IRON GATES PTY LTD v OSHLACK and ANOR [1998] NSWCA 111
NSW Caselaw
Full text
Select any passage to save a personal note with optional tags.
IRON GATES PTY LTD v OSHLACK
SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL
GLEESON CJ, PRIESTLY and BEAZLEY JJA
17 and 18 December 1997, 5 February 1998
[1998] NSWCA 111
ENVIRONMENTAL LAW — _ ENVIRONMENTAL PLANNING AND
ASSESSMENTS ACT 1976, s76 — NATIONAL PARKS AND WILDLIFE ACT 1974
— development, allegedly carried out in breach of conditions of development consent
and in breach of National Parks and Wildlife Act — primary judge's findings as to
extent and severity of breaches challenged — HELD — no successful challenge made
to finding of primary judge.
Gleeson CJ This is an appeal from a decision of the Land and Environment
Court. Some of the issues in the case were decided at first instance by Stein J. The
remaining issues were decided by Pearlman J, the Chief Judge of the Land and
Environment Court. Both Stein J and Pearlman J made orders which are the
subject of the appeal, but it is the reasons for judgment of Stein J, not those of
Pearlman J, which have been the focus of argument.
The appellant is a land developer. In pursuance, or purported pursuance, of a
development consent granted by the second respondent, Richmond River Shire
Council, the appellant carried out development in the form of road construction,
earthworks, and extensive clearing, in connection with a subdivision of an area
of approximately 40 hectares near Evans Head in northern New South Wales.
The development was highly contentious because of the environmentally
sensitive nature of the land. By the time the matter came for hearing before Stein
J, a substantial part of the proposed development had been carried out. The first
respondent alleged, and Stein J found, that the work had been carried out in
contravention of s76(2) of the Environmental Planning and Assessment Act 1979,
and in breach of certain conditions of the development consent. It was further
contended, and held by Stein J, that the appellant had caused damage to the
habitat of threatened species in contravention of s118D of the National Parks and
Wildlife Act 1974.
Stein J granted injunctions restraining the appellant from carrying out further
development pursuant to the consent, and from completing certain roads. He
adjourned for further consideration the question whether there should be
mandatory orders for remediation and reinstatement of the land. It was that issue
which came before Pearlman J. Her Honour made certain orders for remediation
and reinstatement. Insofar as there is a challenge to those orders, the substantial
basis of the challenge is not directed towards Pearlman J's exercise of discretion
but, rather, to the findings of Stein J on which that exercise of discretion was
based. It was argued on behalf of the appellant that, to the extent to which the
appellant was able to make a successful challenge to the findings of Stein J, then
it would have demonstrated that Pearlman J exercised her discretion taking into
account immaterial or inappropriate considerations.
Most of the arguments advanced by way of criticism of judgement of Stein J
were directed towards his findings of fact. That is a significant consideration for
this court. It was also argued that in certain respects Stein J misconstrued the
2 UNREPORTED JUDGMENTS
development consent, but that argument was closely associated with the criticism
of the appreciation which his Honour had made of the facts of the case.
It is also material to note, although there was no dispute about the relevant
legal principles, that decisions such as Mison v Randwick Municipal Council
(1991) 23 NSWLR 734 and Ziade v Woollahra Municipal Coucil (Court of
Appeal, unreported, 28 April 1994) formed part of the legal context in which the
issues in the case were litigated. It is unnecessary to expand upon those
authorities, but an appreciation of what they decided is necessary for a complete
understanding of the dispute, and the way in which it was resolved in the Land
and Environment Court.
The development consent
The development application related to land at Iron Gates known as portions
276 and 277. It contemplated 110 residential lots. It was expected that there
would be later development of adjoining land, but that is not presently material.
As was noted, the proposed development was controversial, and had given rise
to litigation. (See Oshlock v Richmond River Shire Council (1993) 82 LGERA
222). Part of the environmental sensitivity arose out of the presence on the land
of littoral rainforest, and extensive vegetation. Additionally, the land was said to
be a habitat of endangered fauna.
