SOLAH BLUE METAL PTY LTD v TECMA PTY LTD [1995] NSWCA 440
NSW Caselaw
Full text
Select any passage to save a personal note with optional tags.
SOLAH BLUE METAL PTY LTD v TECMA PTY LTD
SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL
KIRBY P, MAHONEY and COLE JJA
4 April 1995, 19 April 1995
[1995] NSWCA 440
PRACTICE AND PROCEDURE Commercial Division — adoption of referee's
report — whether misinterpretation of pleadings and particulars — whether failure
to give reasons — held: No failure. Complaint about referee's report without
substance and want of reasons immaterial.
PRACTICE AND PROCEDURE — Commercial Division of Supreme Court —
reference to referee — definition of matters in dispute — whether referee and Judge
of Commercial Division (Rogers CJ Comm D) failed to address the issue presented
by party upon pleadings of particulars — whether issue of substance in dispute
overlooked or ignored — whether judge failed to give any or adequate reasons for
adopting the report of the referee in the circumstances — whether failure of the
judge to deal with the issue material in the circumstances — held: (Cole JA; Kirby
P and Mahoney JA concurring): (1) The issue contended was not properly before the
referee on the pleadings and particulars so that the referee was not obliged to address
evidence in relation to allegations not pleaded before him. Xuereb and Anor v Viola
and Ors (1988) 18 NSWLR 453 (SC) considered; (2) Although the judge did not
address the submissions of the appellant in his reasons, as they were without
substance he was not obliged to do so for the purpose of rejecting them; (3) Appeal
dismissed with costs.
COURTS AND JUDGES — Commercial Division of Supreme Court — adoption of
report of referee — obligation of referee to give reasons — obligation of judge to give
reasons — whether default in such obligation requiring intervention of Court of
Appeal — held: (1) The referee did not fail to give reasons upon the matters pleaded
and particularised before him; (2) Although the judge did not deal with a matter the
subject of submissions, as that matter was without substance, no error was shown
inviting correction by the Court of Appeal.
ORDERS
Appeal dismissed with costs.
Kirby P I agree with Cole JA.
Mahoney JA I agree with the judgment of Cole JA.
Cole JA This is an appeal from a judgment of Rogers CJ Comm D delivered
16 December 1991 in which his Honour adopted the report of the Honourable RG
Reynolds QC. In consequence a verdict was entered for the defendant.
On the appeal one matter only was argued. Briefly stated, it was contended that
the referee wrongly reported to the Court pursuant to Pt72 that the plaintiff, Solah
Blue Metal Pty Ltd ("Solah Blue') had not alleged in the proceedings before the
Court and the referee that the defendant!, Tecma Pty Ltd ('Tecma') which sold
to Solah a head cone crusher, had "some obligation to act as a consultant engineer
to the plaintiff and advise it generally as to the configuration of the plant and the
acquisition of other components to achieve greater efficiency". The referee
reported:
2 UNREPORTED JUDGMENTS
"As I read the summons, this is not alleged and, even if it was, there is no such
promise on the part of the defendant to be spelled out within the particularised
components of the contract, or at all"!
Solah contended that it had so alleged, and that an examination of the
pleadings and particulars would disclose that was so. In the proceedings
considering the adoption of the report, this error had been asserted by Solah but,
whilst such submission was averted to by Rogers CJ Comm D in argument, it was
not addressed in his judgment which adopted the report. In those circumstances
the appellant sought that the matter be remitted to the Commercial Division to
enable a judge to consider whether that aspect of the referee's report disclosed
error, and if it did, for that Court to consider rejection of that portion of the report.
THE PLEADINGS
The summons was filed in the Commercial Division.
Thus the pleadings took the form prescribed by the Rules for that Division.
In Section A of the summons entitled 'Nature of Dispute" there appeared:
"1. An action by a purchaser against a vendor of an item of quarrying
equipment known as SMD-120 900mm Cone Crusher ('the Cone Crusher') and
a variety of other components and ancillary equipment (all of which including the
Cone Crusher is hereinafter called 'the equipment") for damages and other relief
for:
(d) Failing to advise or assist the defendant in the installation and
commissioning of the equipment as required by the contract, or failure to so
advise or assist the defendant with due care and skill;"2
In s(B) of the summons headed "Issues Likely to Arise", no issue regarding
obligation on the respondent to act as a consultant engineer to the plaintiff either
generally or as to the configuration of its plant was asserted as arising.
In s(C) of the summons, headed "Contentions", the following was pleaded:
"23. By a contract made between the plaintiff and the defendant, the plaintiff
agreed to buy and the defendant agreed to sell the equipment.
PARTICULARS OF CONTRACT
The contract was partly oral and partly in writing. The written part was
contained in the following documents:
(a) Letter dated 5 November, 1986, from the defendants to the plaintiff.
(b) Letter dated 19 November, 1986, from the defendant to the plaintiff.
(c) Letter dated 16 January 1987 from the plaintiff to the defendant.
