STATE OF NEW SOUTH WALES v COYA (CONSTRUCTIONS) PTY LTD; COYA (CONSTRUCTIONS) PTY LTD v STATE OF NEW SOUTH WALES [1995] NSWCA 446
NSW Caselaw
Full text
Select any passage to save a personal note with optional tags.
STATE OF NEW SOUTH WALES v COYA (CONSTRUCTIONS) PTY
LTD; COYA (CONSTRUCTIONS) PTY LTD v STATE OF NEW SOUTH
WALES
SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL
KirBY ACJ, PRIESTLEY and POWELL JJA
24-28 October 1994, 4 August 1995
[1995] NSWCA 446
ARBITRATION — commercial arbitration — application for leave to appeal to
Court of Appeal — proper approach to Supreme Court Act 1970, s101(2)(i) —
principle of restraint — held: Applicable to further application for leave to appeal to
Court of Appeal from refusal of single judge — leave refused.
JUDGES AND COURTS — arbitrator — bias — contact with one party — whether
misconduct — approach to application for leave to appeal — held: Open to
interpretation adopted by single judge — leave refused. WORDS AND PHRASES —
"misconduct".
ARBITRATION — commercial arbitration — leave to appeal — proper approach of
Court of Appeal to — contract between the State and agencies and contractor for
construction of large tunnel 10.5 kms long — overrun of costs when contractor
strikes ground containing soft bedding requiring increased supports — claim by
contractor for increased costs of constructing tunnel referred to arbitration
arbitrator enters award in favour of contractor — State applies to Supreme Court
alternatively for (a) leave to appeal and order remitting for further consideration
defences raised in the arbitration proceedings, or (b) an order removing ie arbitrator
for alleged misconduct involving bias — in Commercial Division, Rolfe J refuses
removal of arbitrator, refuses leave on most points, but upholds two points reducing
arbitrator's award accordingly — upon summons for leave to appeal further to the
Court of Appeal pursuant to Supreme Court Act 1970, s101(2)(i)
ARBITRATION — misconduct — alleged contact by arbitrator with one party and
not another — interpretation of conduct — whether the conduct was such as might
cause a reasonable observer to suspect bias on the part of the arbitrator — whether
alternative interpretation available to the primary judge reviewing the complaint —
whether leave to appeal should be granted by the Court of Appeal
COURTS AND JUDGES — arbitrators — bias actual and imputed — misconduct by
arbitrator alleged — contact with one party and not another — whether such
misconduct as to require removal — substantial arbitration — primary Judge (Rolfe
J) refused orders under s42, s43 and s44 of Commercial Arbitration Act 1984
WORDS AND PHRASES — "misconduct".
Held: (Priestley JA; Kirby ACJ: and Powell JA concurring): (1) The Court of Appeal
should approach a summons for leave to appeal from further decisions of a single Judge
of the Supreme Court reviewing an arbitrator's award, bearing in mind as relevant but not
conclusive the strict limitations imposed by the Commercial Arbitration Act 1984 upon
interference by the Court in the conduct of arbitrations. Promenade Investments Pty Ltd
v State of New South Wales (1991) 26 NSWLR 203 (CA); Natoli v Walker, Court of
Appeal (NSW), unreported, 26 May 1994; [1994] NSWJB 42, applied - (2) The foregoing
2 UNREPORTED JUDGMENTS
principle of restraint applied as much to an application for leave to appeal to the Court of
Appeal challenging a conclusion refusing to remove an arbitrator for misconduct as it does
to challenging a substantive provision of an arbitrator's award; (3) In the present case none
of the challenges and counter-challenges of the State or the contractor were sufficient to
attract leave to appeal to the Court of Appeal; and (4) Such leave should be refused.
Held: (1) Having regard to well established principle, no basis was shown for the grant
of leave to appeal to permit elaboration of the applicable principles governing
apprehended or actual bias; (2) A fair reading of the primary judge's reasons did not show
a misapprehension of the applicable principle; (3) The interpretation of events adopted by
the primary judge was open to him; (4) No basis was shown sufficient to attract the grant
of leave, having regard to the constraints imposed upon intervention by courts in
commercial arbitration by the Commercial Arbitration Act 1984; (5) Leave refused.
Held: (Refusing leave to appeal): No error of legal principle or relevant error of fact
shown - finding by the primary judge was such as to require the grant of leave to appeal
against the order refusing to remove the arbitrator for alleged misconduct - leave refused.
Commercial Arbitration Act 1984, s38, s42, s43, and s44.
Supreme Court Act 1970, s101(2)(i).
ORDERS
(1) Summons for leave to appeal by the State of New South Wales dismissed with costs.
(2) Summons for leave to appeal by Coya (Constructions) Pty Ltd dismissed with costs.
Kirby ACJ I agree with Priestley JA.
Priestley JA INTRODUCTION.
On 22 March 1994 Mr Cameron, Arbitrator, published an award that a
Proprietor pay to a Contractor $17,228,141. This followed a hearing which had
taken thirty-eight sitting days and cost the Contractor in the region of $2 m.
The parties to the contract from which the arbitration arose were Coya
(Constructions) Pty Ltd, which I will call either Coya or the Contractor, and the
Minister for Public Works of the State of New South Wales on behalf of her
Majesty, Queen Elizabeth II, whom I will call the Proprietor.
The arbitration appears to have involved matters of some complexity, but from
remarks made by the Arbitrator in his reasons, he seems to have thought that its
hearing took longer than it should have done. Perhaps the amount of money
involved was partly responsible for this.
No doubt it was for the same reason that the Proprietor made application to a
judge of the Supreme Court for leave to appeal in regard to what the Proprietor
asserted were questions of law wrongly decided by the Arbitrator and also sought
to have him removed on various grounds. Rolfe J heard the Proprietor's
application which appears to have been conducted before him with great tenacity.
He, however, refused all relief sought by the Proprietor, except as to two matters
in regard to which he granted leave to appeal and then upheld the Proprietor's
appeal, reducing the amount of the award by about $1.75m.
The Proprietor then came to this court seeking leave to appeal against the
refusal of Rolfe J to grant leave to appeal in respect of all matters where he had
so refused and also seeking leave to appeal against the other orders he had made
refusing the Proprietor's claims for relief.
The applications for leave to this court were pursued with the same tenacity
and attention to minute detail as in the earlier stages of the proceeding.
