Select any passage to save a personal note with optional tags.
Industrial Court of New South Wales
CITATION: Inspector Bishwa v Refined Sugar Services Pty Ltd & Anor [2006] NSWIRComm 366
PROSECUTOR
Inspector Manujendra Bishwa
PARTIES: FIRST DEFENDANT
Refined Sugar Services Pty Ltd
SECOND DEFENDANT
Sugar Australia Pty Ltd
FILE NUMBER(S): IRC 588 and 589 of 2006
CORAM: Staff J
CATCHWORDS: Occupational health and safety - Prosecutions under s 8(1) and s 10(2) of the Occupational Health & Safety Act 2000 - Explosion caused by combustion of sugar dust at facility for the storage processing and distribution of sugar - No serious injuries - Defendants had comprehensive and impressive systems of safety implemented at the plant although the systems were deficient in some respects - Risks to safety from sugar dust explosion was known and obvious - General and specific deterrence - Availability of simple remedial measures considered - No prior convictions - Whether early plea of guilty considered - Good corporate citizenship - Co-operation - Whether totality principle applies - Subjective factors - Plea of guilty - Penalty imposed - Costs
LEGISLATION CITED: Occupational Health & Safety Act 2000
Occupational Health and Safety Regulation 2001
Capral Aluminium Limited v WorkCover Authority of New South Wales (2000) 49 NSWLR 610
Fisher v Samaras Industries Pty Limited (1996) 82 IR 384
Inspector Green v Big River Timbers Pty Limited; Inspector Green v Big River Timbers (Veneer) Pty Limited [2006] NSWIRComm 279
CASES CITED: Morrison v Coal Operations Australia Ltd (No 2) (2005) 141 IR 465
Morrison v Powercoal Pty Ltd (No 3) (2005) 147 IR 117
R v Gorman (2002) 137 A Crim R 326
R v Thomson; R v Houlton (2000) 49 NSWLR 383
HEARING DATES: 13/11/2006
DATE OF JUDGMENT: 11/24/2006
PROSECUTOR
Mr C O'Donnell of counsel
Solicitor: Mr W Steenson
WorkCover Authority of New South Wales
LEGAL REPRESENTATIVES:
RESPONDENT
Mr R Goot SC
Solicitor: Ms R Sutton
Moray & Agnew
JUDGMENT:
- 1 -
INDUSTRIAL COURT OF NEW SOUTH WALES
CORAM: STAFF J
24 November 2006
Matter No IRC 588 of 2006
INSPECTOR MANUJENDRA BISHWA v REFINED SUGAR SERVICES PTY LTD
Prosecution under s 8(1) of the Occupational Health & Safety Act 2000
Matter No IRC 589 of 2006
INSPECTOR MANUJENDRA BISHWA v SUGAR AUSTRALIA PTY LTD
Prosecution under s 10(2) of the Occupational Health & Safety Act 2000
JUDGMENT
[2006] NSWIRComm 366
1 On 24 April 2004, an explosion caused by friction, which ignited sugar dust within an enclosed bucket elevator, identified as EL02, occurred at the Glebe Island Sugar Terminal, New South Wales ("the site").
2 Refined Sugar Services Pty Ltd ("the first defendant") provided the services of its employees to Sugar Australia Pty Ltd ("the second defendant").
3 The second defendant has control of plant at the site, including the bucket elevator EL02. It has no employees and conducts the manufacture, transport, storage, marketing and distribution of refined sugar and associated products to export markets.
4 The explosion in the bucket elevator EL02, which spread to other items of plant in the building, caused damage to the workhouse building and placed employees of the first defendant who were working outside the workhouse that housed elevator EL02 at risk of injury. Fortunately, no employee was injured as a result of the explosion. Two employees, Carmine Caruccio and John Ryan, were placed at risk of injury.
5 The first defendant was prosecuted under s 8(1) of the Occupational Health & Safety Act 2000 ("the Act") for an alleged failure to ensure the safety of its employees, Carmine Caruccio and John Ryan. The failures alleged in the particulars of the charge were as follows:
(a) At all material times Mackay Sugar Co-Operative Association Limited, E D & F Man Australia Pty Limited and CSR Limited ("collectively referred to as the Joint Venturers") as joint ventures, conducted the business of storing refined sugar and processing it at the premises for distribution.
(b) At all material times Sugar Australia Pty Limited, as the agent of the Joint Venturers, conducted the Joint Venturers' business of storing refined sugar and processing it at the premises for distribution.
(c) At all material times the defendant provided the services of its employees, including Carmine Caruccio and John Ryan, to Sugar Australia Pty Limited for the purpose of Sugar Australia Pty Limited conducting the Joint Venturers' business of storing refined sugar and processing it at the premises for distribution.
(d) The defendant failed to ensure that plant, namely a bucket elevator identified as EL02, provided for use by its employees at the Premises was safe and without risks to health when properly used in that:
i. The defendant failed to ensure that the plant was properly inspected, serviced and maintained to prevent belt drift; and
ii. The defendant failed to ensure that the plant was in good and safe working order.
(e) The defendant also failed to provide its employees with adequate training in the inspection and maintenance of the plant necessary to ensure its employees health and safety at work.
6 The second defendant was charged under s 10(2) of the Act for failing to ensure that the plant it controlled at Lot 1 Somerville Road, Glebe Island, was safe and without risk to health when properly used by persons at a place of work. The particularised failures were as follows:
(a) At all material times Mackay Sugar Co-Operative Association Limited, E D & F Man Australia Pty Limited and CSR Limited ("collectively referred to as the Joint Venturers") as joint venturers, conducted the business of storing refined sugar and processing it at the Premises for distribution.
(b) At all material times the defendant, as the agent of the Joint Venturers, conducted the Joint Venturers' business of storing refined sugar and processing it at the Premises for distribution.
(c) At all material times Refined Sugar Services Pty Limited provided the services of its employees, including Carmine Caruccio and John Ryan, to Sugar Australia Pty Limited for the purpose of Sugar Australia Pty Limited conducting the Joint Venturers' business of storing refined sugar and processing it at the Premises for distribution.
(d) The defendant failed to ensure that plant, namely the bucket elevator identified as EL02, provided for use by people at work at the premises was safe and without risks to health when properly used in that:
i. The defendant failed to ensure that the plant was properly inspected, serviced and maintained to prevent belt drift; and
ii. The defendant failed to ensure that the plant was in good and safe working order.
7 Both defendants pleaded guilty to the charge laid against them.
8 Mr C O'Donnell of counsel, who appeared for the prosecutor, tendered the following evidence in the sentencing proceeding:
(i) agreed statements of facts in respect of each prosecution;
(ii) prior conviction reports for each defendant;
(iii) a factual inspection report by Inspector Stephen Gill dated 30 April 2004;
(iv) 15 coloured photographs;
(v) a process flow document which demonstrated how the operation worked;
(vi) an investigation report into the explosion at the second defendant's premises on 24 April 2004 prepared by Mr D Cockbain & Mr J Burgess, Safety and Forensic Engineering Pty Ltd dated 30 June 2004;
(vii) an investigation report into the explosion at the second defendant's premises prepared by International Safety & Risk Management Group ("ISMA") dated May 2004.
9 As the agreed statements of facts were in similar terms, I propose to only set out the agreed facts provided in respect of the second defendant. Excluding formal parts and the charges, it stated:
…
6. As a result of all or some of the above-mentioned failures, on 24 April 2004, friction resulted in an explosion of sugar dust in elevator EL02 and spread to other items of plant in the workhouse building, located on the premises, causing damage to the workhouse building and placing persons outside the workhouse building who were not in the employment of the defendant, namely Carmine Carruccio and John Ryan, at risk of injury.
The Facts and Circumstances
The Sugar Australia Joint Venture
7. On or about 27 February 1998 Mackay Sugar Co-Operative Association Limited, E D & F Man Australia Pty Limited and CSR Limited ("collectively referred to as the Joint Venturers") entered into an unincorporated joint venture to manufacture, store, market and distribute refined sugar ("the Joint Venture"). On 27 February 1998 the Joint Venturers as principals entered into an Agency Agreement with the defendant as agent. Under the Agency Agreement the Joint Venturers appointed the defendant as their agent to conduct the Joint Venture. Under the terms of the agency agreement, the Joint Venturers retained control of the defendant in its conduct of the Joint Venture.
