Select any passage to save a personal note with optional tags.
LUSTED PTY LTD v GG BEACH (NSW) PTY LTD
SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL
GLEESON CJ, MAHONEY AP and MEAGHER JA
15 July 1994, 15 July 1994
[1994] NSWCA 188
FACTS:
The appellant/defendant appealed against a decision of Phelan DCJ against it on
grounds that the wrong company in the respondent/plaintiff's group was sued and that the
amounts claimed under three agreements were not reasonable.
HELD:
(1) At no stage prior to this appeal did the appellant contest the correctness of the
respondent company as the proper plaintiff. In these circumstances his Honour's finding
on the proper plaintiff is correct.
ORDERS: (1) Appeal dismissed with costs.
Gleeson CJ In this matter I will ask Mr Justice Meagher to give the first
judgment.
Meagher JA This matter is an appeal from a verdict by Judge JB Phelan of the
District Court in favour of the respondent, GG Beach (NSW) Pty Ltd against the
defendant, Lusted Pty Ltd. The agreements on which the plaintiff relied were
three agreements which were entered into in or about August 1977.
The plaintiff claimed, in all, the sum of $20,290.52. A statement of claim was
issued on 27 July 1983. His Honour gave two judgments: an interim judgment of
13 March 1991 and a final judgment on 5 December 1991.
There are two grounds of appeal, in effect. One is that the wrong plaintiff was
sued; of the various Beach companies, it ought not be GG Beach (NSW) Pty Ltd,
but simply GG Beach Pty Ltd. The other ground of appeal was that the amounts
claimed were not reasonable.
As far as the first ground is concerned, the history of this is that each of the
three contracts on which the plaintiff relies were building contracts. It is not in
dispute that building contracts were entered into with one of the Beach
companies. It is conceded that the Chief Executive of the Beach group of
companies had intended that the contracts should be entered into by the plaintiff.
It is apparent from the appeal that that intention by Mr Beach was at some
stage communicated to the defendant, the appellant. It is clear that payments
were made by the present appellant to the present respondent, namely, GG Beach
(NSW) Pty Ltd but, it is also clear enough that in between the initial contract and
the final documentation there were a number of documents issued by the Beach
companies which were sloppy and ambivalent and could possibly lead to a result
different from that which the plaintiff intended.
In the circumstances, his Honour heard a preliminary point: the question of
who was the proper plaintiff. In this case he decided in favour of the respondent.
His Honour decided the proper plaintiff was GG Beach (NSW) Pty Ltd.
On the facts which I have recited, his Honour was clearly entitled to do so. He
was not only entitled by virtue of these facts, he was also entitled if one looks at
the conduct of the litigation.
2 UNREPORTED JUDGMENTS
The present appellant verified his defences on 26 March 1988 and those
defences, although over 15 pages long and raising many issues, did not deny that
the present respondent was the correct party to the contract.
The defences raised by the present appellant admitted that the present
respondent was a contracting party to all three contracts. Those defences were
prepared after the Chief Executive Officer of the appellant had one or more
lengthy conferences with his solicitor. Indeed, there were incorporated into his
verified defences the cross-claim whereby the appellant alleged that was the
contract with the present appellant.
That situation was adhered to by the appellant for four and a half years. When
one takes into account the behaviour of the appellant and the facts which I have
recited, it seems to me that the decision of his Honour as to who was the proper
plaintiff is uncontestably correct.
The only other point which seems to arise on the documents on the appeal
relates to the quantum of the plaintiff's conduct. No argument was advanced to
us that that quantum was incorrect. The point taken on Notice of Appeal must
have been abandoned.
In these circumstances, in my view, the appeal should be dismissed with costs.
GLEESON CJ. I agree and add the following brief observations in relation to
the matter of identification of the correct plaintiff. It is perfectly clear that the
Beach group of companies set out in the first half of 1977 to procure the results
that the business of GG Beach Pty Ltd came to an end on 30 June 1977, in the
sense that that business was taken over by the present respondent, which acquired
the whole of its assets and undertakings.
That was the background against which, some weeks afterwards, the first of
the three contracts in question was entered into. It was a contract relating to what
was called in the evidence "The Wyoming Job".
The arrangements that had been made within the Beach group of companies
were such that it would obviously have been the intention of Mr Beach that the
contracting party in relation to the Wyoming job should be the present
respondent, GG Beach (NSW) Pty Ltd. That intention was communicated by Mr
Beach to the Chief Executive of the appellant. The final quote for the job was a
quote in the name of the present respondent company.
The document that issued from the present appellant in response to that quote
named GG Beach Pty Ltd. That was not signed by anybody in the building group,
for reasons that are not entirely clear.
Thereafter, as Meagher JA has pointed out, there was confusing documentation
exchanged between the parties, some of it referring to the respondent and some
of it to GG Beach Pty Ltd. This culminated in an admission in the pleadings that
the contracting party was the present respondent.
In those circumstances, it was well open to his Honour to conclude that the
respondent was the proper plaintiff. As Mr Fennell, for the respondent observed,
once one reaches that conclusion in relation to the Wyoming job, the inference is
almost irresistible that it was the common intention of the parties that the same
party would be the contracting party in relation to the other two jobs.
Mahoney AP I agree with the judgments of the Chief Justice and Mr Justice
Meagher. There is nothing that I wish to add to them.
GLEESON CJ. There has been a cross appeal criticising the exercise of
discretion by the learned trial judge in relation to the decision he made on the
question of interest.
URJ LUSTED PTY LTD v GG BEACH (NSW) PTY LTD (Mahoney AP) 3
No error of fact or principle in the exercise of that discretion has been shown.
It was a discretionary judgment open to his Honour.
The order of the Court is that the appeal is dismissed with costs and the
cross-appeal is dismissed with costs.
Appeal dismissed with costs.
Counsel for the Appellant: J VAN AALST
10 Instructed by: AUBREY BROWN AND PARTNERS
Counsel for the Respondent: A FENNELL
Instructed by: FERRY STEELE WALKER
Related laws
No related documents linked yet.
You've got 21 of 22 free Acts left this visit. Sign up anytime for Facts, Related, and study briefs too.