FITZGERALD v BANKSTOWN CITY COUNCIL [1995] NSWCA 149
NSW Caselaw
Full text
Select any passage to save a personal note with optional tags.
FITZGERALD v BANKSTOWN CITY COUNCIL
SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL
CLARKE and POWELL JJA and BADGERY-PARKER AJA
29 October 1995, 6 November 1995
[1995] NSWCA 149
LIMITATION OF ACTIONS — Limitation Act 1969, s60G, s60I — Dedousis v The
Water Board (1994) 181 CLR 171, Colarado v Haden Engineering Pty ltd (NSW
Court of Appeal, unreported 6 November 1995) followed.
LIMITATION OF ACTIONS — Limitation Act 1969, s60G, s60I District Court
judge applied Dedousis vy The Water Board (New South Wales Court of Appeal,
unreported 20 August 1993) — reversed, Dedousis v The Water Board (1994) 181
CLR 171. Colarado vy Haden Engineering Pty Ltd (New South Wales Court of
Appeal, unreported 6 November 1995) followed — application remitted to District
Court for rehearing.
Clarke JA For the reasons given by Badgery-Parker AJA in this case and for
reasons analogous with those I gave in Colorado v Haden Engineering Pty Ltd
and Anor (New South Wales Court of Appeal, 6 November, 1995, unreported) I
agree with the orders proposed by Badgery-Parker AJA.
Powell JA I agree with Badgery-Parker AJA.
Badgery-Parker, AJA This is an application for leave to appeal against the
decision of his Honour Judge Herron, QC, in the District Court, refusing the
claimant's motion for an extension of time within which to sue the opponent for
damages in respect of noise induced hearing loss allegedly due to negligence.
The reasons advanced for the grant of leave are inextricably bound up with the
merits of the appeal, and accordingly the court heard argument upon the merits
without first resolving the question of leave. For reasons which will appear, I
have reached the conclusion that leave to appeal should be granted, that the
appeal should be allowed, and that the matter should be returned to the District
court for re-hearing.
The claimant commenced employment with the opponent upon a date which
is not entirely certain but may have been either 19 October 1974 or 13 October
1975, and was still so employed as at 30 June 1987, on which date the Workers
Compensation Act 1987 commenced. In respect of any damage sustained after
that date, the plaintiff could not succeed at common law without satisfying the
provisions of s1516 and s151H of that Act and it would appear that the matter
proceeded in the District Court on the basis that no claim was made in this action
in respect of damage sustained after that date. Throughout the period of his
employment up to 30 June 1987, the plaintiff claims that he was exposed to such
levels of noise as were capable of causing and probably did cause significant loss
of hearing in both ears.
His statement of claim, in which he claimed damages in respect of that loss,
was not filed until 24 August 1993. That claim was provisionally statute barred
in respect of any hearing loss sustained prior to 24 August 1987 and hence in
relation to any hearing loss which, having regard to the provisions of the Workers
2 UNREPORTED JUDGMENTS
Compensation Act 1987, the plaintiff was in a position to assert. Accordingly,
with his statement of claim, the plaintiff filed a notice of motion seeking an
extension of the relevant limitation period, relying alternatively on the provisions
of s58(2) of the Limitation Act 1969 and on the provisions of subdivision (3) of
Division 3 of Pt3 of that Act. The hearing of that motion before his Honour Judge
Herron, QC proceeded only on the second basis, the first being expressly
abandoned at the hearing.
The matter was heard in the District Court on 15 and 18 February 1984, and
his Honour Judge Herron, QC. delivered judgment on 25 February 1994.
His Honour directed himself in accordance with the decision of this court in
Dedousis v The Water Board (unreported, 20 August 1993), that the claimant was
obliged to show, in terms of s60F of the Limitation Act, that he was "unaware of
the fact, nature, extent or cause of the injury, disease or impairment at the
relevant time".
Under the law as it stood at the time when the District Court judge dealt with
this matter, an claimant could not succeed in an application under subdivision (3),
upon the ground that he was at the relevant time unaware of the "cause" of his
injury, if in fact he knew the physical cause, in this case exposure to loud noise.
The contrary view which, accepting (because of the decisions of this court in
James Hardie and Co Pty Ltd v Wootton (1990) 20 NSWLR 713 and Electricity
Commission of New South Wales v Plumb (1992) 27
NSWLR 364) that an applicant for an extension of time under subdivision (3)
was obliged to satisfy the criteria expressed in s60F, construed that section as
meaning that such an applicant was relevantly unaware of the "cause" if he was
unaware of the connection between the injury and the defendant's acts or
omissions (PD v The Australian Red Cross Society, Badgery-Parker, J,
unreported 26 November 1992) had been rejected by this court in Dedousis
(supra).
The evidence before the District Court judge showed that the claimant was
aware of the physical cause of his hearing loss (exposure to loud noise in the
course of his employment) as early as November 1980 when he had lodged a
report of injury in respect of "industrial deafness" sustained "in the course of
employment". Such being the case, upon the interpretation of the statute
endorsed by this court in Dedousis (supra3, the application necessarily failed.