8. Between 27 February 1998 and August 2004 the Joint Venturers or their related bodies corporate owned beneficially all of the issued capital of the defendant in the following proportions: CSR Limited – 50%; Mackay Sugar Co-Operative Association Limited – 25%; and E D & F Man Australia Pty Limited – 25%. In August 2004 CSR Limited acquired the interest of E D & F Man Australia Pty Limited in the Joint Venture and the defendant.
9. On 27 February 1998 the defendant entered into a Services Agreement with Refined Sugar Services Pty Limited. Under the Services Agreement Refined Sugar Services Pty Limited agreed to provide the services of its employees to the Joint Venture as directed by the defendant.
The Glebe Island Sugar Terminal
10. The assets of the Joint Venture include a facility for the storage, processing and distribution of refined sugar at the Premisesthe Premises. The Premises comprises fourteen large silos owned by the Sydney Ports Corporation located on land owned by that Corporation and leased to the defendant, and related plant and equipment owned or leased by the Joint Venturers. The fourteen silos are part of a larger building comprising thirty silos. The silos are aligned in two rows on an east-west axis. The Joint Venture utilises the fourteen easternmost silos. The remaining sixteen silos in the building are used for the storage and distribution of cement by an unrelated entity.
11. The plant and equipment at the Premises owned or leased by the Joint Venturers includes two bucket elevators located in the workhouse at the eastern end of the silo building. Refined sugar is processed, stored and distributed from the Premises in the following way:
(a) refined sugar is transported by ship to a wharf adjacent to the silo building on the northern side of the building;
(b) the sugar is transported from the ship to the top of the silo building by an enclosed conveyor;
(c) at the top of this conveyor the sugar passes onto a horizontal conveyor, which transports the sugar to the top of the silos;
(d) the sugar is dispersed into the silos through an open valve, with silo selection depending on the available capacity of the individual silos;
(e) the sugar is stored in the silos until required for processing and distribution;
(f) when sugar is required for processing and distribution a valve is opened at the bottom of the selected silo and the sugar passes through the valve onto a horizontal chain conveyor, which carries the sugar to the base of two bucket elevators located in the work house at the eastern end of the silo building;
(g) the enclosed vertical bucket elevators – EL0)1 and EL02 ("elevators") carry the sugar to the top of the workhouse and feed the sugar into grading plant, comprising vibrating scalping screens;
(h) the grading plant sorts unbroken lumps from the sugar and further sorts the sugar into fine-grained castor sugar and standard-grained sugar;
(i) the sugar is then processed for distribution either as liquid sugar, or into regular or bulk packages of standard or castor sugar; and
(j) after processing the sugar is loaded onto trucks for distribution.
12. The two elevators are located side by side in the workhouse on a north-south axis. The northern elevator is identified as bucket elevator EL01, the southern as bucket elevator EL02. Each elevator extends vertically from the basement of the workhouse through the floorings of eight stories within the workhouse to a height of approximately 50 metres. Each elevator carries about 400 stainless steel buckets on an endless flat conveyor belt, which rotates on two pulleys, one at the top or head of the mechanism and the other at the bottom or boot of the mechanism. The belt carries the evenly spaced buckets up and down the elevation between the head and boot of the mechanism through two enclosed "legs" positioned side by side and connecting. The head, boot and legs of the elevators (and the elevator assembly of belt, buckets and pulleys) are enclosed in mild steel ducting.
13. The personnel who operate the Premises for the Joint Venture are employed by Refined Sugar Services Pty Limited, which has provided the services of those employees to the defendant pursuant to the Services Agreement since the date of that agreement - 27 February 1998. The plant and equipment used by the Joint Venturers at the Premises is either owned or leased by the Joint Venturers. On 27 February 1998 the Joint Venturers entered into a Plant and Equipment Licence (New South Wales) in respect of these assets, including the elevators ,elevators, and other assets used by the Joint Venturers at other locations. The terms of the licence included the Joint Venturers' agreement to maintain this plant and equipment in good order and condition.
The Incident
14. On 24 April 2004, at about 4.30pm, two employees of Refined Sugar Services Pty Limited, Carmine Caruccio and John Ryan, were returning sugar from broken reject bags of sugar into a chute in the dry goods store which is located next to, and is separated from, the workhouse by fire doors. The chute is located approximately 1 metre away from the fire doors. The chute flows into the inload conveyor - BC02 and BC03 located inside the workhouse.
15. The task performed by Carruccio and Ryan involved feeding sugar from the broken reject bags into the chute manually so that the sugar was conveyed to the elevators for transportation to liquid sugar bins. Caruccio and Ryan were standing near fire safety doors leading to the workhouse when an explosion occurred inside the workhouse. Caruccio heard a loud bang and observed flame come through the fire door and travel past him. There were two other employees of Refined Sugar Services Pty Limited present on the premises at the time, Tony Tuzarovski and Caesar Sanchez.
16. At the time of the incident Refined Sugar Services Pty Limited employed approximately 23 persons at the Premises.
17. As a result of the explosion in EL02 there was damage to elevatorto elevator EL02, other plant and the workhouse. The damage included: the destruction of doors and windows in the workhouse; the shifting of the separation wall between the workhouse and the silos towards the silos; rupturing and distortion of the ducting around the legs and boot of the southern elevator (bucket elevator EL02); damage to the feeding chain conveyor from the south silo to bucket elevator EL02; damage to vents, filters, the lump breaker, the liquid sugar supply bin, the lump removal screen, the scalped sugar bins and grader comprising some of the plant and equipment in the workhouse; and damage to the compartmentation around the staircase to the highest floor within the workhouse.
18. Two experts from Safety and Forensic Engineering Pty Limited ("SAFE"), David Cockbain and John Burgess inspected the premises after the explosion and reached the following conclusions about its cause:
"Our investigation supports the hypothesis that the belt of Bucket Elevator EL02 became misaligned over time such that the belt materials rubbed against the side plates of the bucket elevator enclosure at the head end. A belt tracking (misalignment) detection system was provided that should have detected the belt misalignment and tripped the bucket elevator motor and triggered an alarm. This system did not operate. This undetected rubbing of the belt against the side plates over an undetermined period of time wore away approximately 5 millimetres of the belt material allowing the stainless steel product carrying buckets to come into contact with the mild steel plates of the conveyor.
The contact between the stainless steel buckets and the mild steel side plates of the bucket elevator casing either created a local elevated temperature due to a frictional effect, or alternatively created a spark due to the stainless steel/mild steel interface which subsequently became an ignition source. This ignition source ignited the sugar dust which was in suspension within the air contained within the bucket elevator. An explosion resulted.
The explosion damaged the bucket elevator. The hot gases and other hot by products of combustion were partially vented by the explosion vents in the elevator, and the remainder exited the bucket elevator at both the head and the boot causing subsequent explosions along the process equipment paths. Damage to several affected plant items ranged from nil to significant…
Infra-red detectors at the head and boot end of the bucket elevator operated in response to the explosion and signalled, via the fire alarm panel, the plant controls system to trip individual items of plant and to essentially shut down the plant.
The bucket elevator was fitted with an array of indoor explosion vents, which were intended to mitigate substantial damage to the bucket elevator. For reasons yet to be identified it appears these vents did not limit damage to the bucket elevator. The damage would have been greater if there was no venting on the elevator or no rotary valves on the inlet and outlet of the elevator. Other explosion venting devices that formed part of the operational plant worked as designed.
A localized fire was ignited on the ground floor of the workroom in the bag collecting dust discharged from the plants dust collectors. Windows were blown out on most floors of the workroom as pressure vented to the atmosphere. No personnel were working in the workroom at the time of the explosion. No injuries to personnel resulted. The four personnel on the premises evacuated safely to the nominated muster point. New South Wales Fire Brigade was summoned."
