FRIEND AND BROOKER PTY LTD v COUNCIL OF THE SHIRE OF EUROBODALLA [1993] NSWCA 103
NSW Caselaw
Full text
Select any passage to save a personal note with optional tags.
FRIEND AND BROOKER PTY LTD v COUNCIL OF THE SHIRE OF
EUROBODALLA
SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL
KIRBY P, CLARKE and SHELLER JJA
9 November 1993, 24 November 1993
[1993] NSWCA 103
ARBITRATION — commercial arbitration — duty of arbitrator to find facts
necessary in law to support conclusion.
DAMAGES — contract — multiple causes — causes cooperating and of equal
efficacy — held: Party liable for one liable for all damage caused by both.
CONTRACT — breach — damage — multiple causes — liability for — legal rule —
Simonius Fischer and Co v Holt and Thomson [1979] 2 NSWLR 322 (CA) applied.
ARBITRATION — commercial arbitration — error of law — appeal to Supreme
Court — appeal dismissed by Cole J but leave granted to appeal to Court of Appeal
— claim by building contractor against local authority — arbitrator finds authority
misled contractor concerning works — calculation of consequent damages — alleged
interference in continued trading of contractor — proof of lowered profitability —
proof of additional unprofitable contract — arbitrator finds contractor may have
survived one but not two unprofitable contracts — awards half total loss of profits —
contractor asserts error of law in failing to apply Simonius Vischer and Co v Holt and
Thompson [1979] 2 NSWLR 322 (CA) — held:
(1) If a breach of contract has two causes, both cooperating and of equal efficacy in
causing the loss, a party responsible for the breach is liable to the plaintiff.
Norton Australia Pty Ltd v Streets Ice Cream Pty Ltd (1968) 120 CLR 635
applied;
Alexander and Ors v Cambridge Credit Corporation Ltd and Anor (1987) 9
NSWLR 310 (CA);
(2) The arbitrator failed to find the facts necessary in law to support his conclusion.
Promenade Investments Pty Ltd v State of New South Wales (1992) 26 NSWLR 203
(CA) applied;
(3) Appeal and cross appeal allowed and award remitted to arbitrator with opinion of the
Court of Appeal on questions of law.
DAMAGES - causation - multiple causes - attributability to one party - liability in
contract - held: If a breach of contract has two causes both cooperating and of equal
efficacy in causing loss, a party responsible for the breach is liable to the plaintiff for the
loss.
Simonius Vischer and Co v Holt and Thompson [1979] 2 NSWLR 322 (CA) applied.
CONTRACT - breach - damages - causation - multiple causes - liability for - held: In
a breach of contract with multiple causes, each cooperating and of equal efficacy, a party
responsible for the breach is liable to the plaintiff for the loss.
R W Miller and Co Pty Ltd v Krupp (Australia) Pty Ltd, Supreme Court (NSW),
unreported, 9 June 1992 - Giles J considered.
Kirby P I agree with Clarke JA.
Clarke JA On 15 January 1984 the appellant, Friend and Brooker Pty Ltd
("Friend and Brooker'), and the respondent, the Council of the Shire of
Eurobodalla ("the Shire Council") entered into a schedule of rates contract for the
2 UNREPORTED JUDGMENTS
construction by Friend and Brooker of sewerage reticulation works in North
Narooma for the Shire Council. The work proceeded to practical completion on
27 September 1985 and Friend and Brooker presented its final measurement and
various other claims to the Shire Council in January 1986. A dispute arose when
the claims were rejected by the Shire Council in April 1986. That dispute was
referred to arbitration and after an unfortunate series of events Mr T M
McDougall was appointed arbitrator and he conducted the arbitration. On 19
March 1993 he published his Award in which he found in favour of Friend and
Brooker and awarded it $1,634,964. Following the publication of the award both
sides applied to Cole J for leave to appeal from the award. Cole J refused both
applications and it is apparent from his judgment that each party had sought to
attack the award on a vast array of grounds. In refusing to grant leave to
challenge the Arbitrator's award in respect of claims 50, 51, 52 and 54 his
Honour pointed out that the issue which arose was essentially one of causation
and that on that issue the Tribunal was bound to adopt a common sense approach.
