CPD Holdings Pty Limited v Baguley [2016] NSWCATAP 103
NSW Caselaw
Full text
Select any passage to save a personal note with optional tags.
Civil and Administrative Tribunal
New South Wales
Medium Neutral Citation: CPD Holdings Pty Limited v Baguley [2016] NSWCATAP 103
Hearing dates: 16 March 2016
Date of orders: 12 May 2016
Decision date: 12 May 2016
Jurisdiction: Appeal Panel
Before: N Hennessy LCM, Deputy President
J Lucy, Senior Member
Decision: 1. Leave to appeal is granted in relation to the decision as to costs thrown away because of an adjournment.
2. The decision that "CPD Holdings Pty Limited, shall pay John Baguley and Daniella Baguley's costs in proceedings HB 13/27768 from 19 September 2013 Costs to be agreed or assessed on the usual basis" is set aside.
3. The application for costs in proceedings HB 13/27768 is to be reconsidered either with or without further evidence, in accordance with these reasons.
4. The decision that: "In proceedings HB 13/20778 each party is to pay their own costs" is set aside.
5. The application for costs in proceedings HB 13/20778 is to be reconsidered by the Tribunal, either with or without further evidence, in accordance with these reasons.
6. Within 28 days of the date of these reasons the parties are to file and serve any application for costs on appeal.
7. Within a further 14 days of receipt of any such application, the parties are to file and serve any submissions in reply.
8. If the Appeal Panel considers it appropriate taking into account any submission from the parties, any application for costs will be determined on the papers after that date.
Catchwords: APPEAL – costs decision in home building case – claims by both builder and homeowners – builder's claim settled – homeowners' claim determined – costs principles when proceedings settle – costs principles when proceedings determined
Legislation Cited: Civil and Administrative Tribunal Act 2013 (NSW), s 4, s 80
Consumer, Trader and Tenancy Tribunal Act 2001 (NSW) (repealed), s 53
Consumer, Trader and Tenancy Tribunal Regulation 2009 (NSW) (repealed), cl 20(4).
Category: Principal judgment
Parties: CPD Holdings Pty Limited (Appellant)
John Baguley (1st Respondent)
Daniella Baguley (2nd Respondent)
Representation: Solicitors:
George Aronstan, Solicitor & Attorney (Appellant)
Hancock Alldis & Roskov (Respondents)
File Number(s): AP 15/43112
Decision under appeal Court or tribunal: Civil and Administrative Tribunal
Jurisdiction: Consumer and Commercial Division
Date of Decision: 16 June 2015
Before: J Smith, Senior Member
File Number(s): HB 13/20778
HB 13/27768
reasons for decision
Overview
1. A builder has appealed from a costs decision in a home building dispute. The builder, CPD Holdings Pty Limited, and the homeowners, John and Daniella Baguley, had each brought proceedings against the other. The builder's claim settled on the afternoon of the second day of the hearing with the homeowners agreeing to pay the builder $24,818. The Tribunal determined the homeowners' claim in their favour for the amount of $34,598. That amount was set off against the amount of $24,818 that the homeowners agreed to pay to the builder. The net amount payable by the builder to the homeowners was $9,780.
2. The Tribunal ordered that each party pay their own costs in the builder's claim and that the builder pay the homeowners' costs in the homeowners' claim. The builder's primary submission on appeal is that each party should pay their own costs but that the homeowners should pay the builder's costs thrown away due to the adjournment of a two day hearing scheduled for 9 and 10 December 2013. Alternatively, the builder submitted that the homeowners should pay the costs in the builder's claim and the builder should pay the costs in the homeowners' claim apart from the costs thrown away by the adjournment which should be paid by the homeowners.
3. The three main grounds of appeal were that:
1. the Tribunal should have made one costs order in both proceedings, rather than two separate orders;
2. the Tribunal should not have rejected the builder's application that the homeowners should pay the costs thrown away as a result the adjournment of the hearing scheduled for 9 and 10 December 2013;
3. alternatively to ground 1, because the builder's case settled, the Tribunal should have applied the principles set out by the High Court in Minister for Immigration and Ethnic Affairs; Ex party Lai Qin (1977) 186 CLR 622 including the principle that if a party was almost certain to have succeeded if the matter had been determined, costs should be awarded in favour of that party.