The application for development consent was accompanied by a number of
reports and proposals produced on behalf of the developer, and subsequently
annexed to the development consent, which went into considerable detail as to
the steps to be taken to protect the environment and endangered fauna. The
following are some examples which are of particular relevance to the issues in
this appeal.
Cl3.6 of a report of Walker and Newton Pty Ltd was headed "Subdivision
Design Principals" (sic). It said:
"The principal aim, of the proposal is to maximise the retention of the timbered
areas and the natural environmental character of the site. A principal feature is the
high proportion, of the total site set aside as interconnected vegetation corridors.
These will comprise timbered road reserves, open space areas, environmental
protection areas, and vegetation 'easements' extending into and through timbered
allotments, all being linked to the major vegetated corridor running parallel to the
shores of the Evans River. This interconnection of timbered areas is crucial as a
means of providing useful corridors for fauna moving through the Iron Gates
property as a whole, while maintaining the amenity of the area.
Residential housing will be developed on lots having an area of greater than
800 m2 and will be combined with "green easements', which will ensure the
retention of the tree cover which could be at risk if smaller lot sizes were to be
created.
The use of controls on tree protection within, the subdivision, will have a
number of significant benefits:
* the retention of substantial numbers of trees will provide habitat for fauna.
« the retention of significant vegetation on the site will minimise soil erosion
and sediment flow potential.
Roads will, wherever possible, be designed with minimal cut and fill to reduce
the incidence of site disturbance, both to the physical characteristics and the
existing water table characteristics."
URJ IRON GATES PTY LTD v OSHLACK (Gleeson CJ) 3
Cl3.5 of the same report was headed "Bushfires". It said:
"Considering the prevailing threat of bushfires to the proposed community at
iron Gates, consideration has been given in the development to the measures of
hazard reduction contained in the Plan of Management prepared by Outline
Planning Consultants.
Perimeter access reserved have been provided in areas where the proposed
development abuts natural bushland. These access ways will have a cleared width
of 6m, with a minimum formed width of 4m.
All subdivision, roads are of a sufficient width to allow the passage of fire
control vehicles."
The report of Outline Planning Consultants dealing with perimeter reserves
said:
"Where the subdivision abuts timbered land in a bushfire prone area, perimeter
roads should be located immediately behind the allotments in the bushland with
a minimum cleared width of 6m and a minimum formed width of 4m Such roads
shall be adequately drained to provide continuous dry weather access for fire
fighting vehicles."
The contemplation that the cleared area of perimeter access reserves was to
include an unsealed road capable of carrying fire vehicles is of importance when
regard is had to what was ultimately constructed.
The report of Outline Planning Consultants also said:
"The overall aim of the derived Plan of Management for the site will be to
integrate residential development with the natural environment at the same time
as retaining the timbered character of the Iron Gates property."
The same report had the following to say about drainage:
"Most drainage problems encountered on the site can be overcome by remedial
engineering measures, in sympathy with surrounding environments. Particular
care will need to be taken to ensure that nutrient-rich silt-sediment laden
stormwaters do not adversely impact on nearby sensitive vegetated areas or
habitats. Improved water quality of storm water discharges would result from
retention of ground cover, implementation of erosion, and sediment control and
stabilisation of natural draining lines."
Emphasis was placed on minimising tile size of roads. The report of Outline
Planning Consultants said:
"Tt is proposed that most residential allotments to be created will be situated in
quiet cul-de-sacs or on loop roads. The roads proposed will be narrow winding
roads deliberately designed to ensure that vehicle speeds are reduced to make
access-ways safe not only for pedestrians but also for wildlife.
Given that one of the greatest threats to koalas and wildlife generally are
vehicles, it is recommended that a number of measures be put in place to reduce
the incidence of road accidents and mortality. These include:
* the use of cul-de-sacs and loop roads, to minimise through traffic within any
subdivision within the Iron Gates property.