His Honour was of the view that there was not disclosed in the Award any error
of law or strong evidence that the Arbitrator made an error of law.
Friend and Brooker sought, and was granted, leave to appeal to this Court from
Cole J's decision relating to claims 50, 51, 52 and 54. The substantial point upon
which leave was granted was that the Arbitrator's ultimate award of damages on
those claims was vitiated by a legal error, that is, in failing to apply the correct
legal test to the facts as found. Subsequently, the Shire Council sought leave to
cross-appeal against that part of Cole J's judgment which dealt with claims 50,
51, 52 and 54. During argument on that leave application there was discussion of
questions of remoteness of damage and the Court made it plain that if it granted
leave to the Shire Council to cross-appeal it would restrict argument to the legal
consequences of the Arbitrator's findings of fact on the relevant claims and would
not entertain argument on remoteness issues. Upon that basis leave was granted
to the Shire Council to cross-appeal.
The argument on the appeal has focused on one paragraph, F6.24, of the Award
but it is necessary to set that paragraph in context. In the Award the Arbitrator
referred to the claim made by Friend and Brooker that:
"ESC (Shire Council) supplied information on subsurface conditions which
was misleading in the sense that rock was actually at considerably greater depth
than was indicated. The immediate effect was that F and B (Friend and Brooker)
did not recover money at the rate it expected for the work performed and incurred
greater costs in OTR excavation than the information indicated... "
The recital of the claim then dealt with a number of other alleged breaches of
duty on the part of the Shire Council and then proceeded:
"The immediate consequence of these matters, through the reduction in
income combined with the increasing of costs, was that the job was short of
money and productivity suffered, increasing costs still further. The other and
longer term consequences were that the credit of F and B suffered, increasing
costs both through higher prices imposed on it for goods and services and
through legal costs of creditor action, and that F and B lost the capacity to
continue trading."
The Arbitrator then considered the claims of breach of duty and found "that the
information supplied as to OTR and rock quantities was negligently obtained and
presented, in addition, to being intended to be relied on, and was misleading". He
then found that on the probabilities Friend and Brooker was required to perform
an excessive amount of restoration and/or suffered excessive deductions from
UARJEND AND BROOKER PTY LTD v COUNCIL OF THE SHIRE OF EUROBODALL&
(Clarke JA)
progress payments for allegedly incompetent restoration. Consequently he
concluded that Friend and Brooker had established its claim for damages.
The major relevant damages claim was 54 which was described as a claim for
loss of trading. What Friend and Brooker asserted in this respect was that the
breaches had caused it to incur additional costs and, in addition, caused it to
suffer a near complete loss of ability to continue trading in the post-Narooma era
and therefore lose the profits which it could have expected to have been generated
by continued trading.
The evidence which had been put before the Arbitrator demonstrated that in
the year 1986 and in following years Friend and Brooker's trading activities had
markedly diminished. For instance, between 1980 and 1985 the annual return for
work done varied between $1,323,848 and $5,386,277 whereas in 1986 and the
following years the highest figure returned was $694,265 and that was in 1990.
In the earlier years following 1986 the returns were much lower. The case made
by Friend v Brooker was that the significant reduction in its trading activities
resulted from the Shire Council's breaches of duty in the Narooma contract and
it claimed a loss of profits in respect of that reduction.
For its part the Shire Council contended that Friend and Brooker had underbid
on the Narooma contract, was inexperienced in the type of work, provided
insufficient detailed supervision of the performance of it and had insufficient
resources of capital to carry out the contract. The Arbitrator substantially rejected
each of those claims and then turned his attention to the relationship between the
Shire Council's breaches of duty and the reduced trading performance of Friend
and Brooker. The exercise that he then undertook required that he direct his
attention to a number of other contracts involving Friend and Brooker which it
was said brought about the reduction in trading quite independently of its
involvement in the Narooma contract. The Arbitrator rejected those claims except
in respect of one contract which was described in the Award as the Bridge Street
project. This was a project in which a company called Ilenace Pty Ltd, which was
owned by the principals of Friend and Brooker, entered into a contract with that
company for the construction of a series of town houses at Neutral Bay which it
was intended would be sold by Ilenace Pty Ltd at a profit. The Arbitrator found
that the project was an overall disaster and undoubtedly cost Friend and Brooker
a lot of money.