Maintenance, training and awareness of risk prior to the incident
19. The defendant,defendant had inadequate systems of maintenance in place to prevent an occurrence such as the incident. The defendant, failed to carry out adequate preventative maintenance on the elevator EL02, despite problems with the alignment of the belt in the bucket elevator prior to the incident. Maintenance logbook entries show that there were a number of instances of belt drift and drift sensor faults in the twelve months prior to the incident. The SAFE experts' report suggests that chronic belt drift in bucket elevator EL02 was caused by wear to the lagging on and consequent flattening of the crown on the head drum. The experts concluded that the absence of a crown on the head drum was "a primal cause which allowed the belt to run off track".
21. A fax dated 8 December 2003 from Brad Huckle of H & B Plant Engineering to Andrew Herlihen, the NSW Operations Manager for the Defendant, refers to work carried out on one of the Bucket Elevators on 5 December 2003 due to the failure of the conveyor belt to track correctly. Huckle noted that the belt was tracking "hard to one side and over the edge of the roller at the top. After a number of adjustments the belt still continued to track off. On 8 December 2003 Huckle advised that he had referred the belt to Endless Belts for an opinion in regard to the belt conditions and to ascertain whether replacement was the only option. The belt was not replaced.
22. Joe Matijasko ("Matijasko") was the maintenance supervisor employed by Refined Sugar Services Pty Limited to be responsible for the maintenance and repair of plant and equipment operated by the Defendant at the Premises. Matijasko is a fitter by trade. When interviewed he stated that he had not received any training about the servicing and maintenance of that plant and equipment installed and operated at the site however he was required to inspect the buckets and the belt of the elevators almost every day to ensure that the belt stayed in the same position and did not drift. He admitted that the belt in elevator EL02 had drifted some 30mm to one side and that, despite the drift, the elevator was still in operation because in his opinion it was stable.
23. When interviewed by Inspector Bishwa, Matijasko said that drift sensors were installed in the elevators to ensure that the belt had not drifted from its normal operating position. When asked how often these sensors and other safety mechanisms were inspected to ensure the elevator's effective operation Matijasko replied: "They are not inspected". He later stated that the elevator maintenance program did not include inspection of the safety mechanisms or features fitted to the elevators.
24. The defendant, failed to implement a safe system of inspection, maintenance and servicing of the plant and equipment at the Premises – including the elevator EL02 – to ensure that the plant and equipment was operated in a good and safe condition.
25. The relevant officers of the defendant,defendant were aware of a significant risk of an explosion of sugar dust occurring in the elevators.
Remedial steps taken after the incident
26. Since the incident the defendant has carried out extensive repair and upgrading work to the plant and equipment damaged by the explosion. The flame and belt detection systems have been upgraded and the fire suppression system significantly improved.
27. The defendant has also implemented programmed maintenance management systems, which include periodic inspections and recording of inspections. In conjunction with Refined Sugar Services Pty Ltd training has been provided to ensure that all operations and maintenance personnel are aware of the critical nature of the devices and systems.
28. Inspections and checks have been carried out on components of individual plant. Regular inspections of the elevators have been implemented and the head pulley lagging on elevator EL02 has been replaced to prevent the belt from drifting to the sides of that elevator.
29. A Safety, Health and Environment policy has been developed and signed after the incident with an OHS Committee established and provided with training.
Cooperation with WorkCover
30. The defendant cooperated with WorkCover throughout its investigation of the matter.
Plea of Guilty
31. The defendant entered a plea of guilty to an amended Application for Order.
Prior Convictions
32. The defendant has no prior convictions under the Occupational Health & Safety Act 2000 .
Moiety
33. The prosecution seeks a moiety of any fine imposed upon the defendant.
10 Mr RM Goot SC, who appeared for the defendants, tendered an affidavit of Mr Peter Athanitis who is employed by the first defendant as the Operations Manager, NSW and Depots for Sugar Australia Pty Ltd. He has held the position since 13 October 2004. He was not required for cross-examination. Also present in Court were Mr Ian McMaster, the Director of the first respondent and former CEO of CSR Sugar and Mr Roger Williams, legal counsel for CSR. Mr Tim Hart, who is the current CEO for both defendants, was delayed arriving from overseas.
11 Mr Athanitis was authorised to swear his affidavit on behalf of both defendants. He deposed that the second defendant has been operating since 27 February 1998. At the time of the incident, the shareholders were CSR – 50 per cent, Mackay Sugar Co-Operative Association Limited – 25 per cent and E D & F Man Australia Pty Limited – 25 per cent. The last named company has been renamed CSR Refining Investments Pty Ltd.
12 Prior to and at the time of the incident, the second defendant managed safety by using the Safety, Health and Environment ("SHE") policy and the Safety, Health and Environment Management System ("SHEMS"). The SHE consists of 13 elements in five sections being 151 pages and incorporates a continuous improvement cycle. Section 5.3 deals with fixed plant. It provides, in summary, that all fixed plant shall be itemised (on a register) inspected and maintained in good condition, with particular attention to safety mechanisms such as guards, emergency stops and isolation systems. Maintenance schedules are required, together with a record of relevant inspections, maintenance, repair and alteration. Risk assessments are to be undertaken for fixed plant.
13 Mr Athanitis annexed a most impressive and comprehensive range of materials to his affidavit that demonstrated the culture of occupational safety, maintenance and training systems in place before the incident. These included the following:
(i) The CSR Safety, Health and Environment (SHE) – Management System
(ii) The CSR SHE Standard – 2003 Priority & Best Practice Level Elements
(iii) The Occupational Health and Safety Policy maintained for the Premises
(iv) The Glebe Island Terminal Induction Package. Each contractor to the second defendant and all employees of the first defendant attend a site induction before commencing work at the premises. The site induction includes reference to fire hazards
(v) Training records for employees of the first defendant at the premises
(vi) Safety Focus Workshop Manual dated 5 March 2002. (This manual, together with the Induction Package are most comprehensive document running into some hundreds of pages)
(vii) The Emergency Evacuation Procedures for the second defendant revised in September 2003
(viii) Minutes of Site Safety Meetings at the premises
(ix) A bundle of documents including KPIs for December 2003
(x) Glebe Island Depot Safety Checklist
(xi) Handwritten notes from Hazard Register between 9 November 2003 and 24 November 2003
(xii) Emails dated 28 January 2004 to 26 March 2004 regarding outcome of Glebe Safety Meeting
(xiii) Extract from Audit Report
(xiv) First Aid Report dated 6 March 2004
(xv) Risk Controls Audits - Risk Improvement Recommendations Update, Response prepared by the second defendant in June 2003
(xvi) The Glebe Depot - SHE Standards Gap Audit dated 11 February 2004
14 At the time of the incident, there was located in the control room at the premises, a folder containing the following:
(i) Site Induction document;
(ii) Emergency Evacuation Procedures;
(iii) Plant isolation, Lock out, Tag Out procedures and documentation;
(iv) Vehicle and Mobile Plant Procedures;
(v) Confined Spaces Permit;
(vi) 24 hour Notification Form;
(vii) Hazard and Risk Assessment Procedures;
(viii) An email dated 15 April 2005 from Balz Nater of the Buhler Group sought answers to the causes of the off tracking or misalignment of the belt in the bucket elevators together with details of the cleaning arrangements at the premises that were in place on and before the incident on 25 April 2004. These documents demonstrated that extensive cleaning occurred at the premises every three to four days.
15 Mr Athanitis deposed that the principal safety systems implemented at the premises prior to the incident included a heat sensor at the head of the elevator; fire detection suppression and fighting systems and equipment and explosion relief systems (flameless explosion vents) so that if and when an explosion occurred inside the elevator, it would be safely dissipated by the explosion vents and a maintenance system so that plant and equipment was maintained.
16 At the time of the incident, the flameless explosion vents were the most advanced form of device used to defuse explosions. There were also cleaning systems to minimise sugar dust in and around the plant. The premises underwent regular routine cleaning of sugar dust prior to the incident.