Furthermore, because the application was presented upon the basis that the law
was as established by the decision of this court in Dedousis, no evidence was
adduced relevant to the issue whether the applicant was unaware of the
connection between his injury and the defendant's omissions.
The decision of this court in Dedousis was reversed by the High Court
Dedousis v Water Board (1994) 181 CLR 171 (judgment delivered on 16
November 1994) not on the basis that s60F should be construed as it had been
construed in PD (supra), but because, in the view of the High Court, s60F of the
Act was:
"\.. no more than an introductory provision that indicates the purpose of
subdivision (3). It provides a summary of the effect of the substantive provisions
of the subdivision. The terms of s60F must be interpreted on that basis."
It followed that the success of an application for extension of the limitation
period pursuant to subdivision (3) was now to be understood to depend upon the
ability of the claimant to satisfy the requirements of (relevantly) s60G and s60I
of the Act. S60G (relevantly) provides that the court may make an order
URJ FITZGERALD v BANKSTOWN CITY COUNCIL (Badgery-Parker, AJA) 3
extending the time if the court decides "that it is just and reasonable to do so".
S60I provides (relevantly) that no order may be made under s60G unless the
court is satisfied that the plaintiff:
"(iii) was unaware of the connection between the personal injury and the
defendant's act or omission, at the expiration of the relevant limitation period or
at a time before that expiration when proceedings might reasonably have been
instituted."
In the circumstances of the present case, the only relevant time is the
expiration of the relevant limitation period, which was either 19 October 1980 or
13 October 1981.
Constrained as he was by the earlier decisions of this court, it was unnecessary
for the District Court judge to consider, and he did not consider, what is now seen
to be the relevant issue, namely, whether the plaintiff had established that at that
date he was unaware of the connection between the personal injury and the
defendant's act or omission: nor, as I have pointed out, was evidence adduced in
respect of that issue. That, as it seems to me, is the answer to the otherwise
persuasive submission advanced by Mr. Hoeben on behalf of the defendant to the
effect that the evidence before the District Court judge was insufficient to enable
the claimant to establish the necessary matter required under s60I(1)(a)(iii). It
may be acknowledged that the evidence was insufficient. The reason that it was
insufficient was that the parties and the court proceeded upon a wrong basis.
The proceedings before the District Court judge entirely miscarried because of
the misapprehension on the part of the court and both parties as to the proper
construction of the Limitation Act. The plaintiff's claim that he was unaware of
the connection between the personal injury and the defendant's act or omission
has never been evaluated. In those circumstances, unless this court were of the
view that it was itself in a position to determine the application (and in my view
this court is not in that position) the proper course would seem to be to grant
leave, allow the appeal, and remit the matter to the District Court. For the reasons
explained by Clarke, JA. in Colarado v Haden Engineering Pty Ltd and Anor
(New South Wales Court of Appeal, unreported 6 November 1995), the principle
of finality does not preclude such an order. The making of such an order would
be inappropriate only if it appeared that the application, if considered by the
District Court on a proper basis, would be bound to fail. It would be bound to fail
unless the claimant could show not only that there was evidence available to him
to support the extension of time application, but also, to the extent necessary in
such an application, that there was evidence to establish the cause of action.
Although, where an application to extend the time is based upon s58, there is an
express requirement that that be shown, there is no requirement expressed in the
provisions of subdivision (3) and in particular s60G.
However, as I pointed out in PD (supra at 6):
"\.. the need (s60G(2) for the court to decide that it is just and reasonable to
extend the limitation period must focus attention on the question whether there
is indeed evidence to establish the plaintiff's cause of action. It would rarely be
possible to say that it was just and reasonable to subject the defendant to litigation
otherwise statute barred if it did not appear that there was evidence available to
the plaintiff to establish his cause of action."
In the present proceedings it is relevant to note the contents of the affidavit of
the claimant sought to be adduced as additional evidence in this court only for the
purpose of showing that there is evidence available to establish the cause of
action. The test is not a demanding one: see Martin v Abbott Australasia Pty Ltd
UNREPORTED JUDGMENTS
(1981) 2 NSWLR 430 at 443 per Hunt, J (as he then was). The content of the
affidavit tendered in this court together with the contents of the report of Mr
David J Keck adduced in the District Court satisfies that test.
In those circumstances it is not futile to return the matter to the District Court.
I propose the following orders:
1.
2.
3.
4.
Grant leave to the claimant to appeal from the order of Herron, DCJ of
25 February 1994;
Allow the appeal;
Set aside the judgment of Herron, CJ of 25 February 1994;
Remit the proceedings to the District Court for determination in
accordance with the law;
Order that the costs of the proceedings before Herron, DCJ. be in the
discretion of the judge who hears the remitted application;
Order the opponents to pay the claimant's costs of the application and
appeal and, if qualified, order that they are to have certificates under the
Suitors Fund Act in respect of those costs.
COUNSEL:
Appellant: B Robinson
Respondent: C Hoeben
SOLICITORS:
Appellant: Maurice May and Co
Respondent: Pieterse and Pieterse