1. We refuse leave for the builder to appeal on the first ground. There were two separate proceedings, one of which settled. Regardless of any preliminary view expressed by the Tribunal, the principles that apply when proceedings have settled are different from the principles that apply when proceedings are determined. The Tribunal was correct to deal with each costs application separately.
2. We grant leave to appeal on the second ground. The Tribunal made a finding about the reason for the adjournment but, when giving its reasons for rejecting the builder's costs application, it relied on a contradictory finding.
3. The third ground identifies a question of law and we have found that the Tribunal made an error. In its reasons for decision, the Tribunal correctly set out the legal principles as to costs when a matter settles: Minister for Immigration and Ethnic Affairs; Ex parte Lai Qin (1977) 186 CLR 622. One of those principles is that if one party is "almost certain to have succeeded" costs may be awarded in that party's favour. Despite finding that, "[i]t was clear from an early stage that the builder had a legitimate claim for payment," the Tribunal failed to consider whether, for that reason, this was an appropriate case in which to make a costs order.
Appeal Panel's jurisdiction
1. A decision "concerning the awarding of costs in proceedings" is an "ancillary decision": Civil and Administrative Tribunal Act 2013 (NSW) (NCAT Act), s 4. A party may appeal from such a decision "as of right on any question of law, or with the leave of the Appeal Panel, on any other grounds": NCAT Act, s 80(2)(b).
2. The Civil and Administrative Tribunal was established on 1 January 2014. The Tribunal was given jurisdiction over matters, such as the present matter, that had been commenced in the Consumer, Trader and Tenancy Tribunal ("CTTT"). The costs application was heard on 10 June 2015, but the proceedings were "part heard proceedings" because they had been adjourned part heard by the CTTT in December 2013: NCAT Act, Sch 1, cl 6(1) and 7. As such, while NCAT has jurisdiction to determine the application, "the provisions of any Act, statutory rule or other law that would have applied to or in respect of the proceedings … continue to apply": NCAT Act, Sch 1, cl 7(3)(b).
Tribunal's orders and decision
Orders
1. The Tribunal conducted a short hearing on costs on 10 June 2015. The Tribunal made the following orders on 16 June 2015:
1. CPD Holdings Pty Limited, shall pay John Baguley and Daniella Baguley's costs in proceedings HB 13/27768 from 19 September 2013 (the date legal representation was granted). Costs to be agreed or assessed on the usual basis. (Words in brackets added.)
2. In proceedings HB 13/20778 each party is to pay their own costs.
1. In summary, the builder was to pay the homeowners' costs in the builder's claim and each party was to pay that party's own costs in the homeowners' claim.
Identification of power to make costs order
1. The Tribunal correctly identified the source of its power to make a costs order as being s 53 of the Consumer, Trader and Tenancy Tribunal Act 2001 (NSW) (repealed). The effect of this provision is that the general rule in relation to costs in proceedings before the CTTT was that each party is to pay their own costs. However, "in any proceedings in respect of which the amount claimed or in dispute is more than $30,000, the Tribunal may award costs in relation to the proceedings in such circumstances as it thinks fit": Consumer, Trader and Tenancy Tribunal Act, s 53(2); Consumer, Trader and Tenancy Tribunal Regulation 2009 (NSW) (repealed), cl 20(4).
2. The Tribunal was satisfied that it had jurisdiction to award costs and this finding was not challenged on appeal.
Application for costs in the homeowners' claim
1. The Tribunal concluded at [37], that neither party had conducted themselves in such a way so as to justify an award of costs. Both parties had failed to comply with directions and had failed to particularise the factual and legal basis for their claims until they were legally represented.
2. At [38] the Tribunal rejected the builder's submission in relation to an alleged "Calderbank offer" made by letter of 16 May 2014. The Tribunal also rejected the builder's submission that costs should be awarded because the homeowners refused other offers of settlement.
3. The Tribunal relied on the legal principle set out in Latoudis v Casey (1990) 170 CLR 534 at [3] (per McHugh J) (footnotes omitted):
"An order for costs indemnifies the successful party in litigious proceedings in respect of liability for professional fees and out-of-pocket expenses reasonably incurred in connection with the litigation. The rationale of the order is that it is just and reasonable that the party has caused the other party to incur the costs of litigation should reimburse that party for the liability incurred. The order is not made to punish the unsuccessful party. Its function is a compensatory. Thus, in civil proceedings an order may, and usually will, be made even though the unsuccessful party has nearly succeeded or has acted reasonably in commencing the proceedings."