What has happened to this point in this disputation between the parties
provides a vivid illustration of the difference between what commercial people
and the Commercial Arbitration Act 1984 (the Act) expect of arbitrations and
RATE OF NEW SOUTH WALES v COYA (CONSTRUCTIONS) PTY LTD; COY&
(CONSTRUCTIONS) PTY LTD v STATE OF NEW SOUTH WALES (Priestley JA)
what, only too often, actually happens. Instead of a speedy end to the dispute
what must appear to an outsider as almost unending wrangling between lawyers
is what awaits the parties.
In disputes of some complexity such as this one it is likely that in the nature
of things lawyers will become involved, and the abundant legal learning available
in regard to contractual disputes of the present kind examined and used. This
leads to situations in which it is very difficult for courts to see where to draw the
line between analysis and argument of a reasonable length and their extension
into the unacceptably protracted legal wrangling I have referred to. Any complex
matter may be argued over, in a logical sense, to any length; any factual or legal
analysis may be further refined; and as long as parties pay for further argument,
trained and active minds will provide it.
One thing is clear about this situation; the New South Wales Parliament has
taken note of the excesses that can grow out of commercial arbitration and passed
laws intended to keep it within acceptable bounds. These laws have been directed
in particular at narrowing very sharply the ways in which arbitrator's decisions
can be challenged in the courts.
ARBITRATIONS AND APPEALS UNDER THE ACT.
One object of the Act is to promote the private, prompt and speedy hearing of
contractual disputes which the parties to the contract have agreed should be
decided by arbitration.
To help achieve this object an appeal against an Arbitrator's award is allowed
to the Supreme Court only in restricted circumstances. If all parties to the
arbitration consent an appeal is permitted limited to questions of law arising out
of the award, (s38(2) and s38(4)(a)). In the absence of such consent, if the
Supreme Court grants leave to a party to appeal, then that party may appeal on
any question of law arising out of the award, (s38(2) and s38(4)(b)). S38(5) says
that the Supreme Court shall not grant leave unless the court considers that one
of two sets of two conditions is fulfilled. The first condition is the same in each
of the two sets of conditions: that the determination of the question of law
concerned could substantially affect the rights of one or more parties to the
arbitration agreement. The second condition of the first set of two conditions is
that there is a manifest error of law on the face of the award. The second
condition of the second set of two conditions is that there is strong evidence that
the Arbitrator made an error of law and that the determination of the question
may add or may be likely to add substantially to the certainty of commercial law.
S38(5) took its present form by an amendment to the Act made in 1990. Since
then this court has indicated that the restrictions on appeals on questions of law
arising out of awards of Arbitrators to the Supreme Court must be adhered to:
Promenade Investments Pty Ltd v State of New South Wales (1991) 26 NSWLR
203; Natoli v Walker 26 May 1994, unreported, Kirby P and Mahoney and
Meagher JJA.
Separately from the limited appeal rights, s42 of the Act empowers the court
to entertain an application by a party to an arbitration agreement to set an award
aside if there has been misconduct by an Arbitrator or the Arbitrator or award has
been improperly procured.
Allied with the power given by s42 is a further power given by s44 to the court
to entertain, and in proper cases to grant, an application by a party to an
arbitration agreement for an order removing the Arbitrator on the ground of
misconduct, incompetence or unsuitability.
4 UNREPORTED JUDGMENTS
S43 empowers the court to remit any matter referred to arbitration by an
arbitration agreement together with any directions it thinks proper to the
Arbitrator for reconsideration. $43 is subject to s38(1) which says the court shall
not have jurisdiction to set aside or remit an award on the ground of error of fact
or law on the face of the award.
Applications for leave to appeal under s38(4)(b) are made to a single judge of
the Supreme Court and it is to a single judge that the appeal lies if leave is
granted. From the single judge, an appeal does not lie to this court except by
leave: s101(2)(i) of the Supreme Court Act 1970.
I think it proper to assume that the legislature at the various times it was
dealing with the Act was aware that this court's usual practice in dealing with
leave applications is to do so quite shortly, and on no finally settled rules; the
most usual criteria are the nature of the judgment sought to be appealed from, the
prospects of success, and the requirements of the administration of justice. A very
important matter to a court the increase of whose workload has outstripped that
of its members is that it cannot permit leave applications to be treated in all
respects as if they were appeals; this would both defeat the object of s101(2)
itself, and it would result in the court's workload becoming unmanageable.
It was into this appeals milieu that the proprietor brought its applications for
leave to appeal.
THE PRESENT PROCEEDINGS.
When the hearing of the proceedings before this court began it seemed to the
court it would possibly become expedient to treat the applications for leave as
part of the hearing of any substantive appeals for which leave might be granted,
because that would, in such event, in the end save overall time. One result was
that the case was argued almost as an appeal. In light of the conclusions I have
reached I am not sure this was a good idea. This is a hindsight comment about
something often hard to judge in advance. At all events, because of the
conclusions I have reached and also for reasons indicated in the previous section,
and explained further below, it now seems to me I should keep these reasons
brief. Even so, I must begin by indicating what lies behind the parties' dispute.
In 1987 the parties entered into a schedule of rates contract (the contract)
which was administered for the Proprietor by officers of the Department of Public
Works (PWD). The contract required the contractor to construct a tunnel
approximately 10.5 kilometres long and three metres in diameter through ground
which was expected to be mainly sandstone strata, with lesser amounts of
siltstone and claystone and in regard to which there was no evidence of
significant structural or igneous disturbance. In terms of tunnel support, it was
thought that only nominal support was likely to be required.
What was actually met with in the course of the tunnelling was very different
from what had been expected. Instead of the tunnel being essentially in
competent sandstone, some 65% of its length went through ground containing
siltstone, claystone, soft bedding planes and faults, all requiring some level of
support. In the end 8 kilometres of the total tunnel length was supported by
primary support systems, eventually approved by the contract Superintendent. It
seems that it was the difference between the conditions actually encountered in
the ground through which the tunnel was bored and the conditions expected at the
time of the tender for the contract, which caused the tunnel to cost, in round
terms, something like $17 m more than the approximately $25 m it would have
cost if expectations at the time of making the contract were borne out.
