ATLANTIC CIVIL PTY LTD v WATER ADMINISTRATION MINISTERIAL CORPORATION [1996] NSWCA 26
NSW Caselaw
Full text
Select any passage to save a personal note with optional tags.
ATLANTIC CIVIL PTY LTD v WATER ADMINISTRATION
MINISTERIAL CORPORATION
SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL
GLEESON CJ, MAHONEY P and BEAZLEY JA
4 June 1996, 4 June 1996
[1996] NSWCA 26
CONTRACT — CONSTRUCTION — no question of general principle involved.
In a dispute between a contractor and a public authority there was a dispute as to the
interpretation of a clause in the contract - HELD - The interpretation of the primary judge
was correct - No question of general principle involved.
(After judgment on the first issue in the appeal, the case was settled).
Gleeson CJ This is an appeal from a decision of Giles J in a case that was
placed in the Court's Construction List back in 1991.
The appellant entered into a contract with the respondent to construct a flood
protection levee at Denman on the Hunter River. The contract was in part a lump
sum contract and in part a schedule of rates contract. The part with which we are
presently concerned involved a schedule of rates.
Following the completion of the construction of the levee the appellant made
a number of claims against the respondent and the claims that are relevant to the
present appeal and cross-appeal fall broadly into two categories. The first
category of claims relates to a contention on the part of the appellant that it was
entitled to additional payment in respect of stripping operations of a kind that will
be described further in these reasons for judgment. The second category of claims
related to a contention on the part of the appellant that it had encountered certain
latent conditions in respect of which it was entitled to additional payments under
the contract. With one qualification, the appellant's contentions in respect of the
second category of claims were accepted by the referee and by Giles J. The
qualification can be put to one side for the moment. It forms a part of the appeal
on which we have not yet heard argument.
In relation to the first category of claims the appellant was successful before
the referee, but the referee's report in this respect was rejected by Giles J on the
ground that his Honour disagreed with the referee's interpretation of the relevant
contractual provisions. The respondent has cross-appealed in relation to the
appellant's success, or substantial success, on the latent conditions aspect of the
case. It has been convenient before hearing any argument in relation to the latent
conditions aspect of the case to hear argument from both sides in relation to the
stripping claims. It is that aspect of the case with which these reasons are
intended to deal.
Item 1 in the contract was described as follows:
"Stripping and stockpiling of topsoil, and excavation of other unsuitable
materials, and their stockpiling or disposal as directed by the superintendent."
A unit rate per metre was specified in relation to that item. As was explained
by Jacobs P in Arcos Industries Pty Ltd v The Electricity Commission of New
South Wales (1973) 2 NSWLR 186 at 193, a schedule of rates contract is used
in circumstances where the parties are uncertain as to the quantities with which
2 UNREPORTED JUDGMENTS
a contractor has to deal. So it was in the present case that the contract referred
only to an estimated quantity which would be the subject of this item of work.
The ultimate dispute between the parties turns upon the manner in which the
actual quantity to which the specified unit rate was to be applied is to be
calculated.
The resolution of the dispute turns upon the construction of CLS2-3 of the
contract which is in the following terms:
"S2-3 STRIPPING
(1) The entire areas to be excavated for the pipe culverts and the retaining wall
or to be covered by the levee shall be stripped to a depth of 50mm or as
determined by the Superintendent, to remove all unsuitable materials. The
unsuitable materials shall include all debris, sand, topsoil, vegetable matter and
root affected material and all other perishable and objectionable materials that
may be unsuitable for use for permanent construction required under this
Specification, or that might interfere with the proper bonding of the levee with
the foundation, or the proper compaction of the materials in the levee, or that may
be otherwise objectionable as determined by the Superintendent.
(2) Where so directed by the Superintendent the Contractor shall excavate a
cut-off trench to a depth unaffected by desiccation cracks as shown on the
Drawings.
(3) Material so stripped and excavated shall be dumped and spread in disposal
areas approved by the Superintendent. Selected topsoil as described in CLS3-7
shall be temporarily stockpiled for subsequent spreading upon the faces of the
levee so at to facilitate the establishment of vegetation.
