NSW Caselaw
Land and Environment Court New South Wales
Medium Neutral Citation: Precise Planning v Wollondilly Shire Council [2017] NSWLEC 1142 Hearing dates: Conciliation conference on 21 December 2017 Date of orders: 23 March 2017 Decision date: 23 March 2017 Jurisdiction: Class 1 Before: Dixon C Decision: See (4) below Catchwords: DEVELOPMENT APPLICATION: conciliation conference; agreement between the parties; orders Legislation Cited: Land and Environment Court Act 1979 Category: Principal judgment Parties: Precise Planning (where leave granted below: Alora Davies Developments 101 Pty Ltd) (Applicant) Wollondilly Shire Council (Respondent) File Number(s): 2016/283115 Publication restriction: No
Judgment 1. COMMISSIONER: In this matter, at or after a conciliation conference, an agreement under s 34(3) of the Land and Environment Court Act 1979 (the Court Act) was reached between the parties as to the terms of a decision in the proceedings that was acceptable to the parties. As the presiding Commissioner, I was satisfied that the decision was one that the Court could have made in the proper exercise of its functions (this being the test applied by s 34(3) of the Court Act). As a consequence, s 34(3)(a) of the Act required me to "dispose of the proceedings in accordance with the decision". 2. The Court Act also required me to "set out in writing the terms of the decision" (s 34(3)(b)). The orders made to give effect to the agreement constitute that document. 3. In making the orders to give effect to the agreement between the parties, I was not required to make, and have not made, any merit assessment of the issues that were originally in dispute between the parties. 4. The final orders to give effect to the parties' agreement under s34(3) of the Land and Environment Court Act 1979 are: 1. Leave is granted to the Applicant to amend the name of the Applicant in the proceedings to Alora Davies Developments 101 Pty Ltd; 2. Leave is granted to the Applicant to rely on the following amended plans: Plan Title Author/Drawn By Plan Reference Dated Plan of Subdivision of Lot 4 DP 245153 Paul Brandon Surveyor's Ref 151108 14 September 2016 Rev B Development Overview and Viewport Reference Plan Martens & Associates Pty Ltd Project No. P1605138 9 February 2017 Revision H PS02A050 Sediment & Erosion Control Plan Martens & Associates Pty Ltd Project No. P1605138 9 February 2017 Revision D PS02- B300 Sediment & Erosion Control Details Martens & Associates Pty Ltd Project No. P1605138 9 September 2016 Revision A PS02-B310 Earthwork Grading Plan Martens & Associates Pty Ltd Project No. P1605138 9 February 2017 Revision H PS02-C100 Earthwork Section A-A Martens & Associates Pty Ltd Project No. P1605138 9 February 2017 Revision D PS02-C200 Earthwork Section B-B Martens & Associates Pty Ltd Project No. P1605138 9 February 2017 Revision C PS02-C201 Earthwork Section C-C Martens & Associates Pty Ltd Project No. P1605138 9 February 2017 Revision A PS02-C202 Earthwork Section D-D Martens & Associates Pty Ltd Project No. P1605138 9 February 2017 Revision A PS02-C203 Earthwork Section E-E Martens & Associates Pty Ltd Project No. P1605138 9 February 2017 Revision A PS02-C204 Earthwork Section F-F Martens & Associates Pty Ltd Project No. P1605138 9 February 2017 Revision A PS02-C205 Earthwork Cut & Fill Plan Martens & Associates Pty Ltd Project No. P1605138 9 February 2017 Revision G PS02-C600 Roadworks Plan Martens & Associates Pty Ltd Project No. P1605138 9 February 2017 Revision E PS02-D100 21-MRC01 Longitudinal & Typical Section Martens & Associates Pty Ltd Project No. P1605138 10 January 2017 Revision D PS02-D200 21-MRC02 Longitudinal & Typical Section Martens & Associates Pty Ltd Project No. P1605138 10 January 2017 Revision C PS02-D201 Drainage Plan Martens & Associates Pty Ltd Project No. P1605138 9 February 2017 Revision I PS02-E100 Drains Modelling Catchment Plan and Layout Result Martens & Associates Pty Ltd Project No. P1605138 9 February 2017 Revision E PS02-E610 MUSIC Catchment Plan, Model Layout & Results Martens & Associates Pty Ltd Project No. P1605138 9 February 2017 Revision G PS02-E701 Longitudinal Section of Retaining Wall along Northern Boundary Martens & Associates Pty Ltd Project No. P1605138 9 February 2017 Revision A PS02-G210 Longitudinal Section of Retaining Wall along Southern Boundary Martens & Associates Pty Ltd Project No. P1605138 9 February 2017 Revision A PS02-G211
We try to embed the page this law was scraped from. If the site blocks framing, you still get the link and a local excerpt.
Last checked with source on —
Checking whether the official page can be embedded…
Plain-English simplify of this law: a short summary, key points, and both sides of the argument. Generated on first view via Replicate, then cached. Vote on what helps your study.
No study brief is cached for this law yet. Sign up to generate a plain-English brief.
Sign up to generate