RATE OF NEW SOUTH WALES v COYA (CONSTRUCTIONS) PTY LTD; COYA
(CONSTRUCTIONS) PTY LTD v STATE OF NEW SOUTH WALES (Priestley JA)
Many of the issues in the arbitration related to the question whether the
Proprietor should pay the contractor for the extra cost or whether the contractor
itself was bound to bear it.
Disputes between them went to arbitration, the substantive hearing of which
began on 26 April 1993.
After the Arbitrator made his award the Proprietor went to the Supreme Court
asking for 1. leave to appeal under s38(4) of the Act in regard to a number of
issues, 2. an order under s43 remitting to the Arbitrator for further consideration
defences the Proprietor had raised in the arbitration proceedings and 3. an order
under s42 and s44 that the award be set aside and the Arbitrator removed because
of misconduct on his part involving bias, apprehended or real.
The application for leave came before Rolfe J who refused it in respect of all
but two of the issues the principal sought to raise, refused, except in regard to
some comparatively minor matters, to make an order remitting any matter to the
Arbitrator, and refused to order that the award be set aside or the Arbitrator
removed because of misconduct.
On the two issues in regard to which he granted leave, he upheld the
Proprietor's appeal, so that, as previously mentioned, the amount of the award
was reduced by about $1.75 m.
The Proprietor then applied to this court for leave to appeal against Rolfe J's
judgments and orders in regard to each of the matters on which the Proprietor had
succeeded. Coya sought leave to appeal against the two decisions adverse to it.
THE POINTS SOUGHT TO BE RAISED BY THE PROPRIETOR'S
APPLICATIONS FOR LEAVE TO APPEAL.
The section in the Proprietor's summons for leave to appeal headed "Reasons
why leave should be granted" contained a succinct statement of each point the
Proprietor was seeking to raise. I will deal with the Proprietor's points in the
order in which they were argued, identifying them by their paragraph number in
the Reasons etc section of the Proprietor's summons.
1(b) FAILURE TO TAKE INTO ACCOUNT THE REQUIREMENT OF
SC-20.
The Arbitrator awarded to Coya a sum in excess of $11m on a claim pursuant
to special condition 20 (SC-20) of the contract. SC-20 is set out in full on pages
28 and 29 of Rolfe J's reasons of 4 July 1994. It dealt with latent conditions and
provided that if during the execution of the work under the contract the contractor
encountered unexpected conditions (to put it in that general way for the moment)
he should go through a procedure as a result of which if certain conditions were
fulfilled the Superintendent had to determine whether any variation of the work
under the contract was necessary. If the
Superintendent so determined he had to order a variation under general
condition 40 (GC-40) of the contract. Before the contractor could get the
procedure going under SC-20 which would, if the contractor were successful, end
in a variation under GC-40, the contractor had to have encountered conditions on
the site, using now the exact language of SC-20, "... which he considers:
(a) differ materially from those which would have been ascertainable by the
Contractor if he had done that which by CL12 of the General Conditions of
Contract he is deemed to have done; and
(b) could not reasonably have been anticipated at the date of the Contractor's
Tender by a contractor experienced and competent in carrying out the work of the
type with which the Contract is concerned;"
6 UNREPORTED JUDGMENTS
The Proprietor submitted before Rolfe J that Coya had not fulfilled subpara(b)
and that the Arbitrator in wrongly holding that it had, had made a manifest error
of law on the face of the award. Rolfe J considered the Proprietor's arguments
concerning the meaning of subpara(b) and the Proprietor's submissions that the
way the Arbitrator expressed himself showed that he was not correctly
understanding what was required of the contractor by subpara(b) (submissions
which seem to me to have been highly semantic) and concluded:
"Tn the end, whilst prima facie a question of construction of law, I think that
the matter raised was a question of fact, or so dependent upon the answers to
questions of fact that it cannot give rise to leave to appeal." (at 33 reasons of 4
July 1994)
He continued that if he were wrong in his opinion that the Arbitrator had not
made any mistake in saying that the requirements of SC-20 were met, the mistake
would not be a manifest error on the face of the Award, but at best from the point
of view of the principal's argument, something which would cause
"consideration as to whether the facts found by the Arbitrator, which it was not
in issue he was entitled to find and to rely upon, accommodated the conclusion
to which he came which, in turn, met the contractual requirement."
He then repeated that in any event in his opinion the Arbitrator was clearly
correct.
I agree with Rolfe J in all of his observations.
At this point a question arises whether I should explain my reasons for my
opinion in greater detail. From the point of view both of Coya and the Proprietor,
a large amount of money is at stake and if the Proprietor's argument were correct
the consequences could well be important for both parties.
However, the question I am considering at the moment is not the correctness
of either the Arbitrator's decision or Rolfe J's decision on the point sought to be
raised, whether it be a question of law or fact, which I have very briefly dealt
with. The question, as stated in the Proprietor's summons, is whether Rolfe J
"erred in declining to grant leave to appeal in respect of" what was said to be the
question of law involved in the Arbitrator's decision that Coya had shown before
him that "The (a) and (b) limbs of SC-20 are therefore satisfied". Actually, to be
more accurate, the question I am considering is whether this court should
exercise its discretion to grant leave to appeal under s101 of the Supreme Court
Act against the refusal of Rolfe J to grant leave to appeal under s38(4) of the Act
to argue the point about the correctness of the Arbitrator's decision in question.
It seems to me that the point of requiring a party to an arbitration to obtain
leave under s38(4) within the deliberately rigid confines of s38(5) of the Act, as
well as the point of making an appeal from the order of a single judge under the
Act subject to the leave of this court, would be altogether lost if on an application
for leave such as the present this court should be regarded as being under an
obligation to give reasons as full as if it had been hearing an appeal as of right.
Stated very briefly, what happened in regard to the point now in question is that
the way in which the Arbitrator expressed his finding about subpara(b) did not
precisely echo the language of the sub-paragraph; the Proprietor sought to turn
the verbal differences into evidence of legal misunderstanding by the Arbitrator;
Rolfe J considered the matter carefully and came to the conclusion that the
Arbitrator was not misdirecting himself about the meaning of subpara(b); and for
additional reasons thought the Arbitrator was in any event right in what he did.