* narrow winding road pavements to reduce traffic speed, and hence increase
the chance for motorists to see koalas and wildlife crossing local roads to avoid
collision."
The following conditions attached to the development consent are of particular
significance:
4 UNREPORTED JUDGMENTS
"1 Development of the site shall be carried out generally in, accordance with
the documentation lodged by Walker & Newton (including reports by Outline
Planning Consultants arid Dr Leong Lim), subject to such modifications required
to comply with conditions set out hereafter.
9 All native vegetation is to be retained apart from, that which is required to
be destroyed by constructing work required by this approval or proposed in the
application or within 2m of all proposed boundaries or clearing necessary, for the
establishment of bushfire breaks.
18 Stripping and stockpiling of existing topsoil on site, prior to
commencement of earthworks, and the subsequent re-spreading of this material
so as to provide a minimum thickness of 80mm over the allotments and footpaths
and public reserves, upon completion of the development works.
26 Perimeter access reserves shall be a minimum, width of 15m."
The perimeter access reserves were in three locations, shown on a plan
attached to the development proposal. One was to run along the eastern boundary
of the property. A second was to run roughly in a direction northwest to southeast
adjacent to an environmental buffer zone which was in turn located between
some proposed allotments and littoral rainforest. The third was in the southern
part of the land also between proposed allotments and an environmental buffer
zone adjoining littoral rainforest.
Senior counsel for the appellant emphasised the word "general" in condition 1.
The legal consequence of such a condition was considered by Stein J in his
reasons for judgment. No challenge has been made to the principles enunciated
by his Honour, but there was complaint about the way in which he related those
principles to the facts of the case.
Senior counsel for the appellant also emphasised the reference in condition 26
to the minimum width of perimeter access reserves as 15m. This replaced the
reference to 6m which had been made in the reports. (See cl3.5 in the Walker &
Newton report quoted above). It was rightly pointed out that a necessary
consequence of this increase in the width of perimeter access reserves was either
or both of some decrease in allotment sizes in certain places, or some decrease
in the area of the environmental buffer zone in certain places. This, it was said,
was a matter that was overlooked by Stein J, or given insufficient weight in some
of this findings of fact.
The actual development
The most vivid illustration of the contrast between the development as
proposed and the development as constructed is to be found in an aerial
photograph which was exhibit 1 in the proceedings before Pearlman J.
Substantially everything which the appellant did was done with the knowledge
and approval of either the counsel itself, or of officers of the council. An
argument which was unsuccessfully advanced at first instance, and which was not
pressed on this appeal, was that the approval of the Council of certain
engineering plans had the legal effect of modifying or altering the terms of the
development consent. It was also argued at first instance that the knowledge and
approval of the Council of what was done by the developer was a relevant
URJ IRON GATES PTY LTD v OSHLACK (Gleeson CJ) 5
discretionary consideration to be taken into account in determining the nature of
any relief to be granted against the appellant.
After considering a substantial number of matters of detail to which it will be
necessary to return, Stein J said:
"The cumulative result of the discrepancies of the subdivision development as
contained in the development application and supporting documentation and
expressed in the consent, and as it has been actually undertaken, is that the
development is radically different from the environmental sensitive subdivision,
with 'green easements' and narrow meandering cul-de-sacs utilising natural
drainage, which was approved."
That is a fair general summary of what was disclosed by the evidence.
It is necessary now to turn to the detailed respects in which what was done was
different from what was proposed, in order to consider the challenges made to the
findings of Stein J about those matters.
It should be emphasised that in important respects there was no challenge to
the findings of Stein J. It is only necessary to look at certain photographs,
including the one mentioned above, to see that a number of findings are
unchallengeable. Contrary to what was proposed, there was extensive clearing of
the subject land. Indeed, the timber on substantial portions of it was clear-felled.
