Bench, did not in terms indicate that it had not sought to impugn the Notice
in the Court below upon the ground ultimately discerned in the Court's judgment.
In making this observation, the appellant intends no criticism of the respondent's
conduct, since it is not apparent that the respondent itself had any reason to
apprehend that the Court would necessarily resolve the case against the appellant
on the specific basis ultimately identified in the judgment.
(f) If the appellant had understood, on the other hand, that the respondent was
itself advancing a significantly new case, notwithstanding its Notice of
Contention and the absence of any application to amend the same, it might
reasonably have been expected that the appellant would have been astute to point
out to the Court that there had been no issue nor debate, and that the point was
not now open to the respondent upon the matter in the Court below.
Conclusions
12. The considerations of procedural fairness referred to above suggest that the
Court should not have found it necessary or appropriate to reach any conclusion
adverse to the appellant on the basis of the sufficiency of its Notice.
13. However, the Court has now heard full argument on the correctness of that
conclusion. The authorities now cited strongly indicated that the approach taken
to the construction of the Notice was erroneous. The Court should therefore
review its conclusions in the light of those authorities and in the light of the
opportunity which further consideration of the actual text of the appellant's
Notice has afforded. It would now be open to the Court to recognise that the
Notice, construed according to the principles appearing from the cases, was a
valid Notice which sufficiently complied with the obligation in CL31 to 'specify
the default'."
In the course of my judgment I pointed out that at the time the notice was given
the Works were 80 percent complete. I said:
"Properly understood the notice did not require the Contractor in order to
avoid termination to demolish within ten days so much of the Works as interfered
with the Rights of Carriageway and to redesign them so that they did not so
interfere. It is plain from the language which the Principal used that it did not
intend this by its notice. This is also consistent with what had taken place
between the parties up to that time."
12 UNREPORTED JUDGMENTS
In the course of submissions the appellants say: "(b) The contention that the
'Principal wanted money' appears to derive from inferences (not drawn by the
trial judge) from evidence of a conversation between Mr Slattery and Mr Sundin
(AB76; and reproduced in the Court's judgment at 19-20). However, this
conversation had occurred on 22 June 1990.
(c) By the date of the Notice the situation had materially altered for the worse.
On 10 August 1990 the adjoining owners intimated their intention to cross claim
in the Equity proceedings for an order for the removal of buildings and structures
erected on the right of carriageway (AB78G to K).
(d) In these circumstances it is entirely unfair to assert,in effect, that the
appellant had no bona fide basis for issuing the Notice. It was at very least
entitled to have its contractor take positive steps within the time limited by the
Notice, to set in train the production of a conforming design. Moreover the
Principal would have deferred making such a requirement at its own peril.
10. The first difficulty is occasioned by reason of the fact that the formal
adequacy of the Notice was not in issue in the Court below. Thus:
(a) there was no occasion for evidence being specifically directed to
"surrounding circumstances and accompanying declarations' with the question of
the construction of the Notice actually in mind;
(b) Narrative evidence as to the parties' dealings at various times could not be
expected to have been adduced with the specific question of the construction of
the Notice in mind;
(c) There is thus danger in, for example, treating conversations, such as that on
22 June 1990 (relating to 'money') as definitive or exhaustive of the relevant
circumstances existing two months later. This is especially so when the adjoining
owner's claim for money had in the meantime grown from $20,000 (AB76) to
$800,000 (AB77Q); and the adjoining owners had asserted a specific claim
requiring demolition as at 10 August 1990 (AB78G). Moreover, the appellant had
not been able to obtain a hearing date for its proceedings in the Equity Division.
(d) Nevertheless the reasoning in the judgment (at 38.6) assumes that 'the
Notice was issued in the context of the Principals telling the contractor that it
should contribute to a sum to be paid to the owner of the right of carriageway'.
This conclusion appears to find its foundation only in the conversation some two
months earlier.
(e) More significantly is the observation at 21.3 of the judgment; ".... there is
nothing in the discussion or correspondence between the Principal and the
Contractor to suggest that either entertained as a serious prospect that the
development should be redesigned and demolished and rebuilt so as not to
interfere with the rights of carriageway...' The reality is that there was no proper
evidentiary exploration or forensic debate before Giles J on this very question. It
had not been in issue.