1. The Tribunal applied this principle at [43] concluding that:
"In this case it was necessary for the homeowners to pursue by litigation the award of $34,598 for which they were ultimately successful. It is reasonable that they now be compensated for the costs incurred in that litigation."
1. The Tribunal awarded costs in favour of the homeowners because:
1. the homeowners were ultimately successful on a substantial part of the claim ($34,598 compared with the initial claim of over $75,000); and
2. the builder did not offer to settle the matter by payment to them of $34,598 or more.
1. At [45] the Tribunal rejected the builder's claim that the homeowners should pay the costs thrown away as a result of the abandonment of the hearing scheduled for 9 and 10 December 2013. The Tribunal concluded that the adjournment was to enable the homeowners to file a new expert report. That was said to be necessary because of the builder's failure to file its expert evidence on time.
2. At [53] the Tribunal also ordered costs in relation to a directions hearing conducted on 1 July 2014.
Application for costs in the builder's claim
1. The Tribunal noted that the builder's claim had settled at the hearing. The parties agreed that this had occurred on the afternoon of the second day of hearing. The Tribunal found that the parties' motivation for settling the claim was not a relevant consideration. The Tribunal then quoted the following passages from Minister for Immigration and Ethnic Affairs; Ex Parte Lai Qin (1997) 186 CLR 622 at 624-625 (footnotes omitted):
"In an appropriate case, a court will make an order for costs even when there has been no hearing on the merits and the moving party no longer wishes to proceed with the action. The court cannot try a hypothetical action between the parties. To do so would burden the parties with the costs of a litigated action which by settlement or extra-curial action they had avoided. In some cases, however, the court may be able to conclude that one of the parties has acted so unreasonably that the other party should obtain the costs of the action.
. . .
Moreover, in some cases a judge may feel confident that, although both parties have acted reasonably, one party was almost certain to have succeeded if the matter had been fully tried."
1. The Tribunal expressed the view that it was clear from an early stage that the builder had a "legitimate claim for payment." The Tribunal went on at [50]:
"So much was made clear to the parties at a directions hearing on 1 August 2013. The builder was directed to clarify his claim and it was entirely possible that with some effort and goodwill the builder's claim could have been settled. Instead it escalated from $21,219 then in dispute to the $31,182.20 in dispute at the commencement of the hearing.
I am unable to say that either party acted so unreasonably in respect of the builder's claim that they are entitled to an award costs. Rather I am persuaded that this is a case in which the usual rule should apply that each party should pay its own costs."
Grounds of Appeal
Identification of grounds
1. In the Notice of Appeal the builder did not elect to appeal on a question of law. Leave was sought to appeal on other grounds: NCAT Act, s 80(2)(b). However, in supplementary submissions responding to questions posed by the Appeal Panel, the builder submitted that the Tribunal had made two errors of law. The first was to make two costs orders instead of one and the second was to fail to apply the principles in Re Minister for Immigration and Ethnic Affairs (Cth); Ex parte Lai Qin. While the second question is a question of law, the builder has not applied to amend the grounds of appeal to include the first question as a ground of appeal on a question of law. It would be prejudicial to the homeowners to treat the first purported ground of appeal as a question of law.
2. We will deal firstly with the applications for leave to appeal on grounds other than questions of law and then with the ground of appeal on a question of law raised by the Appeal Panel.
Leave to appeal on grounds other than questions of law
1. In appeals from decisions of the Consumer and Commercial Division, leave to appeal on grounds other than questions of law can only be granted in the limited circumstances set out in Schedule 4, cl 12(1) to the NCAT Act, which provides as follows:
"(1) An Appeal Panel may grant leave under section 80 (2) (b) of this Act for an internal appeal against a Division decision only if the Appeal Panel is satisfied the appellant may have suffered a substantial miscarriage of justice because:
(a) the decision of the Tribunal under appeal was not fair and equitable , or
(b) the decision of the Tribunal under appeal was against the weight of evidence, or
(c) significant new evidence has arisen (being evidence that was not reasonably available at the time the proceedings under appeal were being dealt with)."