17 It was conceded by Mr Goot that the detection systems for belt operations which were used to ensure that the belt was tracking and operating correctly, was not operational at the time of the incident. Mr Athanitis stated that at the time of the incident, the workhouse was clean of sugar dust so that there was no secondary explosion at the time of the explosion in the encased bucket elevator EL02.
18 When the casing was removed from the elevator head, the elevator head showed clear signs of the belt and buckets rubbing on the head casing via heat marks and burnt paint.
19 Mr Joe Matijasko was the maintenance supervisor at the time of the incident and had identified a problem with the belt tracking for the elevator, however he did not identify the wearing of the crown on the elevator head.
20 The Report prepared by ISMA concluded that the explosion of sugar dust in the enclosed elevator, most probably resulted from sugar dust in the elevator being ignited by mechanical friction in the head of the elevator caused by a misaligned conveyor belt due to the wearing of the crown on the head pulley.
21 At the time of the incident, there were no employees in the workhouse. However, Messrs Carrucio and Ryan were located outside the workhouse near the fire doors.
22 Mr Athanitis stated that, in spite of the explosion in the elevator, the damage to the workhouse structure was not extensive and consisted of windows blown out, damage to the fire door adjacent to the elevator and the insulated panel wall sections were forced out of place by the pressure of the explosion. There were no secondary explosions.
23 After the explosion, remedial action was taken. Mr Athanitis annexed the following materials to his affidavit in this regard:
(i) The Safety MAP 4th edition Initial Level Gap Assessment May 2004 carried out by Risk Management & Safety Systems Pty Ltd;
(ii) Draft Health and Safety Management Plan conducted by Risk Management and Safety Systems for Glebe Facility for year ending 30 June 2005;
(iii) HIBBS & Associates – OH&S Consultants Final Report for Atmospheric Monitoriong – Inhalable Dust, Glebe Island Facility dated August 2004;
(iv) Worley Services Safety & Risk Management – Sugar Australia Hazard Analysis Glebe Facility report dated 15 October 2004;
(v) International Safety & Risk Management Group ("ISMA") Sugar Australia Audit on Dust Explosion Risk of the Glebe Island Terminal Sugar Installations Report;
(vi) Letter from Thomas & Coffey re: proposed dust suppression/conveyor dated 24 January 2005;
(vii) HIBBS – OH&S Consultants conducted a risk assessment – combustible dust packing and bulk loading areas – Glebe Island for Sugar Australia in June 2004;
(viii) Risk Assessment - Replacement of Chain conveyor and elevator – Glebe Terminal.
24 The second defendant implemented all recommendations made by the experts.
25 Since the incident, the second defendant has focused on the following:
(i) The creation of risk registers and a risk reduction program for plant;
(ii) Upgrades to high risk administrative controls;
(iii) Upgrades to safety critical preventative management systems;
(iv) Implementation of improved safety committee and reporting structures;
(v) Improved incident investigation and follow-up.
26 These goals and programs have been documented and were presented to the CSR Board on 20 March 2006. A SHE Accreditation Bronze Level Criteria internal assessment has been introduced to assess compliance at the premises with the SHEMS system.
27 Since the incident, the second defendant's Safety and Environment Policy has been reviewed and updated and meetings of the Safety Committee have continued with great focus on safety objectives. Relevant documentation was annexed to Mr Athanitis' affidavit in this regard. Also annexed to his affidavit was the current induction package for persons working at the premises (August 2005) and checklist for employees and contractors; current training matrix for the premises and samples of training certificates. Workshops/training packages provided to employees of the first defendant, include:
(i) A two day workshop dealing with Hazardous Areas Simplified;
(ii) Loading of trucks in the Dry Bulk Loading Areas written by Carmine Caruccio dated May 2006 and General Assessment Tool for Tanker Loading;
(iii) Dust Explosion Awareness and training module questionnaire;
(iv) RMSS – Risk Management Tool for Onsite Risk Assessments:
(a) User Training Program;
(b) Getting Started User Manual;
(c) Incident Manager Guide.
28 The emergency procedures have been updated and copies of the updated procedures were annexed.
29 Mr Athanitis deposed that since the incident, the second defendant has expended $3.9 million in capital equipment improvement across all sites.
30 In relation to the Glebe site, the second defendant has expended $2.8 million on remedial works. Annexed to the affidavit was a copy of the Capital Projects conducted at the site which included:
(i) Explosion Risk Reduction Measures (implementation of Stuvex Explosion Suppression System). A suppression system has been installed on the bucket elevators replacing the flameless venting system;
(ii) Belt drift sensing has been upgraded with additional sensors at the head and boot of the elevator;
(iii) Rotary valves have been modified to reduce the probability of any explosion propagation through the valve bodies;
(iv) Replacement of Bucket Elevator EL02 – EL02 has been re-built with a welded casing and returned to service;
(v) Reclaim of Bucket Elevator EL01 – EL01 has been upgraded with preventative and protective measures similar to EL02 and returned to service;
(vi) Enclosing the BC02 and BC03 conveyors in the workhouse (and photograph of the work) – the in-load conveyor has been enclosed to reduce dust accumulation during ship unloading;
(vii) Bulk Sugar Tanker Earthing;
(viii) Dust Explosion Risk Reduction – Deflagration detection and isolation systems to protect a risk plant;
(ix) Electrical Compliance.
31 Mr Athanitis deposed that the second defendant had adopted an approach to preventative maintenance first developed by the Toyota Car Company in Japan known as Total Productive Maintenance ("TPM"). He included the relevant documentation. The improved system of maintenance of critical safety equipment included:
(i) Sugar Australia – Glebe Terminal Programmed Maintenance Plan YEM 2005;
(ii) Workplace Inspection Checklists – Glebe Island Depot – since December 2004;
(iii) Plant Maintenance Service Records for plant at Glebe Island since January 2005;
(iv) Hygiene Review Checklists since February 2005;
(v) Electrical & Mechanical Preventative Maintenance plans for YEM07.
32 All employees of the first defendant complete Workplace Inspection Checklists and Hygiene Review Checklists.
33 All checklists are logged onto a computer system, which is accessible across all of the second defendant's sites to facilitate information sharing for risk reduction across all sites.
34 In relation to Dust Management, Mr Athanitis stated that a standard dust layer at all sites has been set and this standard is being maintained via cleaning programs, and monitored by weekly audits at maximum of 0.5 millimetres. Dust leakage from conveyor transfer points is being monitored to identify design problems and remedy the situation so that the standard can be reached with less frequent cleaning and a contract cleaner has been employed at the premises.
35 Hazardous area plans and explosion protected electrical equipment registers have been completed for all sites. The second defendant has budgeted $5.4 million for expenditure for implementation of hazardous area classifications and electrical equipment upgrades during the period October 2005 to June 2007 to bring all sites into compliance. Mr Athanitis annexed the following documents in this regard:
(i) Hazardous Areas Inspector Timetable 2006-2009;
(ii) Worley and ISMA Risk Register Matrix;
(iii) Hazardous areas site zoning drawings.
36 Mr Athanitis deposed that the second defendant and employees of the first defendant participated in a conference in November 2005 in which the incident was critically examined and the lessons learned were discussed in order to educate others how to eliminate risks of these types of events in the future. The conference included a slide presentation and a brochure for the Dust Explosion Seminar. Documentation dealing with the objectives for the business of the second defendant in the future were also annexed.
37 Mr Athanitis stated that both defendants deeply regret the incident that occurred and that the second defendant has learnt from the incident and sought to make improvements at the earliest practicable opportunity to all its sites and interests. He stated productivity at the premises has increased from 18 per cent to 60 per cent due to the improvements in safety and equipment effectiveness. The response to safety is proactive and the safety committee is consulted before changes occur to the systems of work, plant and work environment.
38 Mr Athanitis deposed that both defendants have a desire to operate with a total commitment to compliance with all occupational health and safety obligations and both companies co-operated fully the WorkCover Authority of New South Wales in respect of the incident and the investigation process.