(d) Letter dated 6 February, 1987 from the defendant to the plaintiff. The oral
part of the contract arose from:
(e) a conversation between Frank Solah of the plaintiff and Roger Kay of the
defendant in October, 1986, at the defendant's premises at Hoxton Park in which
Roger Kay referring to the Cone Crusher said words to the effect: "It will give
good shape. It will produce 100 cubic metres of good shape per hour of 20mm
or less as a product".
1. Appeal Book, at 1565.
2. Appeal Book, at 27
URJ SOLAH BLUE METAL PTY LTD v TECMA PTY LTD (Cole JA) 3
(f) a conversation between Frank Solah of the plaintiff and Roger Kay of the
defendant on or about the 21st October, 1986, st the plaintifFs quarry site at
Jugiong in which Roger Kay said words to the effect: "To have success here you
will need a third crusher and one of our SMD 120 900mm Cone Crusher would
be well suited for the job."3
In para31 the following was pleaded:
"31. The defendant delivered the equipment to the plaintiff in or about 15th
April, 1987. The defendant failed to provide assistance or advice concerning the
installation and commissioning of the equipment promptly or, if it did, failed to
do so with due care and skill.
PARTICULARS OF PROBLEMS CONCERNING INSTALLATION AND
COMMISSIONING OF THE EQUIPMENT
(a) Due to the unavailability of servants and agents of the defendant, including
two Russian technicians familiar with the equipment, and as a result negligent
advice and assistance (itemised in para31(b), para31(c) and para31(d) below), the
period of installation and commissioning was extended from the expected 2 days
to 6 weeks.
(b) The defendant provided a plan to the plaintiff for the foundation for the
frame on which the equipment was to be mounted. That plan was inaccurate
requiring adjustments to be made to the frame once it had been built by the
defendant.
(c) According to the defendant the distribution hopper located upon the
equipment was incorrectly positioned causing the equipment to overload. The
defendant did not advise the plaintiff to locate the distribution hopper correctly
and failed to identify the problem until late May, 1987.
(d) When the equipment was put into operation after installation and
commissioning, the cone crusher was rotating in the wrong direction. The
defendant failed to advise the plaintiff on the correct method of installation and
operation of the equipment and failed to identify that the equipment was rotating
in the wrong direction until early June, 1987.4
Para36 and para37 of the summons were as follows:
"36. In consideration of the purchase of the Cone crusher by the plaintiff the
defendant, by Mr Kay, undertook the design of the plaintiffs plant [so as] to
incorporate the Cone Crusher. In the presents the defendant undertook to perform
such work with skill and care.
37. In breach of contract the defendant did not exercise care and skill and
failed to include in the design;
(a) a surge bin and feeder before the Cone Crusher with the rate of feed
controlled by the Cone Crusher's power so as to avoid excessive feed to the Cone
Crusher; and
(b) a conveyor to allow excessive recycling load at the Cone Crusher to be
returned to the secondary crusher for crushing.'5
The above contains the totality of the relevant allegations made by the
plaintiff/appellant.
In the amended defence the defendant pleaded;
3. Appeal Book, at 31-32
4. Appeal Book, at 34-35.
5. Appeal Book, at 40.
4 UNREPORTED JUDGMENTS
"6A. That is was a term of the contract between the plaintiff and the defendant,
that installation of the equipment was the responsibility of the plaintiff. It was
however not a term of the contract nor was the defendant lawfully obliged to
provide advice and/or assistance to the plaintiff in relation to the configuration of
the plant.
13. The defendant denies that is was a term of the contract to provide advice
to the plaintiff in relation to:
(a) a surge bin and feeder,
(b) a conveyor to convey any excess recycling load which was required to be
returned to the secondary crusher."6
THE REFEREE'S REPORT
In his report the referee stated:
There is before me a lengthy document entitled "Further Amended
Summons" which is the only legal document setting out the Claims the plaintiff
makes, the legal basis therefor and the particulars thereof. There is no other
formulation of the plaintiff's claim before me.
The following are the causes of action which appear to be relied upon though
imprecisely stated:
E. That it was a term and condition of the contract that the defendant would
advise or assist the plaintiff in the installation of and commissioning of the cone
crusher and the defendant failed to advise and assist;
In formulating these causes of action I have sought as best and as benevolently
as I can to interpret what has been said in the Summons under the heading
"Nature of Dispute" and "Issues Likely to Arise".
There is, in particular, no claim that circumstances were such that there was to
be implied a promise that the cone crusher was of merchantable quality, nor is
there any claim that there was an enforceable promise made collaterally to the
main contract. Further, it is not alleged that the defendant undertook the design
of, or promised to design a plant which incorporated the cone crusher.'7
In dealing with the claim which the referee entitled "Failure to advise and
assist", the referee wrote as follows:
"E. FAILURE TO ADVISE AND ASSIST
In the original quotation of Sth November 1986 it is said:
"We would be pleased to provide assistance relative to installation on the basis
that your staff install; we provide advice and would assist'. The letter of 19th
November, which was designed primarily to clarify the basis of the right to return
the equipment, stated:
"We thank you for your instructions to proceed with supply and assure you of
our willingness to co-operate in the setting up of the new crusher".