1. The meaning of "substantial miscarriage of justice" was summarised by the Appeal Panel in Collins v Urban [2014] NSWCATAP 17 at [71] and [79]. The Appeal Panel stated (at [71]) that the concept of a substantial miscarriage of justice refers to a failure in the way a matter was conducted or decided which deprived the appellant of a chance that was fairly open of achieving a better outcome than occurred. The Appeal Panel also stated (at [79]) that in order to show that a party may have been deprived of a "significant possibility" or a "chance which was fairly open" of achieving a different and more favourable result it would generally be necessary for the party to explain what its case would have been and show that it was fairly arguable. If the party failed to do this, even if there has been a denial of procedural fairness, the Appeal Panel may conclude that it is not satisfied that any substantial miscarriage of justice may have occurred.
2. Where leave to appeal is required, the general principles to be applied in determining whether or not leave to appeal should be granted were set out in Collins v Urban at [84] as follows:
"(1) In order to be granted leave to appeal, the applicant must demonstrate something more than that the primary decision maker was arguably wrong in the conclusion arrived at or that there was a bona fide challenge to an issue of fact: BHP Billiton Ltd v Dunning [2013] NSWCA 421 at [19] and the authorities cited there, Nakad v Commissioner of Police, NSW Police Force [2014] NSWCATAP 10 at [45];
(2) Ordinarily it is appropriate to grant leave to appeal only in matters that involve:
(a) issues of principle;
(b) questions of public importance or matters of administration or policy which might have general application; or
(c) an injustice which is reasonably clear, in the sense of going beyond merely what is arguable, or an error that is plain and readily apparent which is central to the Tribunal's decision and not merely peripheral, so that it would be unjust to allow the finding to stand;
(d) a factual error that was unreasonably arrived at and clearly mistaken; or
(e) the Tribunal having gone about the fact finding process in such an unorthodox manner or in such a way that it was likely to produce an unfair result so that it would be in the interests of justice for it to be reviewed."
Costs orders 1 and 2 are not fair and equitable
1. The builder framed its grounds of appeal and submissions as applying to both the first order, that the builder pays the homeowners' costs from 19 September 2013 in the homeowners' claim, and the second order, that each party pay that party's own costs in the builder's claim.
2. At [114] and [115] of the principal decision (CPD Holdings Pty Ltd t/as The Bathroom Exchange v John Baguley and Daniela Baguley (HB 13/20778) and John Baguley and Daniela Baguley v CPD Holdings Pty Ltd t/as The Bathroom Exchange (HB 13/27768), unreported, 11 July 2013), the Tribunal set out its preliminary view that, because both parties had had some success with their respective applications, each party should pay their own costs.
"In an attempt to avoid the parties being involved in further disputation in regard to costs I have expressed below a preliminary view of how the issue should be resolved. If there are matters of which I am unaware that prevents resolution I have made directions to allow further ventilation of the issue.
Both parties have had some success with their respective applications. However, the two day hearing on 9 and 10 December 2013 was adjourned because of the owners' election to rely on different expert evidence. It would therefore appear to be appropriate that the owners' pay the builder's costs thrown away due to that adjournment. Otherwise, it would be my preliminary view that each party should pay their own costs."
1. It transpired that the parties did not settle the costs issue and a hearing then took place. The builder's submissions on costs addressed costs generally and did not differentiate between the two matters. That is because it was the builder's impression that the Tribunal had expressed a preliminary view that there would only be one costs order. If the builder had that impression it was not justified on the basis of the passage quoted above. The only preliminary view the Tribunal expressed was that each party should pay their own costs and that the homeowners should pay the builder's costs thrown away due to the adjournment.
2. At the costs hearing, the Tribunal asked the homeowners' solicitor whether it would be feasible to determine the costs in relation to the homeowners' application and to isolate that from the costs associated with the preparation of the builder's application. The homeowners' solicitor said that it would be unfair to the builder to deal with the costs of each application separately. That was said to be the case because the decision to settle the builder's case was made late on the second day of the hearing without any regard to costs. The homeowners' solicitor went on to say that because the matter was dealt with as two applications together in the one hearing, the costs application should be dealt with on the same basis.
3. The builder interpreted these statements to be a concession by the homeowner that there should only be one order for costs in relation to both proceedings. The builder submitted that at no stage during the costs hearing did the Tribunal indicate to the parties that it was his intention to depart from his previous view that there should be just one costs order. Because of the ramifications of this fundamental change, it was submitted that procedural fairness required that the builder be informed of the Tribunal's changed position and be given the opportunity to obtain legal advice and make submissions on that issue.
