NSW Caselaw
New South Wales Supreme Court
CITATION : Magnate Projects Pty Limited v Youma Constructions Pty Limited [2006] NSWSC 388
HEARING DATE(S) : 7 April 2006
JUDGMENT DATE : 7 April 2006
JURISDICTION : Equity Division Commercial List
JUDGMENT OF : Brereton J
EX TEMPORE JUDGMENT DATE : 04/07/2006
DECISION : (1) Subject to and conditional upon the payment by the defendant and/or its solicitor Mr Marsh to the plaintiff of $45,000 by 19 April 2006, as referred to below, on account of their liability and the plaintiff's entitlement to costs, I extend time for the filing of objections, pursuant to order 3 of 16 December 2005, to 19 April 2006. ; (2) I order that the defendant and Mr Marsh pay $45,000 to Magnate on account of the costs referred to in paragraph 2 of the order of 16 December 2005 by 19 April 2006. ; (3) I order that the defendant pay the plaintiff's costs of this motion.
CATCHWORDS : COURTS - Orders - Construction - extension of time for compliance - no question of principle
LEGISLATION CITED : Suitors' Fund Act 1951 (NSW)
FAI General Insurance Company Limited v Southern Cross Exploration NL (1988) 165 CLR 268 CASES CITED : Magnate Projects Pty Ltd v Youma Constructions (No 2) Pty Limited [2005] NSWCA 331 Paino v Hofbauer (1988) 13 NSWLR 193
Magnate Projects Pty Limited (CAN 088 303 879) (Plaintiff) Youma Constructions (No 2) Pty Limited (ACN 082 889 674) (Defendant) PARTIES : Youma Constructions (No 2) Pty Limited ACN 082 889 674) (Cross-Claimant) Magnate Projects Pty Limited (CAN 088 303 879) (Cross-Defendant)
We try to embed the page this law was scraped from. If the site blocks framing, you still get the link and a local excerpt.
Last checked with source on —
Checking whether the official page can be embedded…
Plain-English simplify of this law: a short summary, key points, and both sides of the argument. Generated on first view via Replicate, then cached. Vote on what helps your study.
No study brief is cached for this law yet. Sign up to generate a plain-English brief.
Sign up to generate