(4) Payment for stripping of topsoil, excavation of other unsuitable material
and excavation of material for cut-off trenches including stockpiling and disposal
thereof will be made at the unit rate tendered for Item 1 in the Schedule of Rates.
Measurement for payment will be made in excavation only to the lines or batters
shown on the Drawings or as directed by the Superintendent."
More particularly the resolution of the issue turns upon the meaning of the last
sentence of CLS2-3(4) read in the light of the opening sentence of CLS2-3(1)
The evident purpose of these provisions is to provide a reasonable measure of
certainty in the estimation of the quantities by reference to which the appellant
was entitled to be paid for the stripping operation. The drawings which formed
part of the contract showed what was required of the appellant, and, consistently
with the first sentence of CLS2-3, showed that the area on which the levee was
to be constructed was to be stripped to a depth of 50mm or, as was said in some
of the drawings, a minimum of 50mm. In this respect it is significant to note that
the first sentence of CLS2-3 contemplated that the Superintendent might
determine that the areas were to be stripped at least in places to a greater depth
than 50mm.
Both the referee and Giles J took the view that something in the case also
turned upon the construction of CLS3-10 which deals with a cognate issue. That
clause is in the following terms:
"S3-10 MEASUREMENTS AND PAYMENTS
(1) Measurement for payment will be made to the lines and batters specified
on the Drawings or as directed by the Superintendent, and on a basis of cross
sections taken after stripping as specified in CLS2-3 and subject to SS15. The
topsoil spread on the levee will not be included in this measurement.
URUANTIC CIVIL PTY LTD v WATER ADMINISTRATION MINISTERIAL CORPORATION
(Gleeson CJ)
(2) Payment for supplying, placing and compacting Zone | material in the
levee and access ramps except for the sections of the levee included for payments
of items 3-6. will be made at the unit rate tendered for Item 2 in the Schedule of
Rates. This unit rate shall include the cost of all operations required by this
specification including supplying as applicable and spreading and placing of
topsoil and pavement gravel, Borrow Area excavations, transportation of the
materials to the site, and Borrow Area trimming and restoration.
(3) The cost of supplying, placing and compacting Zone 2A and 2B materials,
shall be included in the lump sum price tendered for Item 6 in the Schedule of
Rates.
(4) Payment for supply and placing Zone 3 material on the water face of the
levee where shown on the Drawings or directed by the Superintendent except for
the sections of the levee included for the payment at Item 6 will be made at the
Unit Rate tendered for Item 8 in the Schedule of Rates. This Unit Rate shall
include the cost of all operations required by this Specification including
processing of the rocks stored at the quarry site and its transportation to the site."
The point of departure between the referee, who adopted the appellant's
construction of CLS2-3 and Giles J, who adopted the respondent's construction,
may be summarised as follows. There was no dispute between the parties
concerning situations in which excavation to a depth below 50mm had taken
place pursuant to a direction of the Superintendent. The dispute arose because
there were many situations in which the excavation had been to a depth below
50mm but not pursuant to a direction of the Superintendent. The referee
construed the concluding sentence in CLS2-3(4) as meaning in effect the
contractor is entitled to be paid for the stripping of such material as was removed
and as it was reasonably necessary to remove without carelessness to get to a
depth of 50mm. The referee expressed his views as follows:
"\,.upon the true construction of the contract the plaintiff is entitled to be paid
for all stripping measured to the lines and batters shown on the drawings and
where there is no specific direction to go deeper an excavation which ensures
minimum of 50mm depth but is also entitled to be paid for stripping in places in
excess of that depth being in accordance with the lines shown on the drawings
(which provided for "50mm') provided that this stripping has not been excavated
carelessly so as to involve stripping more than was reasonably necessary to
achieve a 50mm minimum depth of stripping in the circumstances... "
As part of the factual background to that conclusion the referee recorded the
following observations:
150.4 Such directions by the Superintendent's Representative were either oral
or written.
150.5 The Superintendent's Representative inspected all the stripping and
approved it or directed further stripping where he considered that necessary. After
any further stripping was done the Superintendent's Representative inspected and
approved it if he was satisfied.
150.6 The Superintendant's Representative was throughout the work aware of
the stripping being carried out, how it was being carried out, the measurement of
that stripping, and the depth of the stripping.