What was described in the consent as a "wildlife corridor' is, in fact, an
indistinguishable part of a much larger area of flat sandy unvegetated land. The
proposed wildlife corridor was obliterated. Far from retaining all native
vegetation except to the extent to which its destruction was necessary, the
developer, in substantial areas of the subject land, totally destroyed all vegetation.
Those matters are not in dispute. However, one of the most striking aspects of
the difference between what was proposed and what was done, which is in
dispute, relates to the matter of perimeter access reserves and drains. It is
convenient to deal with that item first.
Perimeter access reserves and drains
By agreement with the Council. the developer constructed what were
described by Stein J as massive earthworks in the form of open stormwater drains
running the length of the first two of the three proposed perimeter access reserves
referred to above. What was described as the eastern drain ran just inside the
eastern boundary of the property. What was described as the western drain ran
along the north eastern boundary of an area of littoral rainforest in the centre of
the site. The eastern drain was 317m long. The western drain was 260m long.
Both drains were 15m wide, and between 2 and 4m deep.
There are numerous respects in which the construction of those drains was
inconsistent with the development consent. It is necessary to mention only two.
The eastern drain occupies substantially the whole of the site of what was
supposed to be the perimeter access reserve. The perimeter access reserve was
supposed to provide an unsealed roadway suitable for use by fire fighting
vehicles. That has completely gone.
The western drain at various points encroaches substantially into what was
supposed to be an environmental buffer zone. At certain points it eliminates the
buffer zone altogether, so that as Stein J observed, there are exposed roots of trees
in the littoral rainforest area.
Giving full recognition to the significance of the word "generally" in condition
1 of the development consent, and allowing for the practical significance of
condition 2G insofar as the width of the perimeter access reserves was increased
6 UNREPORTED JUDGMENTS
from 6m to 15m, nevertheless, the finding by Stein J that the construction of these
drains constituted a gross departure from the development consent and a
substantial breach of the conditions of the consent appears to have been not only
fully justified, but virtually inevitable.
Wildlife corridor buffer zones
In relation to the proposed wildlife corridor referred to in the development
consent and attached documents, Stein J said:
"T accept the evidence that the vast majority of the vegetation - undergrowth,
understorey, midstorey and trees - have been removed. This has destroyed the
integrity of the wildlife corridor required by the consent."
The photograph exhibit 1 shows what his Honour was talking about. The
conclusion is unassailable.
In relation to the environmental buffer zones required by the development
consent, Stein J referred to the impact on those zones of the drains to which
reference has already been made. His Honour said:
"While the placement of the drains within the designated buffer zones may be
advantageous to the development by minimising incursions into the area
available for development, it is at the expense of the buffer zone which was
intended as an important environmental safeguard. This is a clear breach of the
consent, and evidently not an inadvertent one."
It was argued on behalf of the appellant that in some way the finding by Stein
J in relation to the wildlife corridor was affected by what was said to be a failure
to appreciate the clearing involved in a certain powerline easement. There is no
warrant for concluding that Stein J was under any misapprehension in relation to
that matter or that his judgment was affected by it.
In relation to the buffer zone, it was argued that Stein J appeared to have
overlooked the significance of the increase in the width of the perimeter access
reserves from 6m to 15m. I am not persuaded that his Honour overlooked that
matter, and there is no reason to doubt that he took into account when making his
factual judgment.
Road widths
It was represented to be an important aspect of this development proposal that
roads would be kept to a minimum width. The Outline Planning report said that
in the main most streets would be cul-de-sacs of widths varying from 4m to 7m.
Short residential streets would be between 4 and 5m wide, and main collector
street widths would be 7m wide.
Stein J's finding about this matter was as follows:
"Mr McCotter's evidence, which I accept, is that the roads constructed on the
site are 7-1lm wide, rather than the 4-7m which had been indicated in the
application. He also gave evidence that the increased road width substantially
increase the amount of vegetation which was removed. Accordingly, as well as
indicating a breach of the condition implied by the Outline Planning report that
roads would be 4-7m, the increased road widths brought about the further breach
of Condition 9 directly the though the additional clearing which that entailed and
indirectly by the greater cut and fill which was undertaken."