(f) Likewise, no occasion arose for any cross examination of Mr Sundin to
suggest to him that he understood the requirements of the Notice as imposing
obligations upon him of the kind contended for. He might reasonably be thought
to have taken the same view of the Notice as that which commended itself to
Giles J at AB738S. This probability is underscored by the content of the
submissions made to Giles J referred to above. Plainly, an acknowledgment by
the respondent's witness that he so understood the Notice, would render otiose
any conjecture as to its meaning or effect. "
URJ WINROBE PTY LTD v SUNDIN'S BUILDING CO PTY LTD [No 2] (Sheller JA) 13
In the respondent's written submissions in reply it was said that the language
of the notice was not ambiguous and that it was unnecessary to refer to
surrounding circumstances to construe it. Further it was said to be not to the point
that the respondent may not have advanced every conceivable argument on the
validity of the notice.
In the well-known passage in the judgment of the majority in the High Court
in Coulton v Holcombe (1986) 162 CLR | at 7-8 their Honours said: "In a case
where, had the issue been raised in the Court below, evidence could have been
given which by any possibility could have prevented the point from succeeding,
this Court has firmly maintained the principle that the point cannot be taken
afterwards: see Suttor v Gundowda Pty Ltd (1950) 81 CLR 418 at 438, Bloemen
v The Commonwealth (1975) 49 ALJR 219."
Later their Honours quoted from the decision of the High Court in University
of Wollongong v Metwally (No 2) (1985) 59 ALJR 481 at 483:
"Tt is elementary that a party is bound by the conduct of his case. Except in the
most exceptional circumstances, it would be contrary to all principle to allow a
party, after a case had been decided against him, to raise a new argument which,
whether deliberately or by inadvertence, he failed to put during the hearing when
he had an opportunity to do so."
Ihave come to the conclusion that if, during the course of argument before us,
the appellants had taken the point, based on Suttor v Gundowda Pty Ltd and
Coulton v Holcombe, we would have considered ourselves bound to proceed on
the basis that the notice given under CL31 was effective to lay the ground for the
determination by the appellants of the contract, if the ground for giving it was
otherwise made out. The appellants have not particularised evidence that they
would or might have called had it been plain to them that the issue was before
Giles J a live one. I am, however, satisfied that if, before Giles J, the point had
been taken that the notice was defective in not sufficiently specifying the default
or what was required to remedy it, the appellants may well have wished to cross
examine or lead evidence of surrounding circumstances at the time the notice was
given to assist in the interpretation of it on the basis that its language was
ambiguous or susceptible of more than one meaning; compare Codelfa
Constructions Pty Ltd v State Rail Authority of New South Wales (1982) 149
CLR 352. In my judgment I referred to the fact that it was consistent with what
had taken place between the parties up to the time of the notice to say that the
Principal did not intend by its notice to require the Contractor to redesign and
reconstruct the Works. The point not having been taken by the respondent I do
not think the appellants should suffer from their inability to call further evidence
as to the surrounding circumstances. Such evidence may well have prevented the
point from succeeding. As I have said, in my opinion, if these matters had been
addressed to us during the hearing of the appeal, we would not have allowed the
respondent to rely upon the point.
The question is what should now be done about it. I accept that the issue was
not raised before Giles J. I think in fairness the most that the respondent can say
is that the point was not conceded. The respondent did not seek by notice of
contention or otherwise, initially, to raise the point on the appeal. In oral
argument it was embraced by the respondent but not in the forefront of its
argument. Such being the case, in my opinion, the matter having been brought to
our attention, and this application having been made, we should review the
14 UNREPORTED JUDGMENTS
judgment and, having done so, vary it and the orders proposed to take account of
the way in which the notice was treated by the parties at the hearing before Giles
J.
I think the costs on the appeal must be reconsidered in light of the appellants'
5 failure during argument to bring these matters to our attention.
I propose the following orders:
1. Motion for review of reasons for judgment and earlier proposed orders,
allowed;
2. Reasons for judgment published by the Court on 30 June 1992, and orders
10 proposed therein, withdrawn;
3. Costs reserved; and
4. Judgment in the appeal reserved.
Cripps JA I agree with the reasons of Sheller JA and the orders he proposes.
15 1. Motion for review of reasons for judgment and earlier proposed orders,
allowed;
2. Reasons for judgment published by the Court on 30 June 1992, and
orders proposed therein withdrawn;
20 3. Costs reserved; and
4. Judgment in the appeal reserved.
Counsel for the Claimant: B Coles QC/JT Svehla
Instructed by: Church and Grace
Counsel for the Opponent: P Donohoe QC/S Deane-Johns
Instructed by: Carroll and O'Dea
Related laws
No related documents linked yet.
You've got 21 of 22 free Acts left this visit. Sign up anytime for Facts, Related, and study briefs too.