In the paragraph which is critical to the issues in this case the Arbitrator
expressed his ultimate conclusion on the reasons for the reduction in Friend and
Brooker's trading in the years between 1986 and 1990. He said: "F and B (Friend
and Brooker) attributes this solely to the losses which were incurred on the
Narooma project and which are the subject of this arbitration. Mr Commisso,
however, has concluded (Exhibit 177) that F and B (Friend and Brooker)
appeared not 'to have had the capacity to undertake the Narooma contract or any
other significant contract after the Bridge Street project'. There is considerable
force in the latter. Although I concluded earlier that the losses incurred on the
development costs of this project should not be included in the results of F and
B (Friend and Brooker) from building and contracting operations per se, the
effect of these losses on F and B's (Friend and Brooker's) liquidity situation is a
different matter. My conclusion is that F and B (Friend and Brooker) may have
survived either the Bridge Street project or the Narooma project by itself but not
the two in combination, as far as continuing to trade at the same level is
4 UNREPORTED JUDGMENTS
concerned. I am, therefore, of the view that of the assessed actual loss of profits
of $662,000 an amount of $331,000 should be awarded as being the consequence
of the Narooma situation."
On the hearing of the appeal both parties contended that there was to be found
a clear error of law in this paragraph Mr D Bennett QC, who appeared for Friend
and Brooker, submitted that the finding of fact made by the Arbitrator should, as
a matter of law, have led him to award the while of the assessed actual loss of
profits of $662,000.
In his submission the factual finding could be interpreted in two ways. First
that there were two concurrent causes of the damage, in which case Friend and
Brooker was entitled to the damages flowing from the breaches of duty as one of
those concurrent causes (Simonius Vischer and Co v Holt and Thompson (1979)
2 NSWLR 322, 346D). Secondly, that Friend and Brooker had been rendered
vulnerable by the earlier Bridge Street project and been pushed over the edge, as
it were, by the Narooma contract. In either event, he submitted, the total assessed
actual loss of profits flowed as damages from the breaches.
Mr Bainton QC, who appeared for the Shire Council, submitted that the
findings of fact did not support any award of damages.
It is, in my opinion, settled law in this State that if a plaintiff is able to establish
that the defendant's breaches of contract were a cause of a particular loss then the
plaintiff will be entitled to be compensated in respect of that loss notwithstanding
that there may have been other concurrent causes. This was the view expressed
by Samuels JA (with whom Moffitt P and Reynolds JA concurred on this point)
in Simonius Vischer when he said (at 346):
"T take the correct principle to be that stated in Chitty on Contract, General
Principles, 23rd Ed, at 670, paral448: 'If a breach of contract is one of two
causes, both co-operating and both of equal efficacy in causing loss to the
plaintiff, the party responsible for the breach is liable to the plaintiff for that
loss'.
As Mr Bennett QC pointed out this principle has been acknowledged by
Professor Treitel (The Law of Contract, 8th Ed, [1991] 865), by Halsbury's Law
of Australia (Vol 6 [110-11160]) and was recently applied by Giles J in R W
Miller and Co Pty Ltd v Krupp (Australia) Pty Ltd (9 June 1992, unreported at
182-183 of the judgment). In the last-mentioned case (an appeal was
compromised by the parties) Giles J collected the cases which supported the
proposition expressed by Samuels JA and pointed out that in Alexander v
Cambridge Credit Corporation Ltd [1987] 9 NSWLR 310, McHugh JA said (at
357-8) that the principle approved in Simonius Vischer was in accordance with
the statement of Barwick CJ in Norton Australia Pty Ltd v Streets Ice Cream Pty
Ltd (1968)120 CLR 635 at 643, that it is sufficient that the breach of contract
'causally contributed to the loss... °.