In challenging that finding, the appellant contended that the reliance upon the
evidence of Mr McCotter was misplaced.
It was also contended that Mr McCotter had undertaken his measurements of
road widths, or pavement widths, erroneously, by including kerbs and channels.
URJ IRON GATES PTY LTD v OSHLACK (Gleeson CJ) 7
Additionally, reference was again made to the use of the word "generally" in
Condition | and it was said that any departure from the terms of the consent was
minimal.
These were all matters for factual judgment by Stein J, and error has not been
demonstrated. There was evidence upon which it was well open to his Honour to
come to the conclusions he expressed. His findings of primary fact are supported
by the evidence. It is true that an appreciation of the significance of the difference
between the width of the roads as constructed, and as originally envisaged, is a
matter upon which different views could be held. However, it has not been shown
that the finding of Stein J should be disturbed.
Allotment sizes
The minimum sizes of the allotments was to be 800 m°2;. This was said to be
of significance in relation to the "green" aspect of the subdivision.
Both before this court, and before Stein J, there was detailed evidence about
the ultimate size of individual allotments. It is not necessary to repeat the detail
of the figures. A number, which Stein J was entitled to regard as substantial, were
less than 800 m°2;, by an extent which Stein J was entitled to regard as
significant. It is not possible to account for the reduction in size in all cases by
reference to the increase in the width of what should have been perimeter access
reserves to 15m.
Breach of condition 18
There was ample evidence, including the evidence of Mr Payne and Mr Ardill,
which warranted a conclusion by Stein J that there had been a contravention of
condition 18.
National Parks and Wildlife Act s118D
S118D provides that a person must not, by an act or omission, do anything that
causes damage to any habitat of a threatened species if the person knows that the
land concerned is habitat of that kind. It was not an issue in this appeal that the
evidence showed that the work undertaken by the developer caused, in sonic
places, some damage of the kind referred to in s118D. The issue in the appeal
related to the matter of knowledge, and turned upon the fact that the developer
contended, in evidence before Stein J, that although it knew that some parts of
portions 276 and 277 constituted habitat of the relevant kind. it did not know that
the particular parts which were the subject of damage constituted habitat.
Before this development occurred there was a great deal of controversy,
including litigation, about the consequences for local fauna of what was
proposed. The appellant had engaged the services of an expert in that subject, Dr
Lim, and his report was one of the documents annexed to the development
consent. Stein J had before him evidence of all of the information that was
available to the developer, and he also had the benefit of seeing the principal
executive of the developer questioned on the subject. In the light of that evidence
he was satisfied that the developer possessed knowledge that the whole of
portions 276 and 277 could properly be described as the habitat of threatened
species.
There was ample evidence to support that finding, and no successful challenge
has been made to his Honour's conclusion of fact.
8 UNREPORTED JUDGMENTS
Conclusion
It has not been demonstrated that this court should interfere with any of the
findings of fact, or any aspect of the discretionary judgment, of Stein J.
Consequently, the challenges to the orders made by Stein J and Pearlman J must
5 fail.
The appeal should be dismissed with costs.
Priestley JA I agree with Gleeson CJ.
10 Beazley JA I agree with Gleeson CJ.
Appeal dismissed.
Counsel for the appellant: D Jackson QC
15 Solicitors for the appellant: Deacons Graham & James
Counsel for the respondent: (1) P W Larkin / J E Stuckey-Clarke
(2) P Beazley
20 Solicitors for the respondent: (1) Environmental Defenders Office
(2) Hannigans, Casino
Related laws
No related documents linked yet.
You've got 21 of 22 free Acts left this visit. Sign up anytime for Facts, Related, and study briefs too.