TODBERN PTY LTD v HURSTVILLE CITY COUNCIL [1998] NSWCA 234
NSW Caselaw
Full text
Select any passage to save a personal note with optional tags.
TODBERN PTY LTD v HURSTVILLE CITY COUNCIL
SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL
COLE, BEAZLEY and STEIN JJA
30 April 1998, 30 April 1998
[1998] NSWCA 234
SOURCE of power for a variation of a Development Consent period - interpretation
of statute — s99 Environmental Planning and Assessment Act 1979 (NSW) — s36
Interpretation Act 1987 (NSW)
Cole JA The judgment of Justice Pearlman dated 17 April 1997 recites the
factual circumstances giving rise to the issues in contention, the competing
submissions of the opposing parties concerning the construction of cl(b) of the
Consent and her Honour's reasons for resolving that construction in favour of the
respondents.
Those same contentions had been re-agitated on appeal. For my Part I would
be content to adopt the reasons of Pearlman J as my own. In my view they are
plainly correct. However, we have been informed that at least three matters have
been raised on this appeal which were not raised in the Court below. I must say
it is not entirely clear to me that that is so.
The first matter is the contention that s99(2) is the only source of power for a
variation of the period referred to in s99(1) Environmental Planning and
Assessment Act 1979 after which a Development Consent lapses.
Accordingly, if the power under s99(2) is to be exercised, then it is said that
there must be a clear exercise of the power under s99(2) and to introduce notions
of acting upon" is to introduce a foreign notion or to pollute the source of referred
to in s99(2). I think it is a sufficient answer to that submission to say that any fair
reading of cl(b) indicates that the period of the consent has been varied pursuant
to s99(2) from five years to two years.
The second contention said to be additional to those argued below is that it is
impermissible to relate the expression "unless acted upon within two years" as
used in the Development Consent, with the expression used in s99(4) namely,
"building, engineering or construction work relating to the building subdivision
or work physically commenced".
The reason why it is said the two notions are different is because of the
contention that one could "act upon" the terms of a Consent without engaging in
physical commencement of work of a building, engineering or construction
nature.
In my view the use of the expression "acted upon" in the Consent means the
performance of acts contemplated within the Environmental Planning and
Assessment Act 1979 as being an act of the type which negates the termination
of the consent or cessation of the consent. Those acts are those referred to in
s99(4) the consent, after all, is a consent under the Environmental Planning and
Assessment Act and is to be read against the background of that Act.
The third contention raised was that there was a distinction to be drawn
between s99(1), s99(2) and s99(3) which speaks of a period of time after a given
date, being the date from which the Consent operates, and a period of a
2 UNREPORTED JUDGMENTS
Development Consent which is said to lapse "within two years". The distinction
is said to be equivalent to the distinction of a period of time from a given date
when compared with a period of time after a given date. The difference is said to
be one day. Accordingly, because the consent speaks of "within" which is
equivalent to "after", that is said to be a different period of time from a period
time calculated "from" a date after a specified date.
In my view that contention fails because of the provisions of s36(1) of the
Interpretation Act, or in the particular circumstances of this case, the provisions
of s36(2) as the date upon which the two year period would expire, in this
instance, falls on a Saturday.
For those reasons, in my view, the appeal should be dismissed with costs.
Beazley JA I agree.
Stein JA I also agree.
Appeal dismissed with costs.
Counsel for the appellants: M Enfield QC/ J B Maston
Solicitors for the appellants: Verekers
Counsel for the first respondent: P Riss
Solicitors for the first respondent: Deacon Graham & James
Counsel for the second respondent: D Parry
Solicitors for the second respondent: Abbott Tout