RATE OF NEW SOUTH WALES v COYA (CONSTRUCTIONS) PTY LTD; COYRK
(CONSTRUCTIONS) PTY LTD v STATE OF NEW SOUTH WALES (Priestley JA)
I do not think the matters relied on by the principal in regard to the point are
of sufficient importance or weight to warrant the grant of leave; nor do I think that
the amount of money involved in the point should change my reaction to the
point itself. In the circumstances I think nothing more is required than to add to
what I have already said the conclusion that in my opinion the court should not
grant leave to appeal in respect of question 1(b).
1(c) EXTENT OF PHYSICAL CONDITIONS. The opening words of SC-20
were:
"Tf during the execution of the work under the Contract, the Contractor
encounters on the site or its surroundings physical conditions..."
About this the Arbitrator said that "physical conditions" must "refer to extent
of condition as well as type of condition" so that both had to be considered by
the Superintendent in deciding whether he was satisfied that the physical
conditions the subject of Coya's claim were physical conditions of the kind the
special condition was talking about.
It was submitted before Rolfe J that this involved an error of law in that the
concept of extent did not form part of the ordinary meaning of the term physical
conditions but imported an additional concept. Rolfe J did not agree with the
submission, saying that -
"the words 'physical conditions' have the easily understood meaning of the
conditions encountered. For them to 'differ materially', or be such as 'could not
reasonably have been anticipated' imports a consideration of degree."
Rolfe J thought this was an answer to the principal's submission, and so do I.
For similar reasons as those given when dealing with the previous point, I do not
think it is desirable for me to go into any lengthier reasons.
I would not grant leave to appeal to this court against Rolfe J's refusal to grant
leave to the Proprietor to appeal to the Supreme Court under s38(4) of the Act on
this point.
1(d) DELAY AS A VARIATION. This submission by the Proprietor was based
on a statement by the Arbitrator that delays in boring the tunnel caused by the
conditions encountered being so different from those envisaged by the contract
were "a variation in terms of GC-40. 1 which can be valued in terms of
GC-40.2".
SC-20 in substance allowed the contractor, upon encountering physical
conditions considered different materially from those it was entitled to expect
under the contract to set on foot a procedure under which the Superintendent
would "determine whether any variation of the work under the Contract" was
necessary. If the Superintendent made that determination he had thereupon to
order a variation under GC-40. GC-40.2 provided a method by which variations
were to be valued.
The Proprietor's submission was that only the matter specifically mentioned in
GC-40.1(b) and (c) could constitute a variation for the purposes of GC-40. This
submission was said to be reinforced by the fact that the contract was a schedule
of rates contract, although the submission did not depend on that. It was also
submitted that GC-40 was indistinguishable for the purposes of the present
argument from the building contract provisions ruled on by the High Court in
Tuta Products Pty Ltd v Hutcherson (1972) 127 CLR 253, in which Stephen J
said that delay could not be a variation for the purposes of the clause
corresponding to GC40.2.
8 UNREPORTED JUDGMENTS
Rolfe J did not accept this submission. He explained his reasons for doing so
in detail which required him to set out at some lengths portions of the Arbitrator's
reasons and provisions of the contract. When those materials were all considered
together, he concluded the explanation of the Arbitrator's reasoning was different
from that which the short passage upon which the principal fastened might lead
a reader to believe. I agree with Rolfe J's explanation of the Arbitrator's line of
thought and will outline what he said, without reproducing the materials from
which he derived it, since they are readily available in his reasons.
Stated shortly, Rolfe J's view was that the Arbitrator had reasoned that Coya
had encountered "latent conditions" for which SC-20 provided; the
Superintendent's failure to be satisfied to that effect was a breach of the contract
for which the Proprietor was liable in damages; this would support a claim for
extra costs by the contractor under GC-35.4, if appropriate; at the same time, and
alternatively, the Arbitrator thought the same substance could be characterised as
a delay which was a variation in terms of GC-40.1.
I set out here a fuller excerpt than I did earlier from the passage upon which
the Proprietor relies for this point. The Arbitrator said: "I accept that the
requirement for such a large increase in primary support installed, over that
which had been indicated as being necessary in the Geotechnical Reports
provided to the Claimant, and over that, which had been scheduled, caused
significant delays to the execution of the excavation of the tunnel and there is no
element of 'double dipping' in the Claimant's claim for damages for such delays.
I also accept that such delay is a variation in terms of GC-40.1 which can be
valued in terms of GC-40.2."
In addition to the interpretation put upon this by Rolfe J which I have already
mentioned and which seems to me, when all the material is read, to be right,
Rolfe J said that the Arbitrator had accepted that the Superintendent should have
determined there was a latent condition and that he was required to value the
effect of that in terms of GC-40. In saying this, Rolfe J was pointing out one
matter which is partly destructive of the principal's submission, that SC-20
requires, in its concluding words, that when the Superintendent has determined
that the materially different physical conditions encountered require a variation of
the contract work, he shall order a variation under GC-40.
Rolfe J thought that this view of the Arbitrator's course of reasoning was made
quite clear by findings the Arbitrator subsequently made, set out at 37 and 38 of
his reasons. One of these was that the Superintendent had failed to consider
whether SC-20 applied to the changed conditions and failed to value at all the
variations to the work under the contract made necessary by those changed
conditions. The breach was of an implied term that obliged the principal to ensure
that the Superintendent properly considered whether the changed conditions were
covered by SC-20 and then to properly value the variations if his consideration
was in favour of the contractor. The Arbitrator had also accepted that there had
been an oral term of the contract which led to a similar result. However, in this
part of his reasons he did not rely upon that oral term.
Rolfe J put in a nutshell his understanding of what the Arbitrator had done,
saying:
"By referring to delay the Arbitrator has tended to focus attention upon that
aspect, rather than focussing full attention on what I am satisfied he did, namely
find a breach of the obligation imposed on the Principal [by the implied
condition]."