Subject to one matter with which I will deal Mr Bainton accepted that if the
finding of fact expressed in paraF6.24 was to the effect that the Shire Council's
breach of contract was one of two concurrent causes of the loss then the
Arbitrator should have awarded Friend and Brooker the total amount of
$662,000. Mr Bainton QC also, as I understood his argument, accepted Mr
Bennett's alternative argument that if the proper conclusion was that the
Arbitrator had determined that the earlier contract had so weakened Friend and
Brooker that the breaches found in respect of the Narooma Contract caused its
failure to survive the same result followed. His essential argument was, however,
UARJEND AND BROOKER PTY LTD v COUNCIL OF THE SHIRE OF EUROBODALLA
(Clarke JA)
that the findings of fact necessary to support the propositions for which Mr
Bennett QC argued were not to be found in the Award.
Mr Bainton QC also suggested during argument that the decision of the High
Court in March v E and M H Stramare Pty Ltd and Anor (1990-91) 171 CLR 506
may have cast doubt on the correctness of the principle which I have discussed.
Stramare, which involved an action in negligence, determined that the 'but for'
test is not a definitive test of causation. In the headnote (which records accurately
enough for present purposes the basic proposition decided) the following appears
"\.. causation is essentially a question of fact to be answered by reference to
common sense and experience and one into which considerations of policy and
value judgments necessarily enter". The propositions for which Stramare stand
do not seem to me to be in any way in conflict with the principle referred to by
Samuels JA and, as Mr Bainton QC did not develop the point, it is unnecessary
to say any more than that in my opinion there is nothing in Stramare which is
inconsistent with the proposition on which Mr Bennett QC relies.
In support of the cross-appeal Mr Bainton submitted that the findings did not
support any award for loss of profits insofar as they left open the prospect that the
losses were all caused by the Bridge Street project. Unless, he submitted, there
was a finding that the Bridge Street project did not solely bring about the failure
to survive it was not open to award any loss of profits to Friend and Brooker as
a consequence of the breaches in the Narooma contract.
What is apparent from this discussion is that there was little, or no, issue
between the parties on the relevant legal principles but that the parties were
divided on the meaning to be attributed to CLF6.24 in the Award when read in
the context of the whole Award. I should add at this stage that, although some
reliance was placed upon para 6.12 in which the Arbitrator expressed the view
that it was no coincidence that the level of trading of Friend and Brooker had
been greatly reduced post Narooma, that clause has not assisted me to glean the
meaning to be attributed to the words used in para F6.24. My reason for saying
this is that para F6.12 does not do any more, in my view, than convey the
Arbitrator's opinion that the Narooma contract had some impact on the level of
trading previously enjoyed by Friend and Brooker.
It is no simple matter to ascertain precisely what the Arbitrator was intending
to convey in paraF6.24. This is not entirely surprising for he was dealing with an
area of the law which involves complex questions and he was not a trained
lawyer. The major difficulty, however, surrounds the use of the words 'may' and
'survive'. The latter word, which is relevantly defined in the Concise Oxford
Dictionary to mean 'continue to exist', was quite inappropriate in that Friend and
Brooker did not collapse after the Narooma contract. If, indeed, Friend and
Brooker had collapsed then the question confronting the Arbitrator would have
been whether the breaches of the Narooma contract were a cause of that collapse.
However, a single event, that is, a collapse, was not under consideration. Rather
the Arbitrator was considering the causes of a reduction in trading levels and the
reduced trading could, it seems to me, have been caused wholly by one or other,
or both, of the stated projects, or partly by one and partly by the other. The word
'may' also creates difficulty as it is equivocal in the circumstances. It conveys to
me no more than that Friend and Brooker may or may not have survived either
project but could not survive the two in combination. The difficulty is that it
leaves open, as it seems to me, the prospect that Friend and Brooker may have
failed to survive (in the sense used by the Arbitrator) the Bridge Street project.
6 UNREPORTED JUDGMENTS
Mr Bennett QC argued that the meaning conveyed by the critical sentence is
that Friend and Brooker probably would have survived either but not the two in
combination. The difficulty is that the Arbitrator did not use that language and
there is nothing in the rest of the paragraph which suggests that that is what he
meant. Mr Bennett submitted, in the alternative, that at the very least the
Arbitrator was conveying that both events contributed to the failure to survive.
That is an attractive argument if 'survived' is understood as antonymous to a
ceasing to exist. But it is more difficult to read the conclusion in that way when
the Arbitrator was discussing a reduction in trading level. As I earlier pointed out,
that reduction may have flowed wholly from the combined effect of the two
projects or it may have resulted partly from one project and partly from another.