39 The first defendant is always striving to reduce the potential for injury to its employees through training and a co-ordinated approach with the management of CSR and the second defendant. This has led to improved policies, procedures and practices so as to provide a safe environment for its employees. Mr Athanitis stated each defendant is doing its utmost to ensure that measures are adopted to ensure that such an incident does not happen in the future.
Submissions
40 Helpfully, both counsel provided the Court with written submissions. Both parties were in agreement in respect of the principles of the law that are required to be applied in a sentencing hearing.
41 Mr O'Donnell's submissions may be summarised this way:
(i) the objective seriousness of each offence is significant;
(ii) explosions of this type have the potential to cause serious injury;
(iii) the belt drift inside the elevator was identified in December 2003;
(iv) the belt was not replaced;
(v) Mr Matijasko, the maintenance supervisor, had not received any training about the servicing and maintaining of the plant and equipment installed and operated at the site. Mr Matijasko, when interviewed by the Inspector stated drift sensors were installed in the elevators to ensure that the belt had not drifted. However, the drift sensors were not inspected and the elevator maintenance program did not include inspections of the safety mechanisms, or features fitted to the elevators;
(vi) the incident was foreseeable;
(vii) clause 62 of the Occupational Health and Safety Regulation 2001 provides for particular risk control measures to prevent the occurrence of fires and explosions;
(viii) it was acknowledged that a great deal of remediation had occurred since the incident and a substantial amount of money had been spent and systems put in place to ensure safety;
(ix) general and specific deterrence are both relevant;
(x) simple and remedial steps were available;
(xi) the defendants are of equal culpability.
42 Mr Goot emphasised the following matters in his submissions:
(i) the defendants acknowledged that this was a serious matter but contended that the absence of injury was due to good planning and good safety systems and a safe and effective evacuation procedure, as explained in the evidence of Mr Athanitis;
(ii) the system of plant, maintenance, and training in place prior to the incident resulted in the cause of the incident being not readily foreseeable;
(iii) in light of the evidence of Mr Athanitis, the risk of re-offending is very low, or non-existent;
(iv) the Court should therefore heavily discount or disregard the element of specific deterrence;
(v) the nature of the offence is at the low end of the middle range of seriousness;
(vi) in respect of subjective matters, emphasis was placed on the culture of occupational safety, maintenance and training systems in place before the incident with particular reference to the standards and systems that were in place and referred to in the evidence of Mr Athanitis;
(vii) the steps taken by the defendants after the incident, as detailed in the affidavit evidence of Mr Athanitis;
(viii) neither defendant has any antecedents;
(ix) the defendants co-operated with the WorkCover Authority of New South Wales;
(x) finally, the defendants submitted that in approaching sentencing, it is appropriate to recognise that although the defendants are separate but related corporate entities and although the concept of "totality" may not apply, it is to be remembered that the business of the first defendant was solely to supply labour to the second defendant and no other entity. Those subjective circumstances ought to be considered in determining penalty.
Relevant Principles
43 The Full Bench in Morrison v Coal Operations Australia Ltd (No 2) (2005) 141 IR 465 succinctly summarised the principles to be applied in determining sentence for an offence under the Act. Their Honours stated at [8] - [15]:
[8] The overall approach to be followed in relation to the determination of sentence is to be found in the first instance within the statutory provisions of the Crimes (Sentencing Procedure) Act 1999 and in particular, in relation to these proceedings, ss 3A Purposes of Sentencing and 21A Aggravating, mitigating and other factors in sentencing.
[9] In R v Way (2004) 60 NSWLR 168, it was emphasised that the provisions of the Crimes (Sentencing Procedure) Act referred to above are not to be construed as representing 'a departure from settled principles of sentencing practice, or an abandonment of the discretion that is essential to any system calling for individualised justice'. As was said at [59]:
[I]t is clear that the legislative policy ... so far as that can be discerned from the legislation itself, was not to create a straight jacket for judges ... but rather [was] intended to provide 'further guidance and structure to judicial discretion.'
[10] The starting point for consideration as to penalty is the objective seriousness of the offence. That is a well established sentencing principle and was conclusively affirmed in the Full Bench decision in Lawrenson Diecasting Pty Ltd v WorkCover Authority of New South Wales (Inspector Ch'ng) (1999) 90 IR 464 at 474 as follows:
[I]t is important to reiterate that the primary factor to be considered when a judicial officer is determining the appropriate sentence to impose is the objective seriousness of the offence charged. In case of prosecutions under the OH&S Act, this proposition has often been expressed by saying that the 'true measure of penalty lies in the nature and quality of the offence' ...
[11] The principle of foreseeability as a factor in determining the objective seriousness of an offence as part of the sentencing process was considered in the Full Bench decision in Capral Aluminium Ltd v WorkCover Authority of New South Wales (2000) 49 NSWLR 610 at 646; 99 IR 29 at 62 as follows:
The question of foreseeability is relevant to the assessment of the seriousness of the offence. We consider that the appropriate approach is that of Walton J, Vice President, in Department of Mineral Resources of NSW (McKensey) v Kembla Coal and Coke Pty Ltd (1999) 92 IR 8 at 27:
Whilst the reasonable foreseeability of an accident may not be relevant to the question of liability under the Act (see Drake Personnel Ltd t/a Drake Industrial v WorkCover Authority of New South Wales (Inspector Ch'ng) (1999) 90 IR 432), the degree of foreseeability is a significant factor to be taken into account when assessing the level of culpability of the defendant. The existence of a reasonably foreseeable risk to safety which is likely to result in serious injury or death is a factor which will be relevant to the assessment of the gravity of the offence.
[12] On the issue of foreseeability, the Full Bench in Capral also stated at 646; 62 - 63:
The existence of a reasonably foreseeable risk of injury will necessarily result in the offence being more serious in nature. However, the absence of foreseeability does not necessarily render the offence as being nominal or not serious. In this regard the relevant approach is that set out in the judgment of Wright J, President, in Ferguson v Nelmac Pty Ltd (at 209 - 210) in these terms:
... reliance on 'hindsight' must be seen in an appropriate perspective in terms of culpability. It is a relevant consideration but the very terms of s 15 impose an obligation on an employer which is not confined to the taking of precautions only when there are warnings or signals of danger or when experience indicates that a risk to safety has arisen and requires remedy. So much is clear from the structure and language of the section which is premised on the requirement to 'ensure ... health, safety and welfare at work' and the decided cases which make plain the nature of the obligation.
[13] It is also necessary to consider the damage and injury suffered in the context of the evidence and "in light of the principles which have been laid down in relation to the relationship between the seriousness of injuries which have been suffered, or which may have been suffered, and the gravity of the offence" ( Capral at 650; 66). On that point the Full Bench in Capral stated:
We consider that the relevant principle can be stated in this way. The gravity of the consequences of an accident, such as the damage or injury, does not, of itself, dictate the seriousness of the offence or the amount of penalty. However, a breach where there was every prospect of serious consequences might be assessed on a different basis to a breach unlikely to have such consequences. The occurrence of death or serious injury may manifest the degree of seriousness of the relevant detriment to safety: Tyler v Sydney Electricity (1993) 47 IR 1 at 5, Inspector Hannah v Wonar Pty Ltd (1992) 34 AILR 377 at 378, Watson v Southern Asphalters Pty Ltd (1996) 83 IR 446 at 456, Wong v Melinda Group Pty Ltd (1998) 82 IR 118 at 131, WorkCover Authority of New South Wales (Inspector Hannah) v Albury City Council (1999) 90 IR 397 at 408 - 409, Lawrenson Diecasting Pty Ltd (at 476), WorkCover Authority of New South Wales (Inspector Ankucic) v McDonald's Australia Ltd (at 428) and Page v Walco Hoist Rentals Pty Ltd (No 2) (at [22]).
[14] The principles of general and specific deterrence are also relevant in sentencing. The approach to be taken on that issue was also dealt with in some detail in Capral at 643 - 645; 59 - 62. Without detailing all that the Full Bench had to say we consider the approach to deterrence in the sentencing process is encapsulated in the following passage from the Full Bench in Capral at 644; 60 as follows:
[B]oth aspects of deterrence are matters which should normally be given weight of some substance in the sentencing process; and although there may be exceptional cases (see, for example, Page v Walco Hoist Rentals Pty Ltd (No 2) [2000] NSWIRComm 39 at [40]-[43] we would expect such cases to be very rare, and where the relevant circumstances were held by the sentencing judge to be established, the judge must indicate with some precision the circumstances which had led to the exceptional course being adopted.