The amended quote of 6th February 1987, which was accepted, provided:
"INSTALLATION
Installation will be carried out by Solah Blue Metal Pty Ltd and the writer will
be pleased to provide assistance.
EXCLUSIONS
6. Appeal Book, at 64-65.
7. Appeal Book, at 1549-1550.
URJ SOLAH BLUE METAL PTY LTD v TECMA PTY LTD (Cole JA) 5
"Tecma excludes the installation and electrical wiring of the equipment from
its supply and responsibility".
The plaintiff's cause of action in this respect is:
"(d) failing to advise or assist the (plaintiff) in the installation and
commissioning of the equipment as required by the contract or failure to so
advise or assist the defendant with due care and skill".
Iam of the opinion that the operative provision is that contained in the quote
of 6th February and that, if there was imposed on the defendant a legal obligation,
it was that Roger Kay (the writer) would provide assistance in the installation.
The defendant claims, by its defence, that no legal obligation arose.
I am inclined to the view that it was part of the consideration and was an
enforceable promise, but this is of little or no consequence because I am
persuaded that Mr Kay rendered all reasonable assistance in the installation of the
cone crusher, even to the extent of bringing in a highly qualified outside
consultant.
At the hearings, counsel for the plaintiff sought to develop a case that the
defendant had some obligation to act as a consultant engineer to the plaintiff and
advise it generally as to the configuration of its plant and the acquisition of other
components to achieve greater efficiency. As I read the Summons, this is not
alleged and, even if it was, there is no such promise on the part of the defendant
to be spelled out within the particularised components of the contract, or at all."8
APPELLANTS SUBMISSIONS
The appellant's contention was that para36 of the Summons when read with
the particulars associated with para23 constituted an allegation by the appellant
that the respondent had contractually undertaken "the design of the plaintiff's
plant (so as) to incorporate the Cone Crusher". The appellant did not plead that
as a collateral warranty or contract. The terms establishing that contractual
obligation were said to be found in particulars (a) to (f) attached to para23. Mr
Heydon QC for the appellant conceded that particulars (e) and (f) did not
particularise conversations which could support the contractual allegation alleged
in para36. His contention was that material which might support that contractual
allegation was to be found in other aspects of conversations which occurred
between Mr Solah and Mr Kay in October 1986. However those other aspects
were not referred to in subpara(e) or subpara(f) of the particulars and thus were
not pleaded. Thus any contractual obligation was left to be found in the letters
referred to in subpara(a) to subpara(d) of the particulars.
The referee found that the contractual arrangements between the parties were
contained in the amended quote of 6 February 1987 which was accepted. The
only obligation under that quotation was:
"INSTALLATION
Installation will be carried out by Solah Blue Metal Pty Ltd and the writer (Mr
Kay) will be pleased to provide assistance."
That clearly does not support an allegation contained in para36 that the
respondent "undertook the design of the plaintiff's plant (so as) to incorporate the
Cone Crusher".
It follows, in my view, that the referee was correct in asserting that the
summons did not plead that the defendant had "some obligation to act as a
consultant engineer to the plaintiff and advise it generally as to the configuration
of its plant and the acquisition of other components to achieve grater efficiency".
8. Appeal Book, at 1564-1565.
6 UNREPORTED JUDGMENTS
The referee was also correct that such a claim was not particularised. He was also
correct in finding that the documents held to constitute the contract between the
parties did not contain any such promise.
A subsidiary argument was mounted. It was that in using the expression "or at
all" as the concluding words of the referee's finding I have quoted, the referee
was intending to address all of the evidence touching upon the allegations of
breach of an alleged obligation of design which was placed before him. By using
those concise words it was argued that the referee had breached the obligation to
provide reasons for his decision?.
That submission should be rejected. Whatever may have been intended by use
of the expression "or at all", the referee was not obliged to address evidence in
relation to allegations not properly before him.
It follows that the complaint made to Rogers CJ Comm D on his consideration
of whether the report should be adopted that the referee had wrongly understood
the pleadings and the contract was without substance. It is true that Rogers CJ
Comm D did not address those submissions. However, as they were without
substance he was not obliged to do so simply for the purpose of rejecting them.
The appeal should be dismissed with costs.
Appeal dismissed with costs.
COUNSEL:
Appellant: JD Heydon QC / JM Jackman
Respondent: FS McAlary QC/JS Drummond
SOLICITORS:
Appellant: Tress Cocks and Maddox
Respondent: Doherty and Partners
9. Xureb and Anor v Viola and Ors (1988) 18 NSWLR 453 at 469.
Related laws
No related documents linked yet.
You've got 21 of 22 free Acts left this visit. Sign up anytime for Facts, Related, and study briefs too.