The reference to the two events in combination supports the argument while the
final award of $331,000 is to contrary effect. On the other hand the final award
could be explained as the consequence of the legal error which Mr Bennett QC
attributes to the Arbitrator.
My conclusion is that the critical finding by the Arbitrator is equivocal and
incapable of supporting either the amount awarded or the total loss for which Mr
Bennett QC opts. On the other hand I do not think it can be said that the finding
leads to the consequence that nothing should be awarded. The findings of fact are
simply an inadequate foundation for any conclusion.
In the result there is a manifest error of law - in the sense in which that word
is used in the Commercial Arbitration Act 1984, s38(5) as discussed in
Promenade Investments Pty Ltd v State of New South Wales [1991] 26 NSWLR
203, at 225 - in that the Arbitrator has failed to find the facts necessary in law to
support his conclusion. As a consequence leave to appeal from this part of his
Award ought to have been granted by Cole J and the appeal allowed. This Court,
which has the powers enjoyed by Cole J (Supreme Court Act, s75A(6)) ought
therefore, in my opinion, to grant leave to appeal and to allow the appeal. Insofar
as the error reflects a failure to find the facts necessary to lead to an ultimate
conclusion on the claim for loss of profits it is appropriate for the Court to remit
the Award, together with this opinion, to Mr McDougall for reconsideration
(Commercial Arbitration Act, 1984, s38(3)(b)). The facts necessary to be found
are whether the Narooma contract was:
(a) a cause of the actual loss of profits of $662,000, or
(b) a cause of part of the actual loss of profits of $662,000 and if so what part.
The consequence of a finding in accordance with (a) would be an award of an
amount of $662,000 to the appellant. The consequence of a finding in accordance
with (b) would be an award of an amount representing that part of the actual loss.
A finding that the Narooma contract was not a cause of the actual loss of profits
or any part of the actual loss of profits would be that no amount would be
awarded under this head. Before expressing the orders which should be made I
should add the observation that the decision on claim 54 was vital to a
consideration of claims 50, 51 and 52 and for this reason those claims should also
be remitted for further consideration in the same way.
I would propose the following orders:
(1) Allow the appeal and cross-appeal and set aside so much of the orders of
Cole J which refused leave to appeal to both parties from the Award of the
Arbitrator in respect of claims 50, 51, 52 and 54.
(2) Grant leave to both parties to appeal from the Arbitrator's award in respect
of those claims;
(3) Uphold the appeal and cross-appeal;
WRJEND AND BROOKER PTY LTD v COUNCIL OF THE SHIRE OF EUROBODALLA
(Sheller JA)
(4) Remit those parts of the Award to the Arbitrator for reconsideration in the
light of this Court's opinion on the question of law;
(5) Respondent to pay appellant's costs of the appeal and, if qualified, to have
a certificate under the Suitors Fund Act.
(6) Appellant to pay respondent's costs of the cross-appeal and, if qualified, to
have a certificate under the Suitors Fund Act.
Sheller JA I have had the benefit of reading the judgment of Clarke JA and
agree with it and the orders therein proposed.
ORDERS
1. Allow the appeal and cross-appeal and set aside so much of the orders
of Cole J which refuse leave to appeal to both parties from the Award of
the Arbitrator in respect of claims 50, 51, 52 and 54;
2. Grant leave to both parties to appeal from the Arbitrator's award in
respect of those claims;
3. Uphold the appeal and cross-appeal;
4. Remit those parts of the award to the arbitrator for reconsideration in the
light of this Court's opinion on the question of law;
5. Respondent to pay appellant's costs of the appeal and, if qualified to
have a certificate under the Suitors' Fund Act 1951; and
6. Appellant (cross respondent) to pay respondent's (cross appellant's)
costs of the cross appeal and, if qualified, to have a certificate under the
Suitors' Fund Act 1951.
Counsel for the Appellant/Cross-Respondent: D M J Bennett QC/R Christie
Counsel for the Respondent/Cross-Appellant: J Bainton QC/R A Vincent
Solicitors for the Appellant/Cross-Respondent: Foulsham and Geddes
Solicitors for the Respondent/Cross-Appellant: Dunhill Madden Butler