[15] In the context of the above well established sentencing principles it will also be necessary to have regard to those general matters going to aggravation, mitigation and other factors identified in s 21A of the Crimes (Sentencing Procedure) Act relevant to the respondents before the Full Bench. As was said in R v Way at [56]:
[I]t is not to be overlooked that there is a well established body of principles that have been developed by the courts over a long period of time. By providing guidance in the form of a list of aggravating and mitigating factors in s 21A, the Parliament did not intend to overrule or disturb those principles or restrict their application. In so far as those principles refer to factors, whether objective or subjective, that affect the "relative seriousness" of the offence, they are expressly preserved by s 21A(1)(c).
Consideration
44 On 24 April 2004 there was a collective failure on the part of each defendant to implement a safe system of inspection, maintenance and servicing of the plant and equipment at the site, including the elevator EL02, to ensure that the plant and equipment was safe and without risks to health when properly used. Each defendant was also aware of the significant risk of an explosion of sugar dust occurring in the elevators.
45 On 8 December 2003, Mr B Huckle of H & B Plant Engineering referred to work having been carried out on one of the bucket elevators on 5 December 2003 which was due to the failure of the conveyor belt to track correctly. Mr Huckle observed that the belt was tracking hard to one side and over the edge of the roller at the top. After a number of adjustments, the belt still continued to track off. On 8 December 2003, Mr Huckle advised that he had referred the belt to Endless Belts for an opinion in regard to the belt conditions and to ascertain whether replacement was the only option. The belt was not replaced.
46 It was an agreed fact that the second defendant, failed to carry out adequate preventative maintenance on the elevator EL02, despite problems with the alignment of the belt in the bucket elevator prior to the incident. Mr Goot acknowledged that the drift sensor which was designed to indicate that the belt was drifting and that maintenance may be required, was not working or not working as it should have been.
47 The International Safety & Risk Management Group ("ISMA"), in their report, stated that the cause of the explosion was as follows:
Inside the head it appeared that belt and buckets have been running against the casing. There are in fact on this side two parallel tracings: one of the belt touching the casing and one of the buckets scratching it on a different but very close location. The belt also showed a carbonized edge at the point where it stopped after the incident, a proof that at that spot the hot casing could cause carbonisation of the belt.
There are clear traces of metal being scratched away at the point where the buckets had been touching the casing. The head also showed marks on the outside at the same locations, indication heat inside, caused by the belt rubbing the carbon steel casing and the stainless steel buckets edge scratching the casing.
All buckets clearly showed the marks where they have been scratching the casing: carbonised sugar and even material of the casing was still attached on some of the buckets: this material was magnetic (proof that is carbon steel) and looked blue black (possible proof that is has been very hot: at least 500C). The fact that the scratching points of most buckets after the incident still were black by carbonized sugar or metal parts, indicates the fact that just before the incident those points still were very hot: if they would be of an earlier event they would have been covered and thus obscured by sugar dust.
The direction of the flame in the downgoing leg also is directed down. In the upgoing buckets the direction is more difficult to distinguish.
48 A second expert's report by Safety Engineering Pty Ltd came to the same conclusion in respect of the cause of the explosion.
49 The risk, therefore, was the potential ignition of combustible sugar dust caused by friction of the conveyor belt not tracking correctly. The potential for conveyor belts to not track correctly was known to the defendants from December 2003.
50 Clause 62(1) of the Occupational Health & Safety Regulation 2001 provides:
62 Fire and explosion—particular risk control measures
(1) An employer must ensure that risks associated with fire or explosion at a place of work are controlled by:
(a) eliminating activities that have the potential to generate flammable or explosive atmospheres from the work process or, if elimination is not possible, minimising the potential for flammable or explosive atmospheres by providing adequate ventilation, and
(b) eliminating potential ignition sources, including naked flame, hot work and electrical equipment, and sources of static electricity, including friction, welding and slipping belts, from proximity to flammable substances, combustible dusts or waste materials, and
(c) enclosing work areas containing flammable or explosive atmospheres, and
(d) removing waste materials and accumulated dust on a regular basis, and
(e) providing for adequate storage, transportation and disposal of flammable substances, and
(f) any other measures necessary to control the risks.
51 Where the defendants were aware that a conveyor belt was not tracking correctly, thus giving rise to the potential of friction in an area where sugar dust was known to exist, or could be expected to exist, leads me to the view that the risk was reasonably foreseeable. This is, of course, a factor to be taken into account when assessing the level of culpability of the defendants.
52 A further particular of the charge in respect of the first defendant was that it failed to provide adequate training in the inspection and maintenance of plant necessary to ensure the safety of its employees at the site.
53 As to the failure to provide adequate training, it was acknowledged by Mr Matijasko, the maintenance supervisor, that he had not received any training about the servicing and maintenance of the elevator EL02, although he was required to inspect the buckets and the belt of the elevators almost every day to ensure the belt stayed in the same position and did not drift. He admitted that the belt in the elevator EL02 had drifted some 30 millimetres to one side and that, despite the drift, the elevator was still in operation because, in his opinion, it was stable.
54 The lack of training is one of the defendants' principal failures and if Mr Matijasko received proper training, he may have formed the opinion that the belt in elevator EL02, having drifted some 30 millimetres, was therefore unstable.
55 In my view, this is a serious matter. The risks associated with an explosion at a place of work are well known. It was an agreed fact that Mr Caruccio heard a loud bang and observed fire coming through the fire door and travel past him. Clearly, there was a risk of serious injury from this incident and it was fortunate that both Mr Caruccio and Mr Ryan, who was standing near the fire safety doors when the explosion occurred, were not injured.
56 I accept that a reason that the employees were not injured was because of the safety systems in place which required the separation of the workhouse containing elevators EL01 and EL02, from the workers feeding sugar into the elevators. Fire doors which were required to be kept shut were placed between the workhouse and where the workers loaded sugar into the elevators. The safety systems included the proper operation of explosion safety vents; maintaining the air surrounding EL02 and keeping the air free of sugar dust thereby ensuring there were no secondary explosions.
57 I am prepared to accept that there was a co-ordinated and coherent approach to safety by the defendants. The breakdown in the paper system, as acknowledged by Mr Goot was caused firstly by the lack of specific training in relation to belt drift and maintenance and secondly by the failure to detect that the sensors were not operating, or not operating appropriately.
58 Senior counsel submitted that as soon as the explosion occurred, the whole system closed down activating other fail safe mechanisms which then operated.
59 In my view, the measures that were available to overcome the risks were simple and straightforward. Clause 62(1)(b) of the Occupational Health and Safety Regulation 2001 emphasises the need to control risks associated with a fire or explosion at a place of work by eliminating potential ignition sources, including slipping belts, from proximity to combustible dusts. There were simple steps available to the defendants to ensure that the belt in EL02 tracked correctly by ensuring that the head drum had a proper crown to prevent belt drift and thus avoiding the consequent source of ignition caused inside EL02 by that belt drift.
60 There was no death or serious injury arising from the defendants' failure, but it is clear that the consequences could have been much more serious than was the case.
61 There was no issue that the penalty should reflect an amount for general deterrence. It is not necessary to do more than repeat the remarks of Hungerford J in Fisher v Samaras Industries Pty Limited (1996) 82 IR 384 at 388 (endorsed by the Full Bench in Capral Aluminium Limited v WorkCover Authority of New South Wales (2000) 49 NSWLR 610 at [71] - [80]):
… the fundamental duty of the Court in this important area of public concern ... [is] to ensure a level of penalty for a breach as will compel attention to occupational health and safety issues so that persons are not exposed to risks to their health and safety at the workplace.