150.7 The Superintendent's Representative never informed the Contractor that
the stripping was too deep and never instructed the Contractor to stop stripping
to a depth greater than exactly SOmm.
4 UNREPORTED JUDGMENTS
150.8 The plaintiff perfomed the stripping from the area covered by the levee
with due care and skill and using appropriate equipment in the circumstances and
this stripping and removal of unsuitable was not excavated carelessly.
150.9 The defendant has paid the plaintiff for 4,222 cubic metres of stripping
under Item | of the Schedule of Rates.
150.10 It was not possible to strip in grass-covered and weed-infested land of
the type encountered at the levee site an exact 50mm. Thus, for practical reasons
any operation which endeavoured to remove a minimum of 50mm below natural
surface cannot avoid taking out an average of considerably more than that, even
when due care is taken.
150.11 The stripping carried out by the plaintiff was reasonably necessary for
the proper preparation of the levee foundation..."
Giles J disagreed with the referee's interpretation of CLS2, essentially for two
reasons. First, his Honour observed that the language of the relevant clause, and
the language in particular of the last sentence, putting to one side the cases where
there had been directions by the Superintendent, was such as to relate the
measurement of quantities for the purposes of payment to the lines or batters
shown on the drawings. In this respect his Honour emphasised the use of the
word "only" in the relevant sentence.
Second, his Honour observed that the evident purpose of the clause was to
provide a reasonably precise mechanical basis for calculation of the quantities by
reference to which the contractor was entitled to be paid.
In that regard his Honour pointed out, rightly in my opinion, that the
interpretation placed upon the clause by the referee introduced into its operations
considerations of the exercise of due care and of reasonable necessity which were
capable of bringing into the administration of the contract substantial uncertainty,
and scope for disputation. The introduction of those considerations does not
reflect anything that is said in the wording of CLS2-3. Potentially, it is productive
of uncertainty of just the kind that the language of the clause seems designed to
avoid.
The reasoning of the arbitrator indicated that he might have been minded
himself to have a considerable degree of sympathy with that point of view if he
had not also had to consider the language of CLS2-3. It appears that what induced
him to take a different and rather more elaborate view of the clause was the
construction he gave to the cognate provision in CLS3-10.
In relation to the meaning of CLS3-10 the point of departure between Giles J
and the referee turned upon their respective views as to the practical significance
of the reference in lines 3 and 4 of subCL(1) to the matter of cross-sections taken
after stripping. The referee gave that clause a wide-ranging operation whereas
Giles J read it as applying in practice to cases where the Superintendent had given
directions contrary to the drawings.
In that respect his Honour pointed out that the reference to stripping is a
reference to "stripping as specified in CLS2-3".
In my view, insofar as it is material (I do not for my own part consider it
decisive) the construction of CLS3-10 preferred by Giles J is the better one.
I have come to the conclusion that the reasons given by Giles J for his
construction of CLS2-3 are persuasive and the appellant has not shown his
Honour to have been in error in relation to this aspect of the case. Accordingly
I will propose in due course in relation to this aspect of the case that the appeal
be dismissed.
URUANTIC CIVIL PTY LTD v WATER ADMINISTRATION MINISTERIAL CORPORATION:
(Beazley JA)
It follows from what I have said that I agree with the construction of the
contract expressed by Giles J at 19 of his reasons for judgment, and not only his
conclusion as to the application to the areas described as (a), (b), (c), (d) and (e).
As I noted earlier, there is an outstanding point of appeal upon which we have
not heard argument upon yet.
Mahoney P I agree with what has been said by the Chief Justice. I do not
desire to add anything myself.
Beazley JA I agree with the reasons of the Chief Justice.
It follows from what I have said that I agree with the construction of the
contract expressed by Giles J at 19 of his reasons for judgment, and not only his
conclusion as to the application to the areas described as (a), (b), (c), (d) and (e).
As I noted earlier, there is an outstanding point of appeal upon which we have
not heard argument upon yet.
Counsel for the appellant: M J Neil QC / R J Wright
Solicitors for the appellant: John Carmody and Co
Counsel for the respondent: M D Young / S Climpson
Solicitors for the respondent: Solicitor for Water Administration Ministerial
Corporation