Consideration
1. The Tribunal is subject to the rules of procedural fairness: Consumer, Trader and Tenancy Tribunal Act 2001 (NSW) (repealed), (repealed), s 28(2). Departure from the way in which the parties conduct their cases, without giving them an opportunity to make submissions about this, may amount to a breach of procedural fairness. In Pantorno v R (1989) 166 CLR 466, Mason CJ and Brennan J said at 473:
"When the parties to an adversarial proceeding agree on a proposition of law and conduct their cases on that basis, their agreement does not bind the trial judge. If the judge determines the law to be different, he may apply the law as he determines it to be, but he must inform the parties of the view he has formed when that is necessary to give them an opportunity to address new issues arising from the judge's departure from the proposition of law on which the case was conducted. Otherwise both parties are taken by surprise: see Fairmount Ltd v Environment Secretary [1976] 1 WLR 1255 at 1265–1266."
1. In Seltsam Pty Limited v Ghaleb [2005] NSWCA 208 at [78], after referring to this passage and other relevant case law, Ipp JA referred to "the general principle that although the basis on which the parties conduct a trial does not bind the judge, if the judge contemplates determining the case on a different basis he or she must inform the parties of this prospect so that they have an opportunity to address any new or changed issues that may arise".
2. At the hearing on costs the Tribunal asked the homeowners' solicitor whether it would be feasible to determine the costs in relation to the homeowners' application and to isolate that from the costs associated with the preparation of the builder's application. The question was not whether the Tribunal was legally bound to treat the costs applications in a particular way. The homeowners' submission was that it would be unfair to do so. The Tribunal ultimately rejected that view.
3. This is not a case where the parties agreed on a proposition of law and the Tribunal departed from that proposition without giving the parties an opportunity to address any new issues. The relevant proposition of law was that the Tribunal may award costs in relation to the proceedings in such circumstances as it thinks fit. No party ever submitted that the Tribunal must, as a matter of law, determine the applications in each proceeding together.
4. The Tribunal did not breach the rules of procedural fairness in this case. It invited the parties' to make submissions on a particular issue and, although the parties agreed as to the approach the Tribunal should take, it ultimately decided to take a different approach.
5. The builder relied on an unreported decision of Li v MACD Developing Pty Ltd (Civil and Administrative Tribunal, unreported, 27 May 2015). In that case, the Member stated at [14] and [15], that:
"The builder has submitted that the Tribunal should hear its costs applications in the owners' proceedings and in the cross application together.
I am satisfied that it is appropriate to hear the two costs applications as one because the proceedings were heard together and it is difficult if not impossible to identify the time that was taken up with evidence on the owners' proceedings as opposed to time that was taken up with evidence on the cross application.
The net outcome of the two sets of proceedings was that the builder recovered $23,856.86 ($32,299.90 - $8,443.04 = $23,856.86)."
1. It is not necessary to determine the correctness of this approach because the facts in these proceedings are materially different. In this case the builder's claim settled with no agreement as to costs while the homeowners' claim was determined by the Tribunal. As is clear from the High Court's decision in Minister for Immigration and Ethnic Affairs; Ex parte Lai Qin (1977) 186 CLR 622, the legal principles that apply to an application for costs when proceedings are settled are different from those that apply following a contested hearing. The Tribunal in this case would have fallen into error if it had applied the same principles to both proceedings.
2. The Tribunal did not breach the rules of procedural fairness and there is no other basis for granting leave to appeal on this ground.
Refusal to order costs for adjourned hearing is not fair and equitable
Tribunal's decision
1. In the reasons for decision at [17] and [22], the Tribunal recited the builder's submission that the adjournment was necessary because of the homeowners' abandonment of their reliance on the expert report of Mr Grieve and the subsequent reliance on a new report by Mr Stanton. The Tribunal acknowledged that, according to the builder, it was the change of expert witness by the homeowners and not any late filing by the builder which led to the adjournment. The Tribunal found at [26] that:
"When the matter came before the Tribunal for hearing on 9 and 10 December 2013 the home-owners, then legally represented, sought to resile from an expert report previously filed and upon which their claim was based and instead to rely on a new report only recently made available to the builder. The hearing was necessarily abandoned and directions were made."
