NSW Caselaw
Land and Environment Court of New South Wales
Loombah Investments v Ku-ring-gai Council [2005] NSWLEC 215 CITATION : This decision has been amended. Please see the end of the judgment for a list of the amendments.
Applicant: Loombah Investments Pty Ltd PARTIES : Respondent: Ku-ring-gai Council
FILE NUMBER(S) : 10816 of 2004
CORAM: Roseth SC
KEY ISSUES: Development Application - Dual Occupancy :-
DATES OF HEARING: 13/12/2004
DATE OF JUDGMENT: 05/03/2005
Applicant: Mr S Kondilios, solicitor LEGAL REPRESENTATIVES: Respondent: Mr G Reilly, solicitor
JUDGMENT: THE LAND AND ENVIRONMENT COURT OF NEW SOUTH WALES
Roseth SC
3 May 2005
10816 of 2004 Loombah Investments Pty ltd v Ku-ring-gai Council
JUDGMENT
The consequence of the Court's decision in this appeal is the grant of development consent subject to detailed conditions. The conditions are not reproduced as part of this decision but are available for inspection at the Council. A copy the Court's Orders and conditions may be obtained from the Court's registry on payment of a fee. For details of the fee payable and process for obtaining a copy of the Orders and conditions see the Court's web site at http://www.lawlink.nsw.gov.au/lec/ 1 Senior Commissioner: This is an appeal against the refusal by Ku-ring-gai Council (the council) of a development application to erect a new dwelling to be the second dwelling of a detached dual occupancy development on lot 31 DP 11447, known as 2 Loombah Avenue, Lindfield.
We try to embed the page this law was scraped from. If the site blocks framing, you still get the link and a local excerpt.
Last checked with source on —
Checking whether the official page can be embedded…
Plain-English simplify of this law: a short summary, key points, and both sides of the argument. Generated on first view via Replicate, then cached. Vote on what helps your study.
No study brief is cached for this law yet. Sign up to generate a plain-English brief.
Sign up to generate