And a little later:
RATE OF NEW SOUTH WALES v COYA (CONSTRUCTIONS) PTY LTD; COYA
(CONSTRUCTIONS) PTY LTD v STATE OF NEW SOUTH WALES (Priestley JA)
"Although the Arbitrator said that delay was a variation in terms of GC-40.1,
which could be valued in terms of GC-40.2, I am not satisfied that this was the
way in which he ultimately determined the amount of damages,... The process the
Arbitrator undertook was to calculate what he described as the 'reduced
efficiency of TBM excavation'.... The proper way to assess the damages flowing
from the breach of contract was by reference to the additional time taken to carry
out the work made necessary by the existence of the latent conditions. The
Arbitrator decided to assess damages based on the number of additional shifts
times shift costs.... In my view his findings as to the number of additional shifts
and the shift costs were determinations on matters of fact.... Once the matter is
viewed in that light I consider the finding is impervious of attack. It is only if one
seeks to say that if the effect of what the Arbitrator was doing was to value
'delay', rather than the consequences of delay that it could be said there is an
error of law... But that, in my opinion, is not what the Arbitrator did."
In my opinion Rolfe J's explanation of what the Arbitrator said, once the whole
of what he said in his reasons relevant to this contention is taken into account, is
persuasive.
This understanding of the Arbitrator's reasoning also disposes of the
Proprietor's argument based on Tuta Products. If GC-40 stood alone, it might be
necessary to give more detailed consideration to that argument, but when the link
between SC-20 and GC-40 is considered and the way in which the Arbitrator's
reasoning truly ran understood, then it seems clear that what was said in Tuta
Products has no bearing on the present case.
There was a further argument which Rolfe J relied on in refusing leave on this
point. The Arbitrator in deciding this point as he did, did not rely upon a breach
of any of the oral terms he found. One of the later submissions in the appeal was
that it was legally incompetent for him to find such oral terms. I do not agree with
that submission for reasons I will later explain. Neither did Rolfe J. On the
Arbitrator's factual findings there would have been breach of two of the oral
terms he found which would have resulted in the additional work being deemed
to be a variation needing to be valued so as to include additional costs (including
delay costs) of carrying it out. Counsel for Coya therefore submitted to Rolfe J
that if the Arbitrator were wrong (which was not conceded) in the method he
actually followed, he would have reached the same conclusion by awarding
damages for breach of the implied oral terms.
Rolfe J thought this argument was correct, and so do I. It is obviously a sound
ground for refusing to allow a point to be argued on appeal, if it seems clear that
if leave were granted and the appeal point succeeded, it would nevertheless later
be held that on the same materials the original answer would be given on a
different and sound basis.
I would not grant leave to the Proprietor to appeal against Rolfe J's decision
on this point.
1(g) PROPRIETOR'S LIABILITY FOR THE SUPERINTENDENT.
This ground principally raised the question whether first the Arbitrator and
next Rolfe J had misunderstood the rule about the relation between, using the
terms used in the present case, the Proprietor and its Superintendent, on which
MacFarlan J acted in Perini Corporation v Commonwealth of Australia (1969) 2
NSWR 530.
The first step in this argument was the contention that despite the Contractor's
assertion that in paraS of its points of claim it was alleging the Proprietor was
under an obligation of the kind discussed by MacFarlan J in Perini, the paragraph
10 UNREPORTED JUDGMENTS
in fact went further and stated the Proprietor's obligation as being to ensure that
the Superintendent came to the right decision. In other words the submission was
that the Contractor never asserted the Perini obligation; a different issue was
pleaded.
I do not agree with this reading of para5. Nor do I think it matters very much.
The Arbitrator's discussion of Perini to my mind makes it clear that he
understood the gist of MacFarlan J's remarks in that case and came to his
conclusions in the light of them, and after the parties had contested the substantial
issue.
The next step in the Proprietor's argument was to assert that a number of
findings made by the Arbitrator, all supporting his conclusion that the Proprietor
was in breach of the Perini type implied condition were not properly raised on the
pleadings. This argument was allied with another argument that the Arbitrator
should not have considered certain material upon which Coya relied in reply.
Rolfe J in dealing with these arguments set out in detail why the course taken
by the Arbitrator was in his opinion permissible. Rolfe J demonstrated, correctly
in my opinion, that there was no material relied upon by the Arbitrator with
which the Proprietor did not have a fair opportunity of dealing and that he came
to his factual conclusions on the basis of material known to the Proprietor, on
arguments known to the Proprietor and in regard to both of which the Proprietor
had a fair opportunity to respond.
Finally it was submitted that there was no evidence to support the Arbitrator's
factual conclusions. A reading of the Arbitrator's reasons and parts of the
transcript seems to me to show that there is nothing in this submission.
What occurred before Rolfe J in regard to this point was typical of a number
of the Proprietor's submissions both before Rolfe J and this court. A meticulous
and legalistic analysis was conducted of the pleadings, there was an attempt to try
and tie all findings of fact and conclusions of law to the exact meaning which the
Proprietor contended the pleadings conveyed, all this being, in some
circumstances, a legitimate approach. But not, in my opinion in the present
circumstances. It is as desirable in arbitration as in litigation that the pleadings
should reflect what the opposing sides are
contending and also the issues actually fought. However, when another
tribunal is looking at what happened in the tribunal of trial, it is neither sensible
nor fair for the form alone of what happened at trial to be looked at and for the
substance to be neglected. In the present instance, it seems to me that the
Arbitrator came to his conclusions on what had actually been fought before him.
To the extent that the fight and the conclusions were not, in the end, accurately
reflected in the pleadings, no prejudice was caused to either party.
Like Rolfe J, I see neither error of law nor unfairness in dealing with fact, in
what the Arbitrator did in regard to this present point.
I would not grant leave to the Proprietor to appeal in respect of this point.
1(e) PAC LINING AS A VARIATION. Pneumatically applied concrete was to
be placed as lining along those parts of the tunnel length driven through weaker
rock. Because the condition of the ground through which the tunnel was driven
was so different from what both the Proprietor and the Contractor were basing
themselves on at the time the contract was made, it became necessary, and the
Superintendent directed, that the PAC be spread over a much greater length of the
tunnel and in a different way from what would have been the case had the ground
conditions been as expected. This caused extra cost which the Contractor claimed
was over and above the extra payment for the increased volume of work paid for
RATE OF NEW SOUTH WALES v COYA (CONSTRUCTIONS) PTY LTD; COYA
(CONSTRUCTIONS) PTY LTD v STATE OF NEW SOUTH WALES (Priestley JA)
by application of schedule rates. The Contractor asserted that the extra work
involved was a variation and claimed the extra cost. A note on one of the
contractual drawings, which the Contractor agreed had contractual force,
referring to the inside lining of the tunnel, said "Extent of PAC lining along
tunnel length and around its perimeter as directed by the Superintendent'. The
Proprietor asserted that this note meant that the contract contemplated the
possibility that the
Superintendent might require any part of the tunnel to be lined as he directed
so that no matter what the extent of his direction was, it could not be a variation.