1. The Tribunal did not refer to this finding when giving its reasons for rejecting the builder's claim that it should be entitled to the costs thrown away as the result of the abandonment of the hearing dates. That reason was set out at [45] and [46]:
"The homeowners claim that the new expert report became necessary due to the builder's failure to file its expert evidence until 6 November 2013 and to serve it until 14 November 2013 in contravention of the Tribunal's directions. That issue was not raised at the time but the non-compliance with directions was not denied by the builder's representative.
In those circumstances I am not satisfied that any additional order should be made to vary the conclusion reached above that the owners have their costs."
Submissions
1. The Tribunal's findings at [45] and [46] are said by the builder to be perverse and not fair and equitable for nine reasons which can be summarised as follows:
1. the Tribunal assumed incorrectly that the builder's expert evidence was served two weeks late when it was only served one week late; and
2. the real need for the adjournment arose not because the evidence was served late but because the homeowners served new expert evidence in chief on the builder on the day of the hearing. They did so because they were unable to reach commercially acceptable arrangements with the previous expert.
1. The homeowners agree that their second expert report, the Cass report, was received 7 days after the due date for service.
2. The builder submitted that the homeowners originally provided an expert report from Mr Grieve in respect of defects as part of their case in chief. On 19 September 2013, the matters were adjourned for a two-day hearing on 9 and 10 December 2013. The Tribunal directed that the builder provide an expert report in reply to the Grieve report by 30 October 2013 and leave was given to the owners to provide short evidence in reply by 29 November 2013.
3. The builders filed an expert report from Mr Cass on 6 November 2013. The owners received that report on 7 November 2013. The evidence was filed one week late. The builder submitted that it would have been reasonable to extend the date for compliance by the owners by one week to 6 December 2013 if an extension was requested. According to the builder, the owners did not request an extension. The owners did not provide evidence in reply in compliance with the Tribunal's order by 19 September 2013.
4. On the morning of the hearing on 9 December 2013, the owners did not appear with Mr Grieve. Instead they appeared with another expert, Mr Stanton. The homeowners' solicitor advised the Tribunal that Mr Stanton had replaced Mr Grieve and that the homeowners no longer relied on the Grieve report. Mr Stanton's report and Scott Schedule were filed and served at that time. The Tribunal was also informed that Mr Grieve was not available for cross-examination. The builder's solicitor objected to the Stanton report on the basis that it was not evidence in reply to the Cass report, but rather new evidence in chief.
5. The Tribunal said that it would admit the Stanton report and adjourn the proceedings to give the builder the opportunity to respond to that report. In relation to costs, the Member said:
"It's looking as though we could adjourn the matter today. Mr and Mrs Baguley would finish up paying the cost of that adjournment because of the late provision of documentation, failing to comply with the Tribunal's directions."
1. The solicitor for the homeowners submitted that the reason for the adjournment was the late provision of evidence by the builder but the Tribunal rejected that submission at p 13 of the 9 December 2013 transcript:
"Except that the (Stanton) report replaces the (Grieve) report that you're now no longer relying upon. It's your evidence in chief; instead of being your short evidence in reply it's evidence in chief, and would inevitably require a response from Mr Cass."
1. The Tribunal then made the following directions:
1. The Tribunal notes the homeowners no longer rely on the report of Mr Grieve but rely on the report of Mr Stanton handed up at the hearing on 9 December 2013;
2. The costs thrown away due to this adjournment are reserved.
1. At [10] of the principal decision the Tribunal noted:
"The matters were again adjourned for the builder's expert to consider the Stanton report. The issue of costs was reserved."
1. At [115] of the principal decision the Tribunal expressed the preliminary view that:
"However, the two-day hearing on 9 and 10 December 2013 was adjourned because of the owners' election to rely on different expert evidence. It would therefore appear to be appropriate that the owners pay the bills as costs thrown away due to that adjournment."
1. In the homeowners' submissions on costs, the following admission was made at [25]:
"Anthony Grieve was the owners' expert. The owners were unable to reach commercially acceptable arrangements for Mr Grieve to prepare his report in reply to Mr Cass's report. Accordingly, Mr Stanton was instructed to prepare a report in reply."