62 In respect of specific deterrence, Mr Goot submitted that the Court should heavily discount or disregard the element of specific deterrence. I do not propose to disregard an element in the penalty in respect of specific deterrence. The second defendant continues to conduct the manufacture, storage and distribution of refined sugar and associated products at the site. The first defendant continues to provide its employees to the second defendant to enable the second defendant to conduct the manufacture, storage and distribution of refined sugar. Any industry in which there is the potential for an explosion presents risks to workplace safety. I propose to include an element in the penalty for specific deterrence in respect of both the defendants, although it will only be small given that I consider the incident surprised both defendants and that they are unlikely to re-offend in light of the remedial action taken.
63 There are a number of relevant subjective considerations. The evidence of Mr Athanitis leads me to the conclusion that there was a culture of occupational safety, maintenance and training systems in place before the incident. However, as I have referred to earlier, it was deficient in respect of specific training in relation to belt drift and the failure to detect that the sensors were not operating, or not operating properly. Although the extensive and elaborate paper systems in existence were found to be wanting with respect to their implementation in certain areas, I accept the systems included detailed work and review procedures; elaborate site induction; occupational health and safety training courses and focus workshops; emergency evacuation procedures; regular site safety meetings; comprehensive record maintaining systems and strict maintenance and cleaning measures; regular reports including atmospheric monitoring, hazard analysis and international risk management.
64 Overall, this is an impressive and largely effective system of safety. If an error or flaw occurred in the system, there was other failsafe mechanisms that came into operation. These systems of safety mitigate what otherwise would have been a very serious offence. The existence and implementation of these systems shows that the defendants had a high regard for safety at the site. In this regard, the Full Bench in Morrison v Powercoal Pty Ltd (No 3) (2005) 147 IR 117 observed at [83]:
[83] We accept on the evidence presented in these proceedings, however, the corporate respondent was generally a responsible employer with a high regard for the safety of its employees. Its occupational health and safety systems and procedures were designed to cope with what is an exceptionally dangerous industry. The existence of a system of work that evidences a defendant's concern with, and regard for, safety may mitigate the seriousness of an offence: see, for example, Department of Mineral Resources (NSW) v Kembla Coal & Coke Pty Ltd (1999) 92 IR 8 at 25; WorkCover Authority (NSW) v Broken Hill Pty Co Ltd (1998) 83 IR 427 at 429; and WorkCover Authority (NSW) v Fernz Construction Materials Ltd (No 2) (2000) 100 IR 23 at 34.
65 It is clear that the defendants moved swiftly to commission a report from experts into the cause of the incident. This was provided by ISMA and its recommendations implemented. In addition, the defendants commissioned an audit of the safety regime at the site by Risk Management and Safety Systems Pty Ltd. The defendants also commissioned external monitoring and risk assessment reports in relation to atmospheric monitoring; hazard analysis; dust explosion risk; dust suppression and packing and in respect of the bulk loading areas. All recommendations were immediately implemented. The SHE and the SHEMS systems referred to in the evidence of Mr Athanitis were upgraded, together with the second defendant's safety and environmental policy. A new health and safety committee's constitution, dated 15 February 2005, was introduced. Induction training and updating emergency procedures also occurred.
66 In addition, the second defendant has expended $2.8 million on remedial works on the elevator EL02, and associated equipment, which has been critically reviewed and substantially rebuilt. A new approach to preventative maintenance and dust management has been adopted since the incident. Hazardous area plans and explosion protected electrical equipment registers have been completed for all of the second defendant's sites. The defendants also conducted a conference in November 2005 to critically examine the incident and the lessons learned in order to educate others how to eliminate risks of these types of events in the future.
67 Neither defendant has any prior convictions and co-operated fully with WorkCover. I regard both defendants as being entitled to a finding of good industrial citizenship.
68 The prosecution acknowledged that each defendant entered a plea of guilty at an early stage and was entitled to a specific discount to reflect the utilitarian value of the plea.
69 Although each defendant pleaded guilty to an amended application for order, the pleas were entered at the first opportunity before the Court after the charges were framed in their present form.
70 In its guideline judgment in R v Thomson; R v Houlton (2000) 49 NSWLR 383 the Court of Criminal Appeal held at [160]:
…
(iii) The utilitarian value of a plea to the criminal justice system should generally be assessed in the range of 10-25 per cent discount on sentence. The primary consideration determining where in the range a particular case should fall, is the timing of the plea. What is to be regarded as an early plea will vary according to the circumstances of the case and is a matter for determination by the sentencing judge.
71 Spigelman CJ, with whom other members of the court agreed, said at [155]:
The top of the range would be expected to be restricted to pleas at the earliest possible opportunity and should not be given, save in an exceptional case, after a matter has been set down for trial. A discount towards the bottom of the range is appropriate for late pleas, for example, on the date fixed for trial, unless there are particular benefits arising from the prospective length and complexity of the trial.
72 In R v Gorman (2002) 137 A Crim R 326 Sperling J, with whom Beazley JA and Carruthers AJ agreed, stated at [64], after referring to the abovementioned passage from the Chief Justice in R v Thomson; R v Houlton:
In my view, where an offender pleads guilty immediately upon charges being reduced by the Crown, that is "an exceptional case" justifying a discount at or close to the top of the range, notwithstanding that the proceedings have long since been set down for trial. …
73 I propose to allow a discount of 25 per cent for the early plea of guilty to the amended charges in accordance with the principles outlined in R v Thomson and R v Gorman.
74 These matters involve the prosecution of the agent conducting the business of a joint venture at the site (the first defendant), as well as the company which supplied the employees to the agent to enable it to conduct that business (the second defendant). Both defendants had specific obligations under the Act. I see no reason why I should not treat the defendants as being equally culpable.
75 Mr Goot submitted that in determining sentence, it was appropriate to recognise that although the defendants are separate but related corporate entities and the concept of totality may not apply, the business of the first defendant was solely to supply labour to the second defendant and for no other entity. I accept that the sole reason for the existence of the first defendant was and is to supply labour to the second defendant. The first defendant was established against the background of employees of CSR being subject to beneficial award conditions and other conditions of employment, including bonus schemes and the like. When it came to establishing the joint venture, whilst CSR is a party, it is not the controlling entity. An issue arose as to how to apply or maintain for the employees of the joint venture, including former CSR employees and new employees, those beneficial entitlements. The first defendant came into existence simply to maintain entitlements for the benefit of the employees of the joint venture.
76 In my view, the issue of totality does not arise. The principle of totality was recently considered by the Full Bench in Inspector Green v Big River Timbers Pty Limited; Inspector Green v Big River Timbers (Veneer) Pty Limited [2006] NSWIRComm 279. Their Honours said at [7] - [14]:
[7] The respondents conceded that the principle of totality does not operate in relation to the corporate defendants merely because they have common directors and shareholders. No challenge was made, in this respect, to the decision of this Court in WorkCover Authority of New South Wales (Inspector Petar Ankucic) v McDonald's Australia Ltd (2000) 95 IR 383 at 454 to 460 and Inspector Sharpin v A Team Concrete (Aust) Pty Ltd & Ors [2004] NSWIRComm 182. However, the respondents argued that those cases are distinguishable on their facts; it was submitted that the respondents were "interlocked" in such a way as to warrant the approach taken by Marks J in Inspector Green (WorkCover) v Metropolitan Administrative Services Pty Ltd [2005] NSWIRComm 12. Although ultimately the respondents abandoned the contention that the principle of totality could apply strictly in this case, we propose to review the more recent consideration of this principle by the Court.