The Arbitrator said: "I accept that the Superintendent had the power to direct
the extent of the PAC lining but the test of whether such a direction constitutes
a variation depends on the extent and location which could be reasonably
contemplated by the Claimant at the time of entering on the Contract. I accept
that such reasonable contemplation was that the PAC would be largely full circle
lining mostly in the vicinity of the Western portal and as a result that the
Superintendent's directions as to the type and location of PAC lining constituted
a variation to the Contract."
The Proprietor's submission before Rolfe J focussed on the words in the above
opinion, "the test of whether such a direction constitutes a variation depends on
the extent and location which could be reasonably contemplated by the Claimant
at the time of entering on the Contract". It was argued that the contract simply
could not be construed in such a way. The submission does not in my opinion
take into account the full scope of what the Arbitrator was saying in dealing with
this item. The Arbitrator had found that the requirements of both subpara(a) and
subpara(b) of SC-20 had been established by the Contractor, that is that the
Contractor had encountered conditions materially different from those (putting it
shortly) on the basis of which the contract was made, and that the consequential
extra work was to be paid for by reference to the variation provisions. The
"reasonable contemplation" of which the Arbitrator was speaking in the criticised
passage was a reference back to the basis on which the Contractor entered the
contract and of the Contractor's subsequently encountering materially different
conditions.
The actual finding made by the Arbitrator on this item was, "I find that the
contract was varied by the rearrangement of the PAC lining". It seems to me that
in the light of the larger context than that chosen by the Proprietor for criticism
lying behind the Arbitrator's finding, it was one that was open to him and one that
justified Rolfe J in saying that he was not satisfied that the Arbitrator's
construction of the note on the drawing was in error.
It was also submitted for the Proprietor that the Arbitrator had not made any
finding about the relationship between the work to which this item related and the
general variation he had identified under SC-20. Rolfe J thought that the fact was
that the Arbitrator had done so and by what I have said a little earlier, I have
indicated I accepted the same position.
In the circumstances I see no basis for interfering with Rolfe J's decision to
refuse leave in regard to this point.
1(f) TIME FOR RESPONSE TO EXTENSION OF TIME CLAIMS.
This point arose under a claim for damages for breach by the Proprietor of its
alleged obligations to ensure the Superintendent determined claims for extension
of time with reasonable despatch. Extensions of time were governed by GC-35.4.
This sub-clause required the Contractor if wanting to claim an extension of time
to give the Superintendent notice not later than twenty-eight days after the cause
12 UNREPORTED JUDGMENTS
of delay arose upon which the application was based. The sub-clause then
required the Superintendent to determine whether the cause of the delay justified
an extension of time, but did not specify a time within which he was to make the
determination. The Arbitrator held that the Superintendent must do so within a
reasonable time, and that in light of the time requirement imposed on the
Contractor, a reasonable time for the Superintendent would be one month.
For the Proprietor it was contended that although the Arbitrator was right to the
extent of his holding that the Superintendent must make his determination within
a reasonable time, he was wrong in law in fixing that at one month and should
have concluded a time should be fixed by reference to the particular facts
applicable to each application by the Contractor.
In some circumstances there might be some force in this contention, as a
matter of logic, although I am doubtful whether it could be said to amount to a
matter of law. However, in the circumstances where the Arbitrator was making
the particular decision after all the applications for extension of time had been
made, I think the general criticism of the proprietor loses any force it may have
had.
Once again, I see no reason for interfering with Rolfe J's refusal of leave on
the point.
REMISSION. Under this ground the Proprietor asked Rolfe J to remit to the
Arbitrator for reconsideration under s43 of the Act certain claims made by the
Proprietor in the arbitration. What was asked for was remission to the Arbitrator
for reconsideration of time limitation defences which in the Proprietor's
submission had been raised before the Arbitrator and ignored by him. The
defences referred to were based on GC-48 and GC-42.6. The defences were
raised in different combinations to different claims and parts of claims. The
Arbitrator accepted in regard to claim H that the Proprietor could not succeed
because of these defences.
In dealing with the Proprietor's submission that the Arbitrator had simply
ignored the defences in regard to other claims, in which he had found in favour
of the Proprietor, Rolfe J said that were it not for the fact that the Arbitrator made
specific reference to the defences in relation to claim H there might be some force
in the submission. In Rolfe J's view however the references to the defences when
dealing with claim H showed the Arbitrator was aware of them and that the
proper inference from reading the whole of the award was that the Arbitrator was
not satisfied that the defences were applicable to the other claims. Rolfe J did not
think that the non-mention of the defences by the Arbitrator in those
circumstances could be said to be an error of law.
In taking this view, Rolfe J was reading the Arbitrator's reasons very broadly,
almost more broadly that I would be prepared to agree with. If I were to disagree
however it seems the disagreement would be on the interpretation of the
Arbitrator's reasons, not itself a matter of particular importance or one which
would necessarily incline this court to grant leave under s101 of the Supreme
Court Act.
A further consideration seems to me to be quite important in these particular
circumstances. In the course of argument on this point counsel for the Proprietor
were asked whether, in the event the question of the availability of these defences
had to be reconsidered by the Arbitrator, there was any realistic chance of the
Proprietor succeeding on them. There was no clear response to this question, as
RATE OF NEW SOUTH WALES v COYA (CONSTRUCTIONS) PTY LTD; COY&
(CONSTRUCTIONS) PTY LTD v STATE OF NEW SOUTH WALES (Priestley JA)
I understood it, beyond the Proprietor's assertion that it was entitled to have
reasons on the point and that it was an error of law for reasons not to have been
given.
After conclusion of the oral argument, further submissions in writing were
filed by leave. These included a submission by Coya dated 3 November 1994
containing materials which show that Coya had put a wealth of evidentiary
material before the Arbitrator upon which, on a number of grounds, it had been
submitted that the defences could not succeed. The strength of this material is
such that it seems unlikely to me that any good purpose would be served by
making an order under s43.
Putting together what I have said about the complained of lack of reasons by
the Arbitrator and what I have mentioned in the preceding paragraph, my
conclusion is that leave to appeal should not be granted on this point.
