CITATION : Concrete Recyclers (Group) Pty Ltd v Parramatta City Council [2005] NSWLEC 758
APPLICANT Concrete Recyclers (Group) Pty Ltd PARTIES : RESPONDENT Parramatta City Council
FILE NUMBER(S) : 11241 of 2005
CORAM: Hussey C
KEY ISSUES: Development Consent :- Section 96 Modification - concrete recycling operation - hours of operation - dust - visual impact
DATES OF HEARING: 25/08/2005 and 14/12/2005 EX TEMPORE JUDGMENT DATE : 12/14/2005
APPLICANT Mr D Wilson, barrister SOLICITORS Mark McDonald LEGAL REPRESENTATIVES:
RESPONDENT Mr C Gough, solicitor SOLICITORS Storey & Gough
JUDGMENT: THE LAND AND ENVIRONMENT COURT OF NEW SOUTH WALES
Hussey C
14 December 2005
11241 of 2004 Concrete Recyclers (Group) Pty Ltd v Paramatta City Council
JUDGMENT
Background 1 This appeal was lodged following council's refusal of a s 96 Modification application for an existing concrete crushing and recycling facility at 14 Thackeray Street, Camellia. 2 The original consent for the development was granted on 3 June 1997 and the subsequent modification was in respect of the following conditions:
26. The hours of operation for the use of the premises is restricted to 6.00 a.m. to 6.00 p.m. Monday to Friday and 7.00 a.m. to 4.00 p.m. Saturday with a further restriction on the operation of any machinery or trucks on the site prior to 7.30 a.m. Monday to Saturday.
We try to embed the page this law was scraped from. If the site blocks framing, you still get the link and a local excerpt.
Last checked with source on —
Checking whether the official page can be embedded…
Plain-English simplify of this law: a short summary, key points, and both sides of the argument. Generated on first view via Replicate, then cached. Vote on what helps your study.
No study brief is cached for this law yet. Sign up to generate a plain-English brief.
Sign up to generate