1. According to the builder, the second statement is incorrect because the report was not a report in reply. It was new evidence in chief to which the builder was entitled to have his expert respond.
2. At [26] of the homeowners' submission on costs it was stated that:
"Due to Mr Stanton's previous commitments he was unable to provide his report by 29 November 2013 and accordingly the owners failed to comply with this order."
1. At the costs hearing on 10 June 2015 the homeowners' solicitor told the Tribunal that they did not resile from their written submissions or seek to change them. However, according to the builder, the homeowners' solicitor then proceeded to contradict his written submissions because:
1. contrary to what was said at [23] of the written submissions, the homeowners' solicitor said that the Cass report was lodged two weeks late on 14 November 2013, instead of one week late on 7 November 2013;
2. contrary to what was said at [25] of the written submissions, the homeowners' solicitor stated the following: "I'm not going to go into the reasons why Mr Grieve was unable, but he was unable to provide his report."
3. contrary to what was said at [25] of the written submissions, the homeowners' solicitor attempted to suggest again that the late service of the Cass report was the cause of the hearing date being vacated rather than the fact that the homeowners had been unable to reach commercially acceptable arrangements with Mr Grieve.
Consideration
1. We are satisfied that the builder may have suffered a substantial miscarriage of justice because the Tribunal's decision on this issue was not fair and equitable.
2. The Tribunal made a fact finding error when it found that the builder's expert evidence was not served until 14 November 2013. It was served on 7 November 2013, 7 days late. More significantly, the Tribunal made a finding of fact at [26] that the hearing was "necessarily abandoned" because the homeowners sought to resile from an expert report previously filed and instead to rely on a new report. Having made that finding, it did not refer to it or take it into account when determining whether the homeowners should pay the builder's costs thrown away because of the adjournment. Instead, the Tribunal made a contradictory finding of fact that the adjournment was necessary due to the builder's failure to file its expert evidence on time.
3. The injustice is clear and central to the Tribunal's decision. The Tribunal should reconsider the builder's application for costs thrown away by the adjournment. We have not upheld any of the grounds of appeal that otherwise relate to the application for costs in the homeowners' claim.
Application of the principles in Minister for Immigration and Ethnic Affairs; Ex parte Lai Qin
1. The builder made the point in its original written submissions that McHugh J in Ex parte Lai Qin held that, when proceedings are settled, "in some cases a judge may feel confident that although both parties have acted reasonably, one party was almost certain to have succeeded if the matter had been fully tried." The builder also noted that the Tribunal found at [50] that:
"It was clear from an early stage that the builder had a legitimate claim for payment. So much was made clear to the parties at a directions hearing on 1 August 2013."
1. Having considered those submissions when determining the appeal on the papers, we invited the parties to make short written submissions on the following questions:
1. did the Tribunal make an error of law in failing to consider, in accordance with the principles in Re Minister for Immigration and Ethnic Affairs (Cth); Ex parte Lai Qin [1997] HCA 6; (1997) 186 CLR 622 at [7] and [8], whether the builder was almost certain to have succeeded in his claim if the matter had been fully tried?
2. if so, should the Appeal Panel consider that question?
3. if so, how should the Appeal Panel answer that question given the Tribunal's finding that the builder had a legitimate claim for payment?
1. The Appeal Panel conducted a short hearing focusing on these questions on 16 March 2016 and directed the parties to file and serve submissions.
2. Despite attempting to distinguish the decision in Ex parte Lai Qin in its original written submissions, the builder submitted, in supplementary submissions, that the Tribunal had erred by not applying the principles in that case.
3. The homeowners submitted that the Tribunal had not made an error of law because it is not certain that the builder would have succeeded in its claim if the matter had been fully tried. The Tribunal was not required to make any findings of fact in regard to the builder's application or determine when, and in what circumstances the contract was terminated. According to the homeowners, those circumstances make it unlikely that the Tribunal could determine that the builder would almost certainly have succeeded in its application. The homeowners also emphasised McHugh J's comment, not included in the Tribunal's quote from the decision (at [20] above), that "...such cases are likely to be rare."