[8] The totality principle was recently considered in the Full Bench decision in Morrison v Powercoal Pty Ltd & Anor (No 3) (2005) 147 IR 117. At [126] the Court held:
[126] … The totality principle was recently considered by Full Benches of this Commission in Abigroup Contractors Pty Limited v WorkCover Authority of New South Wales (Inspector Maltby) [2004] NSWIRComm 270 and WorkCover Authority of New South Wales (Inspector Mansell) v Robert Josef [2004] NSWIRComm 323. There is no utility in us undertaking any reconsideration of the principle because we consider the exhaustive analyses in the aforementioned cases are correct, except to identify what the principle stands for and that was stated succinctly in Crown in Right of the State of NSW (Dept of Education and Training) v Keenan (2001) 105 IR 181 at [36] - [38] and quoted with approval in Abigroup at [76]:
[I]n determining penalties for multiple offences under the Occupational Health and Safety Act the Court is required to determine separately an appropriate penalty for each offence. Having done so, the Court should then consider what the appropriate penalty should be by applying the principle of totality. Where the multiple offences contain common elements, the principle of totality must, for that reason alone, be applied to ensure that the defendant is not punished more than once for the common elements of the offences and to avoid the double jeopardy that would follow if that occurred. The principle must also be applied for the reasons stated in Pearce [ v The Queen (1998) 194 CLR 610] and Mill [ v The Queen (1988) 166 CLR 59].
[37] We should emphasise that the principle that a defendant is not to be punished more than once for the common elements of the offences does not require that a single penalty only should be imposed for the multiple offences. The Court is required to determine a separate penalty for each offence before applying the principle of totality. It will then usually be appropriate to fix separate penalties for each offence. It is in applying the principle of totality - which requires the consideration of the overall criminality involved in the offences - that regard should be had to the principle that a defendant is not to be punished more than once for elements which are common to the offences as well as ensuring the aggregate sentence or penalty is just and appropriate.
[38] In accordance with Pearce , we must first consider the appropriate penalty for each offence, assessed separately.
[9] See also the decision in Inspector Barry Childs v Kirk Group Holdings Pty Limited & Anor (2005) 137 IR 462 per Walton J, Vice-President, where at [62] his Honour also refers to the decisions in O'Sullivan v The Crown in the Right of the State of New South Wales (Department of Education and Training) (2003) 128 IR 158 and Warman International Limited v WorkCover Authority of New South Wales (1998) 80 IR 326.
[10] However, the crux of the appellant's complaint is his Honour's application of the totality principle where there are two separate defendants. The appellant seeks to rely, in this respect, on the decision in WorkCover Authority of New South Wales v McDonald's Australia Limited.
[11] The defendant in that case made submissions similar to those made in the present appeal, namely, that the offenders ought to be treated as one entity: see [242]. After reviewing the authorities relevant to the principle of totality ([243] - [248]), including Camilleri's Stock Feeds Pty Limited v Environmental Protection Authority (1993) 32 NSWLR 683, Pearce v The Queen (1998) 194 CLR 610, Postiglione v The Queen (1997) 189 CLR 295, Walton J, Vice-President, held:
[249] The principle formulated in these cases does not, on its face, assist the defendants' contention. The principle of totality enunciated in these decisions operates in circumstances where a single defendant was convicted of a number of offences. The principle requires a judge who is sentencing an offender for a number of offences to ensure that the aggregation of the sentences imposed for each offence is a just and appropriate measure of the total criminality involved. However, the present matter does not concern a single offender facing multiple charges, but two defendants facing different charges. There is a common substratum of facts, but the defendants, as was conceded by Mr Harmer , have different "contributions".
[12] After distinguishing cases in which a single penalty was imposed for related corporate defendants, his Honour held at [264]:
[264] The principle of totality operates to ensure that the total criminality of a defendant in relation to an incident is properly and justly assessed. It is difficult to envisage how the principle, so expressed, can be used to measure the criminality of more than one defendant no matter how closely related. The principle of totality can be distinguished from the principle of parity which is directly relevant to the assessment of the appropriate penalty for co-offenders. Upon the basis of the authorities I have earlier referred to, the principle of totality would not require the sentencing of the defendants to be undertaken upon the basis that they were effectively treated as a single entity facing two charges.
[13] We consider this correctly states the manner in which totality does or does not apply to separate defendants. The role, or lack thereof, of totality in relation to separate defendants was also outlined by the Full Bench in Inspector Bestre v T & Y Pty Ltd [2005] NSWIRComm 392 at [14]:
[14] The principle of totality is relevant when a court is sentencing a defendant for more than one offence which contain common elements. In relation to totality, his Honour made the following observation which clearly demonstrates an error of law:
In relation to both s 8(2) offences, I find that in each case the nature and quality of the offence indicates that penalties in the medium range are warranted subject to appropriate consideration for the subjective mitigating factors and after taking into account relevant sentencing principles including the principle of parity and the principle of totality.
The two s 8(2) offences referred to by his Honour were committed by two different defendants; this necessarily precludes the principle of totality. Even if his Honour had purported to apply the principle to the two offences committed by the respondent (that is, under ss 8 (2) and 94) the ingredient of commonality was lacking.
[14] The present case is analogous to that in Inspector Sharpin v A Team Concrete where, at [110], Staff J held:
[110] I prefer the approach adopted by Walton J Vice-President in McDonald's Australia Limited. In my view, the principle of totality does not require the three defendants to be treated as effectively one entity facing offences under ss 8(1), 8(2), 10(2) and 26(1) of the Act for the purposes of the assessment of penalty and therefore the principle of totality should not be applied in this matter. Rather, there should be a proper weighing of the respective culpabilities of the defendants and, in this regard, attention should be paid in properly measuring the actual culpability of each defendant in relation to the detriment to safety involved in the accident. Where there are overlapping responsibilities, then the Court will ensure that there occurs a proper apportioning of responsibility by the respective defendants.
77 Their Honours went on to discuss the issue of parity as between co-defendants stating at [15]:
[15] Importantly, his Honour also went on to find:
[111] However, a Full Bench of this Court held in Warman at 341 that where defendants (not being co-offenders) are prosecuted under different sections of the Act, the Court should, nonetheless, adopt "an approach to sentencing which shows consistency and not disparity in punishment in the same way as discussed by Mason J in Lowe " where common factual circumstances exist giving rise to the charges. It should be noted that the Court considered parity in Warman in the context of a labour hire company and the defendant who utilised that labour.
[112] The decision in Warman would require that the defendants, even though prosecuted under different sections of the Act, be treated consistently in accordance with the principles in Lowe v The Queen (1984) 154 CLR 606. At 610 Mason J referred to the principle as follows:
"Just as consistency in punishment - a reflection of the notion of equal justice - is a fundamental element in any rational and fair system of criminal justice, so inconsistency in punishment, because it is regarded as a badge of unfairness and unequal treatment under the law, is calculated to lead to an erosion of public confidence in the integrity of the administration of justice. It is for this reason that the avoidance and elimination of unjustifiable discrepancy in sentencing is a matter of abiding importance to the administration of justice and to the community."
78 It is therefore appropriate, in my view, that I apply the principle of consistency in punishment, or equal justice in the assessment of penalty in these matters.
79 In respect of each of the offences, the statutory maximum penalty is $550,000.
80 I regard the procedures taken by the defendants to improve the occupational health and safety systems as appropriate. I accept that the defendants have demonstrated a strong commitment to workplace safety and that is a factor to be taken into account in their favour.
81 The defendants also accepted responsibility for the incident and expressed contrition for the events that occurred on 24 April 2004. This is a further factor to be taken into account in their favour.
82 Taking into account all of the relevant circumstances, I consider that the appropriate penalty should be:
1. In matter No IRC 588 of 2006 - $50,000.
2. In matter No IRC 589 of 2006 - $50,000.
ORDERS
83 The Court makes the following orders:
In matter No IRC 588 of 2006:
1. The offence is proven and a verdict of guilty is entered.
2. The defendant is convicted of the offence as charged.
3. The defendant is fined an amount of $50,000 with a moiety to the prosecutor.
4. The defendant shall pay the prosecutor's costs of the proceedings in an amount as agreed, or, if agreement cannot be reached, as assessed, in accordance with the Court's Rules.
In matter No IRC 589 of 2006:
1. The offence is proven and a verdict of guilty is entered.
2. The defendant is convicted of the offence as charged.
3. The defendant is fined an amount of $50,000 with a moiety to the prosecutor.
4. The defendant shall pay the prosecutor's costs of the proceedings in an amount as agreed, or, if agreement cannot be reached, as assessed, in accordance with the Court's Rules.
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.