1(a) ORAL TERMS. The Arbitrator found that the contract consisted of the
printed standard form contract with typed additions and variations and oral terms
The Arbitrator did not take the oral terms into account in his decision making, but
Ihave earlier said that a factor in refusing leave in regard to ground 1(d) was the
existence of the oral terms, the Arbitrator's finding of which was not, in my view,
an error of law.
In its oral submissions the Proprietor postponed the argument concerning the
claimed error of law involved in the Arbitrator's finding of the oral terms because
the Proprietor wished to link the subject matter of the oral terms with its claim
of bias against the Arbitrator. It was alleged that the finding of the oral terms was
not only perverse but an act of perversity forming part of the pattern of bias
which the Proprietor claimed the Arbitrator had shown against it.
The Proprietor's submission on the legal point was that as a matter of law the
form of the written contract precluded the incorporation of the oral terms
particularly as they differed from and were inconsistent in application with the
written contract.
I do not think this can be right. Before a tribunal can construe the terms of a
contract, it must be decided what the terms of the contract are. There is no doubt
that a contract can consist of terms partly in writing and partly oral. A court
cannot sensibly decide on what the written and oral terms of a contract are by
looking at one of the alleged written terms and concluding, that because one of
the alleged oral terms is inconsistent with it, as a matter of law the contract could
not include the oral term. In a dispute about the terms of a contract, the party that
is able to point to an alleged written term plainly inconsistent with an alleged oral
term will usually have a very considerable advantage in the contest as to what
comprises the totality of the written and oral terms. The decision maker will
frequently be heavily influenced by the existence of the writing and the conflict
between it and the alleged oral term. Such issues are commonly resolved in
favour of the party asserting the written term to the exclusion of the oral one; but
there is no rule of law that says it must be so, and judges sometimes find the other
way. It seems to me that the settlement of such issues is essentially factual. It
certainly involves the decision of questions of fact. To grant leave on such a
question under s38(5) would necessarily be to involve the court in reviewing
questions of fact, an outcome which s38 is designed to prevent. There may of
course be mixed questions of fact and law where the legal element involved is
such that the court will be prepared to grant leave in an otherwise proper case.
I do not think this is such a case.
14 UNREPORTED JUDGMENTS
What I have said seems to me to be much the same as was said by Kirby P in
Natoli v Walker (supra) at 17 of his reasons and Mahoney JA at 4 and 5 of his
reasons.
I would refuse leave to appeal on this ground.
MISCONDUCT.
In his reasons Rolfe J took sixty-nine pages to set out in full and examine in
detail the issues and arguments raised under this heading. They raised serious
matters, but they raised them in an area where the general rules concerning bias
are well known. Although the Proprietor made submissions to this court that
Rolfe J showed a misunderstanding of those well known rules, I do not think that
submission was made out. At one point Rolfe J said that he did not consider that
a reasonable person could come to the view that the Arbitrator would not bring
to bear an impartial and unbiased mind to his determination, and it was submitted
that the use of the word "would" instead of the word "might" in the phrase "the
Arbitrator would not bring" showed a mistaken understanding by Rolfe J of the
test he had to apply. Assuming for the moment in the Proprietor's favour that the
word should have been "might" and not "would" it seems to me to be quite
apparent from Rolfe J's lengthy discussion of the case law and the citation of
many relevant authorities, including the leading cases in the High Court, that he
was well aware of the various ways in which the test has been stated in recent
years and of the substantially common thread that runs through them all. In the
paragraph preceding the one in which the attacked statement occurs, Rolfe J
stated the test in a way that, in my opinion, is not reasonably open to criticism.
The full tenor of his Honour's discussion of questions of bias in light of the
authorities indicates to me that he decided this aspect of the case in accordance
with those authorities.
There would therefore not be, in my opinion, any point in granting leave to
appeal in order to examine or refine any statements by Rolfe J on the legal
question of the proper test to apply in cases of alleged real or apprehended bias.
Here it is necessary to bear in mind that the Proprietor is seeking leave to
appeal, on its bias claims, pursuant to s101 of the Supreme Court Act.
Counsel for the Proprietor relied upon the difference between an application
for leave to a single judge under s38 of the Arbitration Act to appeal against an
arbitrator's award, with the special barriers to appeal which were inserted in s38
in 1990, and an application for leave to appeal under s101 of the Supreme Court
Act from the decision of a single judge to the Court of Appeal. He submitted that
this court should approach an application for leave to appeal against the judgment
and orders of Rolfe J in the proceedings which were before him under the Act,
in the same way as it approached any other application for leave to appeal,
without regard to the barriers to appeal in s38 of the Act.
This submission is not relevant to those of the present applications for leave
which are seeking leave to appeal against refusals by Rolfe J to grant leave to
appeal under s38. In considering those matters the court cannot escape from the
evident purpose and policy of s38, because it is considering amongst other things
whether Rolfe J erred in his exercise of discretion under s38.
The situation is different, certainly in form, in regard to the Proprietor's
applications for leave to appeal against Rolfe J's refusal to make orders under
42, s43 and s44 of the Act. S42 and s44 are not explicitly linked to s38, although
s43 is made subject to s38(1). I therefore do not think it can be said that an
application for leave under s42 or s44 is governed by the policy apparent in s38.
Nevertheless, it is the fact that the court in dealing with an application for leave
RATE OF NEW SOUTH WALES v COYA (CONSTRUCTIONS) PTY LTD; COYA
(CONSTRUCTIONS) PTY LTD v STATE OF NEW SOUTH WALES (Priestley JA)
to appeal against a judge's orders on a s42 or s44 matter is dealing with a case
where an arbitration under the Act either is proceeding or has got to the stage of
an award being made, and that arbitration has been conducted against the
background of the restriction of appeals to a single judge effected by s38. I do not
think this court is bound to ignore the existence of s38 when dealing with an
application for leave under s42 or s44; s38 is part of the legal mosaic in which
arbitrations under the Act are embedded. I thus think it proper for the court to
treat the policy evident in s38 as a relevant but not conclusive factor in
considering applications for leave to appeal in matters involving arbitrations
under the Act.
With that in mind I come to the factual matters complained of by the Proprietor
under the misconduct heading. On the facts concerning these, as found by Rolfe
J, there was no misconduct. Nor do I think it could be said that the facts as he
found them could create any undesirable impressions in the minds of arbitrators
or those who deal with them about the way arbitrators should behave.
