Tasmanian Legislation
Gas Pipelines (Pipeline Corridor) Ulverstone Order 2014
I make the following order under section 70B of the Gas Pipelines Act 2000 .
14 October 2014
MATTHEW GROOM
Minister for Energy
1. Short title This order may be cited as the Gas Pipelines (Pipeline Corridor) Ulverstone Order 2014 .
2. Commencement This order takes effect on the day on which its making is notified in the Gazette.
3. Interpretation In this order – Act means the Gas Pipelines Act 2000 .
4. Planning corridor (1) In this clause – pipeline means the pipeline that – (a) is referred to in the pipeline licence granted under section 10 of the Act to Tas Gas Networks Pty Ltd on 28 May 2012, as amended; and (b) extends from – (i) the Ulverstone Offtake Facility and terminates at the point situated at 429,562.4E and 5,441,913.0N; and (ii) the point situated at 429,562.4E and 5,441,913.0N and terminates at the Simplot Plant in Mason Street, Ulverstone; and (c) is shown bounded by a heavy, black, broken line on Plan 9756 in the Central Plan Register, a reduced copy of which is set out, by way of illustration only, in Schedule 1 to this order. (2) A planning corridor is declared in respect of the pipeline. (3) The planning corridor declared in respect of the pipeline – (a) extends along the length of the pipeline and is – (i) for so much of the pipeline as is referred to in paragraph (b)(i) of the definition of pipeline in subclause (1) of this clause – 150 metres wide on each side of the pipeline; and (ii) for so much of the pipeline as is referred to in paragraph (b)(ii) of the definition of pipeline in subclause (1) of this clause – 38 metres wide on each side of the pipeline; and (b) extends – (i) away from the end of the pipeline situated at the Ulverstone Offtake Facility in a semicircle with a radius of 150 metres from the centre-line at that end of the pipeline; and (ii) away from the end of the pipeline situated at the Simplot Plant in Mason Street, Ulverstone in a semicircle with a radius of 38 metres from the centre-line at that end of the pipeline. (4) For the purposes of subclause (3)(a) of this clause, the width of each side of the planning corridor in respect of the pipeline is measured – (a) from the centre-line of the pipeline; and (b) at a right angle from the centre-line of the pipeline.
We try to embed the page this law was scraped from. If the site blocks framing, you still get the link and a local excerpt.
Last checked with source on —
Checking whether the official page can be embedded…
Plain-English simplify of this law: a short summary, key points, and both sides of the argument. Generated on first view via Replicate, then cached. Vote on what helps your study.
No study brief is cached for this law yet. Sign up to generate a plain-English brief.
Sign up to generate