4. The Tribunal may award costs in relation to the proceedings in such circumstances as it thinks fit (Consumer, Trader and Tenancy Tribunal Act, s 53(2) and (3)(a); Consumer, Trader and Tenancy Tribunal Regulation, cl 20(4)). In Wright v Foresight Constructions [2011] NSWCA 327, the Court of Appeal said of the CTTT's costs power:
"A power conferred in these terms is 'unfettered' in the sense that the Tribunal may make such order as it thinks appropriate, so long as it acts in accordance with the subject matter, scope and purpose of the power. In relation to the award of costs in litigation, the accepted purpose is, where costs are awarded in favour of one party, to compensate that party for the expense incurred in respect of the litigation."
1. A costs discretion must not only be exercised judicially but in accordance with general legal principles. In Knight v FP Special Assets Ltd [1992] HCA 28; (1992) 174 CLR 178, Mason CJ and Deane J said at 192:
"The wide jurisdiction conferred by the (costs) rule "must be exercised judicially and in accordance with general legal principles pertaining to the law of costs", to take up the words of Lambert 1.A. in Oasis Hotel Ltd. v. Zurich Insurance Co." (Word in brackets added and footnotes omitted.)
1. The power to award costs when proceedings have settled is also unfettered but must be exercised judicially and in accordance with general legal principles pertaining to the law of costs.
2. The exercise of a judicial discretion, such as the discretion to award costs, is appellable according to the criteria set out in House v R (1936) 55 CLR 499 at 505:
"If the judge acts upon a wrong principle, if he allows extraneous or irrelevant matters to guide or affect him, if he mistakes the facts, if he does not take into account some material consideration, then his determination should be reviewed and the appellate court may exercise its own discretion in substitution for his if it has the materials for doing so."
1. The Tribunal correctly identified the legal principles set out by the High Court in Minister for Immigration and Ethnic Affairs; Ex parte Lai Qin (1977) 186 CLR 622 but acted on a wrong principle or did not act on all the correct principles pertaining to the law of costs. It considered whether it could be concluded that one of the parties had acted so unreasonably that the other party should obtain the costs of the action. But despite finding that the builder had a legitimate claim for payment, the Tribunal failed to consider whether costs should be awarded on the basis that one party was almost certain to have succeeded if the matter had been fully tried.
2. The next question posed by the Appeal Panel was whether we should consider that question and, in effect, re-exercise the costs discretion. The builder said that we should do so. The homeowners disagreed.
3. The Appeal Panel has the power to decide to deal with an internal appeal by way of a new hearing if it considers that the grounds for the appeal warrant a new hearing: NCAT Act, s 80(3). The Panel also has power to permit fresh evidence if it considers it appropriate in the circumstances: NCAT Act, s 80(3). This is a matter which has a lengthy history and if it were appropriate for the Appeal Panel to conduct a new hearing on this question we would do so. Unfortunately it is not.
4. The question that needs to be determined is whether the homeowners should be ordered to pay the costs in the builder's claim on the basis that the builder was almost certain to have succeeded if the matter had been fully tried. While the Tribunal expressed the view that "It was clear from an early stage that the builder had a legitimate claim for payment", it did not direct its mind to this question.
5. The Appeal Panel could read transcript and accept fresh evidence on this issue, but the Member who heard the substantive case up to the time when it settled and who expressed the view that the builder had a legitimate claim, is in a better position than the Appeal Panel to re-exercise that discretion. We anticipate that that can be done without further submissions or evidence from the parties, but that is a matter for the Tribunal below.
Orders
1. Leave to appeal is granted in relation to the decision as to costs thrown away because of an adjournment.
2. The decision that "CPD Holdings Pty Limited, shall pay John Baguley and Daniella Baguley's costs in proceedings HB 13/27768 from 19 September 2013. Costs to be agreed or assessed on the usual basis" is set aside.
3. The application for cost in proceedings HB 13/27768 is to be reconsidered either with or without further evidence, in accordance with these reasons.
4. The decision that, "In proceedings HB 13/20778 each party is to pay their own costs" is set aside.
5. The application for costs in proceedings HB 13/20778 is to be reconsidered by the Tribunal, either with or without further evidence, in accordance with these reasons.
6. Within 28 days of the date of these reasons the parties are to file and serve any application for costs on appeal.
7. Within a further 14 days of receipt of any such application, the parties are to file and serve any submissions in reply.
8. If the Appeal Panel considers it appropriate taking into account any submission from the parties, any application for costs will be determined on the papers after that date.
**********
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
Registrar
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Decision last updated: 12 May 2016