The application for leave therefore becomes one, to my mind, in which the
court is being asked to review and reverse findings of fact by a single judge which
involve no error of principle. There may well be cases of sufficient seriousness
for the court to grant such leave. However, I do not think this is one of them.
Further, in my opinion the chances of the Proprietor succeeding in having the
Arbitrator removed and his award set aside are not sufficiently strong to warrant
the court in granting leave in the matter. To succeed, the Proprietor would not
only need to disturb Rolfe J's basic findings of fact but also to overcome the
waiver arguments available to Coya, which seem to me to be powerful. A critical
point in both the general bias argument and the waiver arguments is whether the
Arbitrator on 23 December 1993 gave important information to the legal
representative of Coya which he did not give to the legal representative of the
Proprietor. If the Proprietor's view of what happened on that occasion were
correct, I might be in favour of granting leave. However the version of the facts
relied on by the Proprietor is capable of a far less sinister interpretation than the
Proprietor puts upon it, and it seems to me unlikely that if leave to appeal were
granted, the court on appeal would take a different view from Rolfe J of the
meaning to be ascribed to the evidence.
In these circumstances I do not feel obliged to go any further into the matter
of misconduct in this leave application, in contrast to what would be necessary
if I thought leave should be granted. Having considered all the matters urged by
the Proprietor, this part of the Proprietor's case does not seem to me to be one in
regard to which it is appropriate for the court to grant leave to appeal.
CONCLUSION ON PROPRIETOR'S APPLICATIONS.
In my opinion the Proprietor's applications for leave should be dismissed with
costs.
COYA'S APPLICATIONS FOR LEAVE.
RD FACTOR.
The Proprietor's tender documents stated that the Schedule of Rates had been
prepared on the basis of the Proprietor's design shown on the drawings. These
showed the diameter of the tunnel as the Proprietor designed it. There was
provision in the contract enabling the Contractor to bore the tunnel to a greater
diameter than the Proprietor's design showed. This was to suit the tunneller's
convenience since tunnel boring machines come in different sizes and are no
doubt extremely expensive. At the same time as contracting to permit the
Contractor to construct a tunnel with a larger than design diameter, the contract
16 UNREPORTED JUDGMENTS
also set out to make it clear that extra quantities involved in the Contractor's
taking up the option to bore a larger tunnel would not have to be paid for by the
Proprietor. A clause introducing a method of calculation which became known as
the RD factor provided a mechanism for working out how much actual cost to the
contractor had to be reduced in order to avoid payment by the Proprietor of any
of the extra cost caused by the Contractor's decision to build the larger tunnel.
In the case of pneumatically applied concrete, the Arbitrator as a matter of
interpretation concluded that the RD factor applied only when it was used as a
primary support and not when used for final lining. His interpretation was based
on the way he thought a number of related provisions in the contract should be
read together. The answer to the question whether the RD factor should have
been applied to final PAC lining as well as when PAC was used for primary
support depended on the reading of these provisions. No-one argued otherwise.
Rolfe J was of opinion that a reading of the relevant provisions and the
Arbitrator's reasons showed that he had clearly misconstrued the provisions in
this respect.
I did not understand the Contractor's complaint that Rolfe J was wrong in his
construction of the provisions to be any more than formal. If I am wrong in that,
I agree in any event with Rolfe J. Consistently with what I have been saying
throughout this opinion, I do not think it necessary or expedient to elaborate my
reasons on the construction argument any further.
The Contractor's principal submission in support of this application for leave
was that Rolfe J should not have exercised his discretion to grant leave to appeal
in regard to this matter. First it was submitted that the necessary requirements of
s38(5) had not been made out and second, if they were, in any event, Rolfe J
should have exercised his discretion against granting leave, conformably with the
basic policy of s38.
The amount disallowed by Rolfe J as a result of his decision was $1,002,874.
The error of construction was plain to see in the Arbitrator's reasons. It was not
argued that such an error was not an error of law.
In these circumstances I think the requirements for the granting of leave
imposed by s38 were fulfilled, and it remained only for Rolfe J to exercise
discretion as to whether he would grant leave to appeal. In my opinion he made
no error of principle and displayed no misunderstanding of any relevant factor or
fact in the exercise of his discretion.
In my opinion leave should not be granted to the Contractor on this ground.
TWO ADDITIONAL CREW.
This ground arose from a claim for $743,186 based on the employment of two
additional crew. The Proprietor's liability for the payment in question depended
on a claim for an extension of time having been made before their employment.
The fact was that they were not employed until after the first claim for extension
of time was made so that there could be no causal connection between their being
employed and any breach of contract because of the failure of the Superintendent
to make a determination within the period of one month fixed by the Arbitrator.
Rolfe J seems to me to have been plainly right on this and I do not think that
Coya's brief submissions before this court to the contrary were of any weight.
The main point upon which Coya relied to support this application was that
even if Rolfe J were right, no question of law was involved.
RATE OF NEW SOUTH WALES v COYA (CONSTRUCTIONS) PTY LTD; COYK
(CONSTRUCTIONS) PTY LTD v STATE OF NEW SOUTH WALES (Powell JA)
I think there was. In order to succeed in the particular claim the Contractor had
to establish a number of facts. One of the facts could not be established. There
was therefore no basis in law for the Arbitrator's conclusion. In my opinion this
means his conclusion involved an error of law which was manifest on the face of
the award.
CONCLUSION ON COYA'S APPLICATIONS FOR LEAVE.
In my opinion Coya's application for leave to appeal should be dismissed with
costs.
Powell JA I agree with Priestley JA.
(1) Summons for leave to appeal by the State of New South Wales
dismissed with costs.
(2) Summons for leave to appeal by Coya (Constructions) Pty Ltd
dismissed with costs.
Counsel for the Claimant/Opponent: RV Gyles QC/JM Stowe QC/DD Feller
(State of New South Wales)
Counsel for the Opponent/Claimant: BW Walker SC/G Robinson (Coya
Constructions)
Solicitors for the Claimant/Opponent: Baker and McKenzie (State of New
South Wales)
Solicitors for the Opponent/Claimant: Minter Ellison, Morris Fletcher (Coya
Constructions)