CITATION : FPM Constructions P/L v. The Council of the City of Blue Mountains [2003] NSWSC 201 HEARING DATE(S) : 07/03/03; 11 & 12/03/03 JUDGMENT DATE : 26 March 2003 JURISDICTION: Equity JUDGMENT OF : Bryson J at 1 DECISION : See [28]
CATCHWORDS : Building and Engineering Contracts- construction- remuneration- Preliminaries-AS4300-1995 cl.42,cl.47-lump sum contract incorporated cl.42 Certificates and Payments- Contractor made Payment Claim including part of lump sum allocated to Preliminaries on time basis being proportion of time passed to whole time available- Superintendent allowed on percentage-of-works completed basis - Contractor disputed Certificate, gave notice of dispute and claimed urgent Declaratory Order establishing that time-basis was correct- Contractor contended that time basis was impliedly required because Tender Cash Flow submitted with Tender and incorporated in Contract projected even flow of sums allowed for Preliminaries- no clear identification in Contract of what work was Preliminaries: Held: time basis was not required by express or implied terms and Declaratory Order as sought should not be made - percentage of works completed basis adopted by Superintendent may not be correct and Court would give consideration to further claims - reasons for interlocutory rulings on stay of proceedings, summary disposal, security for costs. LEGISLATION CITED : Commercial Arbitration Act 1984 Supreme Court Act 1970 CASES CITED : Codelfa Constructions Pty Ltd v. State Rail Authority of New South Wales (1982) 149 CLR 337 Schenker & Co. v. Maples Equipment [1990] VR 834 PARTIES : FPM Constructions Pty Ltd - Plaintiff The Council of the City of the Blue Mountains FILE NUMBER(S) : SC 1618/2003 COUNSEL : G. McVay - P M. Ashhurst - D SOLICITORS : James A. Moustacas & Co. - P Phillip Fox Lawyers - D
We try to embed the page this law was scraped from. If the site blocks framing, you still get the link and a local excerpt.
Last checked with source on —
Checking whether the official page can be embedded…
Plain-English simplify of this law: a short summary, key points, and both sides of the argument. Generated on first view via Replicate, then cached. Vote on what helps your study.
No study brief is cached for this law yet. Sign up to generate a plain